Notice Announcing Preliminary Permit Drawing, 4894 [2011-1719]
Download as PDF
4894
Federal Register / Vol. 76, No. 18 / Thursday, January 27, 2011 / Notices
Where all permit applicants are
municipalities or all permit applicants
are non-municipalities, and no
applicant’s plans are better adapted than
the others’ to develop, conserve, and
utilize in the public interest the water
resources of a region, the Commission
issues a permit to the applicant who
filed first in time.2 In this case, because
three applications from entities not
claiming municipal preference are
deemed filed at the same time, the
Commission will conduct a random tie
breaker to determine priority. In the
event that the Commission concludes
that no applicant’s plans are better
adapted than the others, priority will be
determined accordingly.
On January 27, 2011, at 10 a.m.
(Eastern Time), the Secretary of the
Commission, or her designee, will, by
random drawing, determine the filing
priority for the three applicants
identified in this notice. The drawing is
open to the public and will be held in
room 2C, the Commission Meeting
Room, located at 888 First St., NE.,
Washington, DC 20426. The results of
the drawing will be recorded by the
Secretary or her designee. A subsequent
notice will be issued by the Secretary
announcing the results of the drawing.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–1724 Filed 1–26–11; 8:45 am]
BILLING CODE 6717–01–P
Kimberly D. Bose,
Secretary.
DEPARTMENT OF ENERGY
[FR Doc. 2011–1719 Filed 1–26–11; 8:45 am]
BILLING CODE 6717–01–P
Federal Energy Regulatory
Commission
January 20, 2011.
Project No. 13736–000
Project No. 13777–000
mstockstill on DSKH9S0YB1PROD with NOTICES
On May 18, 2010, at 8:30 a.m., the
Commission received two preliminary
permit applications for proposed
projects to be located at the Allegheny
River Lock & Dam No. 7 located on the
Allegheny River in Armstrong County,
Pennsylvania.1 The applications were
2 18 CFR 4.37 (2010). See, e.g., BPUS Generation
Development, LLC, 126 FERC ¶ 61,132 (2009).
1 The Commission is open each day from 8:30
a.m. to 5 p.m., except Saturdays, Sundays, and
holidays. 18 CFR 375.101(c) (2010). The
applications were filed between 5 p.m. on Monday
May 17, 2010, and 8:30 a.m. on Tuesday May 18,
2010. Under the Commission’s Rules of Practice
and Procedure, any document received after regular
business hours is considered filed at 8:30 a.m. on
the next regular business day. 18 CFR
385.2001(a)(2) (2010).
VerDate Mar<15>2010
17:51 Jan 26, 2011
applications were filed by Lock+ Hydro
Friends Fund XL, for Project No. 13746–
000, FFP Missouri 4, LLC, for Project
No. 13750–000, Allegheny 4 Hydro,
LLC, for Project No. 13776–000, and
Three Rivers Hydro, LLC, for Project No.
13782–000.
Where all permit applicants are
municipalities or all permit applicants
are non-municipalities, and no
applicant’s plans are better adapted than
the others’ to develop, conserve, and
utilize in the public interest the water
resources of a region, the Commission
issues a permit to the applicant who
filed first in time.2 In this case, because
four applications from entities not
claiming municipal preference are
deemed filed at the same time, the
Commission will conduct a random tie
breaker to determine priority. In the
event that the Commission concludes
that no applicant’s plans are better
adapted than the others, priority will be
determined accordingly.
On January 27, 2011, at 10 a.m.
(eastern time), the Secretary of the
Commission, or her designee, will, by
random drawing, determine the filing
priority for the four applicants
identified in this notice. The drawing is
open to the public and will be held in
room 2C, the Commission Meeting
Room, located at 888 First St., NE.,
Washington, DC 20426. The results of
the drawing will be recorded by the
Secretary or her designee. A subsequent
notice will be issued by the Secretary
announcing the results of the drawing.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–1712 Filed 1–26–11; 8:45 am]
Notice Announcing Preliminary Permit
Drawing
Lock Hydro Friends
Fund XLI.
Allegheny 7 Hydro, LLC
filed by Lock Hydro Friends Fund XLI,
for Project No. 13736–000, and
Allegheny 7 Hydro, LLC, for Project No.
13777–000.
Where all permit applicants are
municipalities or all permit applicants
are non-municipalities, and no
applicant’s plans are better adapted than
the others’ to develop, conserve, and
utilize in the public interest the water
resources of a region, the Commission
issues a permit to the applicant who
filed first in time.2 In this case, because
two applications from entities not
claiming municipal preference are
deemed filed at the same time, the
Commission will conduct a random tie
breaker to determine priority. In the
event that the Commission concludes
that neither applicant’s plans are better
adapted than the other, priority will be
determined accordingly.
On January 27, 2011, at 10 a.m.
