Approval and Promulgation of Implementation Plans; Georgia; Prevention of Significant Deterioration and Nonattainment New Source Review Rules, 71018-71023 [2010-29246]

Download as PDF 71018 Federal Register / Vol. 75, No. 224 / Monday, November 22, 2010 / Rules and Regulations Viewing Comments and Documents To view comments, as well as documents mentioned in this preamble as being available in the docket, go to https://www.regulations.gov, click on the ‘‘read comments’’ box, which will then become highlighted in blue. In the ‘‘Keyword’’ box insert ‘‘USCG–2010– 0972’’ and click ‘‘Search.’’ Click the ‘‘Open Docket Folder’’ in the ‘‘Actions’’ column. You may also visit the Docket Management Facility in Room W12–140 on the ground floor of the Department of Transportation West Building, 1200 New Jersey Avenue, SE., Washington, DC 20590, between 9 a.m. and 5 p.m., Monday through Friday, except Federal holidays. We have an agreement with the Department of Transportation to use the Docket Management Facility. Privacy Act Anyone can search the electronic form of comments received into any of our dockets by the name of the individual submitting the comment (or signing the comment, if submitted on behalf of an association, business, labor union, etc.). You may review a Privacy Act notice regarding our public dockets in the January 17, 2008, issue of the Federal Register (73 FR 3316). Public Meeting We do not now plan to hold a public meeting. But you may submit a request for one using one of the four methods specified under ADDRESSES. Please explain why one would be beneficial. If we determine that one would aid this rulemaking, we will hold one at a time and place announced by a later notice in the Federal Register. For information on facilities or services for individuals with disabilities or to request special assistance at the public meeting, contact Jim Wetherington at the telephone number or e-mail address indicated under the regulation has been in effect since 2008; however, the bridge for which the regulation was in place (a pontoon bridge) no longer exists. With the completion of the new bridge (a swing bridge) in April 2010, there has been an average of less than one opening per month, which is down from an average of 70 per month in previous years. Currently the land traffic outpaces marine traffic but most all traffic is local and marine traffic is recreational. Vessels will be able to pass under the bridge during the deviation and therefore no alternate routes are recommended at this time. This request is in conjunction with a Notice of Proposed Rulemaking to make the test deviation schedule changes permanent. This deviation is effective from December 7, 2010 through January 6, 2011. Vessel counts were collected and analyzed by the owner and reflect a marked reduction in the number of required openings since the completion of the new bridge and removal of the old one. The expected impact on navigation during the test period will be minimal based on the increase in vertical clearance. The test deviation will allow the bridge to remain unmanned during most of the day by requiring a two-hour notice for an opening of the draw. Coordination will be through Public Notice and Local Notice to Mariners upon date of publication in the Federal Register. In accordance with 33 CFR 117.35(e), the drawbridge must return to its regular operating schedule immediately at the end of the designated time period. This deviation from the operating regulations is authorized under 33 CFR 117.35. section of this notice. jlentini on DSKJ8SOYB1PROD with RULES FOR FURTHER INFORMATION CONTACT Dated: October 26, 2010. David M. Frank, Bridge Administrator. [FR Doc. 2010–29299 Filed 11–19–10; 8:45 am] Basis and Purpose The subject bridge is the S443 Swing Bridge across the Bayou Liberty at mile 2.0, in St. Tammany Parish. The vertical clearance is 7.59 feet (2.31m) above the 2% flowline, elevation 2.5 feet (0.76m) NAVD 1988. Presently, under 33 CFR 117.469, the draw of the S433 Bridge, mile 2.0, at Slidell, shall open on signal, except that between 7 p.m. and 7 a.m., the draw shall open on signal if at least two hours notice is given. The owner requests a test to allow the public to experience the new schedule and determine if the two hour advance notice is sufficient. The current BILLING CODE 9110–04–P VerDate Mar<15>2010 15:58 Nov 19, 2010 Jkt 223001 ENVIRONMENTAL PROTECTION AGENCY 40 CFR Part 52 [EPA–R04–OAR–2006–0649–201059; FRL– 9229–5] Approval and Promulgation of Implementation Plans; Georgia; Prevention of Significant Deterioration and Nonattainment New Source Review Rules Environmental Protection Agency (EPA). AGENCY: PO 00000 Frm 00012 Fmt 4700 Sfmt 4700 ACTION: Final rule. EPA is taking final action to approve portions of the revisions to the Georgia State Implementation Plan (SIP) submitted by the State of Georgia in three submittals dated October 31, 2006, March 5, 2007, and August 22, 2007. The revisions modify Georgia’s Prevention of Significant Deterioration (PSD) and Nonattainment New Source Review (NNSR) permitting rules in the SIP to address changes to the federal New Source Review (NSR) regulations, which were promulgated by EPA on December 31, 2002, and reconsidered with minor changes on November 7, 2003 (collectively, these two final actions are referred to as the ‘‘2002 NSR Reform Rules’’). EPA proposed to approve these revisions on September 4, 2008; one comment letter was received. EPA’s response to comments is included in this notice. DATES: This rule will be effective December 22, 2010. ADDRESSES: EPA has established a docket for this action under Docket Identification No. EPA–R04–OAR– 2006–0649. All documents in the docket are listed on the https:// www.regulations.gov Web site. Although listed in the index, some information may not be publicly available, i.e., Confidential Business Information or other information whose disclosure is restricted by statute. Certain other material, such as copyrighted material, is not placed on the Internet and will be publicly available only in hard copy form. Publicly available docket materials are available either electronically through https:// www.regulations.gov or in hard copy at the Regulatory Development Section, Air Planning Branch, Air, Pesticides and Toxics Management Division, U.S. Environmental Protection Agency, Region 4, 61 Forsyth Street, SW., Atlanta, Georgia 30303–8960. EPA requests that if at all possible, you contact the person listed in the FOR FURTHER INFORMATION CONTACT section to schedule your inspection. The Regional Office’s official hours of business are Monday through Friday, 8:30 to 4:30, excluding federal holidays. FOR FURTHER INFORMATION CONTACT: Ms. Kelly Fortin, Air Permits Section, Air Planning Branch, Air, Pesticides and Toxics Management Division, U.S. Environmental Protection Agency Region 4, 61 Forsyth Street, SW., Atlanta, Georgia 30303. Telephone number: (404) 562–9117; e-mail address: fortin.kelly@epa.gov. SUPPLEMENTARY INFORMATION: Throughout this document, references SUMMARY: E:\FR\FM\22NOR1.SGM 22NOR1 Federal Register / Vol. 75, No. 224 / Monday, November 22, 2010 / Rules and Regulations to ‘‘EPA,’’ ‘‘we,’’ ‘‘us,’’ or ‘‘our,’’ are intended to mean the U.S. Environmental Protection Agency. The supplementary information is arranged as follows: I. What action is EPA taking? II. What is the background for EPA’s action? III. Response to Comments IV. Final Action V. Statutory and Executive Order Reviews jlentini on DSKJ8SOYB1PROD with RULES I. What action is EPA taking? EPA is now taking action, consistent with section 110(k)(3) of the Clean Air Act (CAA or Act), to approve portions of SIP submittals made by the State of Georgia, through the Georgia Environmental Protection Division (EPD), on October 31, 2006, March 5, 2007, and August 22, 2007. These SIP submittals consist of changes to the Georgia Rules for Air Quality Control, Chapter 391–3–1. Specifically, the October 31, 2006, revisions included changes to Rules 391–3–1–.02(7) ‘‘Prevention of Significant Deterioration of Air Quality’’ and 391–3–1–.03(8)(c) ‘‘Permit Requirements’’ related to NNSR. The March 5, 2007, submittal included changes to Rules 391–3–1–.02(7) ‘‘Prevention of Significant Deterioration of Air Quality,’’ and 391–3–1–.03(13)(c) ‘‘Emission Reduction Credits.’’ Finally, the August 22, 2007, submittal included changes to Rules 391–3–1–.02(7) ‘‘Prevention of Significant Deterioration of Air Quality,’’ and 391–3–1–.03(8) ‘‘Permit Requirements.’’ EPA approved most of the non-NSR Reform portions of the submittals (rules 391–3–1–.01(llll), 391–3–1–.02(2)(jjj), 391–3–1–.02(6)(a)4, 391–3–1–.02(12), and 391–3–1–.03(6)(b)) in a previous action (74 FR 62249, November 27, 2009). EPA has not yet acted on rule 391–3–1–.02(2)(ooo). In addition, EPA is not acting on revisions to rules 391–3– 1–.02(8)b, and 391–3–1–.03(9), because these rules are not part of the federallyapproved SIP. EPA disapproved a portion of the March 5, 2007, submittal, subparagraph 391–3–1–.03(13)(c), related to ‘‘Emissions Reduction Credits,’’ in a previous action (73 FR 79653, December 30, 2008). II. What is the background for EPA’s action? On December 31, 2002 (67 FR 80186), EPA published final rule changes to 40 Code of Federal Regulations (CFR) parts 51 and 52, regarding the CAA’s PSD and NNSR programs. On November 7, 2003 (68 FR 63021), EPA published a notice of final action on the reconsideration of the December 31, 2002, final rule changes. The December 31, 2002, and the November 7, 2003, final actions are collectively referred to as the ‘‘2002 NSR VerDate Mar<15>2010 15:58 Nov 19, 2010 Jkt 223001 Reform Rules.’’ For additional information on the 2002 NSR Reform Rules, see 67 FR 80186 (December 31, 2002). For information on the subsequent revisions to these rules, see https://www.epa.gov/nsr. On October 31, 2006, March 5, 2007, and August 22, 2007, EPD submitted revisions to EPA for the purpose of including the revised State NSR permitting rules in the SIP. Copies of Georgia’s revised NSR rules, as well as the State’s Technical Support Document, can be obtained from the Docket, as discussed in the ADDRESSES section above. On September 4, 2008 (73 FR 51606), EPA proposed to approve portions of the above-summarized SIP submittals as they pertain to Georgia’s NSR program, with the exception of the revision to subparagraph 391–3–1–.03(13)(c), related to ‘‘Emissions Reduction Credits,’’ which EPA proposed to disapprove.1 In response to requests for an extension of the public comment period, EPA extended the public comment period on that proposal through November 6, 2008 (73 FR 58084). One comment letter was received and it contained adverse comments. EPA’s response to this comment letter is below in section III, Response to Comments. EPA’s analysis of the State’s NSR reform SIP submittals is contained in the September 4, 2008, Notice of Proposed Rulemaking (NPR). The NPR, the comment letter, and additional information regarding this action may be obtained from the Docket, as discussed in the ADDRESSES section above. III. Response to Comments EPA received one comment letter from the National Resource Defense Council (NRDC) on the September 4, 2008, NPR; this letter included adverse comments. NRDC primarily commented on the requirements of the federal NSR rules, not Georgia’s application of the federal requirements in its own rules. Notably, NRDC participated in litigation challenging EPA’s 2002 promulgation of the NSR Reform Rules, where similar arguments were made by NRDC and dismissed by the DC Circuit Court. New York v. EPA, 413 F.3d 3 (DC Cir. 2005). NRDC’s comments, including exhibits, do not raise any specific concerns with Georgia’s rules, but rather, reiterate arguments made by NRDC to the DC 1 EPA took final action to disapprove the revision to subparagraph 391–3–1–.03(13)(c), related to ‘‘Emissions Reduction Credits,’’ in a previous action (73 FR 79653, December 30, 2008). PO 00000 Frm 00013 Fmt 4700 Sfmt 4700 71019 Circuit regarding Sections 110(l) and 193 of the CAA.2 While NRDC’s comments provide citations to five portions of the Georgia rules, the comments make no attempt to specifically explain or demonstrate how those identified provisions are inconsistent with either Section 110(l) or Section 193 of the CAA. Furthermore, NRDC provides no evidence supporting its allegations that approval of the specific provisions would result in a violation of the CAA or otherwise be ‘‘arbitrary, capricious, an abuse of discretion, and otherwise not in accordance with law.’’ NRDC Comments at 2. The NRDC comments include a list of 31 exhibits which the comment letter incorporates by reference into the comments. NRDC Comments at 1. The 31 exhibits appear to all be related to the DC Circuit Court case New York v. EPA, and were either submitted to that Court for review, or are relevant to that adjudication. To the extent that these exhibits were provided to the DC Circuit, those issues were previously resolved by the Court and/or already responded to by EPA in its responsive court papers. Any other documents included in the 31 exhibits that were not provided to the DC Circuit Court do not provide EPA with any comments specific to the Georgia rules at issue. Despite the lack of Georgia-specific discussion in NRDC’s letter, EPA has responded to the few comments that appear related to the September 4, 2008, NPR to approve portions of Georgia’s SIP submittals pertaining to EPA’s 2002 NSR Reform Rules. Summary of Comments Regarding Section 110(l)—NRDC Comments at 1–6 NRDC stated that finalizing the EPA rulemaking proposal at issue here would violate section 110(l) of the Act. As support for its conclusion, NRDC asserted that ‘‘[t]he 2002 NSR Reform Rule provisions that were not vacated by the DC Circuit in New York v. EPA [citation omitted] allow previouslyprohibited emissions-increases to occur.’’ NRDC Comments at 3. Further, that ‘‘Georgia nevertheless made no 2 NRDC notes that, ‘‘[t]he 2002 rule provisions considered by the DC Circuit in New York v. EPA were EPA regulations, not state ones. The court thus had no occasion to decide whether EPA could approve any state’s versions of any of the 2002 rule provisions consistently with section 110(l) of the Act.’’ NRDC Comments at 3. The Georgia rules at issue here track the federally approved rules, as upheld by the DC Circuit (which NRDC admits— NRDC Comments at 4) and NRDC supported all its comments with information related to the challenge of EPA’s 2002 NSR Reform Rules. NRDC provided no Georgia-specific support for its comments. E:\FR\FM\22NOR1.SGM 22NOR1 71020 Federal Register / Vol. 75, No. 224 / Monday, November 22, 2010 / Rules and Regulations ‘demonstration that the emissions that are allowed by its revised rule but are prohibited by the current SIP would not interfere with attainment or other applicable requirements.’ ’’ As a result, NRDC stated that, ‘‘it cannot be said of Georgia’s plan that it ‘will cause no degradation of air quality.’ ’’ NRDC Comments at 5. NRDC also stated that EPA has not made any findings that Georgia’s rule will not cause degradation of air quality or interfere with any applicable requirements concerning attainment and reasonable further progress, or any other applicable requirements of the CAA. NRDC Comments at 5. EPA Response to Section 110(l) Comments jlentini on DSKJ8SOYB1PROD with RULES EPA’s 2002 NSR Reform Rules were upheld by the DC Circuit Court which reviewed them, with the exception of the pollution control project and clean unit provisions (and the remanded matters). The three significant changes in NSR Reform that were upheld by the DC Circuit were (1) Plantwide applicability limits (PALs), (2) the 2-in10 baseline, and (3) the actual-toprojected actual emission test. The Supplemental Environmental Analysis of the Impact of the 2002 Final NSR Improvement Rules (November 21, 2002) (Supplemental Analysis) discussed each of these three changes individually, and addresses some of the issues raised by NRDC. With regard to PALs, the Supplemental Analysis explained, ‘‘[t]he EPA expects that the adoption of PAL provisions will result in a net environmental benefit. Our experience to date is that the emissions caps found in PAL-type permits result in real emissions reductions, as well as other benefits.’’ Supplemental Analysis at 6. EPA further explained that, Although it is impossible to predict how many and which sources will take PALs, and what actual reductions those sources will achieve for what pollutants, we believe that, on a nationwide basis, PALs are certain to lead to tens of thousands of tons of reductions of volatile organic compounds from source categories where frequent operational changes are made, where these changes are time-sensitive, and where there are opportunities for economical air pollution control measures. These reductions occur because of the incentives that the PAL creates to control existing and new units in order to provide room under the cap to make necessary operational changes over the life of the PAL. Supplemental Analysis at 7. The Supplemental Analysis, and particularly Appendix B, provided additional details regarding EPA’s analysis of PALs and VerDate Mar<15>2010 15:58 Nov 19, 2010 Jkt 223001 anticipated associated emissions decreases. With regard to the 2-in-10 baseline, EPA concluded that, ‘‘[t]he EPA believes that the environmental impact from the change in baseline EPA is now finalizing will not result in any significant change in benefits derived from the NSR program.’’ Supplemental Analysis at 13. This is mainly because ‘‘the number of sources receiving different baselines likely represents a very small fraction of the overall NSR permit universe, excludes new sources and coal fired power plants, and because the baseline may shift in either direction, we conclude that any overall consequences would be negligible.’’ Supplemental Analysis at 14. Additional information regarding the 2in-10 baseline changes is available in the Supplemental Analysis, Appendix F. With regard to the actual-to-projected actual test, EPA concluded, ‘‘we believe that the environmental impacts of the switch to the actual-to-projected actual test are likely to be environmentally beneficial. However, as with the change to the baseline, we believe the vast majority of sources, including new sources, new units, electric utility steam generating units, and units that actually increase emissions as a result of a change, will be unaffected by this change. Thus, the overall impacts of the NSR changes are likely to be environmentally beneficial, but only to a small extent.’’ Supplemental Analysis at 14 (see also Supplemental Analysis Appendix G). For more information on the 2002 NSR Reform Rules, and its supporting technical documents, see, https:// www.epa.gov/nsr/actions.html#2002 (last visited November 2, 2010). Section 110(l) of the CAA states, in relevant part, that ‘‘[t]he Administrator shall not approve a revision of a plan if the revision would interfere with any applicable requirement concerning attainment and reasonable further progress * * * or any other applicable requirement of this chapter.’’ CAA, 42 U.S.C. 7410(l). In ‘‘Approval and Promulgation of Implementation Plans; New Source Review; State of Nevada, Clark County Department of Air Quality and Environmental Management,’’ 69 FR 54006 (September 7, 2004), EPA stated that Section 110(l) does not preclude SIP relaxations. Rather, EPA stated that Section 110(l) only requires that the ‘‘relaxations not interfere with specified requirements of the Act including requirements for attainment and reasonable further progress,’’ and that, therefore, a state can relax its SIP PO 00000 Frm 00014 Fmt 4700 Sfmt 4700 provisions if it is able to show that it can attain or maintain the National Ambient Air Quality Standards (NAAQS) and meet any applicable reasonable further progress goals or other specific requirements. 