Florida Power and Light Company, Turkey Point, Units 3 and 4; Exemption, 802-805 [2011-10]

Download as PDF 802 Federal Register / Vol. 76, No. 4 / Thursday, January 6, 2011 / Notices NUCLEAR REGULATORY COMMISSION [Docket Nos. 50–250 and 50–251; NRC– 2010–0025] Florida Power and Light Company, Turkey Point, Units 3 and 4; Exemption 1.0 Background Florida Power and Light Company (FPL, the licensee) is the holder of Facility Operating License Nos. DPR–31 and DPR–41, which authorize operation of Turkey Point, Unit Nos. 3 and 4 (Turkey Point 3 and 4). The license provides, among other things, that the facility is subject to all rules, regulations, and orders of the U.S. Nuclear Regulatory Commission (NRC) now or hereafter in effect. The facility consists of two pressurized-water reactors located in Florida City, Florida. erowe on DSK5CLS3C1PROD with NOTICES 2.0 Request/Action By letter dated October 13, 2009 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML092950342), and pursuant to Title 10 of the Code of Federal Regulations (CFR), Section 26.9, FPL requested an exemption from the requirements of 10 CFR 26.205(c), ‘‘Work hours scheduling,’’ and (d), ‘‘Work hour controls,’’ during declarations of severe weather conditions such as tropical storm and hurricane force winds at the Turkey Point site. Supplemental responses and responses to requests for additional information (RAI) are dated March 9, 2010 (ADAMS Accession No. ML100770099), September 2, 2010 (ADAMS Accession No. ML102580335), October 6, 2010 (ADAMS Accession No. ML102850047), and October 20, 2010 (ADAMS Accession No. ML103060463). The requested exemption applies to individuals who perform duties identified in 10 CFR 26.4(a)(1) through (a)(5) who are sequestered onsite during the severe wind event, as travel to and from the site during severe wind conditions may be hazardous or not possible. The exemption request states that because of the unpredictable nature and potential speed of a storm, a need to activate the storm crew could occur on short notice and without the ability to meet work hour controls. The exemption request also states that although the plant may not meet the criteria for declaring an emergency based on the NRC-approved emergency action levels, emergency preparedness would require the implementation of the site emergency plan. After the high wind conditions pass, wind damage to the plant and VerDate Mar<15>2010 15:07 Jan 05, 2011 Jkt 223001 surrounding area might preclude sufficient numbers of individuals from immediately returning to the site. Additionally, if mandatory civil evacuations were ordered, this could also delay the return of sufficient relief personnel. The Emergency Coordinator (a senior management official at Turkey Point) will decide when weather conditions permit sufficient personnel to travel safely to and from the site. When this declaration is made, full compliance with 10 CFR 26.205(c) and (d) is again required. The exemption would allow Turkey Point to sequester individuals onsite, when travel to and from the site during high wind conditions is hazardous or not possible due to severe weather conditions. According to the National Weather Service, sustained wind speed of 40 miles per hour (mph) makes travel unsafe for the common traveler. If conditions are such that sustained winds of 73 mph are present onsite, then Turkey Point will declare a Notice of Unusual Event (UE). When this declaration is made, an exemption from these same work hour controls is available under 10 CFR 26.207(d). 3.0 Discussion The NRC staff has reviewed the licensee’s overall request against the regulations contained in 10 CFR 26.205 and 26.207 and related Federal Register Notice Statements of Consideration [73 FR 16965]. Also, the NRC staff reviewed the guidance in Regulatory Guide 5.73, Fatigue Management for Nuclear Power Plant Personnel. Information from the National Hurricane Center (NHC) (https://www.nhc.noaa.gov/) was used to understand various conditions or effects related to tropical storm and hurricane wind speeds. Section 26.205(b) of 10 CFR is the requirement to count work hours and days worked. Section 26.205(b)(3) is the requirement to consider other periods of work not included in Section 26.205(d) so that they can be included in the work hour control calculations when a covered individual resumes covered work. Regulatory Guide 5.73 Regulatory Guide 5.73, Fatigue Management for Nuclear Power Plant Personnel, endorses the Nuclear Energy Institute (NEI) report NEI 06–11, revision 1, ‘‘Managing Personnel Fatigue at Nuclear Power Plants,’’ with certain clarifications, additions and exceptions. Staff has endorsed this guidance for use during declared emergencies. After exiting the emergency, the licensee is immediately subject to the scheduling requirements of 10 CFR 26.205(c) and the work hour/rest break/minimum day off requirements of 10 CFR 26.205(d). As required by 26.205(b)(3), all time worked during the emergency must be tracked to ensure that individuals are not fatigued when work hour controls are reinstated. In a public meeting on July 2, 2010, to discuss lessons learned regarding submitting an exemption request from Part 26, Subpart I work hour controls during periods of severe winds such as a tropical storm or hurricane, the staff concluded that it finds NEI 06–11 Section 7.5 ‘‘Reset from Deviations’’ to be an acceptable method for resuming work hour controls after the recovery period. 10 CRF Part 26 Subpart I, Managing Fatigue Precedence STP Nuclear Operating Company, the licensee for South Texas Project Units 1 and 2 has been granted a similar exemption from severe wind conditions, which can be found in the Federal Register dated July 12, 2010 (75 FR 39707). The fatigue management provisions in 10 CFR Part 26 Subpart I are designed as an integrated approach to managing both cumulative and acute fatigue. The requirement to schedule individuals’ work hours consistent with the objective of preventing impairment from fatigue is found in 10 CFR 26.205(c). Section 26.205(d) of 10 CFR provides the actual work hour controls—which are 16 work hours in any 24-hour period, 26 work hours in any 48-hour period, and 72 work hours in any 7-day period. This section also provides limits on the number of hours an individual may work; limits on the minimum break times between work periods; and limits for the minimum number of days off an individual must be given. Lessons Learned The effects of Hurricane Andrew on the Turkey Point site were used to identify lessons learned to consider when evaluating this request. The following sources were reviewed: • NUREG–1474, ‘‘Effect of Hurricane Andrew on the Turkey Point Nuclear Generating Station from August 20–30, 1992.’’ • NRC Information Notice 93–53, ‘‘Effect of Hurricane Andrew on Turkey Point Nuclear Generating Station and Lessons Learned.’’ • NRC Information Notice 93–53, Supplement 1, ‘‘Effect of Hurricane Andrew on Turkey Point Nuclear Generating Station and Lessons Learned.’’ PO 00000 Frm 00033 Fmt 4703 Sfmt 4703 E:\FR\FM\06JAN1.SGM 06JAN1 Federal Register / Vol. 76, No. 4 / Thursday, January 6, 2011 / Notices erowe on DSK5CLS3C1PROD with NOTICES • NUREG–0933, ‘‘Resolution of Generic Safety Issues,’’ Issue 178: Effect of Hurricane Andrew on Turkey Point (Rev 2). Hurricane Andrew was a Category 5 hurricane that struck the Turkey Point site on August 24, 1992. On September 10, 1992, the NRC and the Institute of Nuclear Power Operations jointly sponsored a team to review the damage of Hurricane Andrew on the nuclear units and the utility’s actions to prepare for the storm and recover from it and compile lessons learned that might benefit other nuclear utilities. The licensee exemption request and the licensee’s site procedures related to severe winds were compared to the actions and lessons learned documented in NUREG–1474, including an indication that detailed methodical preparations should be made prior to the onset of hurricane force winds. The NRC staff has reviewed the FPL exemption request for the Turkey Point site and agrees that preparing the site for the onset of severe wind conditions such as hurricanes, including sequestering enough essential personnel to provide for shift relief, is prudent to ensure plant and personnel safety. 10 CFR 26.207(d) Exemption Pursuant to 10 CFR 26.207(d) licensees need not meet the requirements of Section 26.205(c) and (d) during declared emergencies as defined in the licensee’s emergency plan. The FPL RAI response letter dated March 9, 2010, clarified that the entry condition for the exemption is when site preparations are commenced per the licensee’s severe weather preparation procedure (confirmed tropical storm watch or warning, or confirmed hurricane watch or warning). As defined by the NHC, a tropical storm watch is declared when sustained winds of at least 39 mph are expected somewhere within the specified coastal area. The entry condition for a Turkey Point declaration of an Unusual Event is a confirmed hurricane warning, which is defined by the NHC when sustained winds of 74 mph are expected somewhere within the specified coastal area. Therefore, entry conditions for the requested exemption may precede the declaration of a UE. Section 26.207(d) states that licensees need not meet the requirements of 26.205(c) and (d) during declared emergencies, therefore there is no need for an additional exemption to be granted during the period of a declared emergency for severe winds. Although work hours, breaks, and days off are calculated as usual during a licensedeclared plant emergency, licensees are VerDate Mar<15>2010 15:07 Jan 05, 2011 Jkt 223001 unconstrained in the number of hours they may allow individuals to work performing covered duties or the timing and duration of breaks they must require them to take. The FPL RAI response letter dated March 9, 2010, clarifies that the exit condition for the exemption is when the Emergency Coordinator determines there are sufficient personnel available to meet the requirements of 10 CFR 26.205 (c) and (d). Therefore, exit conditions for this exemption request can possibly come well after the exit of the UE. To summarize, the FPL exemption request for Turkey Point Units 3 and 4 can be characterized, as having three parts: A high wind exemption; a recovery exemption immediately following an Emergency Plan exemption; and a recovery exemption immediately following a high wind exemption. High Wind Exemption A high wind exemption encompasses the period starting with the entry conditions prior to the declaration of a UE (confirmed hurricane warning is in effect). As a tropical storm or hurricane approaches landfall, high wind speeds—in excess of wind speeds that create unsafe travel conditions—are expected. During these times, the National Weather Service typically publishes a projected path of the storm. This condition will be described as the ‘‘high wind condition,’’ or ‘‘period of high winds.’’ FPL requests an exemption from 10 CFR 26.205(c) and (d) work hour controls during periods of high winds. For the purposes of this exemption, declaration of the entry condition allows any onsite individual who performs duties identified in 10 CFR 26.4(a)(1) through (a)(5) to not have to meet the requirements of 10 CFR 26.205(c) and (d) if they are designated as part of the storm crew. This entry condition occurs when there is a confirmed tropical storm watch or warning or when there is a confirmed hurricane watch or warning and the Emergency Coordinator indicates that site preparations should be commenced per the severe weather preparation procedure. The NHC defines a hurricane warning as an announcement that hurricane conditions (sustained winds of 74 mph or higher) are expected somewhere within the specified coastal area. Because severe wind preparedness activities become difficult once winds reach tropical storm force, a hurricane warning is issued 36 hours in advance PO 00000 Frm 00034 Fmt 4703 Sfmt 4703 803 of the anticipated onset of tropicalstorm-force winds (39 to 73 mph). Lessons learned that are published in NUREG–1474 include the acknowledgement that detailed, methodical preparations should be made prior to the onset of hurricane force winds. The NRC staff finds the Turkey Point proceduralized actions are consistent with the lessons learned. Recovery Exemption Immediately Following a High Wind Exemption The period immediately following the high wind exemption, but when the conditions for a UE no longer exist, may still require a recovery period. Also, high winds that make travel unsafe but that fall below the threshold of an emergency, could be present for several days. After the high wind condition has passed, sufficient numbers of personnel may not be able to access the site to relieve the sequestered individuals. An exemption during these conditions is consistent with the intent of the 10 CFR 26.207(d) exemption. Recovery Exemption Immediately Following an Emergency Plan Exemption Following a declared emergency, under 10 CFR 26.207(d), due to high wind conditions, the site may not be accessible by sufficient numbers of personnel to allow relief of the sequestered individuals. Once the high wind conditions have passed and the UE exited, a recovery period might be necessary. An exemption during these circumstances is consistent with the intent of 10 CFR 26.207(d). Once Turkey Point has entered into either the high wind exemption or the 10 CFR 26.207(d) exemption, the licensee should not need to make a declaration that it is invoking the recovery exemption. Unit Shutdown If a hurricane warning is in effect and the storm is projected to reach the site as a Category 1 or 2 hurricane, then shutdown of the units to hot standby (mode 3) is commenced at least two (2) hours before the projected onset of sustained hurricane force winds at the site. Both units will remain offline for the duration of the hurricane force winds (or restoration of reliable offsite power). If the storm is projected to reach the site as a category 3, 4, and 5 hurricane prior to landfall, specific shutdown conditions are established at least two (2) hours before the projected onset of sustained hurricane force winds at the site. Because severe weather preparations are likely commenced prior to the shutdown of the units, then E:\FR\FM\06JAN1.SGM 06JAN1 804 Federal Register / Vol. 76, No. 4 / Thursday, January 6, 2011 / Notices this exemption will allow sufficient personnel onsite to ensure that the facility is properly secured for severe weather. Lessons learned from Hurricane