Notice of Availability of the Record of Decision for the Calico Solar Project and Associated Amendment to the California Desert Conservation Area Resource Management Plan-Amendment, San Bernardino County, CA, 65650 [2010-27027]
Download as PDF
65650
Federal Register / Vol. 75, No. 206 / Tuesday, October 26, 2010 / Notices
Office during regular business hours,
except holidays.
Before including your address, phone
number, e-mail address, or other
personal identifying information in your
comment, you should be aware that
your entire comment—including your
personal identifying information—may
be made publicly available at any time.
While you can ask us in your comment
to withhold your personal identifying
information from public review, we
cannot guarantee that we will be able to
do so.
Authority: 43 CFR 2711.1–2.
Ruth A. Miller,
Shoshone Field Manager.
[FR Doc. 2010–27041 Filed 10–25–10; 8:45 am]
BILLING CODE 4310–GG–P
DEPARTMENT OF THE INTERIOR
Bureau of Land Management
[CACA 49537, LLCAD08000, L51030000,
FX0000, LVRAM109AA03]
Notice of Availability of the Record of
Decision for the Calico Solar Project
and Associated Amendment to the
California Desert Conservation Area
Resource Management PlanAmendment, San Bernardino County,
CA
Bureau of Land Management,
Interior.
ACTION: Notice of availability.
AGENCY:
The Bureau of Land
Management (BLM) announces the
availability of the Record of Decision
(ROD) for a right-of-way (ROW) lease/
grant to Calico Solar Limited Liability
Corporation (LLC) for the Calico Solar
Project (formerly SES Solar One) and an
associated Amendment to the California
Desert Conservation Area Resource
Management Plan (CDCA Plan). The
Calico Solar Project is located in San
Bernardino County, California. The
Secretary of the Interior signed the ROD
on October 20, 2010, which constitutes
the final decision of the Department.
The ROD and the Approved Plan
Amendment are effective immediately.
DATES: These decisions are effective
immediately upon publication of this
notice.
ADDRESSES: Copies of the ROD are
available upon request from the Field
Manager, Barstow Field Office, Bureau
of Land Management, 2601 Barstow
Road, Barstow, California 92311 or at
the following Web site: https://
www.blm.gov/ca/st/en/prog/energy/
fasttrack/calico/fedstatus.html or https://
www.blm.gov/ca/st/en/fo/barstow/
emcdonald on DSK2BSOYB1PROD with NOTICES
SUMMARY:
VerDate Mar<15>2010
18:09 Oct 25, 2010
Jkt 223001
solar_one_calico.html. Copies of the
ROD are also available for public
inspection at the Barstow Field Office.
FOR FURTHER INFORMATION CONTACT: Jim
Stobaugh, National Project Manager, by
telephone: 775–861–6478; mail: BLM
Nevada State Office, P.O. Box 12000,
Reno, Nevada 89520–0006; or e-mail:
Jim_Stobaugh@blm.gov.
SUPPLEMENTARY INFORMATION: After
extensive environmental analysis;
consultation and collaboration with
Federal, state, and local agencies;
consideration of public comments; and
application of relevant Federal laws and
policies, the BLM has decided to offer
Calico Solar LLC a ROW lease/grant for
the construction, operation,
maintenance, and decommissioning of
the 663.5 megawatt (MW), 4,604-acre
Calico Solar Project, including related
project facilities and access roads across
public lands administered by the BLM.
In association with this ROW lease/
grant, the BLM is also amending the
CDCA Plan to allow for the siting of a
solar energy power plant on the
proposed project site. The ROW lease/
grant authorizes the use of public lands
for the project for a term of 30 years, and
the lease/grant is renewable. A
temporary use permit authorizes the use
of public lands for construction of
temporary access roads and
construction space for a term of 3 years
and is also subject to renewal. The
amendment of the CDCA Plan will
allow for the siting of the Calico Solar
Project and related facilities, including
26,450 SunCatcher solar dishes, a 230kilovolt (kV) Calico Substation and 2mile, 230-kv transmission line, and
other project facilities through
incorporation of the Calico Solar Project
into the Energy Production and Utility
Corridors Element of the CDCA Plan.
