Central New York Oil and Gas Company, LLC; Notice of Availability of the Environmental Assessment for the Proposed North-South Project, 61461-61462 [2010-24944]

Download as PDF Federal Register / Vol. 75, No. 192 / Tuesday, October 5, 2010 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP07–417–006; CP08–467–001] Texas Gas Transmission, LLC; Notice of Application mstockstill on DSKH9S0YB1PROD with NOTICES September 28, 2010. Take notice that on September 22, 2010, Texas Gas Transmission, LLC (Texas Gas), 3800 Frederica Street, Owensboro, Kentucky 42301, filed an application in Docket Nos. CP07–417– 006 and CP08–467–001, requesting an amendment to the certificates of public convenience and necessity issued on May 2, 2008 in Docket No. CP07–417– 000 and on April 16, 2009 in Docket No. CP08–467–000 pursuant to section 7(c) of the Natural Gas Act and Part 157 of the Commission’s Regulations. Specifically, Texas Gas requests authorization to increase the maximum design capacity of its Greenville Lateral to 1,053,000 MMBtu per day, all as more fully set forth in the application. The application is on file with the Commission and open to public inspection. This filing is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. Any questions regarding this Application should be directed to Kathy D. Fort, Manager of Certificates and Tariffs, Texas Gas Transmission, LLC, 3800 Frederica Street, Owensboro, Kentucky, 42301 or by telephone at 270–688–6825 or fax at 270–688–5871. Pursuant to section 157.9 of the Commission’s rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission’s public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff’s issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission’s public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and VerDate Mar<15>2010 18:36 Oct 04, 2010 Jkt 223001 state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff’s FEIS or EA. There are two ways to become involved in the Commission’s review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below, file with the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission’s Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 14 copies of filings made with the Commission and must mail a copy to the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding. However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission’s rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest. Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commentors will be placed on the Commission’s environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission’s environmental review process. Environmental commentors will not be required to serve copies of filed documents on all other parties. However, the non-party commentors will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of PO 00000 Frm 00051 Fmt 4703 Sfmt 4703 61461 environmental documents issued by the Commission) and will not have the right to seek court review of the Commission’s final order. The Commission strongly encourages electronic filings of comments, protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: October 19, 2010. Kimberly D. Bose, Secretary. [FR Doc. 2010–24949 Filed 10–4–10; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP10–194–000] Central New York Oil and Gas Company, LLC; Notice of Availability of the Environmental Assessment for the Proposed North-South Project September 27, 2010. The staff of the Federal Energy Regulatory Commission (FERC or Commission) has prepared an environmental assessment (EA) for the North-South Project proposed by Central New York Oil and Gas Company, LLC (CNYOG) in the above referenced docket. CNYOG requests authorization to construct, operate, and maintain two new compressor stations in Tioga County, New York and Bradford County, Pennsylvania. The project, which is associated with CNYOG’s existing Stagecoach Storage Project, would increase the firm natural gas throughout of the existing North and South Laterals to 560 million cubic feet per day and 728 cubic feet per day, respectively. The EA assesses the potential environmental effects of the E:\FR\FM\05OCN1.SGM 05OCN1 mstockstill on DSKH9S0YB1PROD with NOTICES 61462 Federal Register / Vol. 75, No. 192 / Tuesday, October 5, 2010 / Notices construction and operation of the NorthSouth Project in accordance with the requirements of the National Environmental Policy Act. The FERC staff concludes that approval of the proposed project, with appropriate mitigating measures, would not constitute a major federal action significantly affecting the quality of the human environment. The proposed North-South Project includes the following facilities: • One new compressor station in Tioga County, New York (the NS1 Compressor Station) with an electricdriven 13,400-horsepower (hp) centrifugal compressor; • One new compressor station in Bradford County, Pennsylvania (the NS2 Compressor Station) with an electricdriven 15,300-hp centrifugal compressor; • Two 30-inch-diameter natural gas pipelines, each about 820 feet long, connecting the NS2 Compressor Station with Tennessee Gas Pipeline Company’s (TGP) pipeline in Bradford County, Pennsylvania; • An approximately 1,700-foot-long non-jurisdictional powerline to the NS2 Compressor Station; • A 15,000-foot-long nonjurisdictional powerline and an electric substation to supply the NS1 Compressor Station; and • Expansion of existing metering facilities at the interconnects between CNYOG’s North and South Laterals and Millennium Pipeline Company’s and TGP’s pipelines, respectively. The EA has been placed in the public files of the FERC and is available for public viewing on the FERC’s Web site at https://www.ferc.gov using the eLibrary link. A limited number of copies of the EA are available for distribution and public inspection at: Federal Energy Regulatory Commission, Public Reference Room, 888 First Street, NE., Room 2A, Washington, DC 20426, (202) 502–8371. Copies of the EA have been mailed to federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American tribes; potentially affected landowners and other interested individuals and groups; newspapers and libraries in the project area; and parties to this proceeding. Any person wishing to comment on the EA may do so. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. The more specific your comments, the more useful they will be. To ensure that your comments are properly recorded and VerDate Mar<15>2010 18:36 Oct 04, 2010 Jkt 223001 considered prior to a Commission decision on the proposal, it is important that the FERC receives your comments in Washington, DC on or before October 27, 2010. For your convenience, there are three methods you can use to submit your comments to the Commission. In all instances, please reference the project docket number (CP10–194–000) with your submission. The Commission encourages electronic filing of comments and has dedicated eFiling expert staff available to assist you at (202) 502–8258 or efiling@ferc.gov. (1) You may file your comments electronically by using the eComment feature, which is located on the Commission’s Web site at https:// www.ferc.gov under the link to Documents and Filings. An eComment is an easy method for interested persons to submit brief, text-only comments on a project; (2) You may file your comments electronically by using the eFiling feature, which is located on the Commission’s Web site at https:// www.ferc.gov under the link to Documents and Filings. With eFiling you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making. A comment on a particular project is considered a ‘‘Comment on a Filing’’; or (3) You may file a paper copy of your comments at the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Room 1A, Washington, DC 20426. Although your comments will be considered by the Commission, simply filing comments will not serve to make the commentor a party to the proceeding. Any person seeking to become a party to the proceeding must file a motion to intervene pursuant to Rule 214 of the Commission’s Rules of Practice and Procedures (18 CFR 385.214).1 Only intervenors have the right to seek rehearing of the Commission’s decision. Affected landowners and parties with environmental concerns may be granted intervenor status upon showing good cause by stating that they have a clear and direct interest in this proceeding which would not be adequately represented by any other parties. You do 1 Interventions may also be filed electronically via the Internet in lieu of paper. See the previous discussion on filing comments electronically. PO 00000 Frm 00052 Fmt 4703 Sfmt 4703 not need intervenor status to have your comments considered. Additional information about the project is available from the Commission’s Office of External Affairs, at (866) 208–FERC or on the FERC Web site (https://www.ferc.gov) using the eLibrary link. Click on the eLibrary link, click on ‘‘General Search’’ and enter the docket number excluding the last three digits in the Docket Number field (i.e., CP10–194). Be sure you have selected an appropriate date range. For assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov or toll free at (866) 208–3676, or for TTY, contact (202) 502–8659. The eLibrary link also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rulemakings. In addition, the Commission offers a free service called eSubscription which allows you to keep track of all formal issuances and submittals in specific dockets. This can reduce the amount of time you spend researching proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to https://www.ferc.gov/ esubscribenow.htm. Kimberly D. Bose, Secretary. [FR Doc. 2010–24944 Filed 10–4–10; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. PR10–29–002] Enbridge Pipelines (North Texas) L.P.; Notice of Baseline Filing September 29, 2010. Take notice that on September 27, 2010, Enbridge Pipelines (North Texas) L.P. submitted a revised baseline filing of its Statement of Operating Conditions for services provided under section 311 of the Natural Gas Policy Act of 1978 (NGPA). Any person desiring to participate in this rate proceeding must file a motion to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or E:\FR\FM\05OCN1.SGM 05OCN1