Andrew, NUREG–1474, include having both units shutdown and on residual heat removal when the storm strikes so that a loss of offsite power will not jeopardize core cooling. The NRC staff finds the Turkey Point plan is consistent with the lessons learned. Storm Crew Turkey Point plans to sequester sufficient individuals to staff two 12hour shifts of workers consisting of personnel from operations, maintenance, health physics, chemistry, and security, to maintain the safe and secure operation of the facility. The Turkey Point hurricane plan provides for bunking facilities that provide an accommodation for restorative rest for the off crew. A 12-hour break provides each individual with an opportunity for restorative rest. Although, the accommodations and potentially stressful circumstances may not be ideal for restorative rest, the NRC finds that these actions are consistent with the practice of fatigue management when limited personnel are available during severe weather conditions. Maintenance The FPL RAI response letter dated September 2, 2010, clarified that the exemption request does not apply to discretionary maintenance activities. Suspension of work hour controls is for storm preparation activities and those deemed critical for plant and public safety. The staff finds the exclusion of discretionary maintenance from the exemption request to be consistent with the intent of the exemption. erowe on DSK5CLS3C1PROD with NOTICES Procedural Guidance By letter dated October 20, 2010, Turkey Point committed to maintain the following guidance, applicable to this exemption, in a site procedure: • The conditions necessary to sequester site personnel that are consistent with the conditions specified in the Turkey Point exemption request. • Provisions for ensuring that personnel who are not performing duties are provided an opportunity as well as accommodations for restorative rest. • The condition for departure from the exemption is based on the Emergency Coordinator’s determination that adequate staffing is available to meet the requirements of 10 CFR 26.205(c) and (d). VerDate Mar<15>2010 15:07 Jan 05, 2011 Jkt 223001 Returning to Work Hour Controls Turkey Point must return to work hour controls when the Emergency Coordinator determines that adequate staff is available to meet the 10 CFR 26.205(c) and (d) requirements. Upon exiting the exemption, the work hour controls in Section 26.205(c) and (d) apply and the requirements in 26.205(b)(3) must be met. Authorized by Law As stated above, this exemption would apply to the storm crew sequestered on site. The licensee’s request states that adherence to all work hour controls could impede the licensee’s ability to use whatever staff resources may be necessary to respond to a plant emergency and ensure that the plant maintains a safe and secure status. As stated above, 10 CFR 26.9 allows the NRC to grant exemptions from the requirements of 10 CFR 26.205(c) and (d). The NRC staff has determined that granting of the licensee’s proposed exemption will not result in a violation of the Atomic Energy Act of 1954, as amended, or the Commission’s regulations. Therefore, the exemption is authorized by law. No Undue Risk to Public Health and Safety The underlying purposes of 10 CFR 26.205(c) and (d) are to prevent impairment from fatigue due to duration, frequency, or sequencing of successive shifts. Based on the above evaluation, no new accident precursors are created by utilizing whatever staff resources may be necessary to respond to a plant emergency and ensure that the plant maintains a safe and secure status; therefore, the probability of postulated accidents is not increased. Even though it might be necessary to utilize whatever staff resources during severe weather preparation and storm crew activation, opportunities for restorative sleep will be maintained. Also, the consequences of postulated accidents are not increased, because there is no change in the types of accidents previously evaluated. Therefore, there is no undue risk to public health and safety. Consistent With Common Defense and Security The proposed exemption would allow the licensee to utilize whatever staff resources may be necessary to respond to a plant emergency and ensure that the plant maintains a safe and secure status. The licensee will provide sufficient numbers of management and supervision over the storm crew or the resources utilized during the plant emergency to provide additional PO 00000 Frm 00035 Fmt 4703 Sfmt 4703 oversight for monitoring the effects of fatigue to ensure that the safety and security of the facility are maintained. Also, during the plant emergency, opportunities for restorative sleep will be maintained. Therefore, the common defense and security is not impacted by this exemption. Otherwise in the Public Interest The proposed exemption would increase the availability of the licensee staff. The exemption would allow licensee staff to return to the site and perform additional duties to ensure the plant is in a safe configuration during the emergency. Therefore, granting this exemption is otherwise in the public interest. 4.0 Conclusion Granting this exemption is consistent with 10 CFR 26.207(d) Plant Emergencies, which allows the licensee to not meet the requirements of 10 CFR 26.205 (c) and (d) during declared emergencies as defined in the licensee’s emergency plan. The Part 26 Statements of Consideration, page 17148 states that ‘‘Plant emergencies are extraordinary circumstances that may be most effectively addressed through staff augmentation that can only be practically achieved through the use of work hours in excess of the limits of § 26.205(c) and (d).’’ The objective of the exemption is to ensure that the control of work hours do not impede a licensee’s ability to use whatever staff resources may be necessary to respond to a plant emergency and ensure that the plant reaches and maintains a safe and secure status. The actions described in the exemption request and submitted procedures are consistent with the recommendations in NUREG–1474. Also consistent with NUREG–1474, NRC staff expects the licensee would have completed a reasonable amount of hurricane preparation prior to the need to sequester personnel, in order to minimize personnel exposure to high winds. Based on the considerations discussed above, the NRC staff has determined that (1) the proposed exemption is authorized by law, (2) there is a reasonable assurance that the health and safety of the public will not be endangered by the proposed exemption (3) such activities will be consistent with the Commission’s regulations and guidance, and (4) the issuance of the exemption will not be contrary to the common defense and security or to the health and safety of the public. Therefore, the staff finds this request to be acceptable. E:\FR\FM\06JAN1.SGM 06JAN1 Federal Register / Vol. 76, No. 4 / Thursday, January 6, 2011 / Notices Pursuant to 10 CFR 51.32, the Commission has determined that the granting of this exemption will not have a significant effect on the quality of the human environment (75FR 34776; June 18, 2010). This exemption is effective upon issuance. Dated at Rockville, Maryland, this 27th day of December 2010. For the Nuclear Regulatory Commission. Allen G. Howe, Acting