69 FR at 54011–12. Georgia’s Proposed NSR reform rules track the federal NSR Reform Rules, with enhancements, as described in Georgia’s submittal. EPA evaluated Georgia’s rules consistent with its evaluation of the federal rules, and determined that Georgia’s rules were equivalent to or more stringent than the 2002 NSR Reform Rules. Overall, as summarized above, EPA expects that changes in air quality as a result of implementing Georgia’s rules will be consistent with EPA’s position on the federal NSR Reform Rules—that there will be somewhere between neutral and providing a modest contribution to reasonable further progress between the NSR Reform and pre-Reform provisions. EPA’s analysis for the environmental impacts of the three components of the NSR Reform rules (discussed earlier) is informative of how Georgia’s adoption of NSR Reform (based on the federal rules) will affect emissions. EPA has no reason to believe that the environmental impacts will be different from those discussed in the Supplemental Analysis for the NSR Reform rules, and thus, approval of Georgia’s SIP revision would not be contrary to Section 110(l) of the CAA. NRDC cites to five general portions of Georgia’s rules as provisions that would violate Section 110(l). These provisions are: Administrative Code of Georgia (ACG) 391–3–1–.02(7)(a), (7)(b)15, and (7)(b)(21) (from Georgia’s PSD rules); and 391–3–1–.03(8)(c) and (8)(g) (from Georgia’s NNSR rules). NRDC Comments at 2. NRDC provides no evidence supporting its contention that these specific provisions violate Section 110(l). The first provision noted by NRDC, 391–3–1–.02(7)(a), represents general requirements regarding Georgia’s PSD program, which do include some changes per the SIP revision at issue. Nonetheless, without further specificity, it is not clear why or how NRDC believes this provision is a violation of Section 110(l). In addition, NRDC has provided no Georgia-specific documentation that indicates that EPA’s analysis and conclusions regarding the impact of NSR Reform, in the Supplemental Analysis, is not applicable to Georgia’s rules, which are equivalent to or more stringent than the federal rules. In evaluating Georgia’s SIP submissions, EPA compared Georgia’s rules with the existing federal rules and determined that Georgia’s rules were E:\FR\FM\22NOR1.SGM 22NOR1 Federal Register / Vol. 75, No. 224 / Monday, November 22, 2010 / Rules and Regulations equivalent to or more stringent than the NSR reform (federal) rules. EPA also considered Georgia’s approximately thirty enhancements to the federal NSR Reform provisions, including specific anti-backsliding provisions. This comparison was discussed in the proposal to approve Georgia’s SIP revision. Georgia’s anti-backsliding provisions are discussed in their SIP submittal and included in EPA’s docket. EPA also considered Georgia’s numerous responses to comments, included as part of the submittals, wherein Georgia discussed the two-year stakeholder process, as well as answered questions as to why it was including anti-backsliding provisions and discussed the NSR Reform changes in relation to their air quality program. Georgia determined that ‘‘the NAAQS, PSD increment, RFP demonstration and visibility will be protected if these SIP revisions are approved and implemented.’’ See Technical Support for SIP Submittal dated August 4, 2007. Finally, EPA also considered the Supplemental Analysis in reviewing Georgia’s submittal and NRDC’s comments. EPA concluded that approval of Georgia’s SIP revision would not be contrary to Section 110(l) of the CAA. Absent more explicit information demonstrating that Georgia’s plan for implementation of a specific provision of its rules would interfere with any applicable requirement of the CAA and thus should be disapproved under Section 110(l), Georgia’s Technical Support and the Supplemental Analysis support approval. As a result, there is no basis to determine that approval of Georgia’s rules would violate Section 110(l). jlentini on DSKJ8SOYB1PROD with RULES Summary of Comments Regarding Section 193 of the CAA—NRDC Comments at 7–10 NRDC states that NSR is a ‘‘control requirement’’ and thus the requirements of Section 193 apply to the NSR rules at issue in the Georgia SIP revision. NRDC Comments at 7. NRDC further alleges that Georgia’s revisions ‘‘ensure that emissions will not be reduced as much as under the pre-existing rules. In fact, the modifications allow emissions to increase in Georgia’s nonattainment areas.’’ NRDC Comments at 9. Finally, NRDC states that ‘‘because section 193 lies within part D,’’ ‘‘if EPA approves Georgia’s revised plan, that action will additionally exceed the agency’s authority under section 110(k)(3) and violate section 100(l).’’ (Note, the last citation to 100(l) appears to be a typo and should read 110(l).) NRDC Comments at 10. VerDate Mar<15>2010 15:58 Nov 19, 2010 Jkt 223001 EPA Response to Section 193 Related Comments The response to the Section 193 issues raised by NRDC involves many of the same elements of the response above, to the Section 110(l) comments, which is also incorporated by reference here. Section 193 states, in relevant part, that ‘‘[n]o control requirement in effect, or required to be adopted by an order, settlement agreement, or plan in effect before November 15, 1990, in any area which is a nonattainment area for any air pollutant may be modified after November 15, 1990, in any manner unless the modification insures equivalent or greater emission reductions of such air pollutant.’’ Assuming for purposes of this discussion that Section 193 does apply to the instant action, as was discussed earlier in this notice, EPA has previously determined and explained in the Supplemental Analysis, that implementation of the 2002 NSR Reform Rule provisions still in effect (that is, those not vacated by the DC Circuit) are expected to have at least a neutral environmental benefit. In addition, Georgia’s rules include several differences from the federal rule that are likely to result in greater environmental protection. These provisions include, among others: (1) Adjusting the PAL limits downward upon renewal if average actual emissions are less than 80 percent of the PAL limit; (2) antibacksliding provisions included in the major source baseline date to ensure that baseline dates established prior to the effective date of the rule changes remain in effect; (3) additional requirements related to the definition of projected actual emissions intended to result in more accurate estimates of emissions increases; (4) provisions that make the ‘‘demand growth’’ exclusion optional, and require additional recordkeeping to ensure the rules are implemented properly; (5) a requirement that baseline actual emissions not be based on a period for which there is inadequate information; (6) a requirement to adjust baseline actual emissions for new applicable requirements; (7) provisions that require submission of an application prior to construction for all major and minor sources; (8) requirements that the ‘‘reasonable possibility’’ recordkeeping reporting requirements are triggered whenever a minor source permit is required. Therefore, even if Section 193 did apply to this action, EPA does not agree with commenter’s assertions that the SIP submissions approved in this action raise a Section 193 concern. PO 00000 Frm 00015 Fmt 4700 Sfmt 4700 71021 In addition, the core of NRDC’s argument seems to revolve around the DC Circuit Court decision in South Coast Air Quality Management District v. EPA, 472 F.3d 882 (DC Cir. 2006) (finding that NSR associated with the 1hour ozone standard included control requirements). At issue in South Coast was EPA’s determination regarding the revocation of the entire 1-hour ozone program (and corresponding SIP elements), including all the 1-hour nonattainment NSR elements, and whether such elements would continue to be required as part of SIPs implementing the new (at that time) 8-hour ozone standard. The facts in the South Coast case are distinguishable from the instant matter where the Georgia SIP is merely being updated to include changes to the Federal NSR program. EPA is not removing the entirety of Georgia’s NNSR program from the SIP as it pertains to a particular NAAQS. Rather, EPA is simply approving Georgia’s SIP revision that implements rules equivalent to or more stringent than the federal rules; and as discussed earlier in this notice, EPA developed a Supplemental Analysis to support adoption of the federal rules. The Georgia SIP will continue to operate with the full suite of NSR related elements, including a comprehensive minor source program, and the restrictive ‘de-minimus rule,’ which requires sources to aggregate 5-year emissions increases and offset emissions increases greater than 25 tons. IV. Final Action EPA is taking final action to approve portions of three revisions to the Georgia SIP submitted by the State of Georgia on October 31, 2006, March 5, 2007, and August 22, 2007, which address changes to Georgia’s PSD and NNSR programs. V. Statutory and Executive Order Reviews Under the CAA, the Administrator is required to approve a SIP submission that complies with the provisions of the Act and applicable Federal regulations. 42 U.S.C. 7410(k); 40 CFR 52.02(a). Thus, in reviewing SIP submissions, EPA’s role is to approve state choices, provided that they meet the criteria of the CAA. This action merely ensures that State law meets Federal requirements, and does not impose additional requirements beyond those imposed by State law. For that reason, this action: • Is not a ‘‘significant regulatory action’’ subject to review by the Office of Management and Budget under E:\FR\FM\22NOR1.SGM 22NOR1 71022 Federal Register / Vol. 75, No. 224 / Monday, November 22, 2010 / Rules and Regulations Executive Order 12866 (58 FR 51735, October 4, 1993); • Does not impose an information collection burden under the provisions of the Paperwork Reduction Act (44 U.S.C. 3501 et seq.); • Is certified as not having a significant economic impact on a substantial number of small entities under the Regulatory Flexibility Act (5 U.S.C. 601 et seq.); • Does not contain any unfunded mandate or significantly or uniquely affect small governments, as described in the Unfunded Mandates Reform Act of 1995 (Pub. L. 104–4); • Does not have Federalism implications as specified in Executive Order 13132 (64 FR 43255, August 10, 1999); • Is not an economically significant regulatory action based on health or safety risks subject to Executive Order 13045 (62 FR 19885, April 23, 1997); • Is not a significant regulatory action subject to Executive Order 13211 (66 FR 28355, May 22, 2001); • Is not subject to requirements of Section 12(d) of the National Technology Transfer and Advancement Act of 1995 (15 U.S.C. 272 note) because application of those requirements would be inconsistent with the CAA; and • Does not provide EPA with the