Duke Energy Carolinas, LLC; Notice of Application for Amendment of License, and Soliciting Comments, Motions To Intervene, and Protests, 61457-61458 [2010-24947]
Download as PDF
mstockstill on DSKH9S0YB1PROD with NOTICES
Federal Register / Vol. 75, No. 192 / Tuesday, October 5, 2010 / Notices
Please include the project number (P–
1390–063) on any comments, motions,
or recommendations filed.
k. Description of Request: The
applicant proposes a new concrete head
works at the tailrace of the Lundy
Powerhouse. The applicant also
proposes to install a high-density
polyethylene pipeline, with a capacity
of 52 cubic feet per second, within the
existing earthen return ditch extending
from the Lundy Powerhouse tailrace
(near Wilson Creek) back to Mill Creek.
The purpose of the applicant’s proposal
is to provide the means for the applicant
to return a portion of the water that has
been diverted from Lundy Lake through
the Lundy Powerhouse back to Mill
Creek below Lundy Lake. The applicant
is also requesting a new Article 411–A
that requires a plan for engineering,
permitting, construction, and operation
of the proposed modified powerhouse
tailrace diversion structure and Mill
Creek return water conveyance facility.
l. Locations of the Application: A
copy of the application is available for
inspection and reproduction at the
Commission’s Public Reference Room,
located at 888 First Street, NE., Room
2A, Washington, DC 20426, or by calling
(202) 502–8371. This filing may also be
viewed on the Commission’s Web site at
https://www.ferc.gov/docs-filing/
efiling.asp. Enter the docket number
excluding the last three digits in the
docket number field to access the
document. You may also register online
at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
e-mail FERCOnlineSupport@ferc.gov,
for TTY, call (202) 502–8659. A copy is
also available for inspection and
reproduction at the address in item (h)
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
VerDate Mar<15>2010
18:36 Oct 04, 2010
Jkt 223001
o. Filing and Service of Responsive
Documents: Any filing must (1) bear in
all capital letters the title
‘‘COMMENTS’’, ‘‘PROTEST’’, or
‘‘MOTION TO INTERVENE’’ as
applicable; (2) set forth in the heading
the name of the applicant and the
project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, motions to intervene or
protests must set forth their evidentiary
basis and otherwise comply with the
requirements of 18 CFR 4.34(b). All
comments, motions to intervene or
protests should relate to project works
which are the subject of the license
amendment. Agencies may obtain
copies of the application directly from
the applicant. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. If an intervener files
comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency. A copy of all
other filings in reference to this
application must be accompanied by
proof of service on all persons listed in
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–24953 Filed 10–4–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2503–144]
Duke Energy Carolinas, LLC; Notice of
Application for Amendment of License,
and Soliciting Comments, Motions To
Intervene, and Protests
September 27, 2010.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Non-Capacity
Amendment of License.
b. Project No.: 2503–144.
c. Date Filed: August 24, 2010.
PO 00000
Frm 00047
Fmt 4703
Sfmt 4703
61457
d. Applicant: Duke Energy Carolinas,
LLC.
e. Name of Project: Keowee-Toxaway
Pumped-Storage Project.
f. Location: The project is located on
the Keowee, Little, Whitewater,
Toxaway, Thompson and Horsepasture
Rivers, all tributaries of the Savannah
River, in Oconee and Pickens Counties,
South Carolina and in Transylvania
County, North Carolina.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
h. Applicant Contact: Mr. Jeffery G.
Lineberger, P.E., Duke Energy Carolinas,
LLC, 526 South Church Street, P.O. Box
1006, Charlotte, NC 28201, (704) 382–
5942, jeff.lineberger@duke-energy.com/.
i. FERC Contact: Any questions
regarding this notice should be directed
to Mr. Jeremy Jessup (202) 502–6779 or
Jeremy.Jessup@ferc.gov.
j. Deadline for filing comments,
motions to intervene and protest:
October 27, 2010.
All documents may be filed
electronically via the Internet. See, 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site at https://www.ferc.gov/docs-filing/
efiling.asp. If unable to be filed
electronically, documents may be paperfiled. To paper-file, an original and
seven copies should be mailed to:
Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426. Commenters
can submit brief comments up to 6,000
characters, without prior registration,
using the eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments.