Director, Division of Operating Reactor Licensing, Office of Nuclear Reactor Regulation. [FR Doc. 2011–10 Filed 1–5–11; 8:45 am] BILLING CODE 7590–01–P SECURITIES AND EXCHANGE COMMISSION [Release No. 34–63624; File No. SR– NYSEArca–2010–120] Self-Regulatory Organizations; NYSE Arca, Inc.; Notice of Filing of Proposed Rule Change Relating to Listing and Trading Shares of the SPDR Nuveen S&P High Yield Municipal Bond ETF December 30, 2010. Pursuant to Section 19(b)(1) of the Securities Exchange Act of 1934 (‘‘Act’’) 1 and Rule 19b–4 thereunder,2 notice is hereby given that, on December 21, 2010, NYSE Arca, Inc. (‘‘Exchange’’ or ‘‘NYSE Arca’’) filed with the Securities and Exchange Commission (‘‘Commission’’) the proposed rule change as described in Items I and II below, which Items have been prepared by the Exchange. The Commission is publishing this notice to solicit comments on the proposed rule change from interested persons. I. Self-Regulatory Organization’s Statement of the Terms of Substance of the Proposed Rule Change erowe on DSK5CLS3C1PROD with NOTICES The Exchange proposes to list and trade shares of the SPDR Nuveen S&P High Yield Municipal Bond ETF under NYSE Arca Equities Rule 5.2(j)(3), Commentary .02. The text of the proposed rule change is available at the Exchange, the Commission’s Public Reference Room, and https:// www.nyse.com. II. Self-Regulatory Organization’s Statement of the Purpose of, and Statutory Basis for, the Proposed Rule Change In its filing with the Commission, the self-regulatory organization included statements concerning the purpose of, 1 15 2 17 U.S.C. 78s(b)(1). CFR 240.19b–4. VerDate Mar<15>2010 15:07 Jan 05, 2011 Jkt 223001 and basis for, the proposed rule change and discussed any comments it received on the proposed rule change. The text of those statements may be examined at the places specified in Item IV below. The Exchange has prepared summaries, set forth in sections A, B, and C below, of the most significant parts of such statements. A. Self-Regulatory Organization’s Statement of the Purpose of, and the Statutory Basis for, the Proposed Rule Change 1. Purpose The Exchange proposes to list and trade shares (‘‘Shares’’) of the following series of the SPDR Series Trust (‘‘Trust’’) under NYSE Arca Equities Rule 5.2(j)(3), Commentary .02, which governs the listing and trading of Investment Company Units (‘‘Units’’), based on the S&P Municipal Yield Index (‘‘Index’’): SPDR Nuveen S&P HighYield Municipal Bond ETF (‘‘Fund’’ or ‘‘ETF’’).3 The SPDR Nuveen S&P High Yield Municipal Bond ETF 4 seeks to provide investment results that, before fees and expenses, correspond generally to the price and yield performance of the Index, which tracks the U.S. municipal bond market, and to provide income that is exempt from regular federal income taxes.5 3 The Commission has previously approved listing and trading of Units based on certain fixed income indexes. See, e.g., Securities Exchange Act Release No. 48662 (October 20, 2003), 68 FR 61535 (October 28, 2003) (SR–PCX–2003–41) (approving listing and trading pursuant to unlisted trading privileges (‘‘UTP’’) of fixed income funds and the UTP trading of certain iShares® fixed income funds). In addition, the Commission has approved NYSE Arca generic listing rules for Units based on a fixed income index in Securities Exchange Act Release No. 55783 (May 17, 2007), 72 FR 29194 (May 24, 2007) (SR–NYSEArca–2007–36). The Commission has approved pursuant to Section 19(b)(2) of the Exchange Act the listing on the American Stock Exchange (‘‘Amex’’) of exchange traded funds based on fixed income indexes. See, e.g., Securities Exchange Act Release No. 48534 (September 24, 2003), 68 FR 56353 (September 30, 2003) (SR–Amex–2003–75) (order approving listing on Amex of eight series of iShares Lehman Bond Funds). In addition, the Commission has approved two actively managed funds of the PIMCO ETF Trust that hold municipal bonds. See Securities Exchange Act Release No. 60981 (August 27, 2009) (SR–NYSEArca–2009–79) (order approving PIMCO Short-Term Municipal Bond Strategy Fund and PIMCO Intermediate Municipal Bond Strategy Fund, among others). 4 Standard & Poor’s Financial Services LLC is the Index Sponsor with respect to the Index. The Index Sponsor is not affiliated with a broker-dealer and has implemented procedures designed to prevent the use and dissemination of material, non-public information regarding the Index. 5 See the Trust’s registration statement on Form N–1A under the Securities Act of 1933 (15 U.S.C. 77a) and the Investment Company Act of 1940 (15 U.S.C. 80a), dated February 22, 2010 (File No. 333– 57793 and 811–08839) (‘‘Registration Statement’’). The description of the operation of the Trust and PO 00000 Frm 00036 Fmt 4703 Sfmt 4703 805 The Exchange is submitting this proposed rule change because the Index for the Fund does not meet all of the ‘‘generic’’ listing requirements of Commentary .02(a)(2) to NYSE Arca Equities Rule 5.2(j)(3) applicable to listing of Units based on U.S. indexes. The Index meets all such requirements except for those set forth in Commentary .02(a)(2).6 Specifically, as of December 20, 2010, 26.47% of the weight of the Index components have a minimum principal amount outstanding of $100 million or more. According to the Registration Statement, the Index is designed to measure the performance of high yield municipal bonds issued by U.S. states and territories or local governments or agencies, such that interest on the securities is exempt from U.S. federal income tax, but may be subject to the alternative minimum tax and to state and local income taxes. High yield securities are generally rated below investment grade and are commonly referred to as ‘‘junk bonds.’’ The Index is a sub-set of the Standard & Poor’s/ Investortools Municipal Bond Index and the Standard & Poor’s/Investortools High Yield Bond Index and includes publicly issued U.S. dollar denominated, fixed rate, municipal bonds that have a remaining maturity of at least one year. The Index consists of categories of bonds in the following proportions: (i) 70% of the Index constituents are components of the Standard & Poor’s/ Investortools High Yield Bond Index, which are non-rated or are rated below investment grade; (ii) 20% of the Index constituents are components of the Standard & Poor’s/Investortools Bond Index that are rated Baa3, Baa2, or Baa1 by Moody’s Investors Service, or BBB-, BBB, or BBB+ by Standard and Poor’s or Fitch; and (iii) 10% of the Index constituents are components of the Standard & Poor’s/Investortools Bond Index that are rated A3, A2, or A1 by Moody’s Investor Services, or A-, A, or A+ by Standard & Poor’s or Fitch. Bonds that have been escrowed will not be included in the Index. Prerefunded bonds will not be included in the Index. Where the ratings assigned by the agencies are not consistent, the Index will use the middle rating if three ratings are available, and the lower of the Fund herein is based on the Registration Statement. 6 Commentary .02(a)(2) to NYSE Arca Equities Rule 5.2(j)(3) provides that components that in the aggregate account for at least 75% of the weight of the index or portfolio each shall have a minimum principal amount outstanding of $100 million or more. E:\FR\FM\06JAN1.SGM 06JAN1

