Notice of Availability of Final Environmental Impact Statement for the Solar Millennium, Amargosa Farm Road Solar Power Project, Nye County, NV, 63503-63504 [2010-25859]
Download as PDF
Federal Register / Vol. 75, No. 199 / Friday, October 15, 2010 / Notices
mstockstill on DSKH9S0YB1PROD with NOTICES
with the original Refuge lands covered
by the waters of the Salton Sea,
management activities are focused on
about 2,000 acres of primarily leased
land. Approximately 920 acres consist
of managed wetlands that support
resident and migratory birds, and
another 940 acres are farmed to provide
forage for wintering geese and other
migratory birds. Existing public uses
include wildlife observation,
photography, interpretation,
environmental education, waterfowl
hunting, and scientific research.
The Coachella Valley NWR was
established in 1985 under the
authorities of the Endangered Species
Act of 1973 (16 U.S.C. 1534), ‘‘to
conserve (A) fish or wildlife which are
listed as endangered species or
threatened species or (B) plants.’’ The
3,709-acre Refuge, which is part of the
larger Coachella Valley Preserve,
protects the Federally listed endangered
Coachella Valley milk-vetch (Astragalus
lentiginosus var. coachellae) and
threatened Coachella Valley fringe-toed
lizard (Uma inornata), as well as other
desert-dwelling species adapted to
living in the sand dune habitat of the
Coachella Valley. Access onto the
Refuge is limited to a designated
corridor for hiking and equestrian use.
Project Leader (see FOR FURTHER
INFORMATION CONTACT). You may also
submit comments or request a meeting
during the planning process by mail, email, or fax (see ADDRESSES). There will
be additional opportunities to provide
public input once we have prepared a
draft CCP.
Scoping: Preliminary Issues, Concerns,
and Opportunities
We have identified preliminary
issues, concerns, and opportunities for
each Refuge that we may address in the
CCP. Additional issues, concerns, and
opportunities may be identified as a
result of public scoping. For the Sonny
Bono Salton Sea NWR, preliminary
issues include: Increasing the
productivity of existing managed
wetlands to support migratory
waterfowl; adapting to changing
conditions associated with a shrinking
Salton Sea (e.g., conversion of habitat
types, dust management, degraded
water quality); predation in seabird
nesting areas; availability of adequate
nesting habitat for seabirds, particularly
gull-billed terns (Gelochelidon nilotica
vanrossemi); and the effects of climate
change on Refuge resources.
For the Coachella Valley NWR, these
issues include: Habitat and species
management; control of invasive weedy
species; effects of windblown sand on
adjacent properties; public use; and
impacts to Refuge resources as a result
of illegal motorized vehicle activity.
[LLNVS03100 L51010000.ER0000
LVRWF09–F8590; 10–08807; 4500013732;
TAS: 14X5017]
Public Meetings
We will give the public an
opportunity to provide input at a public
meeting (or meetings). You can obtain
the schedule from the Refuge Planner or
VerDate Mar<15>2010
16:01 Oct 14, 2010
Jkt 223001
Public Availability of Comments
Before including your address, phone
number, e-mail address, or other
personal identifying information in your
comment, you should be aware that
your entire comment—including your
personal identifying information—may
be made publicly available at any time.
While you can ask us in your comment
to withhold your personal identifying
information from public review, we
cannot guarantee that we will be able to
do so.
Dated: October 5, 2010.
Alexandra Pitts,
Acting Regional Director, Pacific Southwest
Region, Sacramento, California.
[FR Doc. 2010–25923 Filed 10–14–10; 8:45 am]
BILLING CODE 4310–55–P
DEPARTMENT OF THE INTERIOR
Bureau of Land Management
Notice of Availability of Final
Environmental Impact Statement for
the Solar Millennium, Amargosa Farm
Road Solar Power Project, Nye County,
NV
Bureau of Land Management,
Interior.
ACTION: Notice of Availability.