Please include the project number (P–
2503–144) on any comments, motions,
or recommendations filed.
k. Description of Request: The
applicant proposes to: (1) Amend
portions of the Project’s Exhibit M to
reflect planned runner replacements
and related work for Units 1 and 2 of the
Jocassee Pumped Storage Development
(Jocassee Development), and (2) amend
the authorized installed capacity figures
in the license to reflect the replacements
and upgrades and the current
Commission regulations concerning
authorized installed capacity contained
in 18 CFR 11.1(i) for both the Keowee
Development and the Jocassee
Development. The runner replacement
work will occur from September 2010
through May 2011. When the proposed
work is completed, the revised
authorized installed capacity for the
Project will be 867.6 MW, consisting of
157.5 MW for the Keowee Development
E:\FR\FM\05OCN1.SGM
05OCN1
mstockstill on DSKH9S0YB1PROD with NOTICES
61458
Federal Register / Vol. 75, No. 192 / Tuesday, October 5, 2010 / Notices
and 710.1 MW for the Jocassee
Development.
l. Locations of the Application: A
copy of the application is available for
inspection and reproduction at the
Commission’s Public Reference Room,
located at 888 First Street, NE., Room
2A, Washington, DC 20426, or by calling
(202) 502–8371. This filing may also be
viewed on the Commission’s Web site at
https://www.ferc.gov/docs-filing/
efiling.asp. Enter the docket number
excluding the last three digits in the
docket number field to access the
document. You may also register online
at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
e-mail FERCOnlineSupport@ferc.gov,
for TTY, call (202) 502–8659. A copy is
also available for inspection and
reproduction at the address in item (h)
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
o. Filing and Service of Responsive
Documents: Any filing must (1) Bear in
all capital letters the title
‘‘COMMENTS’’, ‘‘PROTEST’’, or
‘‘MOTION TO INTERVENE’’ as
applicable; (2) set forth in the heading
the name of the applicant and the
project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, motions to intervene or
protests must set forth their evidentiary
basis and otherwise comply with the
requirements of 18 CFR 4.34(b). All
comments, motions to intervene or
protests should relate to project works
which are the subject of the license
amendment. Agencies may obtain
copies of the application directly from
VerDate Mar<15>2010
18:36 Oct 04, 2010
Jkt 223001
the applicant. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. If an intervener files
comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency. A copy of all
other filings in reference to this
application must be accompanied by
proof of service on all persons listed in
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–24947 Filed 10–4–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 1494–386]
Grand River Dam Authority; Notice of
Application for Amendment of License
and Soliciting Comments, Motions To
Intervene, and Protests
September 28, 2010.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Application Type: Non-project use
of project lands and waters.
b. Project No: 1494–386.
c. Date Filed: May 27, 2010,
supplemented on August 12 and August
16, 2010.
d. Applicant: Grand River Dam
Authority.
e. Name of Project: Pensacola
Hydroelectric Project.
f. Location: Grand Lake in Ottawa
County, Oklahoma.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791a–825r.
h. Applicant Contact: Tamara Jahnke,
P.O. Box 409, Vinita, Oklahoma 74301.
Tel: (918) 256–5545.
i. FERC Contact: Mark Carter,
Telephone: (678) 245–3083, and e-mail
mark.carter@ferc.gov.
j. Deadline for filing comments,
motions to intervene, and protests:
October 28, 2010.
Comments, protests, and
interventions may be filed electronically
via the Internet in lieu of paper. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
PO 00000
Frm 00048
Fmt 4703
Sfmt 4703
site (https://www.ferc.gov) under the ‘‘efiling’’ link. The Commission strongly
encourages electronic filings.
All documents (original and eight
copies) should be filed with: Secretary,
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426. Please include the project
number (P–2232–579) on any comments
or motions filed.
The Commission’s Rules of Practice
and Procedure require all interveners
filing documents with the Commission
to serve a copy of that document on
each person whose name appears on the
official service list for the project.
Further, if an intervener files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, it must also
serve a copy of the document on that
resource agency. A copy of any motion
to intervene must also be served upon
each representative of the Applicant
specified in the particular application.
k. Description of Application: The
licensee requests Commission approval
to grant Ottawa County (permittee) an
easement of 1.99 acres of project lands
(1.2 acres of which are wetlands) for use
as a boat ramp and parking lot at Grand
Lake. As mitigation for construction in
a wetland, the licensee would place a
land use restriction on approximately 6
acres of nearby project land for an
aquatic ecosystem preserve.
l. Locations of the Application: A
copy of the application is available for
inspection and reproduction at the
Commission’s Public Reference Room,
located at 888 First Street, NE., Room
2A, Washington, DC 20426, or by calling
(202) 502–8371. This filing may also be
viewed on the Commission’s Web site at
https://www.ferc.gov using the ‘‘eLibrary’’
link. Enter the docket number excluding
the last three digits in the docket
number field (P–2232) to access the
document. You may also register online
at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3676 or
e-mail FERCOnlineSupport@ferc.gov,
for TTY, call (202) 502–8659. A copy is
also available for inspection and
reproduction at the address in item (h)
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
E:\FR\FM\05OCN1.SGM
05OCN1
Agencies
[Federal Register Volume 75, Number 192 (Tuesday, October 5, 2010)]
[Notices]
[Pages 61457-61458]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-24947]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2503-144]
Duke Energy Carolinas, LLC; Notice of Application for Amendment
of License, and Soliciting Comments, Motions To Intervene, and Protests
September 27, 2010.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Non-Capacity Amendment of License.
