Download as PDF Federal Register / Vol. 75, No. 189 / Thursday, September 30, 2010 / Notices DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13833–000] Northern Wasco People’s Utility District; Notice of Preliminary Permit Application Accepted For Filing and Soliciting Comments, Motions To Intervene, and Competing Applications mstockstill on DSKH9S0YB1PROD with NOTICES6 September 22, 2010. On August 23, 2010, Northern Wasco People’s Utility District (Northern Wasco PUD) filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act (FPA), proposing to study the feasibility of the White River Falls Hydroelectric project near Maupin, Wasco County, Oregon. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any landdisturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed project calls for redevelopment of a hydroelectric project constructed in 1902 and decommissioned in 1963. Northern Wasco PUD proposes to reconstruct, replace, and repair some existing features, as well as build new features at the site. The proposed project will consist of the following: (1) New head works; (2) anchors placed throughout the existing weir; (3) a new 600-foot-long, 6-footdiameter penstock to be constructed at the site of the old structure; (4) a new powerhouse with two turbine/generator units with an installed capacity of 3.4 to 4.0-megawatts; (5) a 4.15-kilovolt, 1,800foot-long, underground transmission line connecting to an existing substation; and (6) appurtenant facilities. The estimated annual generation of the White River Falls project is 16,000 megawatt-hours. Applicant Contact: Bob Guidinger, Hydro Dept Manager, Northern Wasco PUD, 2345 River Road, The Dalles, OR 97058; phone: (541) 298–3325. FERC Contact: Patrick Murphy (202) 502–8755. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance of this notice. Competing applications and notices of intent must meet the requirements of 18 CFR 4.36. Comments, motions to intervene, notices of intent, and competing applications may be filed VerDate Mar<15>2010 17:48 Sep 29, 2010 Jkt 220001 electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site https://www.ferc.gov/docs-filing/ efiling.asp. Commenters can submit brief comments up to 6,000 characters, without prior registration, using the eComment system at https:// www.ferc.gov/docs-filing/ ecomment.asp. You must include your name and contact information at the end of your comments. For assistance, please contact FERC Online Support. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and seven copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of the Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–13833–000) in the docket number field to access the document. For assistance, contact FERC Online Support. 60441 BILLING CODE 6717–01–P protests must be filed on or before the date as indicated below. Anyone filing an intervention or protest must serve a copy of that document on the Applicant. Anyone filing an intervention or protest on or before the intervention or protest date need not serve motions to intervene or protests on persons other than the Applicant. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: 5 p.m. Eastern Time on Friday, October 1, 2010. DEPARTMENT OF ENERGY Kimberly D. Bose, Secretary. Kimberly D. Bose, Secretary. [FR Doc. 2010–24513 Filed 9–29–10; 8:45 am] [FR Doc. 2010–24515 Filed 9–29–10; 8:45 am] Federal Energy Regulatory Commission BILLING CODE 6717–01–P [Docket No. PR10–12–001] DEPARTMENT OF ENERGY Arkansas Western Gas Company; Notice of Compliance Filing September 23, 2010. Take notice that on September 17, 2010, Arkansas Western Gas Company (AWG) filed pursuant to an August 20, 2010, Letter Order which required AWG to file within 30 days of the issuance of the August 20 order a stand alone statement of rates that includes all currently effective maximum and minimum rates and fuel charges. Any person desiring to participate in this rate filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or PO 00000 Frm 00038 Fmt 4703 Sfmt 4703 Federal Energy Regulatory Commission [Docket No. CP10–486–000] Colorado Interstate Gas Company; Notice of Intent To Prepare an Environmental Assessment for the Proposed Spruce Hill Air Blending Project and Request for Comments on Environmental Issues September 21, 2010. The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the Spruce Hill Air Blending Project involving construction and operation of facilities by Colorado Interstate Gas Company (CIG) in Douglas County, Colorado. This EA will be used by the Commission in its decision-making process to determine whether the E:\FR\FM\30SEN1.SGM 30SEN1 60442 Federal Register / Vol. 75, No. 189 / Thursday, September 30, 2010 / Notices mstockstill on DSKH9S0YB1PROD with NOTICES6 project is in the public convenience and necessity. