Proposed Residential Exchange Program Settlement Agreement Proceeding (REP-12); Public Hearing and Opportunities for Public Review and Comment, 78694-78703 [2010-31622]
Download as PDF
78694
Federal Register / Vol. 75, No. 241 / Thursday, December 16, 2010 / Notices
srobinson on DSKHWCL6B1PROD with NOTICES
signatories to the settlement agreement
agree not to present evidence or
argument that either rate should be
higher than the existing rates.
The Partial Settlement Agreement
recognizes the possibility that parties to
the BP–12 rate proceeding that have not
signed the Partial Settlement Agreement
may object to the Settlement Proposal.
If any party objects to the Settlement
Proposal, BPA has the right to submit a
revised proposal. If BPA submits a
revised proposal, signatories to the
Partial Settlement Agreement may
contest any aspect of the revised
proposal. If BPA does not revise the
Settlement Proposal, and the
Administrator establishes transmission
rates consistent with the Settlement
Proposal, the signatories may not
challenge approval of the rates by the
Commission or in any judicial forum.
B. Transmission Rates
BPA is proposing four different rates
for the use of its Integrated Network
segment, four different rates for use of
intertie segments, and several other
rates for various purposes.
The four rates for use of the Integrated
Network segment are:
Formula Power Transmission (FPT–
12) rate—The FPT rate is based on the
cost of using specific types of facilities,
including a distance component for the
use of transmission lines, and is charged
on a contract demand basis.
Integration of Resources (IR–12) rate—
The IR rate is a postage stamp, contract
demand rate for the use of the Integrated
Network, similar to Point-to-Point (PTP)
service.
Network Integration Transmission
(NT–12) rate—The NT rate applies to
customers taking network integration
service under the Open Access
Transmission Tariff (OATT) and allows
customers to flexibly serve their retail
load.
Point-to-Point (PTP–12) rate—The
PTP rate is a contract demand rate that
applies to customers taking point-topoint service on BPA’s network
facilities under the OATT. It provides
customers with flexible service from
identified Points of Receipt to identified
Points of Delivery. There are separate
PTP rates for: Long-term firm service;
daily firm and non-firm service; and
hourly firm and non-firm service.
In addition to the four rates for
network use, other proposed
transmission rates include the
following:
The Southern Intertie (IS–12) and the
Montana Intertie (IM–12) rates are
contract demand rates that apply to
customers taking point-to-point service
under the OATT on the Southern
VerDate Mar<15>2010
18:00 Dec 15, 2010
Jkt 223001
Intertie and Montana Intertie. These
rates are structured similarly to the rate
for point-to-point service on network
facilities.
The Townsend-Garrison Transmission
(TGT–12) and the Eastern Intertie (IE–
12) rates are developed pursuant to the
Montana Intertie agreement.
The Use-of-Facilities (UFT–12) rate
establishes a formula for charging for
the use of a specific facility based on the
annual cost of that facility.
The Advance Funding (AF–12) rate
allows Transmission Services to collect
the capital and related costs of specific
facilities through an advance-funding
mechanism.
Other charges that may apply include:
A Delivery Charge for the use of lowvoltage delivery substations; a Power
Factor Penalty Charge; a Reservation Fee
for customers that postpone their
service commencement dates;
incremental rates for transmission
requests that require new facilities; a
penalty charge for failure to comply
with dispatch, curtailment, redispatch,
or load shedding orders; and an
Unauthorized Increase Charge for
customers that exceed their contracted
amounts.
C. Ancillary Services Rates
In this Federal Register notice BPA is
proposing rates for two ancillary
services: Scheduling, System Control,
and Dispatch Service, and Reactive
Supply and Voltage Control from
Generation Sources Service.
3. Changes to Transmission Rates and
Rate Schedules
b. Failure To Comply Penalty Charge
BPA proposes to change the rate for
the Failure to Comply Penalty Charge
from 1000 mills per kilowatthour to the
greater of 500 mills per kilowatthour or
150% of an hourly energy index in the
Pacific Northwest.
c. Integration of Resources (IR–12)—
Ratchet Demand Relief
BPA proposes to add language to the
section on Ratchet Demand Relief
providing that relief from the Ratchet
Demand is not available in the month in
which the Ratchet Demand was
established. For that month, the
customer will be assessed charges based
upon the highest hourly Scheduled
Demand Billing Factor.
d. Changes to Definitions
BPA proposes to modify the
definitions of Dynamic Schedule,
Dynamic Transfer, Daily Service,
Monthly Service, and Weekly Service.
Part V—Proposed 2012 Rate Schedules
BPA’s proposed 2012 Transmission
Rate Schedules are a part of this notice
and are available for viewing and
downloading on BPA’s Web site at
https://www.bpa.gov/corporate/ratecase/
2012/. Copies of the proposed rate
schedules also are available for viewing
in BPA’s Public Reference Room at the
BPA Headquarters, 1st Floor, 905 NE
11th Avenue, Portland, OR 97232.
Issued this 7th day of December, 2010.
Stephen J. Wright,
Administrator and Chief Executive Officer.
[FR Doc. 2010–31621 Filed 12–15–10; 8:45 am]
BILLING CODE P
a. Network Integration Transmission
(NT–12) rate
The NT rate applies to customers
taking network integration service under
the OATT and allows customers to
flexibly serve their retail load.
Transmission Services is proposing to
delete CSL and add a Short Distance
Discount (SDD) to the NT rate, applied
to the NT Base Charge. The SDD would
apply when a Customer has a resource
that: (i) Is designated as a Network
Resource in the customer’s NT Service
Agreement for at least 12 months; and
(ii) uses FCRTS facilities for less than 75
circuit miles for delivery to the
Customer’s Network Load. A designated
network resource that is a system sale
(the designated resource is not
associated with a specific generating
resource) would not qualify for the SDD.
Additionally, any designated resource
that is eligible for the SDD must be
noted as such in the NT Service
Agreement to receive the billing credit.
PO 00000
Frm 00028
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Bonneville Power Administration
[BPA File No.: REP–12]
Proposed Residential Exchange
Program Settlement Agreement
Proceeding (REP–12); Public Hearing
and Opportunities for Public Review
and Comment
Bonneville Power
Administration (BPA), Department of
Energy (DOE).
ACTION: Notice of Residential Exchange
Program Settlement Agreement
Proceeding (REP–12).
AGENCY:
BPA is conducting the 2012
Residential Exchange Program
Settlement Agreement Proceeding (REP–
12) to review the terms and conditions
of a proposed 17-year settlement of
issues regarding the implementation of
SUMMARY:
E:\FR\FM\16DEN1.SGM
16DEN1
srobinson on DSKHWCL6B1PROD with NOTICES
Federal Register / Vol. 75, No. 241 / Thursday, December 16, 2010 / Notices
the Residential Exchange Program
(REP). The REP is a statutory power
exchange program established by
section 5(c) of the Pacific Northwest
Electric Power Planning and
Conservation Act (Northwest Power
Act). The proposed settlement under
review is the 2012 REP Settlement
Agreement (2012 REP Settlement). If
adopted, BPA will include in its power
rates for FY 2012–2028 the REP benefits
stated in the proposed 2012 REP
Settlement.
In addition to reviewing the terms of
the proposed 2012 REP Settlement,
BPA’s REP–12 initial proposal will
describe BPA’s proposed
implementation of the REP for its FY
2012–2013 rates in the event the 2012
REP Settlement is not adopted. The
REP–12 initial proposal will include
studies and testimony supporting BPA’s
proposed implementation of the section
7(b)(2) rate test for the FY 2012–2013
rate period, the section 7(b)(3) surcharge
allocation, Average System Cost (ASC)
forecasts, and the amount of refunds to
be provided to BPA customers
overcharged during the FY 2002–2006
rate period, (i.e., Lookback repayments).
If, at the conclusion of the REP–12
proceeding the Administrator decides
not to adopt the 2012 REP Settlement,
BPA will incorporate into the BP–12
rate proceeding the studies, testimony,
and documentation associated with the
section 7(b)(2) rate test, the section
7(b)(3) surcharge allocation, ASC
forecasts, and Lookback repayment and
use such studies and documentation in
establishing the BP–12 rates.
DATES: Anyone wishing to become a
party to the REP–12 proceeding must
provide written notice, via U.S. Mail or
electronic mail, which must be received
by BPA no later than 3 p.m. on
December 23, 2010.
The REP–12 proceeding begins with a
prehearing conference at 9:00 a.m. on
December 17, 2010, in the BPA Rates
Hearing Room, 2nd Floor, 911 NE 11th
Avenue, Portland, Oregon 97232.
ADDRESSES: 1. Petitions to intervene
should be directed to: Hearing Clerk—
L–7, Bonneville Power Administration,
905 NE 11th Avenue, Portland, Oregon
97232, or may be e-mailed to
rateclerk@bpa.gov. In addition, copies
of the petition must be served
concurrently on BPA’s General Counsel
and directed to Mr. Kurt R. Casad,
Office of General Counsel, 905 NE 11th
Avenue, Portland, Oregon 97232, or via
e-mail to krcasad@bpa.gov (see section
III.A. for more information regarding
interventions).
2. Written comments by participants
should be submitted to the Public
VerDate Mar<15>2010
18:00 Dec 15, 2010
Jkt 223001
Engagement Office, DKE–7, Bonneville
Power Administration, P.O. Box 14428,
Portland, Oregon 97293. Participants
may also submit comments by e-mail at:
https://www.bpa.gov/comment. BPA
requests that all comments and
documents intended to be part of the
Official Record in this rate proceeding
contain the designation REP–12 in the
subject line.
FOR FURTHER INFORMATION CONTACT: Ms.
Heidi Y. Helwig, DKC–7, Public Affairs
Specialist, Bonneville Power
Administration, P.O. Box 3621,
Portland, Oregon 97208; by phone toll
free at 1–800–622–4520; or via e-mail to
hyhelwig@bpa.gov.
Responsible Official: Mr. Raymond D.
Bliven, Power Rates Manager, is the
official responsible for the development
of BPA’s power rates.
SUPPLEMENTARY INFORMATION:
Table of Contents
Part I. Introduction
Part II. Procedures and Scope of Hearing
Part III. Public Participation in REP–12
Part IV. Background of REP Litigation
Part V. Summary of Proposal and Description
of Major Studies
Part VI. Proposed 2012 REP Settlement
Agreement
Part I. Introduction
BPA is conducting an evidentiary
hearing, Docket No. REP–12, to review
the terms and conditions of a proposed
17-year settlement of issues regarding
the implementation of the Residential
Exchange Program (REP). The REP is a
statutory power exchange program
established by section 5(c) of the
Northwest Power Act (Act). See 16
U.S.C. 839c(c). The proposed settlement
under review, the 2012 REP Settlement,
reflects the efforts of a broad group of
regional parties to resolve litigation over
BPA’s implementation of the REP
through a legally sustainable and
equitable settlement agreement. If
adopted by the Administrator, BPA will
include in its power rates for FY 2012–
2028 the REP benefits stated in the
proposed 2012 REP Settlement.
In addition to reviewing the terms of
the proposed 2012 REP Settlement,
BPA’s REP–12 initial proposal will
describe BPA’s proposed
implementation of the REP for its FY
2012–2013 rates in the event the 2012
REP Settlement is not adopted. The
REP–12 initial proposal will include
studies and testimony supporting BPA’s
proposed implementation of the section
7(b)(2) rate test, the section 7(b)(3)
surcharge allocation, ASC forecasts, and
Lookback repayments for the FY 2012–
2013 rate period. Any party wishing to
PO 00000
Frm 00029
Fmt 4703
Sfmt 4703
78695
contest BPA’s proposed implementation
of the section 7(b)(2) rate test, allocation
of section 7(b)(3) surcharge amounts,
development of the ASC forecasts, or
determination of Lookback refund
amounts must raise such arguments in
the REP–12 proceeding. At the same
time BPA is reviewing the proposed
2012 REP Settlement in the REP–12
proceeding, BPA is separately
conducting a BP–12 rate proceeding to
establish power rates for FY 2012–2013.
If, at the conclusion of the REP–12
proceeding, the Administrator decides
not to adopt the 2012 REP Settlement,
BPA will incorporate into the BP–12
rate proceeding the studies, testimony,
and documentation associated with the
section 7(b)(2) rate test, the section
7(b)(3) surcharge allocation, ASC
forecasts, and Lookback repayment, and
use such studies and documentation in
establishing the BP–12 rates.
Part II. Procedures and Scope of
Hearing
A. Procedures Governing the REP–12
Proceeding
Because the proposed 2012 REP
Settlement includes features that are
directly related to BPA’s rates and
ratemaking, the proposed Settlement
will be evaluated under the procedural
terms of section 7(i) of the Act, 16
U.S.C. 839e(i). These procedures
include, among other things:
Publication of a notice of the proposed
rates in the Federal Register; one or
more hearings conducted as
expeditiously as practicable by a
Hearing Officer; public opportunity to
provide both oral and written views
related to the proposed rates;
opportunity to offer refutation or
rebuttal of submitted material; and a
decision by the Administrator based on
the record. This REP–12 proceeding is
governed by § 1010 of BPA’s Rules of
Procedure Governing Rate Hearings, 51
FR 7611 (1986) (BPA Hearing
Procedures). These procedures
implement the statutory section 7(i)
requirements.
Section 1010.7 of BPA’s Hearing
Procedures prohibits ex parte
communications. The ex parte rule
applies to all BPA and DOE employees
and contractors. Except as provided
below, any communications with BPA
and/or DOE personnel regarding BPA’s
rate proceeding by other Executive
Branch agencies, Congress, existing or
potential BPA customers (including
Tribes), and nonprofit or public interest
groups are considered outside
communications and are subject to the
ex parte rule. The general rule does not
apply to communications relating to: (1)
E:\FR\FM\16DEN1.SGM
16DEN1
78696
Federal Register / Vol. 75, No. 241 / Thursday, December 16, 2010 / Notices
Matters of procedure only (the status of
the rate proceeding, for example); (2)
exchanges of data in the course of
business or under the Freedom of
Information Act; (3) requests for factual
information; (4) matters for which BPA
is responsible under statutes other than
the ratemaking provisions; or (5) matters
which all parties agree may be made on
an ex parte basis. The ex parte rule
remains in effect until the
Administrator’s Final Record of
Decision (ROD) is issued.
The Flood Control Act of 1944, 16
U.S.C. 825s, the Federal Columbia River
Transmission System Act, 16 U.S.C.
838, and the Northwest Power Act, 16
U.S.C. 839, provide guidance regarding
BPA ratemaking. The Northwest Power
Act requires BPA to set rates that are
sufficient to recover, in accordance with
sound business principles, the cost of
acquiring, conserving and transmitting
electric power, including amortization
of the Federal investment in the Federal
Columbia River Power System (FCRPS)
over a reasonable period of years, and
certain other costs and expenses
incurred by the Administrator.
BPA’s proposal, study documentation,
and the proposed 2012 REP Settlement
will be available for examination
beginning December 17, 2010, on BPA’s
Web site at https://www.bpa.gov/
corporate/ratecase/2012/rep-12.cfm.
Hard copies of these documents will be
available beginning December 17, 2010,
at BPA’s Public Information Center,
BPA Headquarters Building, 1st Floor,
905 NE. 11th Avenue, Portland, Oregon.
A formal evidentiary rate hearing will
be conducted that is open to rate
proceeding parties. Interested parties
that previously intervened in BPA’s BP–
12 rate proceeding must also file
petitions to intervene in order to take
part in the REP–12 formal hearing. A
proposed schedule for the REP–12
proceeding is stated below. A Hearing
Officer will establish a final schedule at
the prehearing conference.
