Northern Illinois Hydropower, LLC; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions, 62516-62517 [2010-25516]
Download as PDF
srobinson on DSKHWCL6B1PROD with NOTICES
62516
Federal Register / Vol. 75, No. 196 / Tuesday, October 12, 2010 / Notices
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
14 copies of filings made in the
proceeding with the Commission and
must mail a copy to the applicant and
to every other party. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commentors will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commentors will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commentors
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
VerDate Mar<15>2010
17:43 Oct 08, 2010
Jkt 223001
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: October 25, 2010.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–25513 Filed 10–8–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12626–002]
Northern Illinois Hydropower, LLC;
Notice of Application Ready for
Environmental Analysis and Soliciting
Comments, Recommendations, Terms
and Conditions, and Prescriptions
October 4, 2010.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Original major
license.
b. Project No.: 12626–002.
c. Date filed: March 31, 2009.
d. Applicant: Northern Illinois
Hydropower, LLC.
e. Name of Project: Dresden Island
Project.
f. Location: U.S. Army Corps of
Engineers’ Dresden Island Lock and
Dam on the Illinois River, in the Town
of Morris, Grundy County, Illinois.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Damon
Zdunich, Northern Illinois Hydropower,
LLC, 801 Oakland Avenue, Joliet, IL
60435, (312) 320–1610.
i. FERC Contact: Janet Hutzel, (202)
502–8675 or janet.hutzel@ferc.gov.
j. Deadline for filing comments,
recommendations, terms and
PO 00000
Frm 00019
Fmt 4703
Sfmt 4703
conditions, and prescriptions is 60 days
from the issuance of this notice: Reply
comments are due 105 days from the
issuance date of this notice.
All documents may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site https://www.ferc.gov/docs-filing/
efiling.asp. Commenters can submit
brief comments up to 6,000 characters,
without prior registration, using the
eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support.
Although the Commission strongly
encourages electronic filing, documents
may also be paper-filed. To paper-file,
mail an original and seven copies to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted
and is now ready for environmental
analysis.
l. Project Description: The Dresden
Island Project would utilize the Corps of
Engineers’ existing Dresden Island Lock
and Dam and would consist of: (1) A
new 75-foot by 125-foot concrete
powerhouse, located between headgate
sections 10 through 16, containing three
generating units with a total installed
capacity of 10.2 MW; (2) a new 50-foot
by 50-foot switchyard adjacent to
powerhouse building; (3) a new 0.8mile-long transmission line; and (4)
appurtenant facilities. The project
would have an average annual
generation of about 60,000 megawatthours.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the ‘‘eLibrary’’
link. Enter the docket number excluding
the last three digits in the docket
number field to access the document.
For assistance, contact FERC Online
Support. A copy is also available for
inspection and reproduction at the
address in item h above.
E:\FR\FM\12OCN1.SGM
12OCN1
Federal Register / Vol. 75, No. 196 / Tuesday, October 12, 2010 / Notices
All filings must (1) Bear in all capital
letters the title ‘‘COMMENTS,’’ ‘‘REPLY
COMMENTS,’’
‘‘RECOMMENDATIONS,’’ ‘‘TERMS AND
CONDITIONS,’’ or ‘‘PRESCRIPTIONS;’’
(2) set forth in the heading the name of
the applicant and the project number of
the application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
submitting the filing; and (4) otherwise
comply with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, recommendations, terms and
conditions or prescriptions must set
forth their evidentiary basis and
otherwise comply with the requirements
of 18 CFR 4.34(b). Agencies may obtain
copies of the application directly from
the applicant. Each filing must be
accompanied by proof of service on all
persons listed on the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
4.34(b), and 385.2010.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Public notice of the filing of the
initial development application, which
has already been given, established the
due date for filing competing
applications or notices of intent. Under
the Commission’s regulations, any
competing development application
must be filed in response to and in
compliance with public notice of the
initial development application. No
competing applications or notices of
intent may be filed in response to this
notice.
o. A license applicant must file no
later than 60 days following the date of
issuance of this notice: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
srobinson on DSKHWCL6B1PROD with NOTICES
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–25516 Filed 10–8–10; 8:45 am]
BILLING CODE 6717–01–P
VerDate Mar<15>2010
17:43 Oct 08, 2010
Jkt 223001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13802–000]
California Water Service Company;
Notice of Application Accepted for
Filing and Soliciting Comments,
Motions To Intervene, Protests,
Recommendations, and Terms and
Conditions
October 1, 2010.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Conduit
exemption.
b. Project No.: 13802–000.
c. Date filed: June 29, 2010.
d. Applicant: California Water Service
Company.
e. Name of Project: Palos Verdes
Energy Recovery Project.
f. Location: The proposed Palos
Verdes Energy Recovery Project would
be located at 5837 Crest Road West, City
of Rancho Palos Verdes in Los Angeles
County, California. The land on which
all the project structures are located is
owned by the applicant.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
h. Applicant Contact: Erin McCauley,
P.E., Manager of Design, California
Water Service Company, 1720 North
First Street, San Jose, CA 95112–4598,
Telephone (408) 367–8279.
i. FERC Contact: Jake Tung, telephone
(202) 502–8757, and e-mail address
hong.tung@ferc.gov.
j. Status of Environmental Analysis:
This application is ready for
environmental analysis at this time, and
the Commission is requesting
comments, reply comments,
recommendations, terms and
conditions, and prescriptions.
k. Deadline for filing responsive
documents: Due to the small size and
location of the proposed project in a
closed system, as well as the resource
agency consultation letters filed with
the application, the 60-day timeframe
specified in 18 CFR 4.43(b) for filing all
comments, motions to intervene,
protests, recommendations, terms and
conditions, and prescriptions is
shortened to 30 days from the issuance
date of this notice. All reply comments
filed in response to comments
submitted by any resource agency,
Indian tribe, or person, must be filed
with the Commission within 45 days
from the issuance date of this notice.