discretionary authority to address, as appropriate, disproportionate human health or environmental effects, using practicable and legally permissible methods, under Executive Order 12898 (59 FR 7629, February 16, 1994). In addition, this rule does not have tribal implications as specified by Executive Order 13175 (65 FR 67249, November 9, 2000), because the SIP is not approved to apply in Indian country located in the state, and EPA notes that it will not impose substantial direct costs on tribal governments or preempt tribal law. The Congressional Review Act, 5 U.S.C. 801 et seq., as added by the Small Business Regulatory Enforcement Fairness Act of 1996, generally provides that before a rule may take effect, the agency promulgating the rule must submit a rule report, which includes a copy of the rule, to each House of the Congress and to the Comptroller General of the United States. EPA will submit a report containing this action and other required information to the U.S. Senate, the U.S. House of Representatives, and the Comptroller General of the United States prior to publication of the rule in the Federal Register. A major rule cannot take effect until 60 days after it is published in the Federal Register. This action is not a ‘‘major rule’’ as defined by 5 U.S.C. 804(2). Under section 307(b)(1) of the CAA, petitions for judicial review of this action must be filed in the United States Court of Appeals for the appropriate circuit by January 21, 2011. Filing a petition for reconsideration by the Administrator of this final rule does not affect the finality of this action for the purposes of judicial review nor does it extend the time within which a petition for judicial review may be filed, and shall not postpone the effectiveness of such rule or action. This action may not be challenged later in proceedings to enforce its requirements. (See section 307(b)(2).) List of Subjects in 40 CFR Part 52 Environmental protection, Air pollution control, Carbon monoxide, Incorporation by reference, Intergovernmental relations, Lead, Nitrogen dioxide, Ozone, Particulate matter, Reporting and recordkeeping requirements, Sulfur oxides, Volatile organic compounds. Authority: 42 U.S.C. 7401 et seq. Dated: November 12, 2010. Gwendolyn Keyes-Fleming, Regional Administrator, Region 4. ■ 40 CFR part 52 is amended as follows: PART 52—[AMENDED] 1. The authority citation for part 52 continues to read as follows: ■ Authority: 42 U.S.C. 7401 et seq. Subpart L—Georgia 2. In § 52.570(c) the table is amended by revising the entries for ‘‘391–3–1– .02(7)’’ and ‘‘391–3–1–.03’’ to read as follows: ■ § 52.570 * Identification of plan. * * * * (c) * * * EPA APPROVED GEORGIA REGULATIONS State effective date State citation Title/subject * 391–3–1–.02(7) ...... * * Prevention of Significant Deterioration of Air Quality (PSD). * 7/25/2007 * 11/22/2010 [Insert publication]. citation of * * This rule contains NOX as a precursor to ozone for PSD and NSR. * 391–3–1–.03 ........... * * Permits ........................................ * 7/25/2007 * 11/22/2010 [Insert publication]. citation of * * Changes specifically to (8)—Permit Requirements. jlentini on DSKJ8SOYB1PROD with RULES * VerDate Mar<15>2010 * 16:51 Nov 19, 2010 * Jkt 223001 PO 00000 EPA approval date * Frm 00016 Fmt 4700 Explanation * Sfmt 4700 E:\FR\FM\22NOR1.SGM * 22NOR1 * Federal Register / Vol. 75, No. 224 / Monday, November 22, 2010 / Rules and Regulations [FR Doc. 2010–29246 Filed 11–19–10; 8:45 am] Friday, 8 a.m. to 4 p.m., excluding Federal holidays. BILLING CODE 6560–50–P FOR FURTHER INFORMATION CONTACT: * * * * * Domenico Mastrangelo, Air Program, U.S. Environmental Protection Agency, Region 8, Mailcode 8P–AR, 1595 Wynkoop Street, Denver, Colorado 80202–1129, (303) 312–6416, mastrangelo.domenico@epa.gov. ENVIRONMENTAL PROTECTION AGENCY 40 CFR Part 52 [EPA–R08–OAR–2009–0557; FRL–9229–1] SUPPLEMENTARY INFORMATION: Approval and Promulgation of State Implementation Plan Revisions; State of North Dakota; Interstate Transport of Pollution for the 1997 PM2.5 and 8Hour Ozone NAAQS: ‘‘Interference With Maintenance’’ Requirement Definitions Environmental Protection Agency (EPA). ACTION: Final rule. AGENCY: EPA is partially approving the State Implementation Plan revisions submitted by the State of North Dakota on April 6, 2009. Specifically, EPA is approving the portions of the ‘‘Interstate Transport of Air Pollution’’ revisions addressing the ‘‘interference with maintenance’’ requirement of Clean Air Act (CAA) section 110(a)(2)(D)(i) for the 1997 PM2.5 and 8-hour ozone National Ambient Air Quality Standards (NAAQS). The ‘‘interference with maintenance’’ requirement of section 110(a)(2)(D)(i) prohibits a state’s emissions from interfering with maintenance of the NAAQS by any other state. This action is being taken under section 110 of the CAA. DATES: Effective Date: This final rule is effective December 22, 2010. ADDRESSES: EPA has established a docket for this action under Docket ID No. EPA–R08–OAR–2009–0557. All documents in the docket are listed on the https://www.regulations.gov Web site. Although listed in the index, some information is not publicly available, e.g., Confidential Business Information (CBI) or other information whose disclosure is restricted by statute. Certain other material, such as copyrighted material, is not placed on the Internet and will be publicly available only in hard copy form. Publicly available docket materials are available either electronically through https://www.regulations.gov, or in hard copy at the Air Program, Environmental Protection Agency (EPA), Region 8, 1595 Wynkoop Street, Denver, Colorado 80202–1129. EPA requests that if at all possible, you contact the individual listed in the FOR FURTHER INFORMATION CONTACT section to view the hard copy of the docket. You may view the hard copy of the docket Monday through jlentini on DSKJ8SOYB1PROD with RULES SUMMARY: VerDate Mar<15>2010 15:58 Nov 19, 2010 Jkt 223001 For the purpose of this document, we are giving meaning to certain words or initials as follows: (i) The words or initials Act or CAA mean or refer to the Clean Air Act, unless the context indicates otherwise. (ii) The words EPA, we, us or our mean or refer to the United States Environmental Protection Agency. (iii) The initials SIP mean or refer to State Implementation Plan. (iv) The words State or North Dakota mean the State of North Dakota, unless the context indicates otherwise. Table of Contents I . Background II . Response to Comments III. Final Action IV. Statutory and Executive Order Review I. Background On July 18, 1997, EPA promulgated new standards for 8-hour ozone and fine particulate matter (PM2.5). This action is being taken in response to the July 18, 1997 revision to the 8-hour ozone NAAQS, and PM2.5 NAAQS. This action does not address the requirements for the 2006 24- hour PM2.5 NAAQS, or the 2008 8-hour ozone NAAQS; those standards will be addressed in a later action. Section 110(a)(1) of the CAA requires states to submit SIPs to address a new or revised NAAQS within 3 years after promulgation of such standards, or within such shorter period as EPA may prescribe. Section 110(a)(2) lists the elements that such new SIPs must address, as applicable, including section 110(a)(2)(D)(i) which pertains to interstate transport of certain emissions. Section 110(a)(2)(D)(i) of the CAA requires that a state’s SIP must contain adequate provisions prohibiting any source or other type of emissions activity within the state from emitting any air pollutant in amounts which will: (1) Contribute significantly to nonattainment of the NAAQS in any other state; (2) interfere with maintenance of the NAAQS by any other state; (3) interfere with any other state’s required measures to prevent significant deterioration of air quality; PO 00000 Frm 00017 Fmt 4700 Sfmt 4700 71023 or (4) interfere with any other state’s required measures to protect visibility. On April 6, 2009 the State of North Dakota submitted a SIP addressing the section 110(a)(2)(D)(i) four requirements, noted above, for the 1997 8-hour ozone NAAQS and for the 1997 annual and 24-hour PM2.5 NAAQS. The state based its submittal on EPA’s 2006 Guidance discussed below. As noted earlier, in this rulemaking EPA is addressing the requirement that pertains to preventing sources in the State from emitting pollutants in amounts which will interfere with the maintenance of the 1997 ozone and PM2.5 NAAQS by any other state. On August 15, 2006, EPA issued its ‘‘Guidance for State Implementation Plan (SIP) Submissions to Meet Current Outstanding Obligations Under Section 110(a)(2)(D)(i) for the 8-Hour Ozone and PM2.5 National Ambient Air Quality Standards’’ (2006 Guidance) for SIP submissions that states should use to address the requirements of section 110(a)(2)(D)(i). EPA developed this guidance to make recommendations to states for making submissions to meet the requirements of section 110(a)(2)(D)(i) for the 1997 ozone NAAQS and 1997 PM2.5 NAAQS. In a Federal Register action dated September 17, 2010, EPA proposed approval of the North Dakota Interstate Transport SIP portions addressing the interference with maintenance requirement of section 110(a)(2)(D)(i). EPA concluded in its proposed action that the various factual and technical considerations supported a determination that emissions from North Dakota do not interfere with maintenance by any states with areas at risk for maintenance of the 1997 8-hour ozone NAAQS or for maintenance of the 1997 annual and 24-hour PM2.5 NAAQS. EPA did not receive comments that persuade the Agency that there is such interference with maintenance for the 1997 ozone or PM2.5 NAAQS and thus in today’s final action EPA is making a final regulatory determination that North Dakota’s sources do not interfere with maintenance of the 1997 8-hour ozone NAAQS, and the 1997 PM2.5 NAAQS in any other state. II. Response to Comments EPA received one letter dated October 18, 2010 with comments from the WildEarth Guardians (WG) environmental organization. The WG letter includes three separate comments identifiable under sections A., B., and C., and is accessible online at regulations.gov under Docket No. EPA– R08–OAR–2009–0057. Later in this section EPA responds to the significant E:\FR\FM\22NOR1.SGM 22NOR1