Intervention Deadline .............
srobinson on DSKHWCL6B1PROD with NOTICES
Prehearing/BPA Direct Case
Clarification ............................
Motions to Strike ....................
Data Request Deadline ..........
Answers to Motions to Strike
Data Response Deadline .......
Parties File Direct Case .........
Clarification ............................
Motions to Strike ....................
Data Request Deadline ..........
Answers to Motions to Strike
Data Response Deadline .......
Close of Participant Comments.
VerDate Mar<15>2010
18:00 Dec 15, 2010
December
23.
December
17.
January 4–7.
January 11.
January 11.
January 18.
January 18.
February 8.
February 14–
15.
February 22.
February 22.
March 1.
March 1.
March 8.
Jkt 223001
Litigants File Rebuttal ............
Clarification ............................
Motions to Strike ....................
Data Request Deadline ..........
Answers to Motions to Strike
Data Response Deadline .......
Cross-Examination .................
Initial Briefs Filed ...................
Oral Argument ........................
Draft ROD Issued ..................
Briefs on Exceptions ..............
Final ROD—Final Studies ......
March 8.
March 14–15.
March 17.
March 17.
March 25.
March 25.
March 28–
April 1.
April 25.
May 12.
May 23.
June 6.
June 27.
No field hearings will be conducted in
this proceeding.
B. Scope of the REP–12 Proceeding
This section provides guidance to the
Hearing Officer regarding the matters
within the scope of the REP–12
proceeding and the matters not within
the scope of this proceeding.
1. Matters Within the Scope of This
Proceeding
a. Proposed 2012 REP Settlement
All issues related to BPA’s analysis,
methodology, or review of the proposed
2012 REP Settlement, including any
issues related to the models developed
by BPA to evaluate the 2012 REP
Settlement, are expressly within the
scope of this proceeding. Parties
wishing to challenge any aspect of the
proposed 2012 REP Settlement,
including but not limited to any term of
the proposed Settlement or whether
BPA should adopt the Settlement, must
raise such arguments in this proceeding.
b. Section 7(b)(2) Rate Test
Implementation
All issues related to BPA’s
implementation, interpretation, and
forecast of the section 7(b)(2) rate test
are within the scope of this proceeding.
Parties wishing to challenge any aspect
of the implementation of the section
7(b)(2) rate test for either the 2012 REP
Settlement implementation period (FY
2012–2028) or the BP–12 rate period
(FY 2012–2013) must raise such
arguments in this proceeding.
c. Section 7(b)(3) Surcharge
Implementation
All issues related to BPA’s
implementation, interpretation, and
forecast of the section 7(b)(3)
reallocations or surcharges are within
the scope of this proceeding. Parties
wishing to challenge any aspect of the
implementation of section 7(b)(3) for
either the 2012 REP Settlement
implementation period (FY 2012–2028)
or the BP–12 rate period (FY 2012–
2013) must raise such arguments in this
proceeding.
PO 00000
Frm 00030
Fmt 4703
Sfmt 4703
d. Lookback Assumptions
All issues related to BPA’s
implementation, determination,
recovery, and repayment of Lookback
Amounts are within the scope of this
proceeding. Parties wishing to challenge
any aspect of BPA’s Lookback recovery
or repayment for either the 2012 REP
Settlement implementation period (FY
2012–2028) or the BP–12 rate period
(FY 2012–2013) must raise such
arguments in this proceeding.
e. ASC Forecasts
Except as provided below in section
II.B.2.h, all issues related to BPA’s
forecast of utilities’ ASCs for the BP–12
rate test period (FY 2014–2017) and the
2012 REP Settlement implementation
period (FY 2012–2028) are within the
scope of this proceeding. Parties
wishing to challenge any aspect of
BPA’s ASC forecasts for these periods
must raise their arguments in this
proceeding. Challenges to the ASCs
determined in the Draft and Final ASC
reports for FY 2012–2013 are expressly
excluded from the scope of this
proceeding. See Section II.B.2.h.
2. Matters Not Within the Scope of This
Proceeding
a. BP–12 Rate Proceeding Issues
As noted above, BPA is conducting a
rate proceeding to establish wholesale
power and transmission rates for FY
2012–2013 (BP–12) at the same time
BPA is conducting the REP–12
proceeding. Although some of the
information developed in the BP–12 rate
proceeding will be used in the models
in the REP–12 proceeding, parties may
not raise arguments or issues with such
data in the REP–12 proceeding. Instead,
such arguments or issues should be
raised in the BP–12 rate proceeding if
and to the extent such issues are within
the scope of that proceeding. Pursuant
to section 1010.3(f) of BPA’s Hearing
Procedures, the Administrator directs
the Hearing Officer to exclude from the
record all argument, testimony, or other
evidence that seeks in any way to
address the appropriateness or
reasonableness of any issue being
addressed in the BP–12 rate proceeding.
b. Program Cost Estimates
BPA began its 2010 Integrated
Program Review (IPR) process in May
2010. The IPR process is designed to
allow people interested in BPA’s
program levels an opportunity to review
and comment on all of BPA’s expense
and capital spending level estimates in
the same forum prior to the use of those
estimates in setting rates. Concurrent
with the IPR, BPA held regional
E:\FR\FM\16DEN1.SGM
16DEN1
srobinson on DSKHWCL6B1PROD with NOTICES
Federal Register / Vol. 75, No. 241 / Thursday, December 16, 2010 / Notices
conversations about risk mitigation and
debt management practices.
The 2010 IPR focused on FY 2012 and
2013 program levels for BPA’s Power
Services and Transmission Services as
well as a review of FY 2011 program
levels. BPA held 19 technical
workshops and two general manager
meetings at which proposed spending
levels were presented for each of BPA’s
programs. BPA carefully reviewed and
considered the 26 written comments
and numerous oral comments on FY
2012 and 2013 program levels that were
provided during this public process.
On October 27, 2010, BPA issued a
Final Close-Out Letter and
accompanying final report for the IPR,
which summarizes the comments
received and outlines BPA’s responses.
The report also summarizes comments
and BPA’s responses on the regional
conversations about risk mitigation and
debt management. In the Final CloseOut Letter and report, BPA established
the program level cost estimates for both
power and transmission rates that are
used in the BP–12 and REP–12 Initial
Proposals. BPA does not anticipate
additional public review of proposed
spending levels. However, an
abbreviated IPR process may be held if
conditions warrant. BPA would conduct
this process separately from the REP–12
and BP–12 proceedings to share updates
and solicit feedback from customers and
constituents before the final program
levels are incorporated into BPA’s final
rates. BPA’s spending levels for
investments and expenses are not
determined or subject to review in the
REP–12 or BP–12 proceedings.
Pursuant to section 1010.3(f) of BPA’s
Hearing Procedures, the Administrator
directs the Hearing Officer to exclude
from the record all argument, testimony,
or other evidence that seeks in any
manner to address the appropriateness
or reasonableness of the Administrator’s
decisions on cost and spending levels.
If and to the extent that any reexamination of spending levels is
necessary, such re-examination will
occur outside of the REP–12 and BP–12
proceedings. This exclusion does not
extend to portions of BPA’s revenue
requirements related to REP benefits,
Lookback payments, or interest on
Lookback payments. The Administrator
also directs the Hearing Officer to
exclude argument and evidence
regarding BPA’s debt management
practices and policies.
c. Regional Dialogue Policy Decisions
BPA’s Subscription contracts expire
on September 30, 2011, at the end of the
current rate period. BPA previously
engaged customers and interested
VerDate Mar<15>2010
18:00 Dec 15, 2010
Jkt 223001
stakeholders in an extensive Regional
Dialogue process that led to new power
sales contracts. BPA issued its LongTerm Regional Dialogue Final Policy
and ROD on July 19, 2007; its LongTerm Regional Dialogue Contract Policy
and ROD on October 31, 2008; the
Tiered Rate Methodology and ROD on
November 10, 2008; and the Tiered Rate
Methodology Supplemental ROD on
September 2, 2009. On or about
December 1, 2008, BPA and its
customers signed new power sales
contracts under which the customers
will purchase Federal power for the FY
2012–2028 period. Several aspects of
the Regional Dialogue process are still
ongoing, such as establishing customer
contract high water marks and contract
demand quantities, and these processes
and decisions are outside the scope of
the REP–12 proceeding.
Pursuant to § 1010.3(f) of BPA’s
Hearing Procedures, the Administrator
hereby directs the Hearing Officer to
exclude from the record all argument,
testimony, or other evidence that seeks
in any way to address the
appropriateness or reasonableness of
BPA’s decisions made in the Long-Term
Regional Dialogue Final Policy ROD,
Long-Term Regional Dialogue Contract
Policy ROD, the Tiered Rate
Methodology ROD, and the Tiered Rate
Methodology Supplemental ROD.
d. Tiered Rate Methodology (TRM)
BPA previously established the TRM
in a section 7(i) rate hearing. The issues
being examined in the REP–12
proceeding are not governed by the
TRM. Modifications to the TRM are not
within the scope of this proceeding.
Pursuant to § 1010.3(f) of BPA’s Hearing
Procedures, the Administrator hereby
directs the Hearing Officer to exclude
from the record all argument, testimony,
or other evidence that seeks in any way
to propose to revise the TRM developed
by BPA.
e. Service to the Direct Service
Industries (DSIs)
The manner and method by which
BPA could provide service or financial
payments to its DSI customers were
evaluated in Pacific Northwest
Generating Cooperative, et al., v.
Bonneville Power Administration, 580
F.3d 792 (9th Cir. 2008) (PNGC I) and
Pacific Northwest Generating
Cooperative, et al., v. Bonneville Power
Administration, 590 F.3d 1065 (9th Cir.
2010) (PNGC II). In BPA’s BP–12 rate
proceeding, BPA has assumed that it
will continue to serve Alcoa, Inc.
(Alcoa) as well as Port Townsend Paper
Corporation (Port Townsend) during FY
2012–2013. BPA’s decisions to serve the
PO 00000
Frm 00031
Fmt 4703
Sfmt 4703
78697
DSIs, along with the method and level
of service to be provided DSIs in the FY
2012–2013 rate period, will not be
determined in this proceeding.
Pursuant to § 1010.3(f) of BPA’s
Hearing Procedures, the Administrator
directs the Hearing Officer to exclude
from the record all argument, testimony,
or other evidence that seeks in any way
to revisit the appropriateness or
reasonableness of BPA’s decisions
regarding the service to the DSIs,
including BPA’s decision to offer a
contract and the method or level of such
service.
f. Potential Environmental Impacts
Environmental impacts are addressed
in a concurrent National Environmental
Policy Act (NEPA) process. Pursuant to
§ 1010.3(f) of BPA’s Hearing Procedures,
the Administrator directs the Hearing
Officer to exclude from the record all
argument, testimony, or other evidence
that seeks in any way to address the
potential environmental impacts of the
rates being developed in this rate
proceeding.
g. Average System Cost Methodology
Section 5(c) of the Northwest Power
Act established the REP, which provides
benefits to residential and small-farm
consumers of Pacific Northwest utilities
based, in part, on a utility’s ‘‘average
system cost’’ (ASC) of resources. Section
5(c)(7) of the Act requires the
Administrator to consult with regional
interests to develop an ASC
Methodology (ASCM). BPA uses the
ASCM to calculate utilities’ ASCs. On
September 4, 2009, the Federal Energy
Regulatory Commission (Commission)
granted final approval of BPA’s 2008
ASCM. The 2008 ASCM is not subject
to challenge or review in a section 7(i)
proceeding.
Pursuant to § 1010.3(f) of BPA’s
Hearing Procedures, the Administrator
hereby directs the Hearing Officer to
exclude from the record all argument,
testimony, or other evidence that seeks
in any way to address the
appropriateness or reasonableness of the
2008 ASCM.
h. Average System Cost Review
Processes
To receive REP benefits for FY 2012–
2013, utilities must file proposed ASCs
with BPA pursuant to the terms and
conditions of the 2008 ASCM. These
filings are reviewed by BPA staff and
other interested parties in ASC review
processes, which are separate
administrative proceedings conducted
by BPA under the terms of the 2008
ASCM. In the review processes, BPA
staff and other parties evaluate the ASCs
E:\FR\FM\16DEN1.SGM
16DEN1
78698
Federal Register / Vol. 75, No. 241 / Thursday, December 16, 2010 / Notices
filed by participating utilities for
conformance with the requirements of
the 2008 ASCM. At the conclusion of
the processes, BPA issues ASC Reports,
which formally establish the utilities’
ASCs for the Exchange Period, which
coincides with BPA’s rate period.
On June 1, 2010, ten utilities filed
proposed ASCs with BPA for FY 2012–
2013. One utility subsequently
withdrew its ASC filing. BPA staff and
other parties are currently reviewing the
remaining nine filings in the ASC
review processes. Once these ASC
review processes are complete, and BPA
has issued final ASC Reports, BPA will
incorporate the final ASCs into the
administrative record of the REP–12
proceeding. Although these ASC
determinations provide important
information for setting BPA’s rates, they
are not made in section 7(i) hearings.
Parties intending to challenge BPA’s
draft or final ASC determinations for FY
2012–2013 must raise such issues in the
ASC review processes according to the
procedures established in the 2008
ASCM.
Pursuant to § 1010.3(f) of BPA’s
Hearing Procedures, the Administrator
hereby directs the Hearing Officer to
exclude from the record all argument,
testimony, or other evidence that seeks
in any way to address BPA’s draft or
final ASC determinations for FY 2012–
2013.
srobinson on DSKHWCL6B1PROD with NOTICES
i. Contract High Water Mark (CHWM)
Process
Under the Tiered Rate Methodology
(TRM), BPA will establish both CHWMs
and FY 2012–2013 Rate Period High
Water Mark (RHWMs) for public agency
customers that signed contracts for firm
requirements power service at tiered
rates, referred to as CHWM contracts.
The CHWMs and RHWMs will be
established in the CHWM Process,
which will occur mainly in Spring 2011.
In this process, BPA will establish the
maximum planned amount of power a
customer is eligible to purchase at Tier
1 rates during the rate period. The
CHWM Process provides customers an
opportunity to review, comment, and, if
necessary, challenge BPA’s
determinations regarding certain CHWM
and RHWM determinations.
Pursuant to § 1010.3(f) of BPA’s
Hearing Procedures, the Administrator
hereby directs the Hearing Officer to
exclude from the record all argument,
testimony, or other evidence that seeks
in any way to address BPA’s
determination of a customer’s CHWM or
FY 2012–2013 RHWM.
VerDate Mar<15>2010
18:00 Dec 15, 2010
Jkt 223001
Part III. Public Participation in REP–12
comments, views, opinions, and
information from ‘‘participants,’’ who
may submit comments without being
subject to the duties of, or having the
privileges of, parties. Participants’
written comments will be made part of
the official record and considered by the
Administrator. Participants are not
entitled to participate in the prehearing
conference; may not cross-examine
parties’ witnesses, seek discovery, or
serve or be served with documents; and
are not subject to the same procedural
requirements as parties. BPA customers
whose rates are subject to this
proceeding, or their affiliated customer
groups, may not submit participant
comments. Members or employees of
organizations that have intervened in
the rate proceeding may submit general
comments as participants but may not
use the comment procedures to address
specific issues raised by their intervenor
organizations.
Written comments by participants
will be included in the record if they are
received by March 8, 2011. Written
views, supporting information,
questions, and arguments should be
submitted to the address listed in the
ADDRESSES section of this Notice.
Entities or individuals become parties
to the proceeding by filing petitions to
intervene, which must state the name
and address of the entity or person
requesting party status and the entity’s
or person’s interest in the hearing.