Agencies

[Federal Register Volume 76, Number 4 (Thursday, January 6, 2011)]
[Notices]
[Pages 802-805]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2011-10]



[[Page 802]]

-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket Nos. 50-250 and 50-251; NRC-2010-0025]


Florida Power and Light Company, Turkey Point, Units 3 and 4; 
Exemption

1.0 Background

    Florida Power and Light Company (FPL, the licensee) is the holder 
of Facility Operating License Nos. DPR-31 and DPR-41, which authorize 
operation of Turkey Point, Unit Nos. 3 and 4 (Turkey Point 3 and 4). 
The license provides, among other things, that the facility is subject 
to all rules, regulations, and orders of the U.S. Nuclear Regulatory 
Commission (NRC) now or hereafter in effect. The facility consists of 
two pressurized-water reactors located in Florida City, Florida.

2.0 Request/Action

    By letter dated October 13, 2009 (Agencywide Documents Access and 
Management System (ADAMS) Accession No. ML092950342), and pursuant to 
Title 10 of the Code of Federal Regulations (CFR), Section 26.9, FPL 
requested an exemption from the requirements of 10 CFR 26.205(c), 
``Work hours scheduling,'' and (d), ``Work hour controls,'' during 
declarations of severe weather conditions such as tropical storm and 
hurricane force winds at the Turkey Point site. Supplemental responses 
and responses to requests for additional information (RAI) are dated 
March 9, 2010 (ADAMS Accession No. ML100770099), September 2, 2010 
(ADAMS Accession No. ML102580335), October 6, 2010 (ADAMS Accession No. 
ML102850047), and October 20, 2010 (ADAMS Accession No. ML103060463).
    The requested exemption applies to individuals who perform duties 
identified in 10 CFR 26.4(a)(1) through (a)(5) who are sequestered 
onsite during the severe wind event, as travel to and from the site 
during severe wind conditions may be hazardous or not possible. The 
exemption request states that because of the unpredictable nature and 
potential speed of a storm, a need to activate the storm crew could 
occur on short notice and without the ability to meet work hour 
controls. The exemption request also states that although the plant may 
not meet the criteria for declaring an emergency based on the NRC-
approved emergency action levels, emergency preparedness would require 
the implementation of the site emergency plan.
    After the high wind conditions pass, wind damage to the plant and 
surrounding area might preclude sufficient numbers of individuals from 
immediately returning to the site. Additionally, if mandatory civil 
evacuations were ordered, this could also delay the return of 
sufficient relief personnel. The Emergency Coordinator (a senior 
management official at Turkey Point) will decide when weather 
conditions permit sufficient personnel to travel safely to and from the 
site. When this declaration is made, full compliance with 10 CFR 
26.205(c) and (d) is again required.
    The exemption would allow Turkey Point to sequester individuals 
onsite, when travel to and from the site during high wind conditions is 
hazardous or not possible due to severe weather conditions. According 
to the National Weather Service, sustained wind speed of 40 miles per 
hour (mph) makes travel unsafe for the common traveler.
    If conditions are such that sustained winds of 73 mph are present 
onsite, then Turkey Point will declare a Notice of Unusual Event (UE). 
When this declaration is made, an exemption from these same work hour 
controls is available under 10 CFR 26.207(d).