Agencies

[Federal Register Volume 75, Number 224 (Monday, November 22, 2010)]
[Rules and Regulations]
[Pages 71018-71023]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-29246]


=======================================================================
-----------------------------------------------------------------------

ENVIRONMENTAL PROTECTION AGENCY

40 CFR Part 52

[EPA-R04-OAR-2006-0649-201059; FRL-9229-5]


Approval and Promulgation of Implementation Plans; Georgia; 
Prevention of Significant Deterioration and Nonattainment New Source 
Review Rules

AGENCY: Environmental Protection Agency (EPA).

ACTION: Final rule.

-----------------------------------------------------------------------

SUMMARY: EPA is taking final action to approve portions of the 
revisions to the Georgia State Implementation Plan (SIP) submitted by 
the State of Georgia in three submittals dated October 31, 2006, March 
5, 2007, and August 22, 2007. The revisions modify Georgia's Prevention 
of Significant Deterioration (PSD) and Nonattainment New Source Review 
(NNSR) permitting rules in the SIP to address changes to the federal 
New Source Review (NSR) regulations, which were promulgated by EPA on 
December 31, 2002, and reconsidered with minor changes on November 7, 
2003 (collectively, these two final actions are referred to as the 
``2002 NSR Reform Rules''). EPA proposed to approve these revisions on 
September 4, 2008; one comment letter was received. EPA's response to 
comments is included in this notice.

DATES: This rule will be effective December 22, 2010.

ADDRESSES: EPA has established a docket for this action under Docket 
Identification No. EPA-R04-OAR-2006-0649. All documents in the docket 
are listed on the https://www.regulations.gov Web site. Although listed 
in the index, some information may not be publicly available, i.e., 
Confidential Business Information or other information whose disclosure 
is restricted by statute. Certain other material, such as copyrighted 
material, is not placed on the Internet and will be publicly available 
only in hard copy form. Publicly available docket materials are 
available either electronically through https://www.regulations.gov or 
in hard copy at the Regulatory Development Section, Air Planning 
Branch, Air, Pesticides and Toxics Management Division, U.S. 
Environmental Protection Agency, Region 4, 61 Forsyth Street, SW., 
Atlanta, Georgia 30303-8960. EPA requests that if at all possible, you 
contact the person listed in the FOR FURTHER INFORMATION CONTACT 
section to schedule your inspection. The Regional Office's official 
hours of business are Monday through Friday, 8:30 to 4:30, excluding 
federal holidays.

FOR FURTHER INFORMATION CONTACT: Ms. Kelly Fortin, Air Permits Section, 
Air Planning Branch, Air, Pesticides and Toxics Management Division, 
U.S. Environmental Protection Agency Region 4, 61 Forsyth Street, SW., 
Atlanta, Georgia 30303. Telephone number: (404) 562-9117; e-mail 
address: fortin.kelly@epa.gov.