The BLM’s decision authorizes issuance
of a ROW lease/grant to Calico Solar
LLC for the Modified Agency Preferred
Alternative. The Agency Preferred
Alternative is within the scope of
alternatives that were analyzed in the
Final Environmental Impact Statement
(EIS) issued in August 2010.
Modifications to the Agency Preferred
Alternative have been made since
publication of the Final EIS as the result
of additional agency consultation and in
response to public comments. The
Environmental Protection Agency
published a Notice of Availability
(NOA) of the Final EIS in the Federal
Register on August 6, 2010 (75 FR
47620). Publication of the NOA for the
Final EIS initiated a 30-day protest
period for the proposed amendment to
the CDCA Plan. At the close of the
protest period on September 7, 2010,
PO 00000
Frm 00045
Fmt 4703
Sfmt 4703
five protests were received and
resolved. Detailed information on the
protests may be found on the BLM
Washington Office Web site at: https://
www.blm.gov/wo/st/en/prog/planning/
protest_resolution.html. The proposed
amendment to the CDCA Plan was not
modified as a result of the protest
resolution. Simultaneously with the
protest period, the California Governor’s
Office conducted a 30-day consistency
review of the proposed CDCA Plan
amendment/Final EIS to identify any
inconsistencies with state or local plan,
policies or programs. The California
Governor’s office did not identify
inconsistencies between the proposed
amendment to the CDCA Plan/Final EIS.
As a result of the above and additional
consultation with jurisdictional
regulatory agencies, the 6,215-acre, 850–
MW Agency Preferred Alternative for
the Calico Solar Project was modified to
include: (1) A project footprint reduced
from 6,215 acres to 4,604 acres; (2)
generation capacity reduced from 850–
MW (34,000 SunCatchers) to 663.5–MW
(26,540 SunCatchers); and (3)
construction of Phase 1 subdivided into
phase 1a and 1b. The authorized ROW
lease/grant includes all of the above
modifications.
Because this decision is approved by
the Secretary of the Interior, it is not
subject to administrative appeal (43 CFR
4.410(a)(3)).
Authority: 40 CFR 1506.6.
Robert V. Abbey,
Director, Bureau of Land Management.
[FR Doc. 2010–27027 Filed 10–25–10; 8:45 am]
BILLING CODE 4310–40–P
DEPARTMENT OF THE INTERIOR
Bureau of Land Management
[LLUTW01100–LF2000ES–JS0000–
LFESE4J7]
Notice of Closure to Motorized Vehicle
Travel on Public Lands in the Big Pole
Fire Area in Tooele County, UT
Bureau of Land Management,
Interior.
ACTION: Notice of temporary closure
AGENCY:
Notice is hereby given that a
temporary closure to motorized vehicle
travel was implemented as of May 17,
2010. This closure affects 27,100 acres
of public land administered by the Salt
Lake Field Office, Bureau of Land
Management (BLM), within the Big Pole
Fire area in Tooele County, Utah.
DATES: This temporary closure on motor
vehicle travel within the described area
will remain in effect for a minimum of
SUMMARY:
E:\FR\FM\26OCN1.SGM
26OCN1
Agencies
[Federal Register Volume 75, Number 206 (Tuesday, October 26, 2010)]
[Notices]
[Page 65650]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-27027]
-----------------------------------------------------------------------
DEPARTMENT OF THE INTERIOR
Bureau of Land Management
[CACA 49537, LLCAD08000, L51030000, FX0000, LVRAM109AA03]
Notice of Availability of the Record of Decision for the Calico
Solar Project and Associated Amendment to the California Desert
Conservation Area Resource Management Plan-Amendment, San Bernardino
County, CA
AGENCY: Bureau of Land Management, Interior.
ACTION: Notice of availability.
-----------------------------------------------------------------------
SUMMARY: The Bureau of Land Management (BLM) announces the availability
of the Record of Decision (ROD) for a right-of-way (ROW) lease/grant to
Calico Solar Limited Liability Corporation (LLC) for the Calico Solar
Project (formerly SES Solar One) and an associated Amendment to the
California Desert Conservation Area Resource Management Plan (CDCA
Plan). The Calico Solar Project is located in San Bernardino County,
California. The Secretary of the Interior signed the ROD on October 20,
2010, which constitutes the final decision of the Department. The ROD
and the Approved Plan Amendment are effective immediately.