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies on the project. Your input will help the Commission staff determine what issues need to be evaluated in the EA. Please note that the scoping period will close on October 21, 2010. This notice is being sent to the Commission’s current environmental mailing list for this project. State and local government representatives are asked to notify their constituents of this proposed project and encourage them to comment on their areas of concern. If you are a landowner receiving this notice, you may be contacted by a pipeline company representative about the acquisition of an easement to construct, operate, and maintain the proposed facilities. The company would seek to negotiate a mutually acceptable agreement. However, if the project is approved by the Commission, that approval conveys with it the right of eminent domain. Therefore, if easement negotiations fail to produce an agreement, the pipeline company could initiate condemnation proceedings where compensation would be determined in accordance with state law. A fact sheet prepared by the FERC entitled ‘‘An Interstate Natural Gas Facility On My Land? What Do I Need To Know?’’ was attached to the project notice CIG provided to landowners. This fact sheet addresses a number of typically-asked questions, including the use of eminent domain and how to participate in the Commission’s proceedings. It is also available for viewing on the FERC Web site (https:// www.ferc.gov). Summary of the Proposed Project CIG proposes to construct and operate a new air blending station in Douglas County, Colorado. The Spruce Hill Air Blending Project would increase CIG’s firm natural gas transportation capacity to 50,000 dekatherms per day (Dth/day) to meet contractual agreements with Black Hills Utility Holdings, Inc. (Black Hill) as a result of Black Hill’s anticipated demand growth. According to CIG, its project would reduce the input factor of the gas to a level that conforms to the gas quality specifications in CIG’s Tariff for its existing Valley Line, to which the blended gas would be discharged. The Spruce Hill Air Blending Project would consist of the following: • An air blending compressor station (the Spruce Hill Air Blending Station) VerDate Mar<15>2010 17:48 Sep 29, 2010 Jkt 220001 containing a 215-, a 390-, and a 500horsepower air compressor; • A back-pressure regulator; • Air blending controls and instrumentation; • A gas heater; • Auxiliary facilities and piping; • Modifications to the existing Spruce Hill Meter Station; • An interconnection at the air blending station between the existing Spruce Hill Meter Station and CIG’s existing Line No. 212A; and • A powerline connection within CIG’s 35-acre parcel. The general location of the project facilities is shown in Appendix 1.1 Land Requirements for Construction Construction of the proposed facilities would disturb about 5.5 acres of land for the air blending station and its auxiliary facilities. Following construction, about 3.3 acres would be maintained for permanent operation of the project’s facilities; the remaining acreage would be restored and allowed to revert to former uses. All construction would occur within a 35-acre land parcel owned by CIG. The EA Process The National Environmental Policy Act (NEPA) requires the Commission to take into account the environmental impacts that could result from an action whenever it considers the issuance of a Certificate of Public Convenience and Necessity. NEPA also requires us 2 to discover and address concerns the public may have about proposals. This process is referred to as ‘‘scoping’’. The main goal of the scoping process is to focus the analysis in the EA on the important environmental issues. By this notice, the Commission requests public comments on the scope of the issues to address in the EA. All comments received will be considered during the preparation of the EA. In the EA we will discuss impacts that could occur as a result of the construction and operation of the proposed project under these general headings: • Geology and soils; • Land use; • Water resources, fisheries, and wetlands; 1 The appendices referenced in this notice are not being printed in the Federal Register. Copies of appendices were sent to all those receiving this notice in the mail and are available at https:// www.ferc.gov using the link called ‘‘eLibrary’’ or from the Commission’s Public Reference Room, 888 First Street, NE., Washington, DC 20426, or call (202) 502–8371. For instructions on connecting to eLibrary, refer to the last page of this notice. 