SUPPLEMENTARY INFORMATION: Throughout this document, references

[[Page 71019]]

to ``EPA,'' ``we,'' ``us,'' or ``our,'' are intended to mean the U.S. 
Environmental Protection Agency. The supplementary information is 
arranged as follows:

I. What action is EPA taking?
II. What is the background for EPA's action?
III. Response to Comments
IV. Final Action
V. Statutory and Executive Order Reviews

I. What action is EPA taking?

    EPA is now taking action, consistent with section 110(k)(3) of the 
Clean Air Act (CAA or Act), to approve portions of SIP submittals made 
by the State of Georgia, through the Georgia Environmental Protection 
Division (EPD), on October 31, 2006, March 5, 2007, and August 22, 
2007. These SIP submittals consist of changes to the Georgia Rules for 
Air Quality Control, Chapter 391-3-1. Specifically, the October 31, 
2006, revisions included changes to Rules 391-3-1-.02(7) ``Prevention 
of Significant Deterioration of Air Quality'' and 391-3-1-.03(8)(c) 
``Permit Requirements'' related to NNSR. The March 5, 2007, submittal 
included changes to Rules 391-3-1-.02(7) ``Prevention of Significant 
Deterioration of Air Quality,'' and 391-3-1-.03(13)(c) ``Emission 
Reduction Credits.'' Finally, the August 22, 2007, submittal included 
changes to Rules 391-3-1-.02(7) ``Prevention of Significant 
Deterioration of Air Quality,'' and 391-3-1-.03(8) ``Permit 
Requirements.''
    EPA approved most of the non-NSR Reform portions of the submittals 
(rules 391-3-1-.01(llll), 391-3-1-.02(2)(jjj), 391-3-1-.02(6)(a)4, 391-
3-1-.02(12), and 391-3-1-.03(6)(b)) in a previous action (74 FR 62249, 
November 27, 2009). EPA has not yet acted on rule 391-3-1-.02(2)(ooo). 
In addition, EPA is not acting on revisions to rules 391-3-1-.02(8)b, 
and 391-3-1-.03(9), because these rules are not part of the federally-
approved SIP. EPA disapproved a portion of the March 5, 2007, 
submittal, subparagraph 391-3-1-.03(13)(c), related to ``Emissions 
Reduction Credits,'' in a previous action (73 FR 79653, December 30, 
2008).

II. What is the background for EPA's action?

    On December 31, 2002 (67 FR 80186), EPA published final rule 
changes to 40 Code of Federal Regulations (CFR) parts 51 and 52, 
regarding the CAA's PSD and NNSR programs. On November 7, 2003 (68 FR 
63021), EPA published a notice of final action on the reconsideration 
of the December 31, 2002, final rule changes. The December 31, 2002, 
and the November 7, 2003, final actions are collectively referred to as 
the ``2002 NSR Reform Rules.'' For additional information on the 2002 
NSR Reform Rules, see 67 FR 80186 (December 31, 2002). For information 
on the subsequent revisions to these rules, see https://www.epa.gov/nsr.
    On October 31, 2006, March 5, 2007, and August 22, 2007, EPD 
submitted revisions to EPA for the purpose of including the revised 
State NSR permitting rules in the SIP. Copies of Georgia's revised NSR 
rules, as well as the State's Technical Support Document, can be 
obtained from the Docket, as discussed in the ADDRESSES section above.
    On September 4, 2008 (73 FR 51606), EPA proposed to approve 
portions of the above-summarized SIP submittals as they pertain to 
Georgia's NSR program, with the exception of the revision to 
subparagraph 391-3-1-.03(13)(c), related to ``Emissions Reduction 
Credits,'' which EPA proposed to disapprove.\1\ In response to requests 
for an extension of the public comment period, EPA extended the public 
comment period on that proposal through November 6, 2008 (73 FR 58084). 
One comment letter was received and it contained adverse comments. 
EPA's response to this comment letter is below in section III, Response 
to Comments. EPA's analysis of the State's NSR reform SIP submittals is 
contained in the September 4, 2008, Notice of Proposed Rulemaking 
(NPR). The NPR, the comment letter, and additional information 
regarding this action may be obtained from the Docket, as discussed in 
the ADDRESSES section above.
---------------------------------------------------------------------------

    \1\ EPA took final action to disapprove the revision to 
subparagraph 391-3-1-.03(13)(c), related to ``Emissions Reduction 
Credits,'' in a previous action (73 FR 79653, December 30, 2008).
---------------------------------------------------------------------------

III. Response to Comments

    EPA received one comment letter from the National Resource Defense 
Council (NRDC) on the September 4, 2008, NPR; this letter included 
adverse comments. NRDC primarily commented on the requirements of the 
federal NSR rules, not Georgia's application of the federal 
requirements in its own rules. Notably, NRDC participated in litigation 
challenging EPA's 2002 promulgation of the NSR Reform Rules, where 
similar arguments were made by NRDC and dismissed by the DC Circuit 
Court. New York v. EPA, 413 F.3d 3 (DC Cir. 2005). NRDC's comments, 
including exhibits, do not raise any specific concerns with Georgia's 
rules, but rather, reiterate arguments made by NRDC to the DC Circuit 
regarding Sections 110(l) and 193 of the CAA.\2\
---------------------------------------------------------------------------

    \2\ NRDC notes that, ``[t]he 2002 rule provisions considered by 
the DC Circuit in New York v. EPA were EPA regulations, not state 
ones. The court thus had no occasion to decide whether EPA could 
approve any state's versions of any of the 2002 rule provisions 
consistently with section 110(l) of the Act.'' NRDC Comments at 3. 
The Georgia rules at issue here track the federally approved rules, 
as upheld by the DC Circuit (which NRDC admits--NRDC Comments at 4) 
and NRDC supported all its comments with information related to the 
challenge of EPA's 2002 NSR Reform Rules. NRDC provided no Georgia-
specific support for its comments.
---------------------------------------------------------------------------

    While NRDC's comments provide citations to five portions of the 
Georgia rules, the comments make no attempt to specifically explain or 
demonstrate how those identified provisions are inconsistent with 
either Section 110(l) or Section 193 of the CAA. Furthermore, NRDC 
provides no evidence supporting its allegations that approval of the 
specific provisions would result in a violation of the CAA or otherwise 
be ``arbitrary, capricious, an abuse of discretion, and otherwise not 
in accordance with law.'' NRDC Comments at 2.
    The NRDC comments include a list of 31 exhibits which the comment 
letter incorporates by reference into the comments. NRDC Comments at 1. 
The 31 exhibits appear to all be related to the DC Circuit Court case 
New York v. EPA, and were either submitted to that Court for review, or 
are relevant to that adjudication. To the extent that these exhibits 
were provided to the DC Circuit, those issues were previously resolved 
by the Court and/or already responded to by EPA in its responsive court 
papers. Any other documents included in the 31 exhibits that were not 
provided to the DC Circuit Court do not provide EPA with any comments 
specific to the Georgia rules at issue.
    Despite the lack of Georgia-specific discussion in NRDC's letter, 
EPA has responded to the few comments that appear related to the 
September 4, 2008, NPR to approve portions of Georgia's SIP submittals 
pertaining to EPA's 2002 NSR Reform Rules.

Summary of Comments Regarding Section 110(l)--NRDC Comments at 1-6

    NRDC stated that finalizing the EPA rulemaking proposal at issue 
here would violate section 110(l) of the Act. As support for its 
conclusion, NRDC asserted that ``[t]he 2002 NSR Reform Rule provisions 
that were not vacated by the DC Circuit in New York v. EPA [citation 
omitted] allow previously-prohibited emissions-increases to occur.'' 
NRDC Comments at 3. Further, that ``Georgia nevertheless made no

[[Page 71020]]

`demonstration that the emissions that are allowed by its revised rule 
but are prohibited by the current SIP would not interfere with 
attainment or other applicable requirements.' '' As a result, NRDC 
stated that, ``it cannot be said of Georgia's plan that it `will cause 
no degradation of air quality.' '' NRDC Comments at 5. NRDC also stated 
that EPA has not made any findings that Georgia's rule will not cause 
degradation of air quality or interfere with any applicable 
requirements concerning attainment and reasonable further progress, or 
any other applicable requirements of the CAA. NRDC Comments at 5.