BPA’s customers and affiliated customer
groups will be granted intervention
based on petitions filed in conformance
with BPA’s Hearing Procedures. Other
petitioners must explain their interests
in sufficient detail to permit the Hearing
Officer to determine whether the
petitioners have a relevant interest in
the hearing. Pursuant to Rule 1010.1(d)
of BPA’s Hearing Procedures, BPA
waives the requirement in Rule
1010.4(d) that an opposition to an
intervention petition be filed and served
24 hours before the prehearing
conference. The time limit for opposing
a timely intervention will be established
at the prehearing conference. Any party,
including BPA, may oppose a petition
for intervention. All petitions will be
ruled on by the Hearing Officer. Late
interventions are strongly disfavored.
Opposition to an untimely petition to
intervene must be filed and received by
BPA within two days after service of the
petition.
A. Distinguishing Between
‘‘Participants’’ and ‘‘Parties’’
BPA distinguishes between
‘‘participants in’’ and ‘‘parties to’’ the
hearings. Apart from the formal hearing
process, BPA will receive written
B. Developing the Record
The hearing record will include,
among other things, the transcripts of
the hearing, written evidence and
argument entered into the record by
BPA and the parties, written comments
C. The National Environmental Policy
Act
BPA is in the process of assessing the
potential environmental effects that
could result from implementation of the
proposed 2012 REP Settlement,
consistent with NEPA requirements.
BPA is reviewing this proposal for
consistency with BPA’s Business Plan
Environmental Impact Statement
(Business Plan EIS), completed in June
1995 (DOE/EIS–0183). This policy-level
EIS evaluates the environmental
impacts of a range of business plan
alternatives for BPA and is intended to
support a wide range of subsequent BPA
business-related decisions. In the
Record of Decision for the Business Plan
ROD (Business Plan ROD, August 1995),
the BPA Administrator adopted the
Market-Driven Alternative from the
Business Plan EIS. This alternative was
selected because, among other reasons,
it allows BPA to: (1) Recover costs
through rates; (2) competitively market
BPA’s products and services; (3)
develop rates that meet customer needs
for clarity and simplicity; (4) continue
to meet BPA’s legal mandates; and (5)
avoid adverse environmental impacts.
In April 2007, BPA completed a
Supplement Analysis confirming the
Business Plan EIS’s environmental
analysis in light of current regional
conditions and BPA’s current business
practices. The Business Plan EIS and
ROD thus continue to provide a sound
basis for making determinations under
NEPA concerning BPA’s businessrelated decisions.
BPA will document its environmental
evaluation for the proposed 2012 REP
Settlement as part of the Administrator’s
Record of Decision that will be prepared
for this proposal. During the public
review and comment period for the
proposed 2012 REP Settlement, persons
interested in submitting comments
regarding its potential environmental
effects may do so by submitting
comments to Katherine Pierce, NEPA
Compliance Officer, KEC–4, Bonneville
Power Administration, 905 NE. 11th
Avenue, Portland, OR 97232. Any such
comments received by the Close of
Participant Comments deadline
identified in Part II.A will be considered
by BPA’s NEPA compliance staff in the
NEPA evaluation that will be prepared
for this proposal.
PO 00000
Frm 00032
Fmt 4703
Sfmt 4703
E:\FR\FM\16DEN1.SGM
16DEN1
Federal Register / Vol. 75, No. 241 / Thursday, December 16, 2010 / Notices
from participants, and other material
accepted into the record by the Hearing
Officer. The Hearing Officer will then
review the record and certify the record
to the Administrator.
The Administrator will develop the
Final ROD in the REP–12 proceeding
based on the record and such other
materials and information as may have
been submitted to or developed by the
Administrator. The Administrator will
serve copies of the Final ROD on all
parties. BPA will incorporate the
Administrator’s final decision in this
proceeding into its BP–12 Final Rate
Proposal.
Part IV. Background of REP Litigation
srobinson on DSKHWCL6B1PROD with NOTICES
A. Background on the REP
1. Section 5(c) of the Northwest Power
Act
As noted previously, section 5(c) of
the Northwest Power Act established
the REP. 16 U.S.C. 839c(c)(1). Under the
REP, any Pacific Northwest utility may
sell power to BPA at the utility’s ASC.
A utility’s ASC is determined in
accordance with an ASC Methodology
that BPA develops pursuant to the
requirements in the Act. In calculating
a utility’s ASC, section 5(c)(7) of the Act
mandates that BPA exclude from ASC
the cost of resources in an amount
sufficient to serve a new large single
load (NLSL), the cost of additional
resources in an amount sufficient to
meet any additional load outside the
region occurring after the effective date
of the Act, and any costs of any
generating facility which is terminated
prior to initial commercial operation. 16
U.S.C. 839c(c)(7)(A)–(C).
When a utility offers to sell its power
to BPA at its ASC, BPA must purchase
such power and, in return, sell an
equivalent amount of power to the
utility at BPA’s rate for purchases under
the REP, known as the ‘‘PF Exchange
rate.’’ The PF Exchange rate is
developed in accordance with section 7
of the Northwest Power Act. The
amount of power that is bought and sold
under the REP is equal to the utility’s
qualified residential and small farm
load (exchange load). Because the
purchase and sale between BPA and the
utility involves the same amount of
power and is simultaneous, in almost all
instances no actual power is bought or
sold under the REP. Instead, the REP is
generally implemented as a paper
transaction where the net difference
between the utility’s ASC and BPA’s PF
Exchange rate is multiplied by the
utility’s exchange load and converted
into a cash payment to the utility. The
utility is required by law to pass these
payments onto its residential and small
VerDate Mar<15>2010
18:00 Dec 15, 2010
Jkt 223001
farm consumers. 16 U.S.C. 839c(c)(3).
The REP is implemented through a
Residential Purchase and Sale
Agreement (RPSA) executed by BPA
and the utility. The REP is intended to
provide regional residential and small
farm consumers a form of access to the
power produced by the FCRPS.
Although intended primarily for the
benefit of consumers located in
investor-owned utilities’ (IOUs) service
areas, any utility within the region may
participate.
2. Section 7(b)(2) of the Northwest
Power Act and the PF Exchange Rate
The PF Exchange rate is the rate at
which BPA ‘‘sells’’ power to utilities
participating in the REP. Section 7 of
the Act prescribes the manner in which
this rate is set. Under section 7(b)(1),
BPA establishes the PF Exchange rate in
much the same way BPA develops its
PF Public rate. See 16 U.S.C. 839e(b)(1).
Section 7(b)(2) of the Act, however,
requires BPA to perform a ‘‘rate test’’ to
determine whether the PF Public rate
charged to BPA’s consumer-owned
utility customers (COUs) under the Act
would be greater than a rate developed
under five specific assumptions stated
in section 7(b)(2). These five
assumptions are:
(A) The [COUs’] general requirements
had included during such five-year
period the direct service industrial
customer loads which are (i) served by
the Administrator, and (ii) located
within or adjacent to the geographic
service boundaries of such public
bodies and cooperatives;
(B) [the COUs] were served, during
such five-year period, with Federal base
system resources not obligated to other
entities under contracts existing as of
December 5, 1980 (during the remaining
term of such contracts) excluding
obligations to direct service industrial
customer loads included in
subparagraph (A) of this paragraph;
(C) No purchases or sales by the
Administrator as provided in [section
5(c)] of this section were made during
such five-year period;
(D) All resources that would have
been required, during such five-year
period, to meet remaining general
requirements of the public body,
cooperative and Federal agency
customers (other than requirements met
by the available Federal base system
resources determined under
subparagraph (B) of this paragraph)
were (i) purchased from such customers
by the Administrator pursuant to
section 839d of this title, or (ii) not
committed to load pursuant to section
839c(b) of this section and were the
least expensive resources owned or
PO 00000
Frm 00033
Fmt 4703
Sfmt 4703
78699
purchased by public bodies or
cooperatives; and any additional needed
resources were obtained at the average
cost of all other new resources acquired
by the Administrator; and
(E) The quantifiable monetary savings,
during such five-year period, to public
body, cooperative and Federal agency
customers resulting from (i) reduced
public body and cooperative financing
costs as applied to the total amount of
resources, other than Federal base
system resources, identified under
subparagraph (D) of this paragraph, and
(ii) reserve benefits as a result of the
Administrator’s actions under this
chapter were not achieved.
If BPA’s proposed rates developed
under section 7(b)(1) are greater than the
rates calculated under the section
7(b)(2) assumptions, BPA must reduce
the costs included in the 7(b)(1) rate
charged to COUs by assessing a
surcharge pursuant to section 7(b)(3) to
‘‘all other power sold by the
Administrator to all customers.’’ 16
U.S.C. 839e(b)(3). One of the rates
assessed this surcharge is the PF
Exchange rate. Application of the 7(b)(3)
surcharge to the PF Exchange rate has
the effect of increasing the level of the
PF Exchange rate and reducing the
amount of REP benefits paid by COUs
in their PF Public rates.
B. History of the REP
The history of BPA’s implementation
of the REP is marked by controversy and
litigation. Shortly after the passage of
the Northwest Power Act in 1980, BPA
and regional parties negotiated the
terms of BPA’s first ASC Methodology
(1981 ASC Methodology) and the
provisions of 20-year RPSAs that would
be used to implement the REP. After
three years of experience under the 1981
ASC Methodology, BPA’s DSI and COU
customers requested that a consultation
process be held to consider revisions to
the 1981 ASC Methodology. BPA
granted the requests and commenced a
consultation process in 1983. In the
consultation, BPA determined that the
source of data used in the 1981 ASC
Methodology did not include sufficient
detail to ensure that BPA was excluding
terminated plant costs as required by
section 5(c)(7) of the Northwest Power
Act. Consequently, BPA proposed to
revise the ASC Methodology by
expanding the procedures used to
review ASCs and excluding certain
costs that BPA determined were too
difficult to accurately monitor. The
revised ASC Methodology was
completed in 1984 and received
approval from the Commission shortly
thereafter.
E:\FR\FM\16DEN1.SGM
16DEN1
78700
Federal Register / Vol. 75, No. 241 / Thursday, December 16, 2010 / Notices
srobinson on DSKHWCL6B1PROD with NOTICES
BPA’s IOU customers vigorously
opposed the changes to the 1981 ASC
Methodology. Eight IOUs and four State
regulatory agencies filed petitions with
the United States Court of Appeals for
the Ninth Circuit challenging the
Commission’s final approval of the
revised ASC Methodology (1984 ASC
Methodology). See PacifiCorp v. FERC,
795 F.2d 816 (9th Cir. 1986)
(PacifiCorp). In PacifiCorp, the Court
affirmed the Commission’s approval and
BPA’s decision to adopt the 1984 ASC
Methodology. Id. Even though the 1984
ASC Methodology was sustained by the
Court, litigation continued over BPA’s
implementation of the ASC
Methodology. Dozens of BPA’s ASC
determinations were contested before
the Commission, several of which were
ultimately resolved by the Court. See
Wash. Util. & Transp. Comm’n v. FERC,
26 F.3d 935 (9th Cir. 1994); CP Nat.
Corp. v. Bonneville Power Admin., 928
F.2d 905 (9th Cir. 1991).
Due to the burdensome, expensive
and contentious nature of implementing
the 1984 ASC Methodology, BPA and
regional exchanging utilities began
negotiating settlements of the
implementation of the REP. Throughout
the late 1980s and into the 1990s, BPA
and regional exchanging utilities
entered into multiple REP settlements.
By the late 1990s, BPA and five of the
six exchanging IOUs executed REP
settlement agreements that resolved the
implementation of the REP until June
30, 2001.
C. The 2000 REP Settlement Agreements
In early 1996, the governors of Idaho,
Montana, Oregon and Washington
convened the Comprehensive Review of
the Northwest Energy System. The goal
of the review was to develop
recommendations for changes in the
region’s electric utility industry,
focusing on BPA, through an open
public process involving a broad crosssection of regional interests. In
December 1996, after over a year of
intense study, the Comprehensive
Review Steering Committee released its
Final Report. The Final Report proposed
a subscription system for purchasing
specified amounts of power from BPA at
cost with incentives for customers to
take longer-term subscriptions
(Subscription). In connection with its
Subscription proposal, the Steering
Committee encouraged BPA and other
parties in the region to explore a
settlement of the REP with the region’s
IOUs for the FY 2002–2011 period.
In response to the Steering
Committee’s recommendation, BPA and
regional IOUs developed the 2000
Residential Exchange Program
VerDate Mar<15>2010
18:00 Dec 15, 2010
Jkt 223001
Settlement Agreements (2000 REP
Settlement Agreements). Under the 2000
REP Settlement Agreements, the IOUs
agreed to forgo their participation in the
traditional REP for a period of ten years
(FY 2002–2011) in return for certain
payments and deliveries of firm power
from BPA. To recover the costs of the
2000 REP Settlement Agreements for the
FY 2002–2006 rate period, BPA
proposed in its WP–02 Wholesale Power
Rate Proceeding to allocate a significant
portion of the costs of the 2000 REP
Settlement Agreements to the rates
charged to COUs.
D. Challenges to the 2000 REP
Settlements: The Ninth Circuit’s
Decisions in Portland General Electric v.
BPA, Golden Northwest Aluminum v.
BPA, and Snohomish PUD v. BPA
In January of 2001, certain parties
filed petitions with the Ninth Circuit
challenging BPA’s statutory authority to
implement the REP through the 2000
REP Settlement Agreements. In
September of 2003, following final
Commission confirmation and approval
of BPA’s WP–02 rates, parties also filed
challenges to BPA’s decision to recover
the costs of the 2000 REP Settlement
Agreements from the PF rates without
BPA’s traditional manner of
implementing the 7(b)(2) rate test.
While these challenges were pending
before the Court, BPA commenced a
new rate proceeding, the 2007
Wholesale Power Rate Proceeding, to
establish rates for the FY 2007–2009
period (WP–07 rates). In the WP–07
rates, BPA again allocated a significant
portion of the costs of the 2000 REP
Settlement Agreements to the PF rates.
The WP–07 rates were filed with the
Commission on July 28, 2006, and
received interim approval from the
Commission on September 21, 2006.
On May 3, 2007, before final
Commission approval of BPA’s WP–07
rates, the Court issued two decisions in
the pending challenges to the 2000 REP
Settlement Agreements and the thenexpired WP–02 rates. In Portland
General Electric v. Bonneville Power
Admin., 501 F.3d 1009 (9th Cir. 2007)
(PGE), the Court found that BPA had
exceeded its settlement authority when
it entered into the 2000 REP Settlement
Agreements. 501 F.3d at 1037. In a
companion case, Golden Northwest
Aluminum v. Bonneville Power Admin.,
501 F.3d 1037 (9th Cir. 2007) (Golden
NW), the Court also held that BPA had
improperly allocated the cost of the
2000 REP Settlement Agreements to
rates charged to the COUs in violation
of section 7(b)(2). 501 F.3d at 1048. The
Court then remanded the WP–02 rates to
BPA with the instruction to ‘‘set rates in
PO 00000
Frm 00034
Fmt 4703
Sfmt 4703
accordance with this opinion.’’ Id. at
1053.
After issuing the PGE and Golden NW
decisions, the Court also reviewed
challenges to certain amendments to the
2000 REP Settlement Agreements signed
in 2004. See Pub. Util. Dist. No. 1 of
Snohomish County, Wa. v. Bonneville
Power Admin., 506 F.3d 1145 (9th Cir.
2007) (Snohomish). In Snohomish, the
Court remanded the 2004 amendments
to the 2000 REP Settlement Agreements
and a ‘‘Reduction of Risk’’ provision
amended by the 2004 amendments to
BPA. Id. at 1154. The Court explained
that it was remanding these
amendments to BPA in order to permit
BPA to determine ‘‘in the first instance’’
whether these amendments remained
valid in light of the Court’s opinions in
PGE and Golden NW. Id.
