Notice of Competing Preliminary Permit Applications Accepted for Filing and Soliciting Comments, and Motions To Intervene, 73064-73065 [2010-29853]
Download as PDF
73064
Federal Register / Vol. 75, No. 228 / Monday, November 29, 2010 / Notices
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of the Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–13762–000, 13773–000, or 13784–
000) in the docket number field to
access the document. For assistance,
contact FERC Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–29856 Filed 11–26–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13736–000; Project No. 13777–
000]
Lock Hydro Friends Fund XLI;
Allegheny 7 Hydro, LLC; Notice of
Competing Preliminary Permit
Applications Accepted for Filing and
Soliciting Comments, and Motions To
Intervene
November 19, 2010.
mstockstill on DSKH9S0YB1PROD with NOTICES
On May 18, 2010, Lock Hydro Friends
Fund XLI, and Allegheny 7 Hydro, LLC
filed applications, pursuant to section
4(f) of the Federal Power Act, proposing
to study the feasibility of hydropower at
the U.S. Army Corps of Engineers
(Corps) Allegheny River Lock & Dam
No. 7 located on the Allegheny River in
Armstrong County, Pennsylvania. The
sole purpose of a preliminary permit, if
issued, is to grant the permit holder
priority to file a license application
during the permit term. A preliminary
permit does not authorize the permit
holder to perform any land-disturbing
activities or otherwise enter upon lands
or waters owned by others without the
owners’ express permission.
Descriptions of the Proposed Allegheny
River Lock & Dam No. 7 Projects
Lock Hydro Friends Fund XLI’s
project (Project No. 13736–000) would
consist of: (1) Two 24-foot-high, 75-footlong prefabricated concrete walls
attached to the downstream side of the
Corps dam which would support one
frame module; (2) the frame module
would be 109 feet long and weigh 1.16
million pounds and contain 10
generating units with a total combined
capacity of 12.5 megawatts (MW); (3) a
new switchyard containing a
transformer; (4) a proposed 6,000-footlong, 36.7-kilovolt (kV) transmission
line to an existing substation. The
proposed project would have an average
annual generation of 54.787 gigawatthours (GWh), which would be sold to a
local utility.
Applicant Contact: Mr. Mark R.
Stover, Hydro Green Energy LLC, 5090
Richmond Avenue #390, Houston, TX
77056; phone (877) 556–6566 x711.
Allegheny 7 Hydro, LLC’s project
(Project No. 13777–000) would consist
of: (1) A proposed 100-foot-long
excavated power canal; (2) a proposed
powerhouse containing three generating
units having a total installed capacity of
13.3 MW; (3) a 260-foot-long excavated
tailrace; (4) a proposed 2.1-mile-long,
69.0–kV transmission line. The
proposed project would have an average
annual generation of 49.7 GWh, which
would be sold to a local utility.
Applicant Contact: Mr. Brent Smith,
Symbiotics LLC, P.O. Box 535, Rigby, ID
83442; phone (208) 745–0834.
FERC Contact: Michael Spencer, (202)
502–6093.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36. Comments, motions to
intervene, notices of intent, and
competing applications may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of the Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–13736–000 or 13777–000) in the
docket number field to access the
document. For assistance, contact FERC
Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–29852 Filed 11–26–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13740–000; Project No. 13749–
000; Project No. 13775–000; Project No.
13781–000]
Notice of Competing Preliminary
Permit Applications Accepted for
Filing and Soliciting Comments, and
Motions To Intervene
November 19, 2010.
Lock+ Hydro Friends Fund XXXIX ..............................................................................................................................
FFP Missouri 3, LLC ......................................................................................................................................................
Allegheny 3 Hydro, LLC ...............................................................................................................................................
Three Rivers Hydro, LLC ..............................................................................................................................................
