Valley Affordable Housing Corporation; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 5584 [2011-2138]

Download as PDF 5584 Federal Register / Vol. 76, No. 21 / Tuesday, February 1, 2011 / Notices mail of new filing and issuances related to this or other pending projects. For assistance, contact FERC Online Support. Kimberly D. Bose, Secretary. [FR Doc. 2011–2141 Filed 1–31–11; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13944–000] Valley Affordable Housing Corporation; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications srobinson on DSKHWCL6B1PROD with NOTICES January 21, 2011. On December 10, 2010, the Valley Affordable Housing Corporation filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act (FPA), proposing to study the feasibility of the Manville Hydroelectric Project to be located at the Manville Dam, on the Blackstone River, in Providence County, Rhode Island. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land-disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed project would consist of: (1) The existing 22-foot-high, 260foot-long Manville Dam with one-foot flashboards owned by the Town of Cumberland; (2) an existing 76-acre impoundment with a normal water surface elevation of 106 feet (National Geodetic Vertical Datum 1929); (3) a new trashrack and stoplogs; (4) a new approximately 60-foot-wide intake in place of a 60-foot-long section of the spillway that would be removed; (5) new 10-foot-long, 12-foot-wide dual concrete penstocks; (6) a new 30-foottall (extending 20 feet above the spillway), 60-foot-wide powerhouse adjacent to the training walls; (7) a new 25-foot-wide, 5-foot-deep crest gate adjacent to the powerhouse; (8) two new bulb Kaplan turbines with a combined installed capacity of 1,026 kilowatts; (9) a new approximately 800-foot-long, 480volt transmission line; and (10) appurtenant facilities. The project would have an estimated annual generation of 4,221 megawatt-hours. VerDate Mar<15>2010 15:05 Jan 31, 2011 Jkt 223001 Applicant Contact: Peter Bouchard, Valley Affordable Housing Corporation, 895 Mendon Road, Cumberland, RI 02864; phone: (401) 334–2802. FERC Contact: Brandon Cherry; phone: (202) 502–8328. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Competing applications and notices of intent must meet the requirements of 18 CFR 4.36. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site at https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at 1–866–208–3676, or for TTY, (202) 502–8659. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and seven copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–13944) in the docket number field to access the document. For assistance, contact FERC Online Support. Kimberly D. Bose, Secretary. [FR Doc. 2011–2138 Filed 1–31–11; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13882–000] City of Salem, OR; Notice of Competing Preliminary Permit Application Accepted for Filing and Soliciting Comments and Interventions January 21, 2011. On November 19, 2010, the City of Salem, Oregon filed an application for a PO 00000 Frm 00026 Fmt 4703 Sfmt 4703 preliminary permit, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of a hydropower development in the Geren Island Diversion on the North Santiam River in Marion County, Oregon. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed project would consist of three developments: Franzen Reservoir Plant; Turner Control Plant; and Fairmount Reservoir Plant, and would utilize flows from two existing pipelines for the City of Salem’s water system drawing water from the existing Franzen and Fairmount reservoirs. The Franzen Reservoir Plant would consist of: (1) A new penstock intake at the powerhouse site; (2) a new powerhouse with a single turbine/ generator unit at an installed capacity of 0.5 megawatt (MW); and (3) a new standard flow meter to direct flow from the penstock to the turbine. The Turner Control Plant would consist of: (1) A new penstock intake at the powerhouse site; (2) a new powerhouse with a single turbine/ generator unit at an installed capacity of 0.5 MW; and (3) a new standard flow meter to direct flow from the penstock to the turbine. The Fairmount Reservoir Plant would consist of: (1) A new 36-inch-diameter bypass pipeline to convey water from the Franzen reservoir to the Fairmount reservoir; (2) a new powerhouse with a single turbine/generator unit at an installed capacity of 0.1 MW; and (3) a new standard flow meter to direct flow from the penstock to the turbine. The three developments would have a combined capacity of 1.1 MW. The proposed project would have an average annual generation of 8,000,000 kilowatthours. Applicant Contact: Linda Norris, City of Salem, Oregon, 555 Liberty Street SE., Room 220, Salem, OR 97301; phone: (503) 588–6255; e-mail: manager@cityofsalem.net. FERC Contact: Kelly Wolcott (202) 502–6480. Competing Application: This application competes with Project No. 13721–000 filed May 5, 2010. Deadline for filing comments and motions to intervene: 60 days from the issuance of this notice. Comments and motions to intervene may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the E:\FR\FM\01FEN1.SGM 01FEN1

Agencies

[Federal Register Volume 76, Number 21 (Tuesday, February 1, 2011)]
[Notices]
[Page 5584]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-2138]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 13944-000]


Valley Affordable Housing Corporation; Notice of Preliminary 
Permit Application Accepted for Filing and Soliciting Comments, Motions 
To Intervene, and Competing Applications

January 21, 2011.
    On December 10, 2010, the Valley Affordable Housing Corporation 
filed an application for a preliminary permit, pursuant to section 4(f) 
of the Federal Power Act (FPA), proposing to study the feasibility of 
the Manville Hydroelectric Project to be located at the Manville Dam, 
on the Blackstone River, in Providence County, Rhode Island. The sole 
purpose of a preliminary permit, if issued, is to grant the permit 
holder priority to file a license application during the permit term. A 
preliminary permit does not authorize the permit holder to perform any 
land-disturbing activities or otherwise enter upon lands or waters 
owned by others without the owners' express permission.
    The proposed project would consist of: (1) The existing 22-foot-
high, 260-foot-long Manville Dam with one-foot flashboards owned by the 
Town of Cumberland; (2) an existing 76-acre impoundment with a normal 
water surface elevation of 106 feet (National Geodetic Vertical Datum 
1929); (3) a new trashrack and stoplogs; (4) a new approximately 60-
foot-wide intake in place of a 60-foot-long section of the spillway 
that would be removed; (5) new 10-foot-long, 12-foot-wide dual concrete 
penstocks; (6) a new 30-foot-tall (extending 20 feet above the 
spillway), 60-foot-wide powerhouse adjacent to the training walls; (7) 
a new 25-foot-wide, 5-foot-deep crest gate adjacent to the powerhouse; 
(8) two new bulb Kaplan turbines with a combined installed capacity of 
1,026 kilowatts; (9) a new approximately 800-foot-long, 480-volt 
transmission line; and (10) appurtenant facilities. The project would 
have an estimated annual generation of 4,221 megawatt-hours.
    Applicant Contact: Peter Bouchard, Valley Affordable Housing 
Corporation, 895 Mendon Road, Cumberland, RI 02864; phone: (401) 334-
2802.
    FERC Contact: Brandon Cherry; phone: (202) 502-8328.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36. Comments, motions to intervene, notices of intent, and 
competing applications may be filed electronically via the Internet. 
See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's 
Web site at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can 
submit brief comments up to 6,000 characters, without prior 
registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information 
at the end of your comments. For assistance, please contact FERC Online 
Support at FERCOnlineSupport@ferc.gov or toll free at 1-866-208-3676, 
or for TTY, (202) 502-8659. Although the Commission strongly encourages 
electronic filing, documents may also be paper-filed. To paper-file, 
mail an original and seven copies to: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street, NE., 
Washington, DC 20426.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of 
Commission's Web site at  https://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-13944) in the docket number field to access 
the document. For assistance, contact FERC Online Support.

Kimberly D. Bose,
Secretary.
[FR Doc. 2011-2138 Filed 1-31-11; 8:45 am]
BILLING CODE 6717-01-P