Blue Heron Hydro LLC; Notice of Application Accepted for Filing and Soliciting Motions To Intervene and Protests, 4891 [2011-1717]
Download as PDF
Federal Register / Vol. 76, No. 18 / Thursday, January 27, 2011 / Notices
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: February 10, 2011.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–1714 Filed 1–26–11; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13368–002]
Blue Heron Hydro LLC; Notice of
Application Accepted for Filing and
Soliciting Motions To Intervene and
Protests
mstockstill on DSKH9S0YB1PROD with NOTICES
January 20, 2011.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Original
Minor License.
b. Project No.: 13368–002.
c. Date filed: November 1, 2010.
d. Applicant: Blue Heron Hydro LLC.
e. Name of Project: Townshend Dam
Hydroelectric Project.
f. Location: U.S. Army Corps of
Engineers Townshend Dam on the West
River near the Town of Townshend,
Windham County, Vermont.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Lori Barg, Blue
Heron Hydro LLC, 113 Bartlett Road,
Plainfield, Vermont 05667. (802) 454–
1874.
i. FERC Contact: Dr. Nicholas Palso,
(202) 502–8854 or
nicholas.palso@ferc.gov.
j. Deadline for filing motions to
intervene and protests: 60 days from the
issuance date of this notice.
All documents may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site (https://www.ferc.gov/docs-filing/
ferconline.asp) under the ‘‘eFiling’’ link.
VerDate Mar<15>2010
17:51 Jan 26, 2011
Jkt 223001
For a simpler method of submitting text
only comments, click on ‘‘Quick
Comment.’’ For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and eight copies to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
and Procedures require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person on the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
k. This application has been accepted
for filing, but is not ready for
environmental analysis at this time.
l. Project Description: The Townshend
Dam Hydroelectric Project would utilize
the U.S. Army Corps of Engineers’
existing Townshend Dam and reservoir
and would consist of: (1) Two turbine
generator modules located within the
existing intake tower, each containing 6
horizontal mixed flow turbines directly
connected to 6 submersible generator
units for a total installed capacity of 925
kilowatts; (2) a new 12.47- kilovolt, 430foot-long transmission line; and (3)
appurtenant facilities. The project
would have an estimated average annual
generation of approximately 2,000
megawatt-hours.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the ‘‘eLibrary’’
link. Enter the docket number excluding
the last three digits in the docket
number field to access the document.
For assistance, contact FERC Online
Support. A copy is also available for
inspection and reproduction at the
address in item h above.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
e-mail of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Any qualified applicant desiring to
file a competing application must
submit to the Commission, on or before
the specified intervention deadline date,
a competing development application,
PO 00000
Frm 00034
Fmt 4703
Sfmt 9990
4891
or a notice of intent to file such an
application. Submission of a timely
notice of intent allows an interested
person to file the competing
development application no later than
120 days after the specified intervention
deadline date. Applications for
preliminary permits will not be
accepted in response to this notice.
A notice of intent must specify the
exact name, business address, and
telephone number of the prospective
applicant, and must include an
unequivocal statement of intent to
submit a development application. A
notice of intent must be served on the
applicant(s) named in this public notice.
Anyone may submit a protest or a
motion to intervene in accordance with
the requirements of Rules of Practice
and Procedure, 18 CFR 385.210,
385.211, and 385.214. In determining
the appropriate action to take, the
Commission will consider all protests
filed, but only those who file a motion
to intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any protests or
motions to intervene must be received
on or before the specified deadline date
for the particular application.
When the application is ready for
environmental analysis, the
Commission will issue a public notice
requesting comments,
recommendations, terms and
conditions, and prescriptions.
All filings must (1) bear in all capital
letters the title ‘‘PROTEST’’ or ‘‘MOTION
TO INTERVENE,’’ ‘‘NOTICE OF INTENT
TO FILE COMPETING APPLICATION,’’
or ‘‘COMPETING APPLICATION;’’ (2)
set forth in the heading the name of the
applicant and the project number of the
application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
protesting or intervening; and (4)
otherwise comply with the requirements
of 18 CFR 385.2001 through 385.2005.
Agencies may obtain copies of the
application directly from the applicant.