Comments, protests, and
interventions may be filed electronically
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
62517
via the Internet in lieu of paper; see 18
CFR 385.2001(a)(1)(iii). Commenters can
submit brief comments up to 6,000
characters, without prior registration,
using the eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. The Commission
strongly encourages electronic filings.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person in the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
l. Description of Project: The proposed
Palos Verdes Energy Recovery Project
would consist of: (1) A proposed
concrete pad located above the existing
vault with no physical changes to the
existing cement infrastructure; (2) one
reverse-pump turbine generator unit
with a rated capacity of 325 kW; (3) the
turbine generator unit to be installed
within the pipeline using custom
piping, T-flanges and electronic valves;
and (4) appurtenant facilities. The
project construction is tentatively
scheduled to begin in December 2010
and to be commissioned in January
2011. The project would produce an
estimated annual generation of
2,000,000 kilowatt-hours that would be
sold to Southern California Edison.
m. This filing is available for review
and reproduction at the Commission in
the Public Reference Room, Room 2A,
888 First Street, NE., Washington, DC
20426. The filing may also be viewed on
the Web at https://www.ferc.gov/docsfiling/efiling.asp. Enter the docket
number (P–13802) in the docket number
field to access the document. For
assistance, call toll-free 1–866–208–
3676. For TTY, call (202) 502–8659. A
copy is also available for review and
reproduction at the address in item h
above.
n. Development Application—Any
qualified applicant desiring to file a
competing application must submit to
the Commission, on or before the
specified deadline date for the
particular application, a competing
development application, or a notice of
intent to file such an application.
Submission of a timely notice of intent
allows an interested person to file the
competing development application no
later than 120 days after the specified
deadline date for the particular
application. Applications for
preliminary permits will not be
accepted in response to this notice.
E:\FR\FM\12OCN1.SGM
12OCN1
Agencies
[Federal Register Volume 75, Number 196 (Tuesday, October 12, 2010)]
[Notices]
[Pages 62516-62517]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-25516]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 12626-002]
Northern Illinois Hydropower, LLC; Notice of Application Ready
for Environmental Analysis and Soliciting Comments, Recommendations,
Terms and Conditions, and Prescriptions
October 4, 2010.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Original major license.
b. Project No.: 12626-002.
c. Date filed: March 31, 2009.
d. Applicant: Northern Illinois Hydropower, LLC.
e. Name of Project: Dresden Island Project.
f. Location: U.S. Army Corps of Engineers' Dresden Island Lock and
Dam on the Illinois River, in the Town of Morris, Grundy County,
Illinois.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: Damon Zdunich, Northern Illinois Hydropower,
LLC, 801 Oakland Avenue, Joliet, IL 60435, (312) 320-1610.
i. FERC Contact: Janet Hutzel, (202) 502-8675 or
janet.hutzel@ferc.gov.
j. Deadline for filing comments, recommendations, terms and
conditions, and prescriptions is 60 days from the issuance of this
notice: Reply comments are due 105 days from the issuance date of this
notice.
All documents may be filed electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web
site https://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit
brief comments up to 6,000 characters, without prior registration,
using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the
end of your comments. For assistance, please contact FERC Online
Support. Although the Commission strongly encourages electronic filing,
documents may also be paper-filed. To paper-file, mail an original and
seven copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE., Washington, DC 20426.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
k. This application has been accepted and is now ready for
environmental analysis.
l. Project Description: The Dresden Island Project would utilize
the Corps of Engineers' existing Dresden Island Lock and Dam and would
consist of: (1) A new 75-foot by 125-foot concrete powerhouse, located
between headgate sections 10 through 16, containing three generating
units with a total installed capacity of 10.2 MW; (2) a new 50-foot by
50-foot switchyard adjacent to powerhouse building; (3) a new 0.8-mile-
long transmission line; and (4) appurtenant facilities. The project
would have an average annual generation of about 60,000 megawatt-hours.
m. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support. A copy is also available for inspection and
reproduction at the address in item h above.
[[Page 62517]]
All filings must (1) Bear in all capital letters the title
``COMMENTS,'' ``REPLY COMMENTS,'' ``RECOMMENDATIONS,'' ``TERMS AND
CONDITIONS,'' or ``PRESCRIPTIONS;'' (2) set forth in the heading the
name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person submitting the filing; and (4) otherwise comply
with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, recommendations, terms and conditions or prescriptions must
set forth their evidentiary basis and otherwise comply with the
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the
application directly from the applicant. Each filing must be
accompanied by proof of service on all persons listed on the service
list prepared by the Commission in this proceeding, in accordance with
18 CFR 4.34(b), and 385.2010.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via e-mail of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
n. Public notice of the filing of the initial development
application, which has already been given, established the due date for
filing competing applications or notices of intent. Under the
Commission's regulations, any competing development application must be
filed in response to and in compliance with public notice of the
initial development application. No competing applications or notices
of intent may be filed in response to this notice.
o. A license applicant must file no later than 60 days following
the date of issuance of this notice: (1) A copy of the water quality
certification; (2) a copy of the request for certification, including
proof of the date on which the certifying agency received the request;
or (3) evidence of waiver of water quality certification.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010-25516 Filed 10-8-10; 8:45 am]