3.0 Discussion

    The NRC staff has reviewed the licensee's overall request against 
the regulations contained in 10 CFR 26.205 and 26.207 and related 
Federal Register Notice Statements of Consideration [73 FR 16965]. 
Also, the NRC staff reviewed the guidance in Regulatory Guide 5.73, 
Fatigue Management for Nuclear Power Plant Personnel. Information from 
the National Hurricane Center (NHC) (https://www.nhc.noaa.gov/) was used 
to understand various conditions or effects related to tropical storm 
and hurricane wind speeds.

10 CRF Part 26 Subpart I, Managing Fatigue

    The fatigue management provisions in 10 CFR Part 26 Subpart I are 
designed as an integrated approach to managing both cumulative and 
acute fatigue. The requirement to schedule individuals' work hours 
consistent with the objective of preventing impairment from fatigue is 
found in 10 CFR 26.205(c). Section 26.205(d) of 10 CFR provides the 
actual work hour controls--which are 16 work hours in any 24-hour 
period, 26 work hours in any 48-hour period, and 72 work hours in any 
7-day period. This section also provides limits on the number of hours 
an individual may work; limits on the minimum break times between work 
periods; and limits for the minimum number of days off an individual 
must be given.
    Section 26.205(b) of 10 CFR is the requirement to count work hours 
and days worked. Section 26.205(b)(3) is the requirement to consider 
other periods of work not included in Section 26.205(d) so that they 
can be included in the work hour control calculations when a covered 
individual resumes covered work.

Regulatory Guide 5.73

    Regulatory Guide 5.73, Fatigue Management for Nuclear Power Plant 
Personnel, endorses the Nuclear Energy Institute (NEI) report NEI 06-
11, revision 1, ``Managing Personnel Fatigue at Nuclear Power Plants,'' 
with certain clarifications, additions and exceptions.
    Staff has endorsed this guidance for use during declared 
emergencies. After exiting the emergency, the licensee is immediately 
subject to the scheduling requirements of 10 CFR 26.205(c) and the work 
hour/rest break/minimum day off requirements of 10 CFR 26.205(d). As 
required by 26.205(b)(3), all time worked during the emergency must be 
tracked to ensure that individuals are not fatigued when work hour 
controls are reinstated. In a public meeting on July 2, 2010, to 
discuss lessons learned regarding submitting an exemption request from 
Part 26, Subpart I work hour controls during periods of severe winds 
such as a tropical storm or hurricane, the staff concluded that it 
finds NEI 06-11 Section 7.5 ``Reset from Deviations'' to be an 
acceptable method for resuming work hour controls after the recovery 
period.

Precedence

    STP Nuclear Operating Company, the licensee for South Texas Project 
Units 1 and 2 has been granted a similar exemption from severe wind 
conditions, which can be found in the Federal Register dated July 12, 
2010 (75 FR 39707).

Lessons Learned

    The effects of Hurricane Andrew on the Turkey Point site were used 
to identify lessons learned to consider when evaluating this request. 
The following sources were reviewed:
     NUREG-1474, ``Effect of Hurricane Andrew on the Turkey 
Point Nuclear Generating Station from August 20-30, 1992.''
     NRC Information Notice 93-53, ``Effect of Hurricane Andrew 
on Turkey Point Nuclear Generating Station and Lessons Learned.''
     NRC Information Notice 93-53, Supplement 1, ``Effect of 
Hurricane Andrew on Turkey Point Nuclear Generating Station and Lessons 
Learned.''

[[Page 803]]

     NUREG-0933, ``Resolution of Generic Safety Issues,'' Issue 
178: Effect of Hurricane Andrew on Turkey Point (Rev 2).
    Hurricane Andrew was a Category 5 hurricane that struck the Turkey 
Point site on August 24, 1992. On September 10, 1992, the NRC and the 
Institute of Nuclear Power Operations jointly sponsored a team to 
review the damage of Hurricane Andrew on the nuclear units and the 
utility's actions to prepare for the storm and recover from it and 
compile lessons learned that might benefit other nuclear utilities. The 
licensee exemption request and the licensee's site procedures related 
to severe winds were compared to the actions and lessons learned 
documented in NUREG-1474, including an indication that detailed 
methodical preparations should be made prior to the onset of hurricane 
force winds.
    The NRC staff has reviewed the FPL exemption request for the Turkey 
Point site and agrees that preparing the site for the onset of severe 
wind conditions such as hurricanes, including sequestering enough 
essential personnel to provide for shift relief, is prudent to ensure 
plant and personnel safety.