A copy of any protest or motion to
intervene must be served upon each
representative of the applicant specified
in the particular application.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011–1717 Filed 1–26–11; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\27JAN1.SGM
27JAN1
Agencies
[Federal Register Volume 76, Number 18 (Thursday, January 27, 2011)]
[Notices]
[Page 4891]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-1717]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 13368-002]
Blue Heron Hydro LLC; Notice of Application Accepted for Filing
and Soliciting Motions To Intervene and Protests
January 20, 2011.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Original Minor License.
b. Project No.: 13368-002.
c. Date filed: November 1, 2010.
d. Applicant: Blue Heron Hydro LLC.
e. Name of Project: Townshend Dam Hydroelectric Project.
f. Location: U.S. Army Corps of Engineers Townshend Dam on the West
River near the Town of Townshend, Windham County, Vermont.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Lori Barg, Blue Heron Hydro LLC, 113 Bartlett
Road, Plainfield, Vermont 05667. (802) 454-1874.
i. FERC Contact: Dr. Nicholas Palso, (202) 502-8854 or
nicholas.palso@ferc.gov.
j. Deadline for filing motions to intervene and protests: 60 days
from the issuance date of this notice.
All documents may be filed electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web
site (https://www.ferc.gov/docs-filing/ferconline.asp) under the
``eFiling'' link. For a simpler method of submitting text only
comments, click on ``Quick Comment.'' For assistance, please contact
FERC Online Support at FERCOnlineSupport@ferc.gov; call toll-free at
(866) 208-3676; or, for TTY, contact (202) 502-8659. Although the
Commission strongly encourages electronic filing, documents may also be
paper-filed. To paper-file, mail an original and eight copies to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
The Commission's Rules of Practice and Procedures require all
intervenors filing documents with the Commission to serve a copy of
that document on each person on the official service list for the
project. Further, if an intervenor files comments or documents with the
Commission relating to the merits of an issue that may affect the
responsibilities of a particular resource agency, they must also serve
a copy of the document on that resource agency.
k. This application has been accepted for filing, but is not ready
for environmental analysis at this time.
l. Project Description: The Townshend Dam Hydroelectric Project
would utilize the U.S. Army Corps of Engineers' existing Townshend Dam
and reservoir and would consist of: (1) Two turbine generator modules
located within the existing intake tower, each containing 6 horizontal
mixed flow turbines directly connected to 6 submersible generator units
for a total installed capacity of 925 kilowatts; (2) a new 12.47-
kilovolt, 430-foot-long transmission line; and (3) appurtenant
facilities. The project would have an estimated average annual
generation of approximately 2,000 megawatt-hours.
m. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support. A copy is also available for inspection and
reproduction at the address in item h above.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via e-mail of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
n. Any qualified applicant desiring to file a competing application
must submit to the Commission, on or before the specified intervention
deadline date, a competing development application, or a notice of
intent to file such an application. Submission of a timely notice of
intent allows an interested person to file the competing development
application no later than 120 days after the specified intervention
deadline date. Applications for preliminary permits will not be
accepted in response to this notice.
A notice of intent must specify the exact name, business address,
and telephone number of the prospective applicant, and must include an
unequivocal statement of intent to submit a development application. A
notice of intent must be served on the applicant(s) named in this
public notice.
Anyone may submit a protest or a motion to intervene in accordance
with the requirements of Rules of Practice and Procedure, 18 CFR
385.210, 385.211, and 385.214. In determining the appropriate action to
take, the Commission will consider all protests filed, but only those
who file a motion to intervene in accordance with the Commission's
Rules may become a party to the proceeding. Any protests or motions to
intervene must be received on or before the specified deadline date for
the particular application.
When the application is ready for environmental analysis, the
Commission will issue a public notice requesting comments,
recommendations, terms and conditions, and prescriptions.
All filings must (1) bear in all capital letters the title
``PROTEST'' or ``MOTION TO INTERVENE,'' ``NOTICE OF INTENT TO FILE
COMPETING APPLICATION,'' or ``COMPETING APPLICATION;'' (2) set forth in
the heading the name of the applicant and the project number of the
application to which the filing responds; (3) furnish the name,
address, and telephone number of the person protesting or intervening;
and (4) otherwise comply with the requirements of 18 CFR 385.2001
through 385.2005. Agencies may obtain copies of the application
directly from the applicant. A copy of any protest or motion to
intervene must be served upon each representative of the applicant
specified in the particular application.
Kimberly D. Bose,
Secretary.
[FR Doc. 2011-1717 Filed 1-26-11; 8:45 am]
BILLING CODE 6717-01-P