E. BPA’s Response to PGE, Golden NW,
and Snohomish: The WP–07
Supplemental Hearing and the
Development of the 2008 RPSAs
Following the issuance of the PGE,
Golden NW, and Snohomish decisions,
BPA ceased making payments under the
2000 REP Settlement Agreements.
Thereafter, BPA commenced a series of
public meetings to discuss with
interested parties BPA’s response to the
Court’s opinions. At the conclusion of
these meetings, BPA announced that it
was commencing a section 7(i) process
to determine whether and to what
extent the 2000 REP Settlement
Agreements caused illegal costs to be
included in rates charged to the COUs.
This proceeding, referred to as the
WP–07 Supplemental Rate Hearing,
began in February of 2008. In the WP–
07 Supplemental Rate Hearing, BPA
proposed to revise its prospective
WP–07 rates for FY 2009 (the third year
of the rate period), replacing the costs of
the 2000 REP Settlement Agreements
with REP benefits calculated in
accordance with sections 5(c) and
7(b)(2) of the Northwest Power Act. In
addition, BPA proposed to perform an
analysis, referred to as the ‘‘Lookback,’’
to determine whether BPA had
overcharged the COUs during the WP–
02 rate period (i.e., FY 2002–2006) and
the first two years of the WP–07 rate
period (i.e., FY 2007–2008). The
Lookback compared the payments the
IOUs received or would have received
under the 2000 REP Settlement
Agreements with the amount of REP
benefits the IOUs would have received
under a traditional implementation of
the REP pursuant to sections 5(c) and
7(b) of the Northwest Power Act. For
those IOUs that received more in REP
benefits under the 2000 REP Settlement
Agreements than allowed by sections
E:\FR\FM\16DEN1.SGM
16DEN1
Federal Register / Vol. 75, No. 241 / Thursday, December 16, 2010 / Notices
srobinson on DSKHWCL6B1PROD with NOTICES
5(c) and 7(b)(2) of the Act, BPA assessed
a refund obligation known as a
‘‘Lookback Amount.’’ BPA proposed to
collect the Lookback Amounts from the
IOUs by withholding future benefits
owed to the IOUs under the REP and
issuing refunds to the injured COUs.
At the conclusion of the WP–07
Supplemental Hearing in September of
2008, BPA presented its final findings in
the WP–07 Supplemental Record of
Decision (WP–07 Supplemental ROD).
In the WP–07 Supplemental ROD, BPA
determined that the COUs had been
overcharged by approximately $1 billion
during the FY 2002–2008 period. BPA
proposed to return these overcharges to
the injured COUs with an initial lumpsum cash payment in 2008 and then
through future reductions in REP benefit
payments to the applicable IOUs.
In addition to determining the refunds
and overcharges caused by the 2000 REP
Settlement Agreements, the WP–07
Supplemental ROD also addressed
BPA’s final decisions on the appropriate
amount of REP benefits to pay the IOUs,
and include in rates, for FY 2009. To
make this determination, BPA had to
address a host of controversial issues
related to the section 7(b)(2) rate test.
Over 270 pages of the WP–07
Supplemental ROD were dedicated to
addressing the issues and arguments
presented by the parties on the section
7(b)(2) rate test.
Because the traditional REP was being
implemented for FY 2009, BPA also
needed to negotiate and execute new
RPSAs with the IOUs intending to
participate in the REP. Thus, concurrent
with the WP–07 Supplemental Hearing,
BPA also engaged in a public process to
develop a new RPSA. After taking
public comment on a prototype RPSA,
BPA published a final RPSA in
September of 2008. Among other terms
included in the RPSA, BPA adopted a
provision that would allow BPA to
recover the Lookback Amounts from the
IOUs by reducing future REP benefit
payments. BPA’s justification for
including this and other provisions in
the RPSA were explained in the 2008
RPSA Record of Decision (2008 RPSA
ROD).
F. Challenges to BPA’s WP–07
Supplemental ROD and RPSA
Decisions: The Assoc. of Pub. Agency
Customers v. Bonneville Power Admin.,
Idaho Pub. Util. Comm’n v. Bonneville
Power Admin, and Avista Corp. v.
Bonneville Power Admin
BPA’s decisions in the WP–07
Supplemental ROD and the 2008 RPSA
ROD were vigorously opposed by both
COUs and IOUs. The COUs and entities
supporting the COUs’ position claimed
VerDate Mar<15>2010
18:00 Dec 15, 2010
Jkt 223001
that BPA had grossly underestimated
the IOUs’ refund obligation and that the
actual overcharge to COUs for the FY
2002–2008 period was at least $2
billion. The IOUs, public utility
commissions, and ratepayer advocacy
groups, in contrast, argued that no
refunds were owed at all because the
Court did not direct BPA to provide
refunds and because the terms of the
2000 REP Settlement Agreements
specifically prohibited BPA from
recouping REP benefits paid under
those agreements. The IOUs and COUs
also opposed BPA’s interpretation and
implementation of the section 7(b)(2)
rate test for both the Lookback period
and for setting rates in FY 2009.
In December 2008, fourteen petitions
were filed in the Ninth Circuit
challenging the Lookback-related
findings and decisions BPA reached in
the WP–07 Supplemental ROD. These
challenges were consolidated into The
Assoc. of Pub. Agency Customers v.
Bonneville Power Admin., et al. (APAC).
Also in December 2008, seven petitions
were filed by a number of IOUs and
public utility commissions challenging
BPA’s decision to adopt the final
RPSAs. These challenges were
consolidated into Idaho Pub. Util.
Comm’n v. Bonneville Power Admin.
(IPUC). On July 16, 2009, the
Commission granted final approval to
BPA’s WP–07 rates for FY 2009. Shortly
thereafter, fifteen more petitions
challenging BPA’s final WP–07 rates
were filed with the Ninth Circuit and
consolidated into Avista Corp., et al. v.
Bonneville Power Admin. (Avista).
Briefing on the issues in the APAC and
IPUC cases began in August of 2009 and
concluded in March of 2010. Briefing on
the rate issues in Avista has yet to occur.
Shortly after petitions were filed in
the APAC and IPUC cases, BPA
commenced a rate proceeding to
establish rates for the FY 2010–2011
period (WP–10 Rate Proceeding). In the
WP–10 Rate Proceeding, BPA proposed
to continue to implement its Lookback
remedy by reducing the IOUs’
prospective REP benefit payments and
paying refunds to the COUs based on
the determinations made in the WP–07
Supplemental ROD. BPA also proposed
to implement the section 7(b)(2) rate test
in the same manner as in the WP–07
Supplemental ROD. On July 21, 2009,
BPA issued its final ROD in the WP–10
Rate Proceeding (WP–10 ROD.) In
October and November of 2009, five
IOUs filed precautionary petitions for
review with the Ninth Circuit
challenging BPA’s decision to continue
to implement the Lookback remedy in
the WP–10 ROD. These appeals were
consolidated in Portland General Elec.
PO 00000
Frm 00035
Fmt 4703
Sfmt 4703
78701
et al. v. Bonneville Power Admin. (PGE
II). On August 6, 2010, the Commission
granted final approval to BPA’s WP–10
rates. Subsequently, in November of
2010, fifteen petitions were filed with
the Ninth Circuit challenging the
ratemaking decisions BPA reached in
the WP–10 ROD. The petitions
challenging BPA’s WP–10 rate making
decision have yet to be consolidated.
Following the completion of the
briefing in the APAC and IPUC cases,
the litigants in APAC, IPUC, Avista, and
PGE II agreed to engage in mediation in
an attempt to resolve their numerous
disputes. Because many of the issues in
the mediation would affect the
prospective implementation of the REP,
the litigants invited regional parties not
involved in the litigation to participate
in the mediation. The mediation
sessions commenced in early April of
2010 and continued through May of
2010. Over fifty litigants and other
parties participated in the mediation.
Although by the conclusion of the
scheduled mediation sessions the
litigants and parties had not achieved a
settlement, significant progress had
been made toward reaching a
compromise on all existing claims and
the future implementation of the REP.
Principals from most of the litigants
agreed to continue meeting through
August and September in an attempt to
achieve a settlement.
In mid-September 2010, with
assistance from the mediator, a large
contingent of COUs and IOUs agreed to
pursue resolution of the outstanding
litigation and the future implementation
of the REP pursuant to the terms of a
non-binding Agreement in Principle
(AIP). The AIP committed the
negotiated parties to work in good faith
on a final settlement of the REP that
adhered to certain terms and conditions.
From September to December of 2010,
the parties worked to transform the AIP
into a final settlement document. The
final version of the proposed 2012 REP
Settlement is expected to be completed
by mid-December.
G. Proposed 2012 REP Settlement
Agreement
The proposed 2012 REP Settlement
would resolve challenges over BPA’s
implementation of the REP in return for
a stream of REP benefits to the IOUs for
a term of 17 years. The COUs’ obligation
to pay REP benefits in rates would be
limited to the COUs’ share of the stream
of REP benefits as set forth in the
agreement. The distribution of these
REP payments to the IOUs would
depend on each IOU’s respective ASC
and exchange load. The IOUs would
continue to file ASCs with BPA
E:\FR\FM\16DEN1.SGM
16DEN1
78702
Federal Register / Vol. 75, No. 241 / Thursday, December 16, 2010 / Notices
pursuant to the 2008 ASCM. In addition
to the stream of REP benefits, the IOUs
would receive a percentage of certain
BPA Renewable Energy Credits (RECs)
and the payment of certain outstanding
interim payments due under the interim
REP payment agreements between BPA
and the IOUs.
The 2012 REP Settlement reflects a
compromise by a substantial majority of
BPA’s customers and most of the
litigants to the litigation on the
outstanding REP-related issues. It was
developed after extensive negotiations
by representatives of COU customers,
IOU customers, public utility
commissions, and ratepayer advocacy
groups. Many of these entities signed
the AIP and are expected to sign the
2012 REP Settlement once it is
completed. These parties have requested
that BPA review the proposed
settlement, and, if consistent with law,
execute the Agreement and set rates
consistent with its terms.
srobinson on DSKHWCL6B1PROD with NOTICES
Part V. Summary of Proposal and
Description of Major Studies
A. Summary of Proposal
Although BPA firmly believes that
settlement of the existing REP litigation
is in the interest of all BPA ratepayers,
BPA must ensure that the terms and
conditions in the 2012 REP Settlement
are reasonable and comply with all
relevant statutory provisions before
executing the Agreement. BPA is
conducting a section 7(i) proceeding to
provide a forum in which BPA and
other interested parties can evaluate the
reasonableness and legal sufficiency of
the proposed 2012 REP Settlement.
At the conclusion of the REP–12
proceeding, the Administrator will
determine, after reviewing all evidence
and arguments contained in the record,
whether the terms of the proposed 2012
REP Settlement comport with BPA’s
statutory duties and authorities. If the
Administrator determines that the
settlement is consistent with applicable
law, and is broadly supported by BPA’s
customers and other interested parties,
he will sign the proposed 2012 REP
Settlement and set BPA’s FY 2012–2013
rates in accordance with the terms of the
2012 REP Settlement. In such case, the
2012 REP Settlement would replace
BPA’s current construct of withholding
REP benefits due the IOUs and paying
Lookback refund credits to eligible
COUs as described in the WP–07
Supplemental ROD. In addition, the
2012 REP Settlement would settle the
amount of rate protection afforded to
COUs for the term of the agreement,
obviating the need to continue the
litigation over the section 7(b)(2)
VerDate Mar<15>2010
18:00 Dec 15, 2010
Jkt 223001
decisions BPA reached in the WP–07
Supplemental ROD and the WP–10
ROD.
If the Administrator determines the
proposed 2012 REP Settlement is not
consistent with BPA’s statutory duties
or is otherwise unreasonable, the
Administrator will not sign the 2012
REP Settlement but will instead
continue to set rates, recover Lookback
Amounts and issue refunds consistent
with his decisions in the WP–07
Supplemental ROD and the WP–10
ROD.
B. 2012 REP Settlement Analysis Initial
Proposal
To test the reasonableness of the
proposed 2012 REP Settlement, BPA
will perform an analysis that will
develop a range of forecast REP benefits
reflecting the likely amount of REP
benefits the IOUs would receive (and
conversely the amount of rate protection
the COUs would likely receive) in the
absence of the 2012 REP Settlement.
The range of REP benefits will be
developed by quantifying the major
issues being litigated by BPA, the IOUs,
and the COUs in the current and
pending litigation. Broadly speaking,
the major issues being litigated today
are the implementation of the section
7(b)(2) rate test, allocation of rate
protection costs under section 7(b)(3),
and the development and calculation of
the Lookback Amounts. For each of
these main issues, BPA will develop a
17-year forecast of REP benefits that is
based on the parties’ respective legal
positions. The amount of REP benefits
allowed under these various
assumptions will then be compared to
the REP benefits afforded to the IOUs
under the 2012 REP Settlement to test
whether the terms of the 2012 REP
Settlement are reasonable and
consistent with the protections provided
by law.
BPA has modified the near-term Rate
Analysis Model and has developed a
new long-term section 7(b)(2) rate test
model to quantify the parties’ various
litigation positions on rates and forecast
REP benefits. The models will be used
in tandem to quantify the near-term and
long-term financial impacts on REP
benefits under a variety of different
litigation scenarios. Specifically, the
models will evaluate the following
contested issues: Rate test treatment of
conservation resources and their effect
on loads; treatment of conservation
costs in the rate test; rate test accounting
and financing treatment of conservation
resource costs; rate test repayment
study; treatment of Mid-Columbia
resources; treatment of secondary
energy credit; discounting of the stream
PO 00000
Frm 00036
Fmt 4703
Sfmt 4703
of rate projections; elasticity of DSI
loads; and allocation of rate protection
costs to surplus power sales. Other
scenarios may be added during the
course of the proceeding. In addition to
the rate modeling, the quantitative
analysis will include the effect of
parties’ positions on the amount of
Lookback Amounts owed on future REP
benefits.
For purposes of the REP–12 Initial
Proposal, BPA will use the above-noted
issues to produce future REP benefits
under different litigation scenarios.
These scenarios are presented in the
2012 REP Settlement Agreement Study
and Analysis. The models also quantify
the impacts of non-litigation issues on
future REP benefits, such as future
growth in ASCs and BPA program costs.
C. Implementation of 2012 REP
Settlement in Rates
In addition to the settling of the
various REP issues in litigation, the
2012 REP Settlement also specifies
certain ratemaking treatment of REPrelated costs. Implementing the 2012
REP Settlement in ratemaking will affect
the PF Exchange rate, the Industrial
Firm Power rate (IP), and the New
Resources rate (NR). While these
ratemaking treatments have been
already incorporated into the initial rate
proposal in the BP–12 proceeding, the
REP–12 proceeding will be examining
these various ratemaking specifications
to test whether the ratemaking
treatments of the 2012 REP Settlement
are reasonable and consistent with law.
D. Initial Proposal for the Section 7(b)(2)
Rate Test and Lookback Amount
Determinations in the Absence of
Settlement
As noted above, BPA is evaluating the
reasonableness and sustainability of the
2012 REP Settlement in the REP–12
proceeding. If the Administrator
determines that the 2012 REP
Settlement is not reasonable or is
otherwise unlawful, the 2012 REP
Settlement will not be executed and
BPA will set rates assuming no
settlement of the REP. Consequently, as
an alternative to the 2012 REP
Settlement, BPA is also proposing to
implement the section 7(b)(2) rate test,
the section 7(b)(3) allocations and
surcharges, and the Lookback recovery
and return for FY 2012–2013 in
accordance with the decisions BPA
reached in the WP–07 Supplemental
ROD and WP–10 ROD, unless otherwise
stated. If the 2012 REP Settlement is not
adopted, the final decisions BPA
reaches on these issues in this case will
be incorporated into the BP–12 rate
proceeding.