AGENCY:
In accordance with the
National Environmental Policy Act of
1969, as amended, and the Federal Land
Policy and Management Act of 1976, as
amended, the Bureau of Land
Management (BLM) has prepared a
Final Environmental Impact Statement
(EIS) for the Amargosa Farm Road Solar
Power Project, Nye County, Nevada, and
by this notice is announcing its
availability.
SUMMARY:
The BLM will not issue a final
decision on the Amargosa Farm Road
Solar Power Project for a minimum of
30 days from the date the
Environmental Protection Agency
publishes its notice in the Federal
Register.
DATES:
Copies of the Final EIS will
be mailed to individuals, agencies,
organizations, or companies who
ADDRESSES:
PO 00000
Frm 00071
Fmt 4703
Sfmt 4703
63503
previously requested copies or who
responded to the BLM on the Draft EIS.
Printed copies or a compact disc of the
Final EIS are available upon request
from the BLM Southern Nevada District
Office, 4701 N. Torrey Pines Drive, Las
Vegas, Nevada 89130; phone (702) 515–
5000; or e-mail at
solar_millennium@blm.gov. Interested
persons may also view the Final EIS at
the following Web site: https://
www.blm.gov/nv/st/en/prog/energy/fasttrack_renewable.html. Copies of the
Final EIS are available for public
inspection at the following locations in
Nevada:
• BLM Nevada State Office, 1340
Financial Boulevard, Reno.
• BLM Southern Nevada District
Office, 4701 N. Torrey Pines Drive, Las
Vegas.
FOR FURTHER INFORMATION CONTACT:
Gregory Helseth, Renewable Energy
Project Manager, by phone (702) 515–
5173; in writing at the Bureau of Land
Management, Southern Nevada District
Office, Attn: Gregory Helseth, 4701 N.
Torrey Pines Drive, Las Vegas, Nevada
89130; or e-mail
Gregory_Helseth@blm.gov.
SUPPLEMENTARY INFORMATION: Solar
Millennium applied to the BLM for a
right-of-way on public lands to
construct a concentrated solar thermal
parabolic trough power plant facility
approximately 80 miles northwest of
Las Vegas, Nevada, in Nye County. The
project site is located in Amargosa
Valley south of Highway 95. The
proposed project would encompass
4,350 acres of BLM-managed public
lands, and is expected to operate for
about 30 years. The proposed project
would consist of two 242 megawatt drycooled power plants and solar fields
equipped with solar thermal storage
tanks capable of producing additional
energy for 3.5 hours after sundown.
The solar field is highly modular and
consists of ‘‘loops,’’ each consisting of
four curved glass mirror collectors. A
loop is 22 meters wide by 850 meters
long. A solar field consists of 200 to 400
loops. The orientation of the collectors
is north-south and the collectors track
the sun from east to west during the
day. The collector focuses the sun’s
direct beam radiation on a receiver tube.
The row of collectors has a hydraulic
drive unit with sensors to track the
sun’s path throughout the day. The solar
energy heats a transfer fluid which
cycles through a series of exchangers,
ultimately generating electricity.
The project’s proposed facility design
includes the solar fields, power blocks,
buildings, parking area, laydown area,
stormwater retention pond, and
E:\FR\FM\15OCN1.SGM
15OCN1
63504
Federal Register / Vol. 75, No. 199 / Friday, October 15, 2010 / Notices
mstockstill on DSKH9S0YB1PROD with NOTICES
evaporating ponds. A single overhead
230 kilovolt transmission line will
connect the plant to the nearby Valley
Electric substation. Additional elements
of the project include access roads, a
water pipeline, and a bioremediation
area.
The Final EIS describes and analyzes
the project’s site-specific impacts on air
quality, biological resources, cultural
resources, visual resources, water
resources, geological resources,
paleontological resources, land use,
noise, soils, nuisance, public health,
socioeconomics, traffic and
transportation, waste management,
hazardous materials handling, worker
safety, fire protection, facility design
engineering, transmission system
engineering, and transmission line
safety.
