New York Tidal Energy Company; Notice Concluding Pre-Filing Process and Approving Process Plan and Schedule, 70224-70225 [2010-28914]
Download as PDF
mstockstill on DSKH9S0YB1PROD with NOTICES
70224
Federal Register / Vol. 75, No. 221 / Wednesday, November 17, 2010 / Notices
to the proceedings for this project
should, on or before the comment date
stated below, file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
7 copies of filings made with the
Commission and must mail a copy to
the applicant and to every other party in
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commentors will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commentors will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commentors
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 7 copies
VerDate Mar<15>2010
16:21 Nov 16, 2010
Jkt 223001
of the protest or intervention to the
Federal Energy regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: November 30, 2010.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–28911 Filed 11–16–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13846–000]
Qualified Hydro 29, LLC; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
November 9, 2010.
On September 29, 2010, Qualified
Hydro 29, LLC filed an application,
pursuant to section 4(f) of the Federal
Power Act, proposing to study the
feasibility of the Mississinewa Lake
Dam Hydroelectric Project No. 13846, to
be located at the existing Mississinewa
Lake Dam on the Mississinewa River, in
the City of Peru, in Miami County,
Indiana. The Mississinewa Lake Dam is
owned by the United States government
and operated by the U.S. Army Corps of
Engineers.
The proposed project would consist
of: (1) The existing earth filled dam
which is 140 feet in height with an
overall length of 8,000 feet; (2) a new
reinforced concrete powerhouse, 45 feet
by 65 feet, to be located downstream of
the existing stilling basin; (3) a new 75
foot-long, 10.0-foot diameter penstock;
(4) two vertical Kaplan turbinegenerator units with a combined
capacity of 7.0 megawatts; (5) a new 8
MVA substation; (6) a new two milelong, 12.5 to 34.5-kilovolt transmission
line; and (7) appurtenant facilities. The
project would have an estimated annual
generation of 21.0 gigawatt-hours.
PO 00000
Frm 00026
Fmt 4703
Sfmt 4703
Applicant Contact: Ramya
Swaminathan, 33 Commercial Street,
Gloucester, MA 01930, (978) 252–7112.
FERC Contact: Tyrone A. Williams,
(202) 502–6331.
Deadline for filing comments, motions
to intervene, and competing
applications (without notices of intent),
or notices of intent to file competing
applications: 60 days from the issuance
date of this notice. Comments, motions
to intervene, notices of intent, and
competing applications may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site (https://www.ferc.gov/docs-filing/
ferconline.asp) under the ‘‘eFiling’’ link.
For a simpler method of submitting text
only comments, click on ‘‘Quick
Comment.’’ For assistance, please
contact FERC Online Support at
FERCOnlineSupport.gov; call toll-free at
(866) 208–3676; or, for TTY, contact
(202) 502–8659. Although the
Commission strongly recommends
electronic filing, documents may also be
paper-filed. To paper-file, an original
and eight copies should be mailed to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
For more information on how to submit
these types of filings please go to the
Commission’s Web site located at https://
www.ferc.gov/filing-comments.asp.
More information about this project,
including a copy of the application can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–13846) in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–28915 Filed 11–16–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12665–003]
New York Tidal Energy Company;
Notice Concluding Pre-Filing Process
and Approving Process Plan and
Schedule
November 9, 2010.
a. Type of Filing: Notice of Intent to
File Application for License for a
Hydrokinetic Pilot Project.
b. Project No.: 12665–003.
c. Dated Filed: June 1, 2009.