On May 18, 2010, Lock+ Hydro
Friends Fund XXXIX, FFP Missouri 3,
LLC, Allegheny 3 Hydro, LLC, and
Three Rivers Hydro LLC filed
applications, pursuant to section 4(f) of
VerDate Mar<15>2010
21:59 Nov 26, 2010
Jkt 223001
the Federal Power Act, proposing to
study the feasibility of hydropower at
the U.S. Army Corps of Engineers
(Corps) C.W. Bill Young Lock and Dam
located on the Allegheny River in
PO 00000
Frm 00038
Fmt 4703
Sfmt 4703
Project
Project
Project
Project
No.
No.
No.
No.
13740–000
13749–000
13775–000
13781–000
Allegheny County, Pennsylvania. The
sole purpose of a preliminary permit, if
issued, is to grant the permit holder
priority to file a license application
during the permit term. A preliminary
E:\FR\FM\29NON1.SGM
29NON1
mstockstill on DSKH9S0YB1PROD with NOTICES
Federal Register / Vol. 75, No. 228 / Monday, November 29, 2010 / Notices
permit does not authorize the permit
holder to perform any land-disturbing
activities or otherwise enter upon lands
or waters owned by others without the
owners’ express permission.
Descriptions of the proposed C.W. Bill
Young Lock and Dam Projects:
Lock+ Hydro Friends Fund XXXIX’s
project (Project No. 13740–000) would
consist of: (1) Two 41-foot-high, 75-footlong prefabricated concrete walls
attached to the downstream side of the
Corps dam which would support one
frame module; (2) each frame module
would be 109 feet long and weigh 1.16
million pounds and contain 10
generating units with a total combined
capacity of 12.5 megawatts (MW); (3) a
new switchyard containing a
transformer; and (4) a proposed 6,000foot-long, 69-kilovolt (kV) transmission
line connecting to an existing
substation. The proposed project would
have an average annual generation of
54.787 gigawatt-hours (GWh), which
would be sold to a local utility.
Applicant Contact: Mr. Mark R.
Stover, Hydro Green Energy LLC, 5090
Richmond Avenue #390, Houston, TX
77056; phone (877) 556–6566 x711.
FFP Missouri 3, LLC’s project (Project
No. 13749–000) would consist of: (1) An
excavated intake channel slightly longer
and wider than the powerhouse; (2) a
125-foot-long, 160-foot-wide, 60-foothigh proposed powerhouse containing
three generating units having a total
installed capacity of 15.0 MW; (3) an
excavated tailrace channel slightly
longer and wider than the powerhouse;
and (4) a proposed 6,500-foot-long,
ranging from 34.0 to 230-kV
transmission line. The proposed project
would have an average annual
generation of 93.0 GWh, which would
be sold to a local utility.
Applicant Contact: Ms. Ramya
Swaminathan, Free Flow Power
Corporation, 33 Commercial Street,
Gloucester, MA 01930; phone (978)
283–2822.
Allegheny 3 Hydro, LLC’s project
(Project No. 13775–000) would consist
of: (1) A proposed 170-foot-long
excavated power canal; (2) a proposed
powerhouse containing three generating
units having a total installed capacity of
21.0 MW; (3) a 160-foot-long excavated
tailrace; and (4) a proposed 1.6-milelong, 69.0-kV transmission line. The
proposed project would have an average
annual generation of 92.2 GWh, which
would be sold to a local utility.
Applicant Contact: Mr. Brent Smith,
Symbiotics, LLC., P.O. Box 535, Rigby,
ID 83442; phone (208) 745–0834.
Three Rivers Hydro, LLC’s project
(Project No. 13781–000) would consist
of: (1) A proposed 85-foot-long
VerDate Mar<15>2010
17:57 Nov 26, 2010
Jkt 223001
excavated power canal; (2) a 125-footlong, 160-foot-wide, 60-foot-high
proposed powerhouse containing three
generating units having a total installed
capacity of 15.0 MW; (3) a 95-foot-long
excavated tailrace; and (4) a proposed
500-foot-long, 25-kV transmission line.