Three alternatives were analyzed: (A)
Wet-cooling technology; (B) Dry-cooling
technology; and (C) No action
alternative. Alternative A uses
circulating water to condense lowpressure turbine generator exhaust
steam in a shell and tube heat exchanger
(condenser). Alternative B uses an aircooled condenser that cools and
condenses the low-pressure turbine
generator exhaust steam using a large
array of fans that force air over finnedtube heat exchangers arranged in an Aframe bundle configuration. Alternative
B is the BLM’s preferred alternative and
Solar Millennium’s proposed action.
Alternative C is the no action
alternative.
On March 19, 2010, the BLM
published the Notice of Availability for
the Draft EIS for this project in the
Federal Register (75 FR 13301). The
BLM held four public meetings and
allowed the public to comment through
email, mail, public meetings, and by
phone. A total of 461 comments were
received from individuals,
organizations, and agencies.
These comments addressed concerns
with water use mitigation, visual
resource management, noise levels, and
social/economic issues, particularly job
opportunities. Concerns raised during
the review are addressed and specific
responses provided in the Final EIS.
Authority: 40 CFR 1506.6 and 1506.10.
Gayle Marrs-Smith,
Acting Manager Pahrump Field Office.
[FR Doc. 2010–25859 Filed 10–14–10; 8:45 am]
BILLING CODE 4310–HC–P
VerDate Mar<15>2010
16:01 Oct 14, 2010
Jkt 223001
DEPARTMENT OF THE INTERIOR
Bureau of Ocean Energy Management,
Regulation and Enforcement
Outer Continental Shelf, Alaska OCS
Region, Chukchi Sea Planning Area,
Oil and Gas Lease Sale 193
Bureau of Ocean Energy
Management, Regulation and
Enforcement (BOEMRE), Interior.
ACTION: Notice of Availability of a Draft
Supplemental Environmental Impact
Statement (SEIS) and Notice of Public
Hearings.
AGENCY:
The purpose of this SEIS
(OCS EIS/EA BOEMRE 2010–034) is to
provide new analysis in accordance
with the United States (U.S.) District
Court for the District of Alaska Order
remanding the BOEMRE’s Chukchi Sea
Lease Sale 193 Final EIS (FEIS) (OCS
EIS/EA MMS 2007–0026). The District
Court’s Order instructs the BOEMRE to
address three concerns: (1) Analyze the
environmental impact of natural gas
development; (2) determine whether
missing information identified by
BOEMRE in the 193 FEIS was essential
or relevant under 40 CFR 1502.22; and
(3) ‘‘determine whether the cost of
obtaining the missing information was
exorbitant, or the means of doing so
unknown.’’
SUPPLEMENTARY INFORMATION: The FEIS
for Chukchi Sea Lease Sale 193 (OCS
EIS/EA MMS 2007–0026) evaluated the
potential effects of the proposed sale
and three alternatives: a no action
alternative and two alternatives that
incorporate deferral areas of varying size
along the coastward edge of the
proposed sale area.
Sale 193 was held in February of
2008. The BOEMRE received high bids
totaling approximately $2.7 billion and
issued 487 leases. Although the leasesale decision was challenged in the U.S.
District Court for the District of Alaska,
the litigants did not request a
preliminary injunction to halt the sale.
Accordingly, the sale was conducted
and 487 leases were issued. In July
2010, the District Court remanded the
matter for further National
Environmental Policy Act analysis of
certain concerns. The BOEMRE is to
address three concerns: (1) Analyze the
environmental impact of natural gas
development; (2) determine whether
missing information identified by
BOEMRE in the FEIS for Chukchi Sea
Lease Sale 193 was essential or relevant
under 40 CFR 1502.22; and (3)
determine whether the cost of obtaining
the missing information was exorbitant,
or the means of doing so unknown.