EPA Response to Section 110(l) Comments

    EPA's 2002 NSR Reform Rules were upheld by the DC Circuit Court 
which reviewed them, with the exception of the pollution control 
project and clean unit provisions (and the remanded matters). The three 
significant changes in NSR Reform that were upheld by the DC Circuit 
were (1) Plantwide applicability limits (PALs), (2) the 2-in-10 
baseline, and (3) the actual-to-projected actual emission test. The 
Supplemental Environmental Analysis of the Impact of the 2002 Final NSR 
Improvement Rules (November 21, 2002) (Supplemental Analysis) discussed 
each of these three changes individually, and addresses some of the 
issues raised by NRDC.
    With regard to PALs, the Supplemental Analysis explained, ``[t]he 
EPA expects that the adoption of PAL provisions will result in a net 
environmental benefit. Our experience to date is that the emissions 
caps found in PAL-type permits result in real emissions reductions, as 
well as other benefits.'' Supplemental Analysis at 6. EPA further 
explained that,

    Although it is impossible to predict how many and which sources 
will take PALs, and what actual reductions those sources will 
achieve for what pollutants, we believe that, on a nationwide basis, 
PALs are certain to lead to tens of thousands of tons of reductions 
of volatile organic compounds from source categories where frequent 
operational changes are made, where these changes are time-
sensitive, and where there are opportunities for economical air 
pollution control measures. These reductions occur because of the 
incentives that the PAL creates to control existing and new units in 
order to provide room under the cap to make necessary operational 
changes over the life of the PAL.

Supplemental Analysis at 7. The Supplemental Analysis, and particularly 
Appendix B, provided additional details regarding EPA's analysis of 
PALs and anticipated associated emissions decreases.

    With regard to the 2-in-10 baseline, EPA concluded that, ``[t]he 
EPA believes that the environmental impact from the change in baseline 
EPA is now finalizing will not result in any significant change in 
benefits derived from the NSR program.'' Supplemental Analysis at 13. 
This is mainly because ``the number of sources receiving different 
baselines likely represents a very small fraction of the overall NSR 
permit universe, excludes new sources and coal fired power plants, and 
because the baseline may shift in either direction, we conclude that 
any overall consequences would be negligible.'' Supplemental Analysis 
at 14. Additional information regarding the 2-in-10 baseline changes is 
available in the Supplemental Analysis, Appendix F.
    With regard to the actual-to-projected actual test, EPA concluded, 
``we believe that the environmental impacts of the switch to the 
actual-to-projected actual test are likely to be environmentally 
beneficial. However, as with the change to the baseline, we believe the 
vast majority of sources, including new sources, new units, electric 
utility steam generating units, and units that actually increase 
emissions as a result of a change, will be unaffected by this change. 
Thus, the overall impacts of the NSR changes are likely to be 
environmentally beneficial, but only to a small extent.'' Supplemental 
Analysis at 14 (see also Supplemental Analysis Appendix G).
    For more information on the 2002 NSR Reform Rules, and its 
supporting technical documents, see, https://www.epa.gov/nsr/actions.html#2002 (last visited November 2, 2010).
    Section 110(l) of the CAA states, in relevant part, that ``[t]he 
Administrator shall not approve a revision of a plan if the revision 
would interfere with any applicable requirement concerning attainment 
and reasonable further progress * * * or any other applicable 
requirement of this chapter.'' CAA, 42 U.S.C. 7410(l). In ``Approval 
and Promulgation of Implementation Plans; New Source Review; State of 
Nevada, Clark County Department of Air Quality and Environmental 
Management,'' 69 FR 54006 (September 7, 2004), EPA stated that Section 
110(l) does not preclude SIP relaxations. Rather, EPA stated that 
Section 110(l) only requires that the ``relaxations not interfere with 
specified requirements of the Act including requirements for attainment 
and reasonable further progress,'' and that, therefore, a state can 
relax its SIP provisions if it is able to show that it can attain or 
maintain the National Ambient Air Quality Standards (NAAQS) and meet 
any applicable reasonable further progress goals or other specific 
requirements. 69 FR at 54011-12.
    Georgia's Proposed NSR reform rules track the federal NSR Reform 
Rules, with enhancements, as described in Georgia's submittal. EPA 
evaluated Georgia's rules consistent with its evaluation of the federal 
rules, and determined that Georgia's rules were equivalent to or more 
stringent than the 2002 NSR Reform Rules. Overall, as summarized above, 
EPA expects that changes in air quality as a result of implementing 
Georgia's rules will be consistent with EPA's position on the federal 
NSR Reform Rules--that there will be somewhere between neutral and 
providing a modest contribution to reasonable further progress between 
the NSR Reform and pre-Reform provisions. EPA's analysis for the 
environmental impacts of the three components of the NSR Reform rules 
(discussed earlier) is informative of how Georgia's adoption of NSR 
Reform (based on the federal rules) will affect emissions. EPA has no 
reason to believe that the environmental impacts will be different from 
those discussed in the Supplemental Analysis for the NSR Reform rules, 
and thus, approval of Georgia's SIP revision would not be contrary to 
Section 110(l) of the CAA.
    NRDC cites to five general portions of Georgia's rules as 
provisions that would violate Section 110(l). These provisions are: 
Administrative Code of Georgia (ACG) 391-3-1-.02(7)(a), (7)(b)15, and 
(7)(b)(21) (from Georgia's PSD rules); and 391-3-1-.03(8)(c) and (8)(g) 
(from Georgia's NNSR rules). NRDC Comments at 2. NRDC provides no 
evidence supporting its contention that these specific provisions 
violate Section 110(l). The first provision noted by NRDC, 391-3-
1-.02(7)(a), represents general requirements regarding Georgia's PSD 
program, which do include some changes per the SIP revision at issue. 
Nonetheless, without further specificity, it is not clear why or how 
NRDC believes this provision is a violation of Section 110(l). In 
addition, NRDC has provided no Georgia-specific documentation that 
indicates that EPA's analysis and conclusions regarding the impact of 
NSR Reform, in the Supplemental Analysis, is not applicable to 
Georgia's rules, which are equivalent to or more stringent than the 
federal rules.
    In evaluating Georgia's SIP submissions, EPA compared Georgia's 
rules with the existing federal rules and determined that Georgia's 
rules were

[[Page 71021]]

equivalent to or more stringent than the NSR reform (federal) rules. 
EPA also considered Georgia's approximately thirty enhancements to the 
federal NSR Reform provisions, including specific anti-backsliding 
provisions. This comparison was discussed in the proposal to approve 
Georgia's SIP revision. Georgia's anti-backsliding provisions are 
discussed in their SIP submittal and included in EPA's docket. EPA also 
considered Georgia's numerous responses to comments, included as part 
of the submittals, wherein Georgia discussed the two-year stakeholder 
process, as well as answered questions as to why it was including anti-
backsliding provisions and discussed the NSR Reform changes in relation 
to their air quality program. Georgia determined that ``the NAAQS, PSD 
increment, RFP demonstration and visibility will be protected if these 
SIP revisions are approved and implemented.'' See Technical Support for 
SIP Submittal dated August 4, 2007. Finally, EPA also considered the 
Supplemental Analysis in reviewing Georgia's submittal and NRDC's 
comments. EPA concluded that approval of Georgia's SIP revision would 
not be contrary to Section 110(l) of the CAA. Absent more explicit 
information demonstrating that Georgia's plan for implementation of a 
specific provision of its rules would interfere with any applicable 
requirement of the CAA and thus should be disapproved under Section 
110(l), Georgia's Technical Support and the Supplemental Analysis 
support approval. As a result, there is no basis to determine that 
approval of Georgia's rules would violate Section 110(l).

Summary of Comments Regarding Section 193 of the CAA--NRDC Comments at 
7-10

    NRDC states that NSR is a ``control requirement'' and thus the 
requirements of Section 193 apply to the NSR rules at issue in the 
Georgia SIP revision. NRDC Comments at 7. NRDC further alleges that 
Georgia's revisions ``ensure that emissions will not be reduced as much 
as under the pre-existing rules. In fact, the modifications allow 
emissions to increase in Georgia's nonattainment areas.'' NRDC Comments 
at 9. Finally, NRDC states that ``because section 193 lies within part 
D,'' ``if EPA approves Georgia's revised plan, that action will 
additionally exceed the agency's authority under section 110(k)(3) and 
violate section 100(l).'' (Note, the last citation to 100(l) appears to 
be a typo and should read 110(l).) NRDC Comments at 10.