10 CFR 26.207(d) Exemption

    Pursuant to 10 CFR 26.207(d) licensees need not meet the 
requirements of Section 26.205(c) and (d) during declared emergencies 
as defined in the licensee's emergency plan. The FPL RAI response 
letter dated March 9, 2010, clarified that the entry condition for the 
exemption is when site preparations are commenced per the licensee's 
severe weather preparation procedure (confirmed tropical storm watch or 
warning, or confirmed hurricane watch or warning). As defined by the 
NHC, a tropical storm watch is declared when sustained winds of at 
least 39 mph are expected somewhere within the specified coastal area. 
The entry condition for a Turkey Point declaration of an Unusual Event 
is a confirmed hurricane warning, which is defined by the NHC when 
sustained winds of 74 mph are expected somewhere within the specified 
coastal area. Therefore, entry conditions for the requested exemption 
may precede the declaration of a UE.
    Section 26.207(d) states that licensees need not meet the 
requirements of 26.205(c) and (d) during declared emergencies, 
therefore there is no need for an additional exemption to be granted 
during the period of a declared emergency for severe winds. Although 
work hours, breaks, and days off are calculated as usual during a 
license-declared plant emergency, licensees are unconstrained in the 
number of hours they may allow individuals to work performing covered 
duties or the timing and duration of breaks they must require them to 
take.
    The FPL RAI response letter dated March 9, 2010, clarifies that the 
exit condition for the exemption is when the Emergency Coordinator 
determines there are sufficient personnel available to meet the 
requirements of 10 CFR 26.205 (c) and (d). Therefore, exit conditions 
for this exemption request can possibly come well after the exit of the 
UE.
    To summarize, the FPL exemption request for Turkey Point Units 3 
and 4 can be characterized, as having three parts: A high wind 
exemption; a recovery exemption immediately following an Emergency Plan 
exemption; and a recovery exemption immediately following a high wind 
exemption.

High Wind Exemption

    A high wind exemption encompasses the period starting with the 
entry conditions prior to the declaration of a UE (confirmed hurricane 
warning is in effect). As a tropical storm or hurricane approaches 
landfall, high wind speeds--in excess of wind speeds that create unsafe 
travel conditions--are expected. During these times, the National 
Weather Service typically publishes a projected path of the storm. This 
condition will be described as the ``high wind condition,'' or ``period 
of high winds.''
    FPL requests an exemption from 10 CFR 26.205(c) and (d) work hour 
controls during periods of high winds. For the purposes of this 
exemption, declaration of the entry condition allows any onsite 
individual who performs duties identified in 10 CFR 26.4(a)(1) through 
(a)(5) to not have to meet the requirements of 10 CFR 26.205(c) and (d) 
if they are designated as part of the storm crew. This entry condition 
occurs when there is a confirmed tropical storm watch or warning or 
when there is a confirmed hurricane watch or warning and the Emergency 
Coordinator indicates that site preparations should be commenced per 
the severe weather preparation procedure.
    The NHC defines a hurricane warning as an announcement that 
hurricane conditions (sustained winds of 74 mph or higher) are expected 
somewhere within the specified coastal area. Because severe wind 
preparedness activities become difficult once winds reach tropical 
storm force, a hurricane warning is issued 36 hours in advance of the 
anticipated onset of tropical-storm-force winds (39 to 73 mph).
    Lessons learned that are published in NUREG-1474 include the 
acknowledgement that detailed, methodical preparations should be made 
prior to the onset of hurricane force winds. The NRC staff finds the 
Turkey Point proceduralized actions are consistent with the lessons 
learned.

Recovery Exemption Immediately Following a High Wind Exemption

    The period immediately following the high wind exemption, but when 
the conditions for a UE no longer exist, may still require a recovery 
period. Also, high winds that make travel unsafe but that fall below 
the threshold of an emergency, could be present for several days. After 
the high wind condition has passed, sufficient numbers of personnel may 
not be able to access the site to relieve the sequestered individuals. 
An exemption during these conditions is consistent with the intent of 
the 10 CFR 26.207(d) exemption.

Recovery Exemption Immediately Following an Emergency Plan Exemption

    Following a declared emergency, under 10 CFR 26.207(d), due to high 
wind conditions, the site may not be accessible by sufficient numbers 
of personnel to allow relief of the sequestered individuals. Once the 
high wind conditions have passed and the UE exited, a recovery period 
might be necessary. An exemption during these circumstances is 
consistent with the intent of 10 CFR 26.207(d).
    Once Turkey Point has entered into either the high wind exemption 
or the 10 CFR 26.207(d) exemption, the licensee should not need to make 
a declaration that it is invoking the recovery exemption.

Unit Shutdown

    If a hurricane warning is in effect and the storm is projected to 
reach the site as a Category 1 or 2 hurricane, then shutdown of the 
units to hot standby (mode 3) is commenced at least two (2) hours 
before the projected onset of sustained hurricane force winds at the 
site. Both units will remain offline for the duration of the hurricane 
force winds (or restoration of reliable offsite power). If the storm is 
projected to reach the site as a category 3, 4, and 5 hurricane prior 
to landfall, specific shutdown conditions are established at least two 
(2) hours before the projected onset of sustained hurricane force winds 
at the site. Because severe weather preparations are likely commenced 
prior to the shutdown of the units, then

[[Page 804]]

this exemption will allow sufficient personnel onsite to ensure that 
the facility is properly secured for severe weather.
    Lessons learned from Hurricane Andrew, NUREG-1474, include having 
both units shutdown and on residual heat removal when the storm strikes 
so that a loss of offsite power will not jeopardize core cooling. The 
NRC staff finds the Turkey Point plan is consistent with the lessons 
learned.

Storm Crew

    Turkey Point plans to sequester sufficient individuals to staff two 
12-hour shifts of workers consisting of personnel from operations, 
maintenance, health physics, chemistry, and security, to maintain the 
safe and secure operation of the facility. The Turkey Point hurricane 
plan provides for bunking facilities that provide an accommodation for 
restorative rest for the off crew. A 12-hour break provides each 
individual with an opportunity for restorative rest. Although, the 
accommodations and potentially stressful circumstances may not be ideal 
for restorative rest, the NRC finds that these actions are consistent 
with the practice of fatigue management when limited personnel are 
available during severe weather conditions.