E:\FR\FM\17NON1.SGM
17NON1
Federal Register / Vol. 75, No. 221 / Wednesday, November 17, 2010 / Notices
d. Submitted By: New York Tidal
Energy Company.
e. Name of Project: East River Tidal
Energy Pilot Project.
f. Location: In the East River at Hell
Gate, in New York City, New York. The
project would not occupy Federal lands.
g. Filed Pursuant to: 18 CFR 5.3 of the
Commission’s regulations.
h. Applicant Contact: Daniel Power,
Oceana Energy Company, 1785
Massachusetts Avenue, NW., Suite 100,
Washington, DC 20036; phone: (202)
465–6405.
i. FERC Contact: Timothy Konnert
(202) 502–6359.
j. New York Tidal Energy Company
(NYTEC) has filed with the Commission:
(1) A notice of intent (NOI) to file an
application for a pilot hydrokinetic
hydropower project and a draft license
application with monitoring plans; (2) a
request for waivers of certain Integrated
Licensing Process (ILP) regulations
necessary for expedited processing of a
license application for a hydrokinetic
pilot project; (3) a proposed process
plan and schedule; and (4) a request to
be designated as the non-Federal
representative for section 7 of the
Endangered Species Act (ESA)
consultation and for section 106
consultation under the National Historic
Preservation Act.
k. A notice was issued on June 10,
2009 soliciting comments on the draft
license application from agencies and
stakeholders. Comments were filed by
Federal and State agencies, and nongovernmental organizations. No
comments were filed opposing the
request to waive the integrated licensing
process regulations or the proposed
process plan and schedule.
l. The June 10, 2009 notice approved
NYTEC’s request to be designated as the
non-Federal representative for section 7
of the ESA with the U.S. Fish and
Wildlife Service and the National
Marine Fisheries Service, and its request
to initiate consultation under section
106 of the National Historic
Preservation Act with the New York
State Historic Preservation Officer.
70225
m. The proposed East River Tidal
Energy Pilot Project would consist of:
(1) A 2-meter-diameter 20-kilowatt (kW)
capacity hydrokinetic device during
Phase 1, which would be replaced by a
6-meter-diameter 200-kW device in
Phase 2; (2) a 1,300-foot-long
transmission cable that would
interconnect with the existing Wards
Island Park System; and (3) appurtenant
facilities for operating and maintaining
the project. Based on the proposed 250
hours of testing operation per-year, the
project is estimated to have an annual
generation of 5 megawatt-hours peryear, which would be sold to a local
utility.
n. The pre-filing process has been
concluded and the requisite regulations
have been waived such that the process
and schedule indicated below can be
implemented.
o. Post-filing process schedule. The
post-filing process will be conducted
pursuant to the following schedule.
Revisions to the schedule may be made
as needed.
Milestones
Dates
Final license application expected ..............................................................................................................................................
Issue notice of acceptance and ready for environmental analysis and request for interventions .............................................
Issue biological assessment .......................................................................................................................................................
Comments and interventions due ...............................................................................................................................................
Issue notice of availability of environmental assessment ...........................................................................................................
Comments due and 10(j) resolution, if needed ..........................................................................................................................
January 31, 2011.
February 15, 2011.
February 15, 2011.
March 17, 2011.
May 16, 2011.
June 15, 2011.
p. Register online at https://ferc.gov/
esubscribenow.htm to be notified via email of new filing and issuances related
to this or other pending projects. For
assistance, contact FERC Online
Support.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–28914 Filed 11–16–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP11–17–000]
El Paso Natural Gas Company; Notice
of Application
mstockstill on DSKH9S0YB1PROD with NOTICES
November 9, 2010.
Take notice that on October 29, 2010,
El Paso Natural Gas Company (EPNG),
P.O. Box 1087, Colorado Springs,
Colorado 80944, filed in the above
referenced docket an application,
pursuant to section 7(c)(1)(b) of the
Natural Gas Act (NGA) and Rule
207(a)(5) of the Commission’s
VerDate Mar<15>2010
16:21 Nov 16, 2010
Jkt 223001
regulations, requesting the temporary
deactivation of sixteen compressor units
on its South Mainline System in
Arizona and New Mexico and five
compressor units on its San Juan
Triangle and North Mainline System in
Arizona and New Mexico, all as more
fully set forth in the application which
is on file with the Commission and open
to public inspection. The filing is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site
Web at https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket number
excluding the last three digits in the
docket number field to access the
document. For assistance, contact FERC
at FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TTY, (202)
502–8659.
Any questions concerning this
application may be directed to Susan C.