(eastern time), the Secretary of the
Commission, or her designee, will, by
random drawing, determine the filing
priority for the two applicants identified
in this notice. The drawing is open to
the public and will be held in room 2C,
the Commission Meeting Room, located
at 888 First St., NE., Washington, DC
20426. The results of the drawing will
be recorded by the Secretary or her
designee. A subsequent notice will be
issued by the Secretary announcing the
results of the drawing.
Jkt 223001
DEPARTMENT OF ENERGY
BILLING CODE 6717–01–P
Federal Energy Regulatory
Commission
DEPARTMENT OF ENERGY
Notice Announcing Preliminary Permit
Drawing
Federal Energy Regulatory
Commission
January 20, 2011.
Notice Announcing Preliminary Permit
Drawing
Lock+ Hydro Friends
Fund XL.
FFP Missouri 4, LLC .......
Allegheny 4 Hydro, LLC
Three Rivers Hydro, LLC
Project No. 13746–000
Project No. 13750–000
Project No. 13776–000
Project No. 13782–000
On May 18, 2010, at 8:30 a.m., the
Commission received four preliminary
permit applications for proposed
projects to be located at the Allegheny
River Lock and Dam No. 4 located on
the Allegheny River in Allegheny
County, Pennsylvania.1 The
2 18 CFR 4.37 (2010). See, e.g., BPUS Generation
Development, LLC, 126 FERC ¶ 61,132 (2009).
1 The Commission is open each day from 8:30
a.m. to 5 p.m., except Saturdays, Sundays, and
holidays. 18 CFR 375.101(c) (2010). The
PO 00000
Frm 00037
Fmt 4703
Sfmt 4703
January 20, 2011.
FFP Missouri 15, LLC .....
Morgantown Hydro, LLC
Three Rivers Hydro, LLC
Project No. 13762–000
Project No. 13773–000
Project No. 13784–000
On May 18, 2010, at 8:30 a.m., the
Commission received three preliminary
permit applications for proposed
applications were filed between 5 p.m. on Monday
May 17, 2010, and 8:30 a.m. on Tuesday May 18,
2010. Under the Commission’s Rules of Practice
and Procedure, any document received after regular
business hours is considered filed at 8:30 a.m. on
the next regular business day. 18 CFR
385.2001(a)(2) (2010).
2 18 CFR 4.37 (2010). See, e.g., BPUS Generation
Development, LLC, 126 FERC ¶ 61,132 (2009).
E:\FR\FM\27JAN1.SGM
27JAN1
Agencies
[Federal Register Volume 76, Number 18 (Thursday, January 27, 2011)]
[Notices]
[Page 4894]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-1719]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice Announcing Preliminary Permit Drawing
January 20, 2011.
Lock Hydro Friends Fund XLI............... Project No. 13736-000
Allegheny 7 Hydro, LLC.................... Project No. 13777-000
On May 18, 2010, at 8:30 a.m., the Commission received two
preliminary permit applications for proposed projects to be located at
the Allegheny River Lock & Dam No. 7 located on the Allegheny River in
Armstrong County, Pennsylvania.\1\ The applications were filed by Lock
Hydro Friends Fund XLI, for Project No. 13736-000, and Allegheny 7
Hydro, LLC, for Project No. 13777-000.
---------------------------------------------------------------------------
\1\ The Commission is open each day from 8:30 a.m. to 5 p.m.,
except Saturdays, Sundays, and holidays. 18 CFR 375.101(c) (2010).
The applications were filed between 5 p.m. on Monday May 17, 2010,
and 8:30 a.m. on Tuesday May 18, 2010. Under the Commission's Rules
of Practice and Procedure, any document received after regular
business hours is considered filed at 8:30 a.m. on the next regular
business day. 18 CFR 385.2001(a)(2) (2010).
---------------------------------------------------------------------------
Where all permit applicants are municipalities or all permit
applicants are non-municipalities, and no applicant's plans are better
adapted than the others' to develop, conserve, and utilize in the
public interest the water resources of a region, the Commission issues
a permit to the applicant who filed first in time.\2\ In this case,
because two applications from entities not claiming municipal
preference are deemed filed at the same time, the Commission will
conduct a random tie breaker to determine priority. In the event that
the Commission concludes that neither applicant's plans are better
adapted than the other, priority will be determined accordingly.
---------------------------------------------------------------------------
\2\ 18 CFR 4.37 (2010). See, e.g., BPUS Generation Development,
LLC, 126 FERC ] 61,132 (2009).
---------------------------------------------------------------------------
On January 27, 2011, at 10 a.m. (eastern time), the Secretary of
the Commission, or her designee, will, by random drawing, determine the
filing priority for the two applicants identified in this notice. The
drawing is open to the public and will be held in room 2C, the
Commission Meeting Room, located at 888 First St., NE., Washington, DC
20426. The results of the drawing will be recorded by the Secretary or
her designee. A subsequent notice will be issued by the Secretary
announcing the results of the drawing.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011-1719 Filed 1-26-11; 8:45 am]