Agencies

[Federal Register Volume 75, Number 192 (Tuesday, October 5, 2010)]
[Notices]
[Pages 61461-61462]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-24944]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP10-194-000]


Central New York Oil and Gas Company, LLC; Notice of Availability 
of the Environmental Assessment for the Proposed North-South Project

September 27, 2010.
    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) has prepared an environmental assessment (EA) for the 
North-South Project proposed by Central New York Oil and Gas Company, 
LLC (CNYOG) in the above referenced docket. CNYOG requests 
authorization to construct, operate, and maintain two new compressor 
stations in Tioga County, New York and Bradford County, Pennsylvania. 
The project, which is associated with CNYOG's existing Stagecoach 
Storage Project, would increase the firm natural gas throughout of the 
existing North and South Laterals to 560 million cubic feet per day and 
728 cubic feet per day, respectively.
    The EA assesses the potential environmental effects of the

[[Page 61462]]

construction and operation of the North-South Project in accordance 
with the requirements of the National Environmental Policy Act. The 
FERC staff concludes that approval of the proposed project, with 
appropriate mitigating measures, would not constitute a major federal 
action significantly affecting the quality of the human environment.
    The proposed North-South Project includes the following facilities:
     One new compressor station in Tioga County, New York (the 
NS1 Compressor Station) with an electric-driven 13,400-horsepower (hp) 
centrifugal compressor;
     One new compressor station in Bradford County, 
Pennsylvania (the NS2 Compressor Station) with an electric-driven 
15,300-hp centrifugal compressor;
     Two 30-inch-diameter natural gas pipelines, each about 820 
feet long, connecting the NS2 Compressor Station with Tennessee Gas 
Pipeline Company's (TGP) pipeline in Bradford County, Pennsylvania;
     An approximately 1,700-foot-long non-jurisdictional 
powerline to the NS2 Compressor Station;
     A 15,000-foot-long non-jurisdictional powerline and an 
electric substation to supply the NS1 Compressor Station; and
     Expansion of existing metering facilities at the 
interconnects between CNYOG's North and South Laterals and Millennium 
Pipeline Company's and TGP's pipelines, respectively.
    The EA has been placed in the public files of the FERC and is 
available for public viewing on the FERC's Web site at https://www.ferc.gov using the eLibrary link. A limited number of copies of the 
EA are available for distribution and public inspection at: Federal 
Energy Regulatory Commission, Public Reference Room, 888 First Street, 
NE., Room 2A, Washington, DC 20426, (202) 502-8371.
    Copies of the EA have been mailed to federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American tribes; 
potentially affected landowners and other interested individuals and 
groups; newspapers and libraries in the project area; and parties to 
this proceeding.
    Any person wishing to comment on the EA may do so. Your comments 
should focus on the potential environmental effects, reasonable 
alternatives, and measures to avoid or lessen environmental impacts. 
The more specific your comments, the more useful they will be. To 
ensure that your comments are properly recorded and considered prior to 
a Commission decision on the proposal, it is important that the FERC 
receives your comments in Washington, DC on or before October 27, 2010.
    For your convenience, there are three methods you can use to submit 
your comments to the Commission. In all instances, please reference the 
project docket number (CP10-194-000) with your submission. The 
Commission encourages electronic filing of comments and has dedicated 
eFiling expert staff available to assist you at (202) 502-8258 or 
efiling@ferc.gov.
    (1) You may file your comments electronically by using the eComment 
feature, which is located on the Commission's Web site at https://www.ferc.gov under the link to Documents and Filings. An eComment is an 
easy method for interested persons to submit brief, text-only comments 
on a project;
    (2) You may file your comments electronically by using the eFiling 
feature, which is located on the Commission's Web site at https://www.ferc.gov under the link to Documents and Filings. With eFiling you 
can provide comments in a variety of formats by attaching them as a 
file with your submission. New eFiling users must first create an 
account by clicking on ``eRegister.'' You will be asked to select the 
type of filing you are making. A comment on a particular project is 
considered a ``Comment on a Filing''; or
    (3) You may file a paper copy of your comments at the following 
address: Kimberly D. Bose, Secretary, Federal Energy Regulatory 
Commission, 888 First Street, NE., Room 1A, Washington, DC 20426.
    Although your comments will be considered by the Commission, simply 
filing comments will not serve to make the commentor a party to the 
proceeding. Any person seeking to become a party to the proceeding must 
file a motion to intervene pursuant to Rule 214 of the Commission's 
Rules of Practice and Procedures (18 CFR 385.214).\1\ Only intervenors 
have the right to seek rehearing of the Commission's decision.
---------------------------------------------------------------------------

    \1\ Interventions may also be filed electronically via the 
Internet in lieu of paper. See the previous discussion on filing 
comments electronically.
---------------------------------------------------------------------------

    Affected landowners and parties with environmental concerns may be 
granted intervenor status upon showing good cause by stating that they 
have a clear and direct interest in this proceeding which would not be 
adequately represented by any other parties. You do not need intervenor 
status to have your comments considered.
    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC or on the 
FERC Web site (https://www.ferc.gov) using the eLibrary link. Click on 
the eLibrary link, click on ``General Search'' and enter the docket 
number excluding the last three digits in the Docket Number field 
(i.e., CP10-194). Be sure you have selected an appropriate date range. 
For assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to https://www.ferc.gov/esubscribenow.htm.

Kimberly D. Bose,
Secretary.
[FR Doc. 2010-24944 Filed 10-4-10; 8:45 am]
BILLING CODE 6717-01-P