b. Project No.: 2503-144.
c. Date Filed: August 24, 2010.
d. Applicant: Duke Energy Carolinas, LLC.
e. Name of Project: Keowee-Toxaway Pumped-Storage Project.
f. Location: The project is located on the Keowee, Little,
Whitewater, Toxaway, Thompson and Horsepasture Rivers, all tributaries
of the Savannah River, in Oconee and Pickens Counties, South Carolina
and in Transylvania County, North Carolina.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791a-825r.
h. Applicant Contact: Mr. Jeffery G. Lineberger, P.E., Duke Energy
Carolinas, LLC, 526 South Church Street, P.O. Box 1006, Charlotte, NC
28201, (704) 382-5942, jeff.lineberger@duke-energy.com/.
i. FERC Contact: Any questions regarding this notice should be
directed to Mr. Jeremy Jessup (202) 502-6779 or Jeremy.Jessup@ferc.gov.
j. Deadline for filing comments, motions to intervene and protest:
October 27, 2010.
All documents may be filed electronically via the Internet. See, 18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's Web site
at https://www.ferc.gov/docs-filing/efiling.asp. If unable to be filed
electronically, documents may be paper-filed. To paper-file, an
original and seven copies should be mailed to: Secretary, Federal
Energy Regulatory Commission, 888 First Street, NE., Washington, DC
20426. Commenters can submit brief comments up to 6,000 characters,
without prior registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and
contact information at the end of your comments.
Please include the project number (P-2503-144) on any comments,
motions, or recommendations filed.
k. Description of Request: The applicant proposes to: (1) Amend
portions of the Project's Exhibit M to reflect planned runner
replacements and related work for Units 1 and 2 of the Jocassee Pumped
Storage Development (Jocassee Development), and (2) amend the
authorized installed capacity figures in the license to reflect the
replacements and upgrades and the current Commission regulations
concerning authorized installed capacity contained in 18 CFR 11.1(i)
for both the Keowee Development and the Jocassee Development. The
runner replacement work will occur from September 2010 through May
2011. When the proposed work is completed, the revised authorized
installed capacity for the Project will be 867.6 MW, consisting of
157.5 MW for the Keowee Development
[[Page 61458]]
and 710.1 MW for the Jocassee Development.
l. Locations of the Application: A copy of the application is
available for inspection and reproduction at the Commission's Public
Reference Room, located at 888 First Street, NE., Room 2A, Washington,
DC 20426, or by calling (202) 502-8371. This filing may also be viewed
on the Commission's Web site at https://www.ferc.gov/docs-filing/efiling.asp. Enter the docket number excluding the last three digits in
the docket number field to access the document. You may also register
online at https://www.ferc.gov/docs-filing/esubscription.asp to be
notified via email of new filings and issuances related to this or
other pending projects. For assistance, call 1-866-208-3676 or e-mail
FERCOnlineSupport@ferc.gov, for TTY, call (202) 502-8659. A copy is
also available for inspection and reproduction at the address in item
(h) above.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Comments, Protests, or Motions to Intervene: Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214. In determining the appropriate action to take, the Commission
will consider all protests or other comments filed, but only those who
file a motion to intervene in accordance with the Commission's Rules
may become a party to the proceeding. Any comments, protests, or
motions to intervene must be received on or before the specified
comment date for the particular application.
o. Filing and Service of Responsive Documents: Any filing must (1)
Bear in all capital letters the title ``COMMENTS'', ``PROTEST'', or
``MOTION TO INTERVENE'' as applicable; (2) set forth in the heading the
name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person protesting or intervening; and (4) otherwise
comply with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, motions to intervene or protests must set forth their
evidentiary basis and otherwise comply with the requirements of 18 CFR
4.34(b). All comments, motions to intervene or protests should relate
to project works which are the subject of the license amendment.
Agencies may obtain copies of the application directly from the
applicant. A copy of any protest or motion to intervene must be served
upon each representative of the applicant specified in the particular
application. If an intervener files comments or documents with the
Commission relating to the merits of an issue that may affect the
responsibilities of a particular resource agency, they must also serve
a copy of the document on that resource agency. A copy of all other
filings in reference to this application must be accompanied by proof
of service on all persons listed in the service list prepared by the
Commission in this proceeding, in accordance with 18 CFR 4.34(b) and
385.2010.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010-24947 Filed 10-4-10; 8:45 am]