2 ‘‘We’’, ‘‘us’’, and ‘‘our’’ refer to the environmental staff of the Commission’s Office of Energy Projects. PO 00000 Frm 00039 Fmt 4703 Sfmt 4703 • Cultural resources; • Vegetation and wildlife; • Air quality and noise; • Endangered and threatened species; and • Public safety. We will also evaluate reasonable alternatives to the proposed project or portions of the project, and make recommendations on how to lessen or avoid impacts on the various resource areas. Our independent analysis of the issues will be presented in the EA. The EA will be placed in the public record and, depending on the comments received during the scoping process, may be published and distributed to the public. A comment period will be allotted if the EA is published for review. We will consider all comments on the EA before we make our recommendations to the Commission. To ensure your comments are considered, please carefully follow the instructions in the Public Participation section below. With this notice, we are asking agencies with jurisdiction and/or special expertise with respect to environmental issues to formally cooperate with us in the preparation of the EA. These agencies may choose to participate once they have evaluated the proposal relative to their responsibilities. Agencies that would like to request cooperating agency status should follow the instructions for filing comments provided under the Public Participation section of this notice. Consultations Under Section 106 of the National Historic Preservation Act In accordance with the Advisory Council on Historic Preservation’s implementing regulations for section 106 of the National Historic Preservation Act, we are using this notice to initiate consultation with the Colorado State Historic Preservation Office, and to solicit their views and those of other government agencies, interested Indian tribes, and the public on the project’s potential effects on historic properties.3 We will define the project-specific Area of Potential Effects (APE) in consultation with the SHPO as the project is further developed. On natural gas facility projects, the APE at a minimum encompasses all areas subject to ground disturbance (examples include construction right-of-way, 3 The Advisory Council on Historic Preservation’s regulations are at Title 36, Code of Federal Regulations, Part 800. Historic properties are defined in those regulations as any prehistoric or historic district, site, building, structure, or object included in or eligible for inclusion in the National Register for Historic Places. E:\FR\FM\30SEN1.SGM 30SEN1 Federal Register / Vol. 75, No. 189 / Thursday, September 30, 2010 / Notices contractor/pipe storage yards, compressor stations, and access roads). Our EA for this project will document our findings on the impacts on historic properties and summarize the status of consultations under section 106. mstockstill on DSKH9S0YB1PROD with NOTICES6 Public Participation You can make a difference by providing us with your specific comments or concerns about the project. Your comments should focus on the potential environmental effects, reasonable alternatives, and measures to avoid or lessen environmental impacts. The more specific your comments, the more useful they will be. To ensure that your comments are timely and properly recorded, please send your comments so that they will be received in Washington, DC on or before October 21, 2010. For your convenience, there are three methods which you can use to submit your comments to the Commission. In all instances please reference the project docket number (CP10–486–000) with your submission. The Commission encourages electronic filing of comments and has expert eFiling staff available to assist you at (202) 502–8258 or efiling@ferc.gov. (1) You may file your comments electronically by using the eComment feature, which is located on the Commission’s Web site at www.ferc.gov under the link to Documents and Filings. An eComment is an easy method for interested persons to submit brief, text-only comments on a project; (2) You may file your comments electronically by using the eFiling feature, which is located on the Commission’s Web site at www.ferc.gov under the link to Documents and Filings. With eFiling you can provide comments in a variety of formats by attaching them as a file with your submission. New eFiling users must first create an account by clicking on ‘‘eRegister.’’ You will be asked to select the type of filing you are making. A comment on a particular project is considered a ‘‘Comment on a Filing’’; or (3) You may file a paper copy of your comments at the following address: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Room 1A, Washington, DC 20426. Environmental Mailing List The environmental mailing list includes federal, state, and local government representatives and agencies; elected officials; environmental and public interest groups; Native American Tribes; other interested parties; and local libraries VerDate Mar<15>2010 17:48 Sep 29, 2010 Jkt 220001 and newspapers. This list also includes all affected landowners (as defined in the Commission’s regulations) who are potential right-of-way grantors, whose property may be used temporarily for project purposes, or who own homes within certain distances of aboveground facilities, and anyone who submits comments on the project. We will update the environmental mailing list as the analysis proceeds to ensure that we send the information related to this environmental review to all individuals, organizations, and government entities interested in and/or potentially affected by the proposed project. If the EA is published for distribution, copies will be sent to the environmental mailing list for public review and comment. If you would prefer to receive a paper copy of the document instead of the CD version or would like to remove your name from the mailing list, please return the attached Information Request (Appendix 2). Becoming an Intervenor In addition to involvement in the EA scoping process, you may want to become an ‘‘intervenor’’ which is an official party to the Commission’s proceeding. Intervenors play a more formal role in the process and are able to file briefs, appear at hearings, and be heard by the courts if they choose to appeal the Commission’s final ruling. An intervenor formally participates in the proceeding by filing a request to intervene. Instructions for becoming an intervenor are included in the User’s Guide under the ‘‘e-filing’’ link on the Commission’s Web site. 60443 proceedings by automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to https:// www.ferc.gov/esubscribenow.htm. Finally, public meetings or site visits will be posted on the Commission’s calendar located at https://www.ferc.gov/ EventCalendar/EventsList.aspx along with other related information. Kimberly D. Bose, Secretary. [FR Doc. 2010–24514 Filed 9–29–10; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. EC10–67–001] BHE Holdings, Inc., Maine & Maritimes Corporation; Notice of Filing September 22, 2010. Take notice that, on September 15, 2010, BHE Holdings, Inc. and Maine & Maritimes Corporation (Merger Applicants) submitted an amendment to an earlier application that was filed on May 11, 2010, in the above-referenced proceeding pursuant to section 203 of the Federal Power Act. Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211, 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will Additional Information not serve to make protestants parties to the proceeding. Any person wishing to Additional information about the become a party must file a notice of project is available from the Commission’s Office of External Affairs, intervention or motion to intervene, as at (866) 208–FERC, or on the FERC Web appropriate. Such notices, motions, or protests must be filed on or before the site at https://www.ferc.gov using the comment date. Anyone filing a motion ‘‘eLibrary’’ link. Click on the eLibrary link, click on ‘‘General Search’’ and enter to intervene or protest must serve a copy of that document on the Applicant and the docket number, excluding the last all the parties in this proceeding. three digits in the Docket Number field The Commission encourages (i.e., CP10–486). Be sure you have electronic submission of protests and selected an appropriate date range. For interventions in lieu of paper using the assistance, please contact FERC Online Support at FercOnlineSupport@ferc.gov ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically or toll free at (866) 208–3676, or for should submit an original and 14 copies TTY, contact (202) 502–8659. The eLibrary link also provides access to the of the protest or intervention to the texts of formal documents issued by the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC Commission, such as orders, notices, 20426. and rulemakings. In addition, the Commission now This filing is accessible online at offers a free service called eSubscription https://www.ferc.gov, using the which allows you to keep track of all ‘‘eLibrary’’ link and is available for formal issuances and submittals in review in the Commission’s Public specific dockets. This can reduce the Reference Room in Washington, DC. amount of time you spend researching There is an ‘‘eSubscription’’ link on the PO 00000 Frm 00040 Fmt 4703 Sfmt 4703 E:\FR\FM\30SEN1.SGM 30SEN1