E:\FR\FM\16DEN1.SGM
16DEN1
Federal Register / Vol. 75, No. 241 / Thursday, December 16, 2010 / Notices
E. Major Studies
1. 2012 REP Settlement Agreement
Study and Analysis
The 2012 REP Settlement Agreement
Study and Analysis (REP Study)
describes the terms of the 2012 REP
Settlement and provides the analytical
work BPA staff is performing to test the
reasonableness of the 2012 REP
Settlement. The REP Study is comprised
of two major parts.
Part I of the REP Study reviews the
history of the REP and the background
underlying the current litigation. This
portion of the REP Study also contains
an overview of the section 7(b)(2) rate
test and a description of how rate
protection works in BPA ratemaking.
Part I also describes the terms of the
proposed 2012 REP Settlement and
explains how BPA staff intends to
implement the terms of the proposed
settlement in BPA’s rates.
Part II of the REP Study contains BPA
staff’s evaluation and analysis of the
2012 REP Settlement. This portion of
the REP Study begins with an
explanation of the criteria BPA staff is
using to evaluate the 2012 REP
Settlement. This section is followed by
an overview of the models BPA staff
developed to create a variety of nearand long-term forecasts of REP benefits
under various scenarios. Part II of the
REP Study also describes the various
factors that will have an effect on REP
benefits, such as the current and future
issues in litigation and issues related to
ASCs and the PF Exchange rate. At the
end of Part II of the REP Study, BPA
staff presents its scenario analysis. In
this section, BPA staff presents nearand long-term REP benefits under
different scenarios. These scenario REP
benefits are compared to the REP
benefits provided under the proposed
2012 REP Settlement to determine, from
an analytical perspective, whether the
2012 REP Settlement affords rate
protection to COUs and is otherwise
reasonable.
srobinson on DSKHWCL6B1PROD with NOTICES
2. FY 2012–2013 7(b)(2) Rate Test and
Documentation
This Study will be used only if the
2012 REP Settlement is not adopted.
BPA has interpreted the Northwest
Power Act and described how the
section 7(b)(2) rate test will be
performed in the Section 7(b)(2) Legal
Interpretation (Legal Interpretation) and
Section 7(b)(2) Implementation
Methodology (Implementation
Methodology) published in August,
2008. The Section 7(b)(2) Rate Test
Study explains and documents the
results of the rate test.
VerDate Mar<15>2010
18:00 Dec 15, 2010
Jkt 223001
The 7(b)(2) rate test triggers in this
proposal if no REP settlement is
assumed, creating rate protection for
preference customers and causing test
period costs to be reallocated to others.
The PF Public rate applied to the
general requirements of COUs has been
reduced by the rate protection amount
and reallocated to other rates pursuant
to section 7(b)(3). BPA’s other rates, the
PF Exchange rate and the NR and IP
rates, have been increased by an
allocation of the rate protection amount.
An allocation of the rate protection
amount has also been assigned to
surplus power sales.
3. FY 2012–2013 Lookback Study
This Study will only be used if the
2012 REP Settlement is not adopted.
This Study explains and documents
BPA’s proposed modifications to the
amounts to be recovered from the IOUs
and applied to the Lookback Amounts
determined in the final WP–07
Supplemental Proposal. The Study also
sets forth the accounting of the
Lookback Amounts expected to be
recovered from IOUs and repaid to
COUs during the FY 2012–2013 rate
period. BPA also explains in this Study
what amount of Lookback will be
recovered from IOUs and returned to
applicable COUs for the FY 2012–2013
rate period.
Part VI—Proposed 2012 REP Settlement
Agreement
On December 17, 2010, a draft of the
proposed 2012 REP Settlement will be
available for viewing and downloading
on BPA’s Web site at https://
www.bpa.gov/corporate/ratecase/2012/
rep-12.cfm. Copies of the draft 2012 REP
Settlement will also be available for
viewing in BPA’s Public Reference
Room at the BPA Headquarters, 1st
Floor, 905 NE. 11th Avenue, Portland,
OR 97232.
Issued this 7th day of December 2010.
Stephen J. Wright,
Administrator and Chief Executive Officer.
[FR Doc. 2010–31622 Filed 12–15–10; 8:45 am]
BILLING CODE P
PO 00000
Frm 00037
Fmt 4703
Sfmt 4703
78703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. IC10–542–001, FERC–542]
Commission Information Collection
Activities, Proposed Collection;
Comment Request; Submitted for OMB
Review
December 9, 2010.
Federal Energy Regulatory
Commission.
ACTION: Notice.
AGENCY:
In compliance with the
requirements of section 3507 of the
Paperwork Reduction Act of 1995, 44
U.S.C. 3507, the Federal Energy
Regulatory Commission (FERC or the
Commission) has submitted the
information collection described below
to the Office of Management and Budget
(OMB) for review and extension of this
information collection requirement. Any
interested person may file comments
directly with OMB and should address
a copy of those comments to the
Commission as explained below. The
Commission received no comments in
response to an earlier Federal Register
notice of August 2010 (75 FR 45609)
and has notified OMB of this in its
submission.
SUMMARY:
Further comments on this
collection of information are due by
January 18, 2011.
ADDRESSES: Address further comments
on this collection of information to the
Office of Management and Budget,
Office of Information and Regulatory
Affairs, Attention: Federal Energy
Regulatory Commission Desk Officer.
Comments to OMB should be filed
electronically, c/o
oira_submission@omb.eop.gov and
include OMB Control Number 1902–
0070 for reference. The Desk Officer
may be reached by telephone at 202–
395–4638.
A copy of the comments should also
be sent to the Federal Energy Regulatory
Commission and should refer to Docket
No. IC10–542–001. Comments may be
filed either electronically or in paper
format. Those persons filing
electronically do not need to make a
paper filing. Documents filed
electronically via the Internet must be
prepared in an acceptable filing format
and in compliance with the Federal
Energy Regulatory Commission
submission guidelines. Complete filing
instructions and acceptable filing
formats are available at https://
www.ferc.gov/help/submissionguide.asp. To file the document
DATES:
E:\FR\FM\16DEN1.SGM
16DEN1
Agencies
[Federal Register Volume 75, Number 241 (Thursday, December 16, 2010)]
[Notices]
[Pages 78694-78703]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-31622]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Bonneville Power Administration
[BPA File No.: REP-12]
Proposed Residential Exchange Program Settlement Agreement
Proceeding (REP-12); Public Hearing and Opportunities for Public Review
and Comment
AGENCY: Bonneville Power Administration (BPA), Department of Energy
(DOE).
ACTION: Notice of Residential Exchange Program Settlement Agreement
Proceeding (REP-12).
-----------------------------------------------------------------------
SUMMARY: BPA is conducting the 2012 Residential Exchange Program
Settlement Agreement Proceeding (REP-12) to review the terms and
conditions of a proposed 17-year settlement of issues regarding the
implementation of
[[Page 78695]]
the Residential Exchange Program (REP). The REP is a statutory power
exchange program established by section 5(c) of the Pacific Northwest
Electric Power Planning and Conservation Act (Northwest Power Act). The
proposed settlement under review is the 2012 REP Settlement Agreement
(2012 REP Settlement). If adopted, BPA will include in its power rates
for FY 2012-2028 the REP benefits stated in the proposed 2012 REP
Settlement.
In addition to reviewing the terms of the proposed 2012 REP
Settlement, BPA's REP-12 initial proposal will describe BPA's proposed
implementation of the REP for its FY 2012-2013 rates in the event the
2012 REP Settlement is not adopted. The REP-12 initial proposal will
include studies and testimony supporting BPA's proposed implementation
of the section 7(b)(2) rate test for the FY 2012-2013 rate period, the
section 7(b)(3) surcharge allocation, Average System Cost (ASC)
forecasts, and the amount of refunds to be provided to BPA customers
overcharged during the FY 2002-2006 rate period, (i.e., Lookback
repayments). If, at the conclusion of the REP-12 proceeding the
Administrator decides not to adopt the 2012 REP Settlement, BPA will
incorporate into the BP-12 rate proceeding the studies, testimony, and
documentation associated with the section 7(b)(2) rate test, the
section 7(b)(3) surcharge allocation, ASC forecasts, and Lookback
repayment and use such studies and documentation in establishing the
BP-12 rates.
DATES: Anyone wishing to become a party to the REP-12 proceeding must
provide written notice, via U.S. Mail or electronic mail, which must be
received by BPA no later than 3 p.m. on December 23, 2010.
The REP-12 proceeding begins with a prehearing conference at 9:00
a.m. on December 17, 2010, in the BPA Rates Hearing Room, 2nd Floor,
911 NE 11th Avenue, Portland, Oregon 97232.
ADDRESSES: 1. Petitions to intervene should be directed to: Hearing
Clerk--L-7, Bonneville Power Administration, 905 NE 11th Avenue,
Portland, Oregon 97232, or may be e-mailed to rateclerk@bpa.gov. In
addition, copies of the petition must be served concurrently on BPA's
General Counsel and directed to Mr. Kurt R. Casad, Office of General
Counsel, 905 NE 11th Avenue, Portland, Oregon 97232, or via e-mail to
krcasad@bpa.gov (see section III.A. for more information regarding
interventions).
2. Written comments by participants should be submitted to the
Public Engagement Office, DKE-7, Bonneville Power Administration, P.O.
Box 14428, Portland, Oregon 97293. Participants may also submit
comments by e-mail at: https://www.bpa.gov/comment. BPA requests that
all comments and documents intended to be part of the Official Record
in this rate proceeding contain the designation REP-12 in the subject
line.
FOR FURTHER INFORMATION CONTACT: Ms. Heidi Y. Helwig, DKC-7, Public
Affairs Specialist, Bonneville Power Administration, P.O. Box 3621,
Portland, Oregon 97208; by phone toll free at 1-800-622-4520; or via e-
mail to hyhelwig@bpa.gov.
Responsible Official: Mr. Raymond D. Bliven, Power Rates Manager,
is the official responsible for the development of BPA's power rates.
SUPPLEMENTARY INFORMATION:
Table of Contents
Part I. Introduction
Part II. Procedures and Scope of Hearing
Part III. Public Participation in REP-12
Part IV. Background of REP Litigation
Part V. Summary of Proposal and Description of Major Studies
Part VI. Proposed 2012 REP Settlement Agreement
Part I. Introduction
BPA is conducting an evidentiary hearing, Docket No. REP-12, to
review the terms and conditions of a proposed 17-year settlement of
issues regarding the implementation of the Residential Exchange Program
(REP). The REP is a statutory power exchange program established by
section 5(c) of the Northwest Power Act (Act). See 16 U.S.C. 839c(c).
The proposed settlement under review, the 2012 REP Settlement, reflects
the efforts of a broad group of regional parties to resolve litigation
over BPA's implementation of the REP through a legally sustainable and
equitable settlement agreement. If adopted by the Administrator, BPA
will include in its power rates for FY 2012-2028 the REP benefits
stated in the proposed 2012 REP Settlement.
In addition to reviewing the terms of the proposed 2012 REP
Settlement, BPA's REP-12 initial proposal will describe BPA's proposed
implementation of the REP for its FY 2012-2013 rates in the event the
2012 REP Settlement is not adopted. The REP-12 initial proposal will
include studies and testimony supporting BPA's proposed implementation
of the section 7(b)(2) rate test, the section 7(b)(3) surcharge
allocation, ASC forecasts, and Lookback repayments for the FY 2012-2013
rate period. Any party wishing to contest BPA's proposed implementation
of the section 7(b)(2) rate test, allocation of section 7(b)(3)
surcharge amounts, development of the ASC forecasts, or determination
of Lookback refund amounts must raise such arguments in the REP-12
proceeding. At the same time BPA is reviewing the proposed 2012 REP
Settlement in the REP-12 proceeding, BPA is separately conducting a BP-
12 rate proceeding to establish power rates for FY 2012-2013. If, at
the conclusion of the REP-12 proceeding, the Administrator decides not
to adopt the 2012 REP Settlement, BPA will incorporate into the BP-12
rate proceeding the studies, testimony, and documentation associated
with the section 7(b)(2) rate test, the section 7(b)(3) surcharge
allocation, ASC forecasts, and Lookback repayment, and use such studies
and documentation in establishing the BP-12 rates.
Part II. Procedures and Scope of Hearing
A. Procedures Governing the REP-12 Proceeding
Because the proposed 2012 REP Settlement includes features that are
directly related to BPA's rates and ratemaking, the proposed Settlement
will be evaluated under the procedural terms of section 7(i) of the
Act, 16 U.S.C. 839e(i). These procedures include, among other things:
Publication of a notice of the proposed rates in the Federal Register;
one or more hearings conducted as expeditiously as practicable by a
Hearing Officer; public opportunity to provide both oral and written
views related to the proposed rates; opportunity to offer refutation or
rebuttal of submitted material; and a decision by the Administrator
based on the record. This REP-12 proceeding is governed by Sec. 1010
of BPA's Rules of Procedure Governing Rate Hearings, 51 FR 7611 (1986)
(BPA Hearing Procedures). These procedures implement the statutory
section 7(i) requirements.
Section 1010.7 of BPA's Hearing Procedures prohibits ex parte
communications. The ex parte rule applies to all BPA and DOE employees
and contractors. Except as provided below, any communications with BPA
and/or DOE personnel regarding BPA's rate proceeding by other Executive
Branch agencies, Congress, existing or potential BPA customers
(including Tribes), and nonprofit or public interest groups are
considered outside communications and are subject to the ex parte rule.
The general rule does not apply to communications relating to: (1)
[[Page 78696]]
Matters of procedure only (the status of the rate proceeding, for
example); (2) exchanges of data in the course of business or under the
Freedom of Information Act; (3) requests for factual information; (4)
matters for which BPA is responsible under statutes other than the
ratemaking provisions; or (5) matters which all parties agree may be
made on an ex parte basis. The ex parte rule remains in effect until
the Administrator's Final Record of Decision (ROD) is issued.
The Flood Control Act of 1944, 16 U.S.C. 825s, the Federal Columbia
River Transmission System Act, 16 U.S.C. 838, and the Northwest Power
Act, 16 U.S.C. 839, provide guidance regarding BPA ratemaking. The
Northwest Power Act requires BPA to set rates that are sufficient to
recover, in accordance with sound business principles, the cost of
acquiring, conserving and transmitting electric power, including
amortization of the Federal investment in the Federal Columbia River
Power System (FCRPS) over a reasonable period of years, and certain
other costs and expenses incurred by the Administrator.
BPA's proposal, study documentation, and the proposed 2012 REP
Settlement will be available for examination beginning December 17,
2010, on BPA's Web site at https://www.bpa.gov/corporate/ratecase/2012/rep-12.cfm. Hard copies of these documents will be available beginning
December 17, 2010, at BPA's Public Information Center, BPA Headquarters
Building, 1st Floor, 905 NE. 11th Avenue, Portland, Oregon.
A formal evidentiary rate hearing will be conducted that is open to
rate proceeding parties. Interested parties that previously intervened
in BPA's BP-12 rate proceeding must also file petitions to intervene in
order to take part in the REP-12 formal hearing. A proposed schedule
for the REP-12 proceeding is stated below. A Hearing Officer will
establish a final schedule at the prehearing conference.
------------------------------------------------------------------------
------------------------------------------------------------------------
Intervention Deadline.................... December 23.