SUMMARY:
PO 00000
Frm 00072
Fmt 4703
Sfmt 4703
The SEIS will provide the Secretary
with sufficient information and analysis
to make an informed decision amongst
the alternatives. In effect, the Secretary
will decide whether to affirm, modify,
or cancel Sale 193. This notice relates
solely to the Supplemental Draft EIS for
Chukchi Sale 193. It does not preclude
possible additional environmental
analysis with regard to future leasing or
permitting actions.
Draft Supplemental EIS Availability:
To obtain a copy of the Draft SEIS, you
may contact the Bureau of Ocean Energy
Management, Regulation and
Enforcement, Alaska OCS Region, 3801
Centerpoint Drive, Suite 500,
Anchorage, Alaska 99503–5820,
telephone 907–334–5200. You may also
view the Draft SEIS at the above
address, on the BOEMRE Web site at
https://alaska.boemre.gov, or at the
Alaska Resources Library and
Information Service, 3211 Providence
Drive, Suite 111, Anchorage.
Written Comments: Interested parties
may submit their written comments on
the Draft SEIS until November 29, 2010
to the Regional Director, Alaska OCS
Region, Bureau of Ocean Energy
Management, Regulation and
Enforcement, 3801 Centerpoint Drive,
Suite 500, Anchorage, Alaska 99503–
5820. You may also hand deliver
comments to this address. Comments
should be labeled ‘‘Attn: Chukchi Sea
Draft SEIS.’’ Comments may be
submitted via e-mail at
BOEMREAKPublicCommen@boemre.gov
(Note: please use e-mail address exactly
as it appears. Do not add the letter ‘‘t’’
or anything else to the address.). Please
include ‘‘Attn: Chukchi Sea Draft SEIS’’
in the subject line, and your name and
return address in the message. BOEMRE
will not accept anonymous comments.
Be advised that your entire
comment—including your personal
identifying information—may be made
publicly available at any time. While
you may request us to withhold from
public review your personal identifying
information, we cannot guarantee that
we will be able to do so.
Public Hearings: Public hearings on
the Draft SEIS will be held as follows:
Monday, November 1, 2011, Kotzebue
Middle/High School, Kotzebue,
Alaska;
Tuesday, November 2, 2010, Oalgi
Community Center, Point Hope, Alaska;
Wednesday, November 3, 2010, Point
Lay Community Center, Point Lay,
Alaska;
Thursday, November 4, 2010, Robert
James Community Center,
Wainwright, Alaska;
Friday, November 5, 2010, Inupiat
Heritage Center, Barrow, Alaska;
E:\FR\FM\15OCN1.SGM
15OCN1
Agencies
[Federal Register Volume 75, Number 199 (Friday, October 15, 2010)]
[Notices]
[Pages 63503-63504]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-25859]
-----------------------------------------------------------------------
DEPARTMENT OF THE INTERIOR
Bureau of Land Management
[LLNVS03100 L51010000.ER0000 LVRWF09-F8590; 10-08807; 4500013732; TAS:
14X5017]
Notice of Availability of Final Environmental Impact Statement
for the Solar Millennium, Amargosa Farm Road Solar Power Project, Nye
County, NV
AGENCY: Bureau of Land Management, Interior.
ACTION: Notice of Availability.
-----------------------------------------------------------------------
SUMMARY: In accordance with the National Environmental Policy Act of
1969, as amended, and the Federal Land Policy and Management Act of
1976, as amended, the Bureau of Land Management (BLM) has prepared a
Final Environmental Impact Statement (EIS) for the Amargosa Farm Road
Solar Power Project, Nye County, Nevada, and by this notice is
announcing its availability.
DATES: The BLM will not issue a final decision on the Amargosa Farm
Road Solar Power Project for a minimum of 30 days from the date the
Environmental Protection Agency publishes its notice in the Federal
Register.