Maintenance

    The FPL RAI response letter dated September 2, 2010, clarified that 
the exemption request does not apply to discretionary maintenance 
activities. Suspension of work hour controls is for storm preparation 
activities and those deemed critical for plant and public safety. The 
staff finds the exclusion of discretionary maintenance from the 
exemption request to be consistent with the intent of the exemption.

Procedural Guidance

    By letter dated October 20, 2010, Turkey Point committed to 
maintain the following guidance, applicable to this exemption, in a 
site procedure:
     The conditions necessary to sequester site personnel that 
are consistent with the conditions specified in the Turkey Point 
exemption request.
     Provisions for ensuring that personnel who are not 
performing duties are provided an opportunity as well as accommodations 
for restorative rest.
     The condition for departure from the exemption is based on 
the Emergency Coordinator's determination that adequate staffing is 
available to meet the requirements of 10 CFR 26.205(c) and (d).

Returning to Work Hour Controls

    Turkey Point must return to work hour controls when the Emergency 
Coordinator determines that adequate staff is available to meet the 10 
CFR 26.205(c) and (d) requirements. Upon exiting the exemption, the 
work hour controls in Section 26.205(c) and (d) apply and the 
requirements in 26.205(b)(3) must be met.

Authorized by Law

    As stated above, this exemption would apply to the storm crew 
sequestered on site. The licensee's request states that adherence to 
all work hour controls could impede the licensee's ability to use 
whatever staff resources may be necessary to respond to a plant 
emergency and ensure that the plant maintains a safe and secure status. 
As stated above, 10 CFR 26.9 allows the NRC to grant exemptions from 
the requirements of 10 CFR 26.205(c) and (d). The NRC staff has 
determined that granting of the licensee's proposed exemption will not 
result in a violation of the Atomic Energy Act of 1954, as amended, or 
the Commission's regulations. Therefore, the exemption is authorized by 
law.

No Undue Risk to Public Health and Safety

    The underlying purposes of 10 CFR 26.205(c) and (d) are to prevent 
impairment from fatigue due to duration, frequency, or sequencing of 
successive shifts. Based on the above evaluation, no new accident 
precursors are created by utilizing whatever staff resources may be 
necessary to respond to a plant emergency and ensure that the plant 
maintains a safe and secure status; therefore, the probability of 
postulated accidents is not increased. Even though it might be 
necessary to utilize whatever staff resources during severe weather 
preparation and storm crew activation, opportunities for restorative 
sleep will be maintained. Also, the consequences of postulated 
accidents are not increased, because there is no change in the types of 
accidents previously evaluated. Therefore, there is no undue risk to 
public health and safety.

Consistent With Common Defense and Security

    The proposed exemption would allow the licensee to utilize whatever 
staff resources may be necessary to respond to a plant emergency and 
ensure that the plant maintains a safe and secure status. The licensee 
will provide sufficient numbers of management and supervision over the 
storm crew or the resources utilized during the plant emergency to 
provide additional oversight for monitoring the effects of fatigue to 
ensure that the safety and security of the facility are maintained. 
Also, during the plant emergency, opportunities for restorative sleep 
will be maintained. Therefore, the common defense and security is not 
impacted by this exemption.

Otherwise in the Public Interest

    The proposed exemption would increase the availability of the 
licensee staff. The exemption would allow licensee staff to return to 
the site and perform additional duties to ensure the plant is in a safe 
configuration during the emergency. Therefore, granting this exemption 
is otherwise in the public interest.

4.0 Conclusion

    Granting this exemption is consistent with 10 CFR 26.207(d) Plant 
Emergencies, which allows the licensee to not meet the requirements of 
10 CFR 26.205 (c) and (d) during declared emergencies as defined in the 
licensee's emergency plan. The Part 26 Statements of Consideration, 
page 17148 states that ``Plant emergencies are extraordinary 
circumstances that may be most effectively addressed through staff 
augmentation that can only be practically achieved through the use of 
work hours in excess of the limits of Sec.  26.205(c) and (d).'' The 
objective of the exemption is to ensure that the control of work hours 
do not impede a licensee's ability to use whatever staff resources may 
be necessary to respond to a plant emergency and ensure that the plant 
reaches and maintains a safe and secure status.
    The actions described in the exemption request and submitted 
procedures are consistent with the recommendations in NUREG-1474. Also 
consistent with NUREG-1474, NRC staff expects the licensee would have 
completed a reasonable amount of hurricane preparation prior to the 
need to sequester personnel, in order to minimize personnel exposure to 
high winds.
    Based on the considerations discussed above, the NRC staff has 
determined that (1) the proposed exemption is authorized by law, (2) 
there is a reasonable assurance that the health and safety of the 
public will not be endangered by the proposed exemption (3) such 
activities will be consistent with the Commission's regulations and 
guidance, and (4) the issuance of the exemption will not be contrary to 
the common defense and security or to the health and safety of the 
public. Therefore, the staff finds this request to be acceptable.

[[Page 805]]

    Pursuant to 10 CFR 51.32, the Commission has determined that the 
granting of this exemption will not have a significant effect on the 
quality of the human environment (75FR 34776; June 18, 2010). This 
exemption is effective upon issuance.

    Dated at Rockville, Maryland, this 27th day of December 2010.

    For the Nuclear Regulatory Commission.
Allen G. Howe,
Acting Director, Division of Operating Reactor Licensing, Office of 
Nuclear Reactor Regulation.
[FR Doc. 2011-10 Filed 1-5-11; 8:45 am]
BILLING CODE 7590-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.