Prehearing/BPA Direct Case............... December 17.
Clarification............................ January 4-7.
Motions to Strike........................ January 11.
Data Request Deadline.................... January 11.
Answers to Motions to Strike............. January 18.
Data Response Deadline................... January 18.
Parties File Direct Case................. February 8.
Clarification............................ February 14-15.
Motions to Strike........................ February 22.
Data Request Deadline.................... February 22.
Answers to Motions to Strike............. March 1.
Data Response Deadline................... March 1.
Close of Participant Comments............ March 8.
Litigants File Rebuttal.................. March 8.
Clarification............................ March 14-15.
Motions to Strike........................ March 17.
Data Request Deadline.................... March 17.
Answers to Motions to Strike............. March 25.
Data Response Deadline................... March 25.
Cross-Examination........................ March 28-April 1.
Initial Briefs Filed..................... April 25.
Oral Argument............................ May 12.
Draft ROD Issued......................... May 23.
Briefs on Exceptions..................... June 6.
Final ROD--Final Studies................. June 27.
------------------------------------------------------------------------
No field hearings will be conducted in this proceeding.
B. Scope of the REP-12 Proceeding
This section provides guidance to the Hearing Officer regarding the
matters within the scope of the REP-12 proceeding and the matters not
within the scope of this proceeding.
1. Matters Within the Scope of This Proceeding
a. Proposed 2012 REP Settlement
All issues related to BPA's analysis, methodology, or review of the
proposed 2012 REP Settlement, including any issues related to the
models developed by BPA to evaluate the 2012 REP Settlement, are
expressly within the scope of this proceeding. Parties wishing to
challenge any aspect of the proposed 2012 REP Settlement, including but
not limited to any term of the proposed Settlement or whether BPA
should adopt the Settlement, must raise such arguments in this
proceeding.
b. Section 7(b)(2) Rate Test Implementation
All issues related to BPA's implementation, interpretation, and
forecast of the section 7(b)(2) rate test are within the scope of this
proceeding. Parties wishing to challenge any aspect of the
implementation of the section 7(b)(2) rate test for either the 2012 REP
Settlement implementation period (FY 2012-2028) or the BP-12 rate
period (FY 2012-2013) must raise such arguments in this proceeding.
c. Section 7(b)(3) Surcharge Implementation
All issues related to BPA's implementation, interpretation, and
forecast of the section 7(b)(3) reallocations or surcharges are within
the scope of this proceeding. Parties wishing to challenge any aspect
of the implementation of section 7(b)(3) for either the 2012 REP
Settlement implementation period (FY 2012-2028) or the BP-12 rate
period (FY 2012-2013) must raise such arguments in this proceeding.
d. Lookback Assumptions
All issues related to BPA's implementation, determination,
recovery, and repayment of Lookback Amounts are within the scope of
this proceeding. Parties wishing to challenge any aspect of BPA's
Lookback recovery or repayment for either the 2012 REP Settlement
implementation period (FY 2012-2028) or the BP-12 rate period (FY 2012-
2013) must raise such arguments in this proceeding.
e. ASC Forecasts
Except as provided below in section II.B.2.h, all issues related to
BPA's forecast of utilities' ASCs for the BP-12 rate test period (FY
2014-2017) and the 2012 REP Settlement implementation period (FY 2012-
2028) are within the scope of this proceeding. Parties wishing to
challenge any aspect of BPA's ASC forecasts for these periods must
raise their arguments in this proceeding. Challenges to the ASCs
determined in the Draft and Final ASC reports for FY 2012-2013 are
expressly excluded from the scope of this proceeding. See Section
II.B.2.h.
2. Matters Not Within the Scope of This Proceeding
a. BP-12 Rate Proceeding Issues
As noted above, BPA is conducting a rate proceeding to establish
wholesale power and transmission rates for FY 2012-2013 (BP-12) at the
same time BPA is conducting the REP-12 proceeding. Although some of the
information developed in the BP-12 rate proceeding will be used in the
models in the REP-12 proceeding, parties may not raise arguments or
issues with such data in the REP-12 proceeding. Instead, such arguments
or issues should be raised in the BP-12 rate proceeding if and to the
extent such issues are within the scope of that proceeding. Pursuant to
section 1010.3(f) of BPA's Hearing Procedures, the Administrator
directs the Hearing Officer to exclude from the record all argument,
testimony, or other evidence that seeks in any way to address the
appropriateness or reasonableness of any issue being addressed in the
BP-12 rate proceeding.
b. Program Cost Estimates
BPA began its 2010 Integrated Program Review (IPR) process in May
2010. The IPR process is designed to allow people interested in BPA's
program levels an opportunity to review and comment on all of BPA's
expense and capital spending level estimates in the same forum prior to
the use of those estimates in setting rates. Concurrent with the IPR,
BPA held regional
[[Page 78697]]
conversations about risk mitigation and debt management practices.
The 2010 IPR focused on FY 2012 and 2013 program levels for BPA's
Power Services and Transmission Services as well as a review of FY 2011
program levels. BPA held 19 technical workshops and two general manager
meetings at which proposed spending levels were presented for each of
BPA's programs. BPA carefully reviewed and considered the 26 written
comments and numerous oral comments on FY 2012 and 2013 program levels
that were provided during this public process.
On October 27, 2010, BPA issued a Final Close-Out Letter and
accompanying final report for the IPR, which summarizes the comments
received and outlines BPA's responses. The report also summarizes
comments and BPA's responses on the regional conversations about risk
mitigation and debt management. In the Final Close-Out Letter and
report, BPA established the program level cost estimates for both power
and transmission rates that are used in the BP-12 and REP-12 Initial
Proposals. BPA does not anticipate additional public review of proposed
spending levels. However, an abbreviated IPR process may be held if
conditions warrant. BPA would conduct this process separately from the
REP-12 and BP-12 proceedings to share updates and solicit feedback from
customers and constituents before the final program levels are
incorporated into BPA's final rates. BPA's spending levels for
investments and expenses are not determined or subject to review in the
REP-12 or BP-12 proceedings.
Pursuant to section 1010.3(f) of BPA's Hearing Procedures, the
Administrator directs the Hearing Officer to exclude from the record
all argument, testimony, or other evidence that seeks in any manner to
address the appropriateness or reasonableness of the Administrator's
decisions on cost and spending levels. If and to the extent that any
re-examination of spending levels is necessary, such re-examination
will occur outside of the REP-12 and BP-12 proceedings. This exclusion
does not extend to portions of BPA's revenue requirements related to
REP benefits, Lookback payments, or interest on Lookback payments. The
Administrator also directs the Hearing Officer to exclude argument and
evidence regarding BPA's debt management practices and policies.
c. Regional Dialogue Policy Decisions
BPA's Subscription contracts expire on September 30, 2011, at the
end of the current rate period. BPA previously engaged customers and
interested stakeholders in an extensive Regional Dialogue process that
led to new power sales contracts. BPA issued its Long-Term Regional
Dialogue Final Policy and ROD on July 19, 2007; its Long-Term Regional
Dialogue Contract Policy and ROD on October 31, 2008; the Tiered Rate
Methodology and ROD on November 10, 2008; and the Tiered Rate
Methodology Supplemental ROD on September 2, 2009. On or about December
1, 2008, BPA and its customers signed new power sales contracts under
which the customers will purchase Federal power for the FY 2012-2028
period. Several aspects of the Regional Dialogue process are still
ongoing, such as establishing customer contract high water marks and
contract demand quantities, and these processes and decisions are
outside the scope of the REP-12 proceeding.
Pursuant to Sec. 1010.3(f) of BPA's Hearing Procedures, the
Administrator hereby directs the Hearing Officer to exclude from the
record all argument, testimony, or other evidence that seeks in any way
to address the appropriateness or reasonableness of BPA's decisions
made in the Long-Term Regional Dialogue Final Policy ROD, Long-Term
Regional Dialogue Contract Policy ROD, the Tiered Rate Methodology ROD,
and the Tiered Rate Methodology Supplemental ROD.
d. Tiered Rate Methodology (TRM)
BPA previously established the TRM in a section 7(i) rate hearing.
The issues being examined in the REP-12 proceeding are not governed by
the TRM. Modifications to the TRM are not within the scope of this
proceeding. Pursuant to Sec. 1010.3(f) of BPA's Hearing Procedures,
the Administrator hereby directs the Hearing Officer to exclude from
the record all argument, testimony, or other evidence that seeks in any
way to propose to revise the TRM developed by BPA.
e. Service to the Direct Service Industries (DSIs)
The manner and method by which BPA could provide service or
financial payments to its DSI customers were evaluated in Pacific
Northwest Generating Cooperative, et al., v. Bonneville Power
Administration, 580 F.3d 792 (9th Cir. 2008) (PNGC I) and Pacific
Northwest Generating Cooperative, et al., v. Bonneville Power
Administration, 590 F.3d 1065 (9th Cir. 2010) (PNGC II). In BPA's BP-12
rate proceeding, BPA has assumed that it will continue to serve Alcoa,
Inc. (Alcoa) as well as Port Townsend Paper Corporation (Port Townsend)
during FY 2012-2013. BPA's decisions to serve the DSIs, along with the
method and level of service to be provided DSIs in the FY 2012-2013
rate period, will not be determined in this proceeding.
Pursuant to Sec. 1010.3(f) of BPA's Hearing Procedures, the
Administrator directs the Hearing Officer to exclude from the record
all argument, testimony, or other evidence that seeks in any way to
revisit the appropriateness or reasonableness of BPA's decisions
regarding the service to the DSIs, including BPA's decision to offer a
contract and the method or level of such service.
f. Potential Environmental Impacts
Environmental impacts are addressed in a concurrent National
Environmental Policy Act (NEPA) process. Pursuant to Sec. 1010.3(f) of
BPA's Hearing Procedures, the Administrator directs the Hearing Officer
to exclude from the record all argument, testimony, or other evidence
that seeks in any way to address the potential environmental impacts of
the rates being developed in this rate proceeding.
g. Average System Cost Methodology
Section 5(c) of the Northwest Power Act established the REP, which
provides benefits to residential and small-farm consumers of Pacific
Northwest utilities based, in part, on a utility's ``average system
cost'' (ASC) of resources. Section 5(c)(7) of the Act requires the
Administrator to consult with regional interests to develop an ASC
Methodology (ASCM). BPA uses the ASCM to calculate utilities' ASCs. On
September 4, 2009, the Federal Energy Regulatory Commission
(Commission) granted final approval of BPA's 2008 ASCM. The 2008 ASCM
is not subject to challenge or review in a section 7(i) proceeding.
Pursuant to Sec. 1010.3(f) of BPA's Hearing Procedures, the
Administrator hereby directs the Hearing Officer to exclude from the
record all argument, testimony, or other evidence that seeks in any way
to address the appropriateness or reasonableness of the 2008 ASCM.
h. Average System Cost Review Processes
To receive REP benefits for FY 2012-2013, utilities must file
proposed ASCs with BPA pursuant to the terms and conditions of the 2008
ASCM. These filings are reviewed by BPA staff and other interested
parties in ASC review processes, which are separate administrative
proceedings conducted by BPA under the terms of the 2008 ASCM. In the
review processes, BPA staff and other parties evaluate the ASCs
[[Page 78698]]
filed by participating utilities for conformance with the requirements
of the 2008 ASCM. At the conclusion of the processes, BPA issues ASC
Reports, which formally establish the utilities' ASCs for the Exchange
Period, which coincides with BPA's rate period.
On June 1, 2010, ten utilities filed proposed ASCs with BPA for FY
2012-2013. One utility subsequently withdrew its ASC filing. BPA staff
and other parties are currently reviewing the remaining nine filings in
the ASC review processes. Once these ASC review processes are complete,
and BPA has issued final ASC Reports, BPA will incorporate the final
ASCs into the administrative record of the REP-12 proceeding. Although
these ASC determinations provide important information for setting
BPA's rates, they are not made in section 7(i) hearings. Parties
intending to challenge BPA's draft or final ASC determinations for FY
2012-2013 must raise such issues in the ASC review processes according
to the procedures established in the 2008 ASCM.
Pursuant to Sec. 1010.3(f) of BPA's Hearing Procedures, the
Administrator hereby directs the Hearing Officer to exclude from the
record all argument, testimony, or other evidence that seeks in any way
to address BPA's draft or final ASC determinations for FY 2012-2013.
i. Contract High Water Mark (CHWM) Process
Under the Tiered Rate Methodology (TRM), BPA will establish both
CHWMs and FY 2012-2013 Rate Period High Water Mark (RHWMs) for public
agency customers that signed contracts for firm requirements power
service at tiered rates, referred to as CHWM contracts. The CHWMs and
RHWMs will be established in the CHWM Process, which will occur mainly
in Spring 2011. In this process, BPA will establish the maximum planned
amount of power a customer is eligible to purchase at Tier 1 rates
during the rate period. The CHWM Process provides customers an
opportunity to review, comment, and, if necessary, challenge BPA's
determinations regarding certain CHWM and RHWM determinations.
Pursuant to Sec. 1010.3(f) of BPA's Hearing Procedures, the
Administrator hereby directs the Hearing Officer to exclude from the
record all argument, testimony, or other evidence that seeks in any way
to address BPA's determination of a customer's CHWM or FY 2012-2013
RHWM.
C. The National Environmental Policy Act
BPA is in the process of assessing the potential environmental
effects that could result from implementation of the proposed 2012 REP
Settlement, consistent with NEPA requirements. BPA is reviewing this
proposal for consistency with BPA's Business Plan Environmental Impact
Statement (Business Plan EIS), completed in June 1995 (DOE/EIS-0183).
This policy-level EIS evaluates the environmental impacts of a range of
business plan alternatives for BPA and is intended to support a wide
range of subsequent BPA business-related decisions. In the Record of
Decision for the Business Plan ROD (Business Plan ROD, August 1995),
the BPA Administrator adopted the Market-Driven Alternative from the
Business Plan EIS. This alternative was selected because, among other
reasons, it allows BPA to: (1) Recover costs through rates; (2)
competitively market BPA's products and services; (3) develop rates
that meet customer needs for clarity and simplicity; (4) continue to
meet BPA's legal mandates; and (5) avoid adverse environmental impacts.
In April 2007, BPA completed a Supplement Analysis confirming the
Business Plan EIS's environmental analysis in light of current regional
conditions and BPA's current business practices. The Business Plan EIS
and ROD thus continue to provide a sound basis for making
determinations under NEPA concerning BPA's business-related decisions.
BPA will document its environmental evaluation for the proposed
2012 REP Settlement as part of the Administrator's Record of Decision
that will be prepared for this proposal. During the public review and
comment period for the proposed 2012 REP Settlement, persons interested
in submitting comments regarding its potential environmental effects
may do so by submitting comments to Katherine Pierce, NEPA Compliance
Officer, KEC-4, Bonneville Power Administration, 905 NE. 11th Avenue,
Portland, OR 97232. Any such comments received by the Close of
Participant Comments deadline identified in Part II.A will be
considered by BPA's NEPA compliance staff in the NEPA evaluation that
will be prepared for this proposal.
Part III. Public Participation in REP-12
A. Distinguishing Between ``Participants'' and ``Parties''
BPA distinguishes between ``participants in'' and ``parties to''
the hearings. Apart from the formal hearing process, BPA will receive
written comments, views, opinions, and information from
``participants,'' who may submit comments without being subject to the
duties of, or having the privileges of, parties. Participants' written
comments will be made part of the official record and considered by the
Administrator. Participants are not entitled to participate in the
prehearing conference; may not cross-examine parties' witnesses, seek
discovery, or serve or be served with documents; and are not subject to
the same procedural requirements as parties. BPA customers whose rates
are subject to this proceeding, or their affiliated customer groups,
may not submit participant comments. Members or employees of
organizations that have intervened in the rate proceeding may submit
general comments as participants but may not use the comment procedures
to address specific issues raised by their intervenor organizations.