ADDRESSES: Copies of the Final EIS will be mailed to individuals,
agencies, organizations, or companies who previously requested copies
or who responded to the BLM on the Draft EIS. Printed copies or a
compact disc of the Final EIS are available upon request from the BLM
Southern Nevada District Office, 4701 N. Torrey Pines Drive, Las Vegas,
Nevada 89130; phone (702) 515-5000; or e-mail at solar_millennium@blm.gov. Interested persons may also view the Final EIS at
the following Web site: https://www.blm.gov/nv/st/en/prog/energy/fast-track_renewable.html. Copies of the Final EIS are available for public
inspection at the following locations in Nevada:
BLM Nevada State Office, 1340 Financial Boulevard, Reno.
BLM Southern Nevada District Office, 4701 N. Torrey Pines
Drive, Las Vegas.
FOR FURTHER INFORMATION CONTACT: Gregory Helseth, Renewable Energy
Project Manager, by phone (702) 515-5173; in writing at the Bureau of
Land Management, Southern Nevada District Office, Attn: Gregory
Helseth, 4701 N. Torrey Pines Drive, Las Vegas, Nevada 89130; or e-mail
Gregory_Helseth@blm.gov.
SUPPLEMENTARY INFORMATION: Solar Millennium applied to the BLM for a
right-of-way on public lands to construct a concentrated solar thermal
parabolic trough power plant facility approximately 80 miles northwest
of Las Vegas, Nevada, in Nye County. The project site is located in
Amargosa Valley south of Highway 95. The proposed project would
encompass 4,350 acres of BLM-managed public lands, and is expected to
operate for about 30 years. The proposed project would consist of two
242 megawatt dry-cooled power plants and solar fields equipped with
solar thermal storage tanks capable of producing additional energy for
3.5 hours after sundown.
The solar field is highly modular and consists of ``loops,'' each
consisting of four curved glass mirror collectors. A loop is 22 meters
wide by 850 meters long. A solar field consists of 200 to 400 loops.
The orientation of the collectors is north-south and the collectors
track the sun from east to west during the day. The collector focuses
the sun's direct beam radiation on a receiver tube. The row of
collectors has a hydraulic drive unit with sensors to track the sun's
path throughout the day. The solar energy heats a transfer fluid which
cycles through a series of exchangers, ultimately generating
electricity.
The project's proposed facility design includes the solar fields,
power blocks, buildings, parking area, laydown area, stormwater
retention pond, and
[[Page 63504]]
evaporating ponds. A single overhead 230 kilovolt transmission line
will connect the plant to the nearby Valley Electric substation.
Additional elements of the project include access roads, a water
pipeline, and a bioremediation area.
The Final EIS describes and analyzes the project's site-specific
impacts on air quality, biological resources, cultural resources,
visual resources, water resources, geological resources,
paleontological resources, land use, noise, soils, nuisance, public
health, socioeconomics, traffic and transportation, waste management,
hazardous materials handling, worker safety, fire protection, facility
design engineering, transmission system engineering, and transmission
line safety.
Three alternatives were analyzed: (A) Wet-cooling technology; (B)
Dry-cooling technology; and (C) No action alternative. Alternative A
uses circulating water to condense low-pressure turbine generator
exhaust steam in a shell and tube heat exchanger (condenser).
Alternative B uses an air-cooled condenser that cools and condenses the
low-pressure turbine generator exhaust steam using a large array of
fans that force air over finned-tube heat exchangers arranged in an A-
frame bundle configuration. Alternative B is the BLM's preferred
alternative and Solar Millennium's proposed action. Alternative C is
the no action alternative.
On March 19, 2010, the BLM published the Notice of Availability for
the Draft EIS for this project in the Federal Register (75 FR 13301).
The BLM held four public meetings and allowed the public to comment
through email, mail, public meetings, and by phone. A total of 461
comments were received from individuals, organizations, and agencies.
These comments addressed concerns with water use mitigation, visual
resource management, noise levels, and social/economic issues,
particularly job opportunities. Concerns raised during the review are
addressed and specific responses provided in the Final EIS.
Authority: 40 CFR 1506.6 and 1506.10.
Gayle Marrs-Smith,
Acting Manager Pahrump Field Office.
[FR Doc. 2010-25859 Filed 10-14-10; 8:45 am]
BILLING CODE 4310-HC-P