Stires, Director, Regulatory Affairs, El
Paso Natural Gas Company, P.O. Box
1087, Colorado Springs, Colorado 80944
at (719) 667–7514 or by fax at (719) 667–
7534.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
Commission staff will either: complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify Federal and
State agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
Federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
E:\FR\FM\17NON1.SGM
17NON1
Agencies
[Federal Register Volume 75, Number 221 (Wednesday, November 17, 2010)]
[Notices]
[Pages 70224-70225]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-28914]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 12665-003]
New York Tidal Energy Company; Notice Concluding Pre-Filing
Process and Approving Process Plan and Schedule
November 9, 2010.
a. Type of Filing: Notice of Intent to File Application for License
for a Hydrokinetic Pilot Project.
b. Project No.: 12665-003.
c. Dated Filed: June 1, 2009.
[[Page 70225]]
d. Submitted By: New York Tidal Energy Company.
e. Name of Project: East River Tidal Energy Pilot Project.
f. Location: In the East River at Hell Gate, in New York City, New
York. The project would not occupy Federal lands.
g. Filed Pursuant to: 18 CFR 5.3 of the Commission's regulations.
h. Applicant Contact: Daniel Power, Oceana Energy Company, 1785
Massachusetts Avenue, NW., Suite 100, Washington, DC 20036; phone:
(202) 465-6405.
i. FERC Contact: Timothy Konnert (202) 502-6359.
j. New York Tidal Energy Company (NYTEC) has filed with the
Commission: (1) A notice of intent (NOI) to file an application for a
pilot hydrokinetic hydropower project and a draft license application
with monitoring plans; (2) a request for waivers of certain Integrated
Licensing Process (ILP) regulations necessary for expedited processing
of a license application for a hydrokinetic pilot project; (3) a
proposed process plan and schedule; and (4) a request to be designated
as the non-Federal representative for section 7 of the Endangered
Species Act (ESA) consultation and for section 106 consultation under
the National Historic Preservation Act.
k. A notice was issued on June 10, 2009 soliciting comments on the
draft license application from agencies and stakeholders. Comments were
filed by Federal and State agencies, and non-governmental
organizations. No comments were filed opposing the request to waive the
integrated licensing process regulations or the proposed process plan
and schedule.
l. The June 10, 2009 notice approved NYTEC's request to be
designated as the non-Federal representative for section 7 of the ESA
with the U.S. Fish and Wildlife Service and the National Marine
Fisheries Service, and its request to initiate consultation under
section 106 of the National Historic Preservation Act with the New York
State Historic Preservation Officer.
m. The proposed East River Tidal Energy Pilot Project would consist
of: (1) A 2-meter-diameter 20-kilowatt (kW) capacity hydrokinetic
device during Phase 1, which would be replaced by a 6-meter-diameter
200-kW device in Phase 2; (2) a 1,300-foot-long transmission cable that
would interconnect with the existing Wards Island Park System; and (3)
appurtenant facilities for operating and maintaining the project. Based
on the proposed 250 hours of testing operation per-year, the project is
estimated to have an annual generation of 5 megawatt-hours per-year,
which would be sold to a local utility.
n. The pre-filing process has been concluded and the requisite
regulations have been waived such that the process and schedule
indicated below can be implemented.
o. Post-filing process schedule. The post-filing process will be
conducted pursuant to the following schedule. Revisions to the schedule
may be made as needed.
------------------------------------------------------------------------
Milestones Dates
------------------------------------------------------------------------
Final license application expected... January 31, 2011.
Issue notice of acceptance and ready February 15, 2011.
for environmental analysis and
request for interventions.
Issue biological assessment.......... February 15, 2011.
Comments and interventions due....... March 17, 2011.
Issue notice of availability of May 16, 2011.
environmental assessment.
Comments due and 10(j) resolution, if June 15, 2011.
needed.
------------------------------------------------------------------------
p. Register online at https://ferc.gov/esubscribenow.htm to be
notified via e-mail of new filing and issuances related to this or
other pending projects. For assistance, contact FERC Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010-28914 Filed 11-16-10; 8:45 am]
BILLING CODE 6717-01-P