EPA Response to Section 193 Related Comments

    The response to the Section 193 issues raised by NRDC involves many 
of the same elements of the response above, to the Section 110(l) 
comments, which is also incorporated by reference here.
    Section 193 states, in relevant part, that ``[n]o control 
requirement in effect, or required to be adopted by an order, 
settlement agreement, or plan in effect before November 15, 1990, in 
any area which is a nonattainment area for any air pollutant may be 
modified after November 15, 1990, in any manner unless the modification 
insures equivalent or greater emission reductions of such air 
pollutant.''
    Assuming for purposes of this discussion that Section 193 does 
apply to the instant action, as was discussed earlier in this notice, 
EPA has previously determined and explained in the Supplemental 
Analysis, that implementation of the 2002 NSR Reform Rule provisions 
still in effect (that is, those not vacated by the DC Circuit) are 
expected to have at least a neutral environmental benefit. In addition, 
Georgia's rules include several differences from the federal rule that 
are likely to result in greater environmental protection. These 
provisions include, among others: (1) Adjusting the PAL limits downward 
upon renewal if average actual emissions are less than 80 percent of 
the PAL limit; (2) anti-backsliding provisions included in the major 
source baseline date to ensure that baseline dates established prior to 
the effective date of the rule changes remain in effect; (3) additional 
requirements related to the definition of projected actual emissions 
intended to result in more accurate estimates of emissions increases; 
(4) provisions that make the ``demand growth'' exclusion optional, and 
require additional recordkeeping to ensure the rules are implemented 
properly; (5) a requirement that baseline actual emissions not be based 
on a period for which there is inadequate information; (6) a 
requirement to adjust baseline actual emissions for new applicable 
requirements; (7) provisions that require submission of an application 
prior to construction for all major and minor sources; (8) requirements 
that the ``reasonable possibility'' recordkeeping reporting 
requirements are triggered whenever a minor source permit is required. 
Therefore, even if Section 193 did apply to this action, EPA does not 
agree with commenter's assertions that the SIP submissions approved in 
this action raise a Section 193 concern.
    In addition, the core of NRDC's argument seems to revolve around 
the DC Circuit Court decision in South Coast Air Quality Management 
District v. EPA, 472 F.3d 882 (DC Cir. 2006) (finding that NSR 
associated with the 1-hour ozone standard included control 
requirements). At issue in South Coast was EPA's determination 
regarding the revocation of the entire 1-hour ozone program (and 
corresponding SIP elements), including all the 1-hour nonattainment NSR 
elements, and whether such elements would continue to be required as 
part of SIPs implementing the new (at that time) 8-hour ozone standard. 
The facts in the South Coast case are distinguishable from the instant 
matter where the Georgia SIP is merely being updated to include changes 
to the Federal NSR program. EPA is not removing the entirety of 
Georgia's NNSR program from the SIP as it pertains to a particular 
NAAQS. Rather, EPA is simply approving Georgia's SIP revision that 
implements rules equivalent to or more stringent than the federal 
rules; and as discussed earlier in this notice, EPA developed a 
Supplemental Analysis to support adoption of the federal rules. The 
Georgia SIP will continue to operate with the full suite of NSR related 
elements, including a comprehensive minor source program, and the 
restrictive `de-minimus rule,' which requires sources to aggregate 5-
year emissions increases and offset emissions increases greater than 25 
tons.

IV. Final Action

    EPA is taking final action to approve portions of three revisions 
to the Georgia SIP submitted by the State of Georgia on October 31, 
2006, March 5, 2007, and August 22, 2007, which address changes to 
Georgia's PSD and NNSR programs.

V. Statutory and Executive Order Reviews

    Under the CAA, the Administrator is required to approve a SIP 
submission that complies with the provisions of the Act and applicable 
Federal regulations. 42 U.S.C. 7410(k); 40 CFR 52.02(a). Thus, in 
reviewing SIP submissions, EPA's role is to approve state choices, 
provided that they meet the criteria of the CAA. This action merely 
ensures that State law meets Federal requirements, and does not impose 
additional requirements beyond those imposed by State law. For that 
reason, this action:
     Is not a ``significant regulatory action'' subject to 
review by the Office of Management and Budget under

[[Page 71022]]

Executive Order 12866 (58 FR 51735, October 4, 1993);
     Does not impose an information collection burden under the 
provisions of the Paperwork Reduction Act (44 U.S.C. 3501 et seq.);
     Is certified as not having a significant economic impact 
on a substantial number of small entities under the Regulatory 
Flexibility Act (5 U.S.C. 601 et seq.);
     Does not contain any unfunded mandate or significantly or 
uniquely affect small governments, as described in the Unfunded 
Mandates Reform Act of 1995 (Pub. L. 104-4);
     Does not have Federalism implications as specified in 
Executive Order 13132 (64 FR 43255, August 10, 1999);
     Is not an economically significant regulatory action based 
on health or safety risks subject to Executive Order 13045 (62 FR 
19885, April 23, 1997);
     Is not a significant regulatory action subject to 
Executive Order 13211 (66 FR 28355, May 22, 2001);
     Is not subject to requirements of Section 12(d) of the 
National Technology Transfer and Advancement Act of 1995 (15 U.S.C. 272 
note) because application of those requirements would be inconsistent 
with the CAA; and
     Does not provide EPA with the discretionary authority to 
address, as appropriate, disproportionate human health or environmental 
effects, using practicable and legally permissible methods, under 
Executive Order 12898 (59 FR 7629, February 16, 1994).
    In addition, this rule does not have tribal implications as 
specified by Executive Order 13175 (65 FR 67249, November 9, 2000), 
because the SIP is not approved to apply in Indian country located in 
the state, and EPA notes that it will not impose substantial direct 
costs on tribal governments or preempt tribal law.
    The Congressional Review Act, 5 U.S.C. 801 et seq., as added by the 
Small Business Regulatory Enforcement Fairness Act of 1996, generally 
provides that before a rule may take effect, the agency promulgating 
the rule must submit a rule report, which includes a copy of the rule, 
to each House of the Congress and to the Comptroller General of the 
United States. EPA will submit a report containing this action and 
other required information to the U.S. Senate, the U.S. House of 
Representatives, and the Comptroller General of the United States prior 
to publication of the rule in the Federal Register. A major rule cannot 
take effect until 60 days after it is published in the Federal 
Register. This action is not a ``major rule'' as defined by 5 U.S.C. 
804(2).
    Under section 307(b)(1) of the CAA, petitions for judicial review 
of this action must be filed in the United States Court of Appeals for 
the appropriate circuit by January 21, 2011. Filing a petition for 
reconsideration by the Administrator of this final rule does not affect 
the finality of this action for the purposes of judicial review nor 
does it extend the time within which a petition for judicial review may 
be filed, and shall not postpone the effectiveness of such rule or 
action. This action may not be challenged later in proceedings to 
enforce its requirements. (See section 307(b)(2).)

List of Subjects in 40 CFR Part 52

    Environmental protection, Air pollution control, Carbon monoxide, 
Incorporation by reference, Intergovernmental relations, Lead, Nitrogen 
dioxide, Ozone, Particulate matter, Reporting and recordkeeping 
requirements, Sulfur oxides, Volatile organic compounds.

    Authority:  42 U.S.C. 7401 et seq.

    Dated: November 12, 2010.
Gwendolyn Keyes-Fleming,
Regional Administrator, Region 4.

0
40 CFR part 52 is amended as follows:

PART 52--[AMENDED]

0
1. The authority citation for part 52 continues to read as follows:

    Authority:  42 U.S.C. 7401 et seq.

Subpart L--Georgia

0
2. In Sec.  52.570(c) the table is amended by revising the entries for 
``391-3-1-.02(7)'' and ``391-3-1-.03'' to read as follows:


Sec.  52.570  Identification of plan.

* * * * *
    (c) * * *

                                        EPA Approved Georgia Regulations
----------------------------------------------------------------------------------------------------------------
                                                           State
        State citation             Title/subject      effective date    EPA approval date        Explanation
----------------------------------------------------------------------------------------------------------------
 
                                                  * * * * * * *
391-3-1-.02(7)...............  Prevention of               7/25/2007  11/22/2010 [Insert    This rule contains
                                Significant                            citation of           NOX as a precursor
                                Deterioration of Air                   publication].         to ozone for PSD
                                Quality (PSD).                                               and NSR.
 
                                                  * * * * * * *
391-3-1-.03..................  Permits..............       7/25/2007  11/22/2010 [Insert    Changes specifically
                                                                       citation of           to (8)--Permit
                                                                       publication].         Requirements.
 
                                                  * * * * * * *
----------------------------------------------------------------------------------------------------------------