The proposed project would have an
average annual generation of 93.0 GWh,
which would be sold to a local utility.
Applicant Contact: Mr. Joseph Watt,
Esq., Three Rivers Hydro, LLC, 316
South Clinton Street, Suite 4, Syracuse,
NY 13202; phone (315) 477–9914.
FERC Contact: Tim Looney (202) 502–
6096.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36. Comments, motions to
intervene, notices of intent, and
competing applications may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and seven copies to: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of the Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–13740–000, 13749–000, 13775–000,
or 13781) in the docket number field to
access the document. For assistance,
contact FERC Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–29853 Filed 11–26–10; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00039
Fmt 4703
Sfmt 4703
73065
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP11–22–000]
Tennessee Gas Pipeline Company;
Notice of Application
November 18, 2010.
Take notice that on November 5, 2010
Tennessee Gas Pipeline Company
(Tennessee), 1001 Louisiana Street,
Houston, Texas 77002, filed in Docket
No. CP11–22–000, an application
pursuant to section 3 of the Natural Gas
Act (NGA), to amend its authorization
under NGA section 3 and Presidential
Permits to allow it to import and export
natural gas from the United States to
Canada utilizing Tennessee’s existing
cross-border facilities. Specifically,
Tennessee proposes that its Presidential
Permits be amended and reissued, and
authorizations under Section 3 of the
NGA be amended to authorize
Tennessee to operate bi-directionally
two existing international border
crossings between Canada and the
United States located near Niagara Falls,
New York. Tennessee proposes no new
facilities, all as more fully set forth in
the application which is on file with the
Commission and open to public
inspection. This filing may also be
viewed on the Commission’s Web site at
https://www.ferc.gov using the ‘‘eLibrary’’
link. Enter the docket number,
excluding the last three digits, in the
docket number field to access the
document. For assistance, call (202)
502–8659 or TTY, (202) 208–3676.
Any questions regarding this
application should be directed to Mr.
Thomas Joyce, Manager, Certificates,
Tennessee Gas Pipeline Company, 1001
Louisiana Street, Houston, Texas 77002,
phone (713) 420–3299 or facsimile (713)
420–1605 or e-mail
tom.joyce@elpaso.com.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the below listed
comment date, file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
E:\FR\FM\29NON1.SGM
29NON1
Agencies
[Federal Register Volume 75, Number 228 (Monday, November 29, 2010)]
[Notices]
[Pages 73064-73065]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-29853]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 13740-000; Project No. 13749-000; Project No. 13775-000;
Project No. 13781-000]
Notice of Competing Preliminary Permit Applications Accepted for
Filing and Soliciting Comments, and Motions To Intervene
November 19, 2010.
Lock+ Hydro Friends Fund XXXIX... Project No. 13740-000
FFP Missouri 3, LLC.............. Project No. 13749-000
Allegheny 3 Hydro, LLC........... Project No. 13775-000
Three Rivers Hydro, LLC.......... Project No. 13781-000
On May 18, 2010, Lock+ Hydro Friends Fund XXXIX, FFP Missouri 3,
LLC, Allegheny 3 Hydro, LLC, and Three Rivers Hydro LLC filed
applications, pursuant to section 4(f) of the Federal Power Act,
proposing to study the feasibility of hydropower at the U.S. Army Corps
of Engineers (Corps) C.W. Bill Young Lock and Dam located on the
Allegheny River in Allegheny County, Pennsylvania. The sole purpose of
a preliminary permit, if issued, is to grant the permit holder priority
to file a license application during the permit term. A preliminary
[[Page 73065]]
permit does not authorize the permit holder to perform any land-
disturbing activities or otherwise enter upon lands or waters owned by
others without the owners' express permission.