Written comments by participants will be included in the record if
they are received by March 8, 2011. Written views, supporting
information, questions, and arguments should be submitted to the
address listed in the ADDRESSES section of this Notice.
Entities or individuals become parties to the proceeding by filing
petitions to intervene, which must state the name and address of the
entity or person requesting party status and the entity's or person's
interest in the hearing. BPA's customers and affiliated customer groups
will be granted intervention based on petitions filed in conformance
with BPA's Hearing Procedures. Other petitioners must explain their
interests in sufficient detail to permit the Hearing Officer to
determine whether the petitioners have a relevant interest in the
hearing. Pursuant to Rule 1010.1(d) of BPA's Hearing Procedures, BPA
waives the requirement in Rule 1010.4(d) that an opposition to an
intervention petition be filed and served 24 hours before the
prehearing conference. The time limit for opposing a timely
intervention will be established at the prehearing conference. Any
party, including BPA, may oppose a petition for intervention. All
petitions will be ruled on by the Hearing Officer. Late interventions
are strongly disfavored. Opposition to an untimely petition to
intervene must be filed and received by BPA within two days after
service of the petition.
B. Developing the Record
The hearing record will include, among other things, the
transcripts of the hearing, written evidence and argument entered into
the record by BPA and the parties, written comments
[[Page 78699]]
from participants, and other material accepted into the record by the
Hearing Officer. The Hearing Officer will then review the record and
certify the record to the Administrator.
The Administrator will develop the Final ROD in the REP-12
proceeding based on the record and such other materials and information
as may have been submitted to or developed by the Administrator. The
Administrator will serve copies of the Final ROD on all parties. BPA
will incorporate the Administrator's final decision in this proceeding
into its BP-12 Final Rate Proposal.
Part IV. Background of REP Litigation
A. Background on the REP
1. Section 5(c) of the Northwest Power Act
As noted previously, section 5(c) of the Northwest Power Act
established the REP. 16 U.S.C. 839c(c)(1). Under the REP, any Pacific
Northwest utility may sell power to BPA at the utility's ASC. A
utility's ASC is determined in accordance with an ASC Methodology that
BPA develops pursuant to the requirements in the Act. In calculating a
utility's ASC, section 5(c)(7) of the Act mandates that BPA exclude
from ASC the cost of resources in an amount sufficient to serve a new
large single load (NLSL), the cost of additional resources in an amount
sufficient to meet any additional load outside the region occurring
after the effective date of the Act, and any costs of any generating
facility which is terminated prior to initial commercial operation. 16
U.S.C. 839c(c)(7)(A)-(C).
When a utility offers to sell its power to BPA at its ASC, BPA must
purchase such power and, in return, sell an equivalent amount of power
to the utility at BPA's rate for purchases under the REP, known as the
``PF Exchange rate.'' The PF Exchange rate is developed in accordance
with section 7 of the Northwest Power Act. The amount of power that is
bought and sold under the REP is equal to the utility's qualified
residential and small farm load (exchange load). Because the purchase
and sale between BPA and the utility involves the same amount of power
and is simultaneous, in almost all instances no actual power is bought
or sold under the REP. Instead, the REP is generally implemented as a
paper transaction where the net difference between the utility's ASC
and BPA's PF Exchange rate is multiplied by the utility's exchange load
and converted into a cash payment to the utility. The utility is
required by law to pass these payments onto its residential and small
farm consumers. 16 U.S.C. 839c(c)(3). The REP is implemented through a
Residential Purchase and Sale Agreement (RPSA) executed by BPA and the
utility. The REP is intended to provide regional residential and small
farm consumers a form of access to the power produced by the FCRPS.
Although intended primarily for the benefit of consumers located in
investor-owned utilities' (IOUs) service areas, any utility within the
region may participate.
2. Section 7(b)(2) of the Northwest Power Act and the PF Exchange Rate
The PF Exchange rate is the rate at which BPA ``sells'' power to
utilities participating in the REP. Section 7 of the Act prescribes the
manner in which this rate is set. Under section 7(b)(1), BPA
establishes the PF Exchange rate in much the same way BPA develops its
PF Public rate. See 16 U.S.C. 839e(b)(1). Section 7(b)(2) of the Act,
however, requires BPA to perform a ``rate test'' to determine whether
the PF Public rate charged to BPA's consumer-owned utility customers
(COUs) under the Act would be greater than a rate developed under five
specific assumptions stated in section 7(b)(2). These five assumptions
are:
(A) The [COUs'] general requirements had included during such five-
year period the direct service industrial customer loads which are (i)
served by the Administrator, and (ii) located within or adjacent to the
geographic service boundaries of such public bodies and cooperatives;
(B) [the COUs] were served, during such five-year period, with
Federal base system resources not obligated to other entities under
contracts existing as of December 5, 1980 (during the remaining term of
such contracts) excluding obligations to direct service industrial
customer loads included in subparagraph (A) of this paragraph;
(C) No purchases or sales by the Administrator as provided in
[section 5(c)] of this section were made during such five-year period;
(D) All resources that would have been required, during such five-
year period, to meet remaining general requirements of the public body,
cooperative and Federal agency customers (other than requirements met
by the available Federal base system resources determined under
subparagraph (B) of this paragraph) were (i) purchased from such
customers by the Administrator pursuant to section 839d of this title,
or (ii) not committed to load pursuant to section 839c(b) of this
section and were the least expensive resources owned or purchased by
public bodies or cooperatives; and any additional needed resources were
obtained at the average cost of all other new resources acquired by the
Administrator; and
(E) The quantifiable monetary savings, during such five-year
period, to public body, cooperative and Federal agency customers
resulting from (i) reduced public body and cooperative financing costs
as applied to the total amount of resources, other than Federal base
system resources, identified under subparagraph (D) of this paragraph,
and (ii) reserve benefits as a result of the Administrator's actions
under this chapter were not achieved.
If BPA's proposed rates developed under section 7(b)(1) are greater
than the rates calculated under the section 7(b)(2) assumptions, BPA
must reduce the costs included in the 7(b)(1) rate charged to COUs by
assessing a surcharge pursuant to section 7(b)(3) to ``all other power
sold by the Administrator to all customers.'' 16 U.S.C. 839e(b)(3). One
of the rates assessed this surcharge is the PF Exchange rate.
Application of the 7(b)(3) surcharge to the PF Exchange rate has the
effect of increasing the level of the PF Exchange rate and reducing the
amount of REP benefits paid by COUs in their PF Public rates.
B. History of the REP
The history of BPA's implementation of the REP is marked by
controversy and litigation. Shortly after the passage of the Northwest
Power Act in 1980, BPA and regional parties negotiated the terms of
BPA's first ASC Methodology (1981 ASC Methodology) and the provisions
of 20-year RPSAs that would be used to implement the REP. After three
years of experience under the 1981 ASC Methodology, BPA's DSI and COU
customers requested that a consultation process be held to consider
revisions to the 1981 ASC Methodology. BPA granted the requests and
commenced a consultation process in 1983. In the consultation, BPA
determined that the source of data used in the 1981 ASC Methodology did
not include sufficient detail to ensure that BPA was excluding
terminated plant costs as required by section 5(c)(7) of the Northwest
Power Act. Consequently, BPA proposed to revise the ASC Methodology by
expanding the procedures used to review ASCs and excluding certain
costs that BPA determined were too difficult to accurately monitor. The
revised ASC Methodology was completed in 1984 and received approval
from the Commission shortly thereafter.
[[Page 78700]]
BPA's IOU customers vigorously opposed the changes to the 1981 ASC
Methodology. Eight IOUs and four State regulatory agencies filed
petitions with the United States Court of Appeals for the Ninth Circuit
challenging the Commission's final approval of the revised ASC
Methodology (1984 ASC Methodology). See PacifiCorp v. FERC, 795 F.2d
816 (9th Cir. 1986) (PacifiCorp). In PacifiCorp, the Court affirmed the
Commission's approval and BPA's decision to adopt the 1984 ASC
Methodology. Id. Even though the 1984 ASC Methodology was sustained by
the Court, litigation continued over BPA's implementation of the ASC
Methodology. Dozens of BPA's ASC determinations were contested before
the Commission, several of which were ultimately resolved by the Court.
See Wash. Util. & Transp. Comm'n v. FERC, 26 F.3d 935 (9th Cir. 1994);
CP Nat. Corp. v. Bonneville Power Admin., 928 F.2d 905 (9th Cir. 1991).
Due to the burdensome, expensive and contentious nature of
implementing the 1984 ASC Methodology, BPA and regional exchanging
utilities began negotiating settlements of the implementation of the
REP. Throughout the late 1980s and into the 1990s, BPA and regional
exchanging utilities entered into multiple REP settlements. By the late
1990s, BPA and five of the six exchanging IOUs executed REP settlement
agreements that resolved the implementation of the REP until June 30,
2001.
C. The 2000 REP Settlement Agreements
In early 1996, the governors of Idaho, Montana, Oregon and
Washington convened the Comprehensive Review of the Northwest Energy
System. The goal of the review was to develop recommendations for
changes in the region's electric utility industry, focusing on BPA,
through an open public process involving a broad cross-section of
regional interests. In December 1996, after over a year of intense
study, the Comprehensive Review Steering Committee released its Final
Report. The Final Report proposed a subscription system for purchasing
specified amounts of power from BPA at cost with incentives for
customers to take longer-term subscriptions (Subscription). In
connection with its Subscription proposal, the Steering Committee
encouraged BPA and other parties in the region to explore a settlement
of the REP with the region's IOUs for the FY 2002-2011 period.
In response to the Steering Committee's recommendation, BPA and
regional IOUs developed the 2000 Residential Exchange Program
Settlement Agreements (2000 REP Settlement Agreements). Under the 2000
REP Settlement Agreements, the IOUs agreed to forgo their participation
in the traditional REP for a period of ten years (FY 2002-2011) in
return for certain payments and deliveries of firm power from BPA. To
recover the costs of the 2000 REP Settlement Agreements for the FY
2002-2006 rate period, BPA proposed in its WP-02 Wholesale Power Rate
Proceeding to allocate a significant portion of the costs of the 2000
REP Settlement Agreements to the rates charged to COUs.
D. Challenges to the 2000 REP Settlements: The Ninth Circuit's
Decisions in Portland General Electric v. BPA, Golden Northwest
Aluminum v. BPA, and Snohomish PUD v. BPA
In January of 2001, certain parties filed petitions with the Ninth
Circuit challenging BPA's statutory authority to implement the REP
through the 2000 REP Settlement Agreements. In September of 2003,
following final Commission confirmation and approval of BPA's WP-02
rates, parties also filed challenges to BPA's decision to recover the
costs of the 2000 REP Settlement Agreements from the PF rates without
BPA's traditional manner of implementing the 7(b)(2) rate test.
While these challenges were pending before the Court, BPA commenced
a new rate proceeding, the 2007 Wholesale Power Rate Proceeding, to
establish rates for the FY 2007-2009 period (WP-07 rates). In the WP-07
rates, BPA again allocated a significant portion of the costs of the
2000 REP Settlement Agreements to the PF rates. The WP-07 rates were
filed with the Commission on July 28, 2006, and received interim
approval from the Commission on September 21, 2006.
On May 3, 2007, before final Commission approval of BPA's WP-07
rates, the Court issued two decisions in the pending challenges to the
2000 REP Settlement Agreements and the then-expired WP-02 rates. In
Portland General Electric v. Bonneville Power Admin., 501 F.3d 1009
(9th Cir. 2007) (PGE), the Court found that BPA had exceeded its
settlement authority when it entered into the 2000 REP Settlement
Agreements. 501 F.3d at 1037. In a companion case, Golden Northwest
Aluminum v. Bonneville Power Admin., 501 F.3d 1037 (9th Cir. 2007)
(Golden NW), the Court also held that BPA had improperly allocated the
cost of the 2000 REP Settlement Agreements to rates charged to the COUs
in violation of section 7(b)(2). 501 F.3d at 1048. The Court then
remanded the WP-02 rates to BPA with the instruction to ``set rates in
accordance with this opinion.'' Id. at 1053.
After issuing the PGE and Golden NW decisions, the Court also
reviewed challenges to certain amendments to the 2000 REP Settlement
Agreements signed in 2004. See Pub. Util. Dist. No. 1 of Snohomish
County, Wa. v. Bonneville Power Admin., 506 F.3d 1145 (9th Cir. 2007)
(Snohomish). In Snohomish, the Court remanded the 2004 amendments to
the 2000 REP Settlement Agreements and a ``Reduction of Risk''
provision amended by the 2004 amendments to BPA. Id. at 1154. The Court
explained that it was remanding these amendments to BPA in order to
permit BPA to determine ``in the first instance'' whether these
amendments remained valid in light of the Court's opinions in PGE and
Golden NW. Id.
E. BPA's Response to PGE, Golden NW, and Snohomish: The WP-07
Supplemental Hearing and the Development of the 2008 RPSAs
Following the issuance of the PGE, Golden NW, and Snohomish
decisions, BPA ceased making payments under the 2000 REP Settlement
Agreements. Thereafter, BPA commenced a series of public meetings to
discuss with interested parties BPA's response to the Court's opinions.
At the conclusion of these meetings, BPA announced that it was
commencing a section 7(i) process to determine whether and to what
extent the 2000 REP Settlement Agreements caused illegal costs to be
included in rates charged to the COUs. This proceeding, referred to as
the WP-07 Supplemental Rate Hearing, began in February of 2008. In the
WP-07 Supplemental Rate Hearing, BPA proposed to revise its prospective
WP-07 rates for FY 2009 (the third year of the rate period), replacing
the costs of the 2000 REP Settlement Agreements with REP benefits
calculated in accordance with sections 5(c) and 7(b)(2) of the
Northwest Power Act. In addition, BPA proposed to perform an analysis,
referred to as the ``Lookback,'' to determine whether BPA had
overcharged the COUs during the WP-02 rate period (i.e., FY 2002-2006)
and the first two years of the WP-07 rate period (i.e., FY 2007-2008).
The Lookback compared the payments the IOUs received or would have
received under the 2000 REP Settlement Agreements with the amount of
REP benefits the IOUs would have received under a traditional
implementation of the REP pursuant to sections 5(c) and 7(b) of the
Northwest Power Act. For those IOUs that received more in REP benefits
under the 2000 REP Settlement Agreements than allowed by sections
[[Page 78701]]
5(c) and 7(b)(2) of the Act, BPA assessed a refund obligation known as
a ``Lookback Amount.'' BPA proposed to collect the Lookback Amounts
from the IOUs by withholding future benefits owed to the IOUs under the
REP and issuing refunds to the injured COUs.
At the conclusion of the WP-07 Supplemental Hearing in September of
2008, BPA presented its final findings in the WP-07 Supplemental Record
of Decision (WP-07 Supplemental ROD). In the WP-07 Supplemental ROD,
BPA determined that the COUs had been overcharged by approximately $1
billion during the FY 2002-2008 period. BPA proposed to return these
overcharges to the injured COUs with an initial lump-sum cash payment
in 2008 and then through future reductions in REP benefit payments to
the applicable IOUs.
In addition to determining the refunds and overcharges caused by
the 2000 REP Settlement Agreements, the WP-07 Supplemental ROD also
addressed BPA's final decisions on the appropriate amount of REP
benefits to pay the IOUs, and include in rates, for FY 2009. To make
this determination, BPA had to address a host of controversial issues
related to the section 7(b)(2) rate test. Over 270 pages of the WP-07
Supplemental ROD were dedicated to addressing the issues and arguments
presented by the parties on the section 7(b)(2) rate test.