Agencies

[Federal Register Volume 75, Number 189 (Thursday, September 30, 2010)]
[Notices]
[Pages 60441-60443]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-24514]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP10-486-000]


Colorado Interstate Gas Company; Notice of Intent To Prepare an 
Environmental Assessment for the Proposed Spruce Hill Air Blending 
Project and Request for Comments on Environmental Issues

September 21, 2010.
    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Spruce Hill Air Blending 
Project involving construction and operation of facilities by Colorado 
Interstate Gas Company (CIG) in Douglas County, Colorado. This EA will 
be used by the Commission in its decision-making process to determine 
whether the

[[Page 60442]]

project is in the public convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the project. Your input will help the Commission staff 
determine what issues need to be evaluated in the EA. Please note that 
the scoping period will close on October 21, 2010.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives are asked to notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, you may be contacted 
by a pipeline company representative about the acquisition of an 
easement to construct, operate, and maintain the proposed facilities. 
The company would seek to negotiate a mutually acceptable agreement. 
However, if the project is approved by the Commission, that approval 
conveys with it the right of eminent domain. Therefore, if easement 
negotiations fail to produce an agreement, the pipeline company could 
initiate condemnation proceedings where compensation would be 
determined in accordance with state law.
    A fact sheet prepared by the FERC entitled ``An Interstate Natural 
Gas Facility On My Land? What Do I Need To Know?'' was attached to the 
project notice CIG provided to landowners. This fact sheet addresses a 
number of typically-asked questions, including the use of eminent 
domain and how to participate in the Commission's proceedings. It is 
also available for viewing on the FERC Web site (https://www.ferc.gov).

Summary of the Proposed Project

    CIG proposes to construct and operate a new air blending station in 
Douglas County, Colorado. The Spruce Hill Air Blending Project would 
increase CIG's firm natural gas transportation capacity to 50,000 
dekatherms per day (Dth/day) to meet contractual agreements with Black 
Hills Utility Holdings, Inc. (Black Hill) as a result of Black Hill's 
anticipated demand growth. According to CIG, its project would reduce 
the input factor of the gas to a level that conforms to the gas quality 
specifications in CIG's Tariff for its existing Valley Line, to which 
the blended gas would be discharged.
    The Spruce Hill Air Blending Project would consist of the 
following:
     An air blending compressor station (the Spruce Hill Air 
Blending Station) containing a 215-, a 390-, and a 500-horsepower air 
compressor;
     A back-pressure regulator;
     Air blending controls and instrumentation;
     A gas heater;
     Auxiliary facilities and piping;
     Modifications to the existing Spruce Hill Meter Station;
     An interconnection at the air blending station between the 
existing Spruce Hill Meter Station and CIG's existing Line No. 212A; 
and
     A powerline connection within CIG's 35-acre parcel.
    The general location of the project facilities is shown in Appendix 
1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice are not being 
printed in the Federal Register. Copies of appendices were sent to 
all those receiving this notice in the mail and are available at 
https://www.ferc.gov using the link called ``eLibrary'' or from the 
Commission's Public Reference Room, 888 First Street, NE., 
Washington, DC 20426, or call (202) 502-8371. For instructions on 
connecting to eLibrary, refer to the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the proposed facilities would disturb about 5.5 
acres of land for the air blending station and its auxiliary 
facilities. Following construction, about 3.3 acres would be maintained 
for permanent operation of the project's facilities; the remaining 
acreage would be restored and allowed to revert to former uses. All 
construction would occur within a 35-acre land parcel owned by CIG.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\2\ to discover and address concerns the public may have about 
proposals. This process is referred to as ``scoping''. The main goal of 
the scoping process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EA. All comments 
received will be considered during the preparation of the EA.
---------------------------------------------------------------------------