Descriptions of the proposed C.W. Bill Young Lock and Dam Projects:
Lock+ Hydro Friends Fund XXXIX's project (Project No. 13740-000)
would consist of: (1) Two 41-foot-high, 75-foot-long prefabricated
concrete walls attached to the downstream side of the Corps dam which
would support one frame module; (2) each frame module would be 109 feet
long and weigh 1.16 million pounds and contain 10 generating units with
a total combined capacity of 12.5 megawatts (MW); (3) a new switchyard
containing a transformer; and (4) a proposed 6,000-foot-long, 69-
kilovolt (kV) transmission line connecting to an existing substation.
The proposed project would have an average annual generation of 54.787
gigawatt-hours (GWh), which would be sold to a local utility.
Applicant Contact: Mr. Mark R. Stover, Hydro Green Energy LLC, 5090
Richmond Avenue 390, Houston, TX 77056; phone (877) 556-6566
x711.
FFP Missouri 3, LLC's project (Project No. 13749-000) would consist
of: (1) An excavated intake channel slightly longer and wider than the
powerhouse; (2) a 125-foot-long, 160-foot-wide, 60-foot-high proposed
powerhouse containing three generating units having a total installed
capacity of 15.0 MW; (3) an excavated tailrace channel slightly longer
and wider than the powerhouse; and (4) a proposed 6,500-foot-long,
ranging from 34.0 to 230-kV transmission line. The proposed project
would have an average annual generation of 93.0 GWh, which would be
sold to a local utility.
Applicant Contact: Ms. Ramya Swaminathan, Free Flow Power
Corporation, 33 Commercial Street, Gloucester, MA 01930; phone (978)
283-2822.
Allegheny 3 Hydro, LLC's project (Project No. 13775-000) would
consist of: (1) A proposed 170-foot-long excavated power canal; (2) a
proposed powerhouse containing three generating units having a total
installed capacity of 21.0 MW; (3) a 160-foot-long excavated tailrace;
and (4) a proposed 1.6-mile-long, 69.0-kV transmission line. The
proposed project would have an average annual generation of 92.2 GWh,
which would be sold to a local utility.
Applicant Contact: Mr. Brent Smith, Symbiotics, LLC., P.O. Box 535,
Rigby, ID 83442; phone (208) 745-0834.
Three Rivers Hydro, LLC's project (Project No. 13781-000) would
consist of: (1) A proposed 85-foot-long excavated power canal; (2) a
125-foot-long, 160-foot-wide, 60-foot-high proposed powerhouse
containing three generating units having a total installed capacity of
15.0 MW; (3) a 95-foot-long excavated tailrace; and (4) a proposed 500-
foot-long, 25-kV transmission line. The proposed project would have an
average annual generation of 93.0 GWh, which would be sold to a local
utility.
Applicant Contact: Mr. Joseph Watt, Esq., Three Rivers Hydro, LLC,
316 South Clinton Street, Suite 4, Syracuse, NY 13202; phone (315) 477-
9914.
FERC Contact: Tim Looney (202) 502-6096.
Deadline for filing comments, motions to intervene, competing
applications (without notices of intent), or notices of intent to file
competing applications: 60 days from the issuance of this notice.
Competing applications and notices of intent must meet the requirements
of 18 CFR 4.36. Comments, motions to intervene, notices of intent, and
competing applications may be filed electronically via the Internet.
See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's
Web site https://www.ferc.gov/docs-filing/efiling.asp. Commenters can
submit brief comments up to 6,000 characters, without prior
registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information
at the end of your comments. For assistance, please contact FERC Online
Support at FERCOnlineSupport@ferc.gov; call toll-free at (866) 208-
3676; or, for TTY, contact (202) 502-8659. Although the Commission
strongly encourages electronic filing, documents may also be paper-
filed. To paper-file, mail an original and seven copies to: Kimberly D.
Bose, Secretary, Federal Energy Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
More information about this project, including a copy of the
application, can be viewed or printed on the ``eLibrary'' link of the
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P-13740-000, 13749-000, 13775-000, or 13781)
in the docket number field to access the document. For assistance,
contact FERC Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010-29853 Filed 11-26-10; 8:45 am]