DATES: These decisions are effective immediately upon publication of
this notice.
ADDRESSES: Copies of the ROD are available upon request from the Field
Manager, Barstow Field Office, Bureau of Land Management, 2601 Barstow
Road, Barstow, California 92311 or at the following Web site: https://www.blm.gov/ca/st/en/prog/energy/fasttrack/calico/fedstatus.html or
https://www.blm.gov/ca/st/en/fo/barstow/solar_one_calico.html. Copies
of the ROD are also available for public inspection at the Barstow
Field Office.
FOR FURTHER INFORMATION CONTACT: Jim Stobaugh, National Project
Manager, by telephone: 775-861-6478; mail: BLM Nevada State Office,
P.O. Box 12000, Reno, Nevada 89520-0006; or e-mail: Jim_Stobaugh@blm.gov.
SUPPLEMENTARY INFORMATION: After extensive environmental analysis;
consultation and collaboration with Federal, state, and local agencies;
consideration of public comments; and application of relevant Federal
laws and policies, the BLM has decided to offer Calico Solar LLC a ROW
lease/grant for the construction, operation, maintenance, and
decommissioning of the 663.5 megawatt (MW), 4,604-acre Calico Solar
Project, including related project facilities and access roads across
public lands administered by the BLM. In association with this ROW
lease/grant, the BLM is also amending the CDCA Plan to allow for the
siting of a solar energy power plant on the proposed project site. The
ROW lease/grant authorizes the use of public lands for the project for
a term of 30 years, and the lease/grant is renewable. A temporary use
permit authorizes the use of public lands for construction of temporary
access roads and construction space for a term of 3 years and is also
subject to renewal. The amendment of the CDCA Plan will allow for the
siting of the Calico Solar Project and related facilities, including
26,450 SunCatcher solar dishes, a 230-kilovolt (kV) Calico Substation
and 2-mile, 230-kv transmission line, and other project facilities
through incorporation of the Calico Solar Project into the Energy
Production and Utility Corridors Element of the CDCA Plan. The BLM's
decision authorizes issuance of a ROW lease/grant to Calico Solar LLC
for the Modified Agency Preferred Alternative. The Agency Preferred
Alternative is within the scope of alternatives that were analyzed in
the Final Environmental Impact Statement (EIS) issued in August 2010.
Modifications to the Agency Preferred Alternative have been made since
publication of the Final EIS as the result of additional agency
consultation and in response to public comments. The Environmental
Protection Agency published a Notice of Availability (NOA) of the Final
EIS in the Federal Register on August 6, 2010 (75 FR 47620).
Publication of the NOA for the Final EIS initiated a 30-day protest
period for the proposed amendment to the CDCA Plan. At the close of the
protest period on September 7, 2010, five protests were received and
resolved. Detailed information on the protests may be found on the BLM
Washington Office Web site at: https://www.blm.gov/wo/st/en/prog/planning/protest_resolution.html. The proposed amendment to the CDCA
Plan was not modified as a result of the protest resolution.
Simultaneously with the protest period, the California Governor's
Office conducted a 30-day consistency review of the proposed CDCA Plan
amendment/Final EIS to identify any inconsistencies with state or local
plan, policies or programs. The California Governor's office did not
identify inconsistencies between the proposed amendment to the CDCA
Plan/Final EIS. As a result of the above and additional consultation
with jurisdictional regulatory agencies, the 6,215-acre, 850-MW Agency
Preferred Alternative for the Calico Solar Project was modified to
include: (1) A project footprint reduced from 6,215 acres to 4,604
acres; (2) generation capacity reduced from 850-MW (34,000 SunCatchers)
to 663.5-MW (26,540 SunCatchers); and (3) construction of Phase 1
subdivided into phase 1a and 1b. The authorized ROW lease/grant
includes all of the above modifications.
Because this decision is approved by the Secretary of the Interior,
it is not subject to administrative appeal (43 CFR 4.410(a)(3)).
Authority: 40 CFR 1506.6.
Robert V. Abbey,
Director, Bureau of Land Management.
[FR Doc. 2010-27027 Filed 10-25-10; 8:45 am]