    \2\ ``We'', ``us'', and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the proposed project under these 
general headings:
     Geology and soils;
     Land use;
     Water resources, fisheries, and wetlands;
     Cultural resources;
     Vegetation and wildlife;
     Air quality and noise;
     Endangered and threatened species; and
     Public safety.
    We will also evaluate reasonable alternatives to the proposed 
project or portions of the project, and make recommendations on how to 
lessen or avoid impacts on the various resource areas.
    Our independent analysis of the issues will be presented in the EA. 
The EA will be placed in the public record and, depending on the 
comments received during the scoping process, may be published and 
distributed to the public. A comment period will be allotted if the EA 
is published for review. We will consider all comments on the EA before 
we make our recommendations to the Commission. To ensure your comments 
are considered, please carefully follow the instructions in the Public 
Participation section below.
    With this notice, we are asking agencies with jurisdiction and/or 
special expertise with respect to environmental issues to formally 
cooperate with us in the preparation of the EA. These agencies may 
choose to participate once they have evaluated the proposal relative to 
their responsibilities. Agencies that would like to request cooperating 
agency status should follow the instructions for filing comments 
provided under the Public Participation section of this notice.

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with the Colorado State Historic Preservation Office, and to solicit 
their views and those of other government agencies, interested Indian 
tribes, and the public on the project's potential effects on historic 
properties.\3\ We will define the project-specific Area of Potential 
Effects (APE) in consultation with the SHPO as the project is further 
developed. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way,

[[Page 60443]]

contractor/pipe storage yards, compressor stations, and access roads). 
Our EA for this project will document our findings on the impacts on 
historic properties and summarize the status of consultations under 
section 106.
---------------------------------------------------------------------------

    \3\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Historic 
properties are defined in those regulations as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register for Historic 
Places.
---------------------------------------------------------------------------

Public Participation

    You can make a difference by providing us with your specific 
comments or concerns about the project. Your comments should focus on 
the potential environmental effects, reasonable alternatives, and 
measures to avoid or lessen environmental impacts. The more specific 
your comments, the more useful they will be. To ensure that your 
comments are timely and properly recorded, please send your comments so 
that they will be received in Washington, DC on or before October 21, 
2010.
    For your convenience, there are three methods which you can use to 
submit your comments to the Commission. In all instances please 
reference the project docket number (CP10-486-000) with your 
submission. The Commission encourages electronic filing of comments and 
has expert eFiling staff available to assist you at (202) 502-8258 or 
efiling@ferc.gov.
    (1) You may file your comments electronically by using the eComment 
feature, which is located on the Commission's Web site at www.ferc.gov 
under the link to Documents and Filings. An eComment is an easy method 
for interested persons to submit brief, text-only comments on a 
project;
    (2) You may file your comments electronically by using the eFiling 
feature, which is located on the Commission's Web site at www.ferc.gov 
under the link to Documents and Filings. With eFiling you can provide 
comments in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on ``eRegister.'' You will be asked to select the type of filing you 
are making. A comment on a particular project is considered a ``Comment 
on a Filing''; or
    (3) You may file a paper copy of your comments at the following 
address: Kimberly D. Bose, Secretary, Federal Energy Regulatory 
Commission, 888 First Street, NE., Room 1A, Washington, DC 20426.

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project. We will update the environmental mailing list 
as the analysis proceeds to ensure that we send the information related 
to this environmental review to all individuals, organizations, and 
government entities interested in and/or potentially affected by the 
proposed project.
    If the EA is published for distribution, copies will be sent to the 
environmental mailing list for public review and comment. If you would 
prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (Appendix 2).

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are 
included in the User's Guide under the ``e-filing'' link on the 
Commission's Web site.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site at https://www.ferc.gov using the ``eLibrary'' link. Click 
on the eLibrary link, click on ``General Search'' and enter the docket 
number, excluding the last three digits in the Docket Number field 
(i.e., CP10-486). Be sure you have selected an appropriate date range. 
For assistance, please contact FERC Online Support at 
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission now offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to https://www.ferc.gov/esubscribenow.htm.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at https://www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

Kimberly D. Bose,
Secretary.
[FR Doc. 2010-24514 Filed 9-29-10; 8:45 am]