Because the traditional REP was being implemented for FY 2009, BPA
also needed to negotiate and execute new RPSAs with the IOUs intending
to participate in the REP. Thus, concurrent with the WP-07 Supplemental
Hearing, BPA also engaged in a public process to develop a new RPSA.
After taking public comment on a prototype RPSA, BPA published a final
RPSA in September of 2008. Among other terms included in the RPSA, BPA
adopted a provision that would allow BPA to recover the Lookback
Amounts from the IOUs by reducing future REP benefit payments. BPA's
justification for including this and other provisions in the RPSA were
explained in the 2008 RPSA Record of Decision (2008 RPSA ROD).
F. Challenges to BPA's WP-07 Supplemental ROD and RPSA Decisions: The
Assoc. of Pub. Agency Customers v. Bonneville Power Admin., Idaho Pub.
Util. Comm'n v. Bonneville Power Admin, and Avista Corp. v. Bonneville
Power Admin
BPA's decisions in the WP-07 Supplemental ROD and the 2008 RPSA ROD
were vigorously opposed by both COUs and IOUs. The COUs and entities
supporting the COUs' position claimed that BPA had grossly
underestimated the IOUs' refund obligation and that the actual
overcharge to COUs for the FY 2002-2008 period was at least $2 billion.
The IOUs, public utility commissions, and ratepayer advocacy groups, in
contrast, argued that no refunds were owed at all because the Court did
not direct BPA to provide refunds and because the terms of the 2000 REP
Settlement Agreements specifically prohibited BPA from recouping REP
benefits paid under those agreements. The IOUs and COUs also opposed
BPA's interpretation and implementation of the section 7(b)(2) rate
test for both the Lookback period and for setting rates in FY 2009.
In December 2008, fourteen petitions were filed in the Ninth
Circuit challenging the Lookback-related findings and decisions BPA
reached in the WP-07 Supplemental ROD. These challenges were
consolidated into The Assoc. of Pub. Agency Customers v. Bonneville
Power Admin., et al. (APAC). Also in December 2008, seven petitions
were filed by a number of IOUs and public utility commissions
challenging BPA's decision to adopt the final RPSAs. These challenges
were consolidated into Idaho Pub. Util. Comm'n v. Bonneville Power
Admin. (IPUC). On July 16, 2009, the Commission granted final approval
to BPA's WP-07 rates for FY 2009. Shortly thereafter, fifteen more
petitions challenging BPA's final WP-07 rates were filed with the Ninth
Circuit and consolidated into Avista Corp., et al. v. Bonneville Power
Admin. (Avista). Briefing on the issues in the APAC and IPUC cases
began in August of 2009 and concluded in March of 2010. Briefing on the
rate issues in Avista has yet to occur.
Shortly after petitions were filed in the APAC and IPUC cases, BPA
commenced a rate proceeding to establish rates for the FY 2010-2011
period (WP-10 Rate Proceeding). In the WP-10 Rate Proceeding, BPA
proposed to continue to implement its Lookback remedy by reducing the
IOUs' prospective REP benefit payments and paying refunds to the COUs
based on the determinations made in the WP-07 Supplemental ROD. BPA
also proposed to implement the section 7(b)(2) rate test in the same
manner as in the WP-07 Supplemental ROD. On July 21, 2009, BPA issued
its final ROD in the WP-10 Rate Proceeding (WP-10 ROD.) In October and
November of 2009, five IOUs filed precautionary petitions for review
with the Ninth Circuit challenging BPA's decision to continue to
implement the Lookback remedy in the WP-10 ROD. These appeals were
consolidated in Portland General Elec. et al. v. Bonneville Power
Admin. (PGE II). On August 6, 2010, the Commission granted final
approval to BPA's WP-10 rates. Subsequently, in November of 2010,
fifteen petitions were filed with the Ninth Circuit challenging the
ratemaking decisions BPA reached in the WP-10 ROD. The petitions
challenging BPA's WP-10 rate making decision have yet to be
consolidated.
Following the completion of the briefing in the APAC and IPUC
cases, the litigants in APAC, IPUC, Avista, and PGE II agreed to engage
in mediation in an attempt to resolve their numerous disputes. Because
many of the issues in the mediation would affect the prospective
implementation of the REP, the litigants invited regional parties not
involved in the litigation to participate in the mediation. The
mediation sessions commenced in early April of 2010 and continued
through May of 2010. Over fifty litigants and other parties
participated in the mediation. Although by the conclusion of the
scheduled mediation sessions the litigants and parties had not achieved
a settlement, significant progress had been made toward reaching a
compromise on all existing claims and the future implementation of the
REP. Principals from most of the litigants agreed to continue meeting
through August and September in an attempt to achieve a settlement.
In mid-September 2010, with assistance from the mediator, a large
contingent of COUs and IOUs agreed to pursue resolution of the
outstanding litigation and the future implementation of the REP
pursuant to the terms of a non-binding Agreement in Principle (AIP).
The AIP committed the negotiated parties to work in good faith on a
final settlement of the REP that adhered to certain terms and
conditions. From September to December of 2010, the parties worked to
transform the AIP into a final settlement document. The final version
of the proposed 2012 REP Settlement is expected to be completed by mid-
December.
G. Proposed 2012 REP Settlement Agreement
The proposed 2012 REP Settlement would resolve challenges over
BPA's implementation of the REP in return for a stream of REP benefits
to the IOUs for a term of 17 years. The COUs' obligation to pay REP
benefits in rates would be limited to the COUs' share of the stream of
REP benefits as set forth in the agreement. The distribution of these
REP payments to the IOUs would depend on each IOU's respective ASC and
exchange load. The IOUs would continue to file ASCs with BPA
[[Page 78702]]
pursuant to the 2008 ASCM. In addition to the stream of REP benefits,
the IOUs would receive a percentage of certain BPA Renewable Energy
Credits (RECs) and the payment of certain outstanding interim payments
due under the interim REP payment agreements between BPA and the IOUs.
The 2012 REP Settlement reflects a compromise by a substantial
majority of BPA's customers and most of the litigants to the litigation
on the outstanding REP-related issues. It was developed after extensive
negotiations by representatives of COU customers, IOU customers, public
utility commissions, and ratepayer advocacy groups. Many of these
entities signed the AIP and are expected to sign the 2012 REP
Settlement once it is completed. These parties have requested that BPA
review the proposed settlement, and, if consistent with law, execute
the Agreement and set rates consistent with its terms.
Part V. Summary of Proposal and Description of Major Studies
A. Summary of Proposal
Although BPA firmly believes that settlement of the existing REP
litigation is in the interest of all BPA ratepayers, BPA must ensure
that the terms and conditions in the 2012 REP Settlement are reasonable
and comply with all relevant statutory provisions before executing the
Agreement. BPA is conducting a section 7(i) proceeding to provide a
forum in which BPA and other interested parties can evaluate the
reasonableness and legal sufficiency of the proposed 2012 REP
Settlement.
At the conclusion of the REP-12 proceeding, the Administrator will
determine, after reviewing all evidence and arguments contained in the
record, whether the terms of the proposed 2012 REP Settlement comport
with BPA's statutory duties and authorities. If the Administrator
determines that the settlement is consistent with applicable law, and
is broadly supported by BPA's customers and other interested parties,
he will sign the proposed 2012 REP Settlement and set BPA's FY 2012-
2013 rates in accordance with the terms of the 2012 REP Settlement. In
such case, the 2012 REP Settlement would replace BPA's current
construct of withholding REP benefits due the IOUs and paying Lookback
refund credits to eligible COUs as described in the WP-07 Supplemental
ROD. In addition, the 2012 REP Settlement would settle the amount of
rate protection afforded to COUs for the term of the agreement,
obviating the need to continue the litigation over the section 7(b)(2)
decisions BPA reached in the WP-07 Supplemental ROD and the WP-10 ROD.
If the Administrator determines the proposed 2012 REP Settlement is
not consistent with BPA's statutory duties or is otherwise
unreasonable, the Administrator will not sign the 2012 REP Settlement
but will instead continue to set rates, recover Lookback Amounts and
issue refunds consistent with his decisions in the WP-07 Supplemental
ROD and the WP-10 ROD.
B. 2012 REP Settlement Analysis Initial Proposal
To test the reasonableness of the proposed 2012 REP Settlement, BPA
will perform an analysis that will develop a range of forecast REP
benefits reflecting the likely amount of REP benefits the IOUs would
receive (and conversely the amount of rate protection the COUs would
likely receive) in the absence of the 2012 REP Settlement. The range of
REP benefits will be developed by quantifying the major issues being
litigated by BPA, the IOUs, and the COUs in the current and pending
litigation. Broadly speaking, the major issues being litigated today
are the implementation of the section 7(b)(2) rate test, allocation of
rate protection costs under section 7(b)(3), and the development and
calculation of the Lookback Amounts. For each of these main issues, BPA
will develop a 17-year forecast of REP benefits that is based on the
parties' respective legal positions. The amount of REP benefits allowed
under these various assumptions will then be compared to the REP
benefits afforded to the IOUs under the 2012 REP Settlement to test
whether the terms of the 2012 REP Settlement are reasonable and
consistent with the protections provided by law.
BPA has modified the near-term Rate Analysis Model and has
developed a new long-term section 7(b)(2) rate test model to quantify
the parties' various litigation positions on rates and forecast REP
benefits. The models will be used in tandem to quantify the near-term
and long-term financial impacts on REP benefits under a variety of
different litigation scenarios. Specifically, the models will evaluate
the following contested issues: Rate test treatment of conservation
resources and their effect on loads; treatment of conservation costs in
the rate test; rate test accounting and financing treatment of
conservation resource costs; rate test repayment study; treatment of
Mid-Columbia resources; treatment of secondary energy credit;
discounting of the stream of rate projections; elasticity of DSI loads;
and allocation of rate protection costs to surplus power sales. Other
scenarios may be added during the course of the proceeding. In addition
to the rate modeling, the quantitative analysis will include the effect
of parties' positions on the amount of Lookback Amounts owed on future
REP benefits.
For purposes of the REP-12 Initial Proposal, BPA will use the
above-noted issues to produce future REP benefits under different
litigation scenarios. These scenarios are presented in the 2012 REP
Settlement Agreement Study and Analysis. The models also quantify the
impacts of non-litigation issues on future REP benefits, such as future
growth in ASCs and BPA program costs.
C. Implementation of 2012 REP Settlement in Rates
In addition to the settling of the various REP issues in
litigation, the 2012 REP Settlement also specifies certain ratemaking
treatment of REP-related costs. Implementing the 2012 REP Settlement in
ratemaking will affect the PF Exchange rate, the Industrial Firm Power
rate (IP), and the New Resources rate (NR). While these ratemaking
treatments have been already incorporated into the initial rate
proposal in the BP-12 proceeding, the REP-12 proceeding will be
examining these various ratemaking specifications to test whether the
ratemaking treatments of the 2012 REP Settlement are reasonable and
consistent with law.
D. Initial Proposal for the Section 7(b)(2) Rate Test and Lookback
Amount Determinations in the Absence of Settlement
As noted above, BPA is evaluating the reasonableness and
sustainability of the 2012 REP Settlement in the REP-12 proceeding. If
the Administrator determines that the 2012 REP Settlement is not
reasonable or is otherwise unlawful, the 2012 REP Settlement will not
be executed and BPA will set rates assuming no settlement of the REP.
Consequently, as an alternative to the 2012 REP Settlement, BPA is also
proposing to implement the section 7(b)(2) rate test, the section
7(b)(3) allocations and surcharges, and the Lookback recovery and
return for FY 2012-2013 in accordance with the decisions BPA reached in
the WP-07 Supplemental ROD and WP-10 ROD, unless otherwise stated. If
the 2012 REP Settlement is not adopted, the final decisions BPA reaches
on these issues in this case will be incorporated into the BP-12 rate
proceeding.
[[Page 78703]]
E. Major Studies
1. 2012 REP Settlement Agreement Study and Analysis
The 2012 REP Settlement Agreement Study and Analysis (REP Study)
describes the terms of the 2012 REP Settlement and provides the
analytical work BPA staff is performing to test the reasonableness of
the 2012 REP Settlement. The REP Study is comprised of two major parts.
Part I of the REP Study reviews the history of the REP and the
background underlying the current litigation. This portion of the REP
Study also contains an overview of the section 7(b)(2) rate test and a
description of how rate protection works in BPA ratemaking. Part I also
describes the terms of the proposed 2012 REP Settlement and explains
how BPA staff intends to implement the terms of the proposed settlement
in BPA's rates.
Part II of the REP Study contains BPA staff's evaluation and
analysis of the 2012 REP Settlement. This portion of the REP Study
begins with an explanation of the criteria BPA staff is using to
evaluate the 2012 REP Settlement. This section is followed by an
overview of the models BPA staff developed to create a variety of near-
and long-term forecasts of REP benefits under various scenarios. Part
II of the REP Study also describes the various factors that will have
an effect on REP benefits, such as the current and future issues in
litigation and issues related to ASCs and the PF Exchange rate. At the
end of Part II of the REP Study, BPA staff presents its scenario
analysis. In this section, BPA staff presents near- and long-term REP
benefits under different scenarios. These scenario REP benefits are
compared to the REP benefits provided under the proposed 2012 REP
Settlement to determine, from an analytical perspective, whether the
2012 REP Settlement affords rate protection to COUs and is otherwise
reasonable.
2. FY 2012-2013 7(b)(2) Rate Test and Documentation
This Study will be used only if the 2012 REP Settlement is not
adopted.
BPA has interpreted the Northwest Power Act and described how the
section 7(b)(2) rate test will be performed in the Section 7(b)(2)
Legal Interpretation (Legal Interpretation) and Section 7(b)(2)
Implementation Methodology (Implementation Methodology) published in
August, 2008. The Section 7(b)(2) Rate Test Study explains and
documents the results of the rate test.
The 7(b)(2) rate test triggers in this proposal if no REP
settlement is assumed, creating rate protection for preference
customers and causing test period costs to be reallocated to others.
The PF Public rate applied to the general requirements of COUs has been
reduced by the rate protection amount and reallocated to other rates
pursuant to section 7(b)(3). BPA's other rates, the PF Exchange rate
and the NR and IP rates, have been increased by an allocation of the
rate protection amount. An allocation of the rate protection amount has
also been assigned to surplus power sales.
3. FY 2012-2013 Lookback Study
This Study will only be used if the 2012 REP Settlement is not
adopted.
This Study explains and documents BPA's proposed modifications to
the amounts to be recovered from the IOUs and applied to the Lookback
Amounts determined in the final WP-07 Supplemental Proposal. The Study
also sets forth the accounting of the Lookback Amounts expected to be
recovered from IOUs and repaid to COUs during the FY 2012-2013 rate
period. BPA also explains in this Study what amount of Lookback will be
recovered from IOUs and returned to applicable COUs for the FY 2012-
2013 rate period.
Part VI--Proposed 2012 REP Settlement Agreement
On December 17, 2010, a draft of the proposed 2012 REP Settlement
will be available for viewing and downloading on BPA's Web site at
https://www.bpa.gov/corporate/ratecase/2012/rep-12.cfm. Copies of the
draft 2012 REP Settlement will also be available for viewing in BPA's
Public Reference Room at the BPA Headquarters, 1st Floor, 905 NE. 11th
Avenue, Portland, OR 97232.
Issued this 7th day of December 2010.
Stephen J. Wright,
Administrator and Chief Executive Officer.
[FR Doc. 2010-31622 Filed 12-15-10; 8:45 am]
BILLING CODE P