Notice of Intent To Prepare a Legislative Environmental Impact Statement for the Proposed Extension of the Chocolate Mountain Aerial Gunnery Range Land Withdrawal, 58370-58372 [2010-23984]

Download as PDF srobinson on DSKHWCL6B1PROD with NOTICES 58370 Federal Register / Vol. 75, No. 185 / Friday, September 24, 2010 / Notices properties. USACE Detroit District, and Wayne County, MI acting as the nonfederal sponsor, have formed a partnership to reevaluate the flooding issues along the NBEC. The GRR/EIS, will update a feasibility study and EIS completed by USACE in 1988. The purpose of this GRR/EIS is reanalysis of the federal interest in developing flood risk management measures on the NBEC. The analysis will include reformulation of the authorized plan from the 1988 study for applicability. The GRR/EIS will incorporate a review of developments in the floodplain during the last 22 years, consideration of changing needs of the local communities, and current environmental conditions. When complete, the GRR/EIS will recommend if flood mitigation measures should occur with federal assistance. Federal funding for the GRR/EIS phase originates from American Recovery and Reinvestment Act funds, which requires the GRR/EIS to be developed on an accelerated schedule. Project Authority: The GRR/EIS is being completed based on authorization by Section 102 of the River and Harbor Act of 1966 (Pub. L. 89–789). The original study Feasibility Report and Environmental Impact Statement for Flood Protection in the Ecorse Creek Drainage Basin, Wayne County, Michigan, 1987 (Revised 1988) recommended the development of a retention basin as the selected plan. Construction of the selected plan from the 1988 feasibility study was further authorized by Section 101(a) (14) of the Water Resources Development Act (WRDA) of 1990. Construction never occurred. Project authorization was extended in Section 3179 of the WRDA of 2007 to conduct the GRR. Project Alternatives: A number of flood risk management alternatives will be evaluated as part of the GRR/EIS including retention basins, stream widening and restoration, flood walls and levees, along with non-structural measures such as management plans, warning systems and property acquisition. Draft EIS Scoping Process: The scoping process for public input will involve Federal, State, and local agencies, along with affected Indian tribes, other interested parties and entities. Coordination with natural resources and environmental agencies will be conducted under the Fish and Wildlife Coordination Act, Endangered Species Act, Clean Water Act, Clean Air Act, and the National Historic Preservation Act. A public meeting will be held (see DATES) to include discussion of environmental issues VerDate Mar<15>2010 16:12 Sep 23, 2010 Jkt 220001 associated with potential flood risk management alternatives. Issues to be considered during the development of the Draft EIS and public review and input process include: aesthetics, dredged material disposal, water quality, air and noise quality, hazardous, toxic and radiological waste, threatened and endangered species, environmental justice, wetlands, historic properties, recreation, cumulative impacts, natural resource mitigation and other issues that may affect public health and welfare. It is estimated the Draft EIS will be available for public review and comment in late 2011. John M. Niemiec, Project Manager. [FR Doc. 2010–23934 Filed 9–23–10; 8:45 am] BILLING CODE 3720–58–P DEPARTMENT OF DEFENSE Department of the Navy Notice of Intent To Prepare a Legislative Environmental Impact Statement for the Proposed Extension of the Chocolate Mountain Aerial Gunnery Range Land Withdrawal Lead Agency: Department of the Navy, DoD. Cooperating Agency: Bureau of Land Management, Department of the Interior. ACTION: Notice. Pursuant to Section 102(2)(c) of the National Environmental Policy Act (NEPA) of 1969 and regulations implemented by the Council on Environmental Quality (40 Code of Federal Regulations [CFR] Parts 1500– 1508), the Department of the Navy (DoN) and the United States Marine Corps (USMC), with the cooperation of the Bureau of Land Management (BLM), intends to prepare a Legislative Environmental Impact Statement (L–EIS) and conduct public scoping meetings for the proposed extension of the withdrawal of approximately 226,711 acres of public land in Imperial and Riverside counties, California, for continued military use of the Chocolate Mountain Aerial Gunnery Range (CMAGR). The California Military Lands Withdrawal and Overflights Act of 1994 (Pub. L. 103–433) withdrew 226,711 acres of public land to DoN, reserving these lands for defense-related purposes for a period of 20 years (until October 31, 2014). The Act provides that the DoN may seek extension of the CMAGR withdrawal. As part of the withdrawal SUMMARY: PO 00000 Frm 00024 Fmt 4703 Sfmt 4703 process, the Secretary of the Navy is required to publish a Draft L–EIS addressing legislative alternatives and the effects of continued withdrawal. The CMAGR Draft L–EIS will evaluate the environmental effects of the proposal to extend the land withdrawal for an additional 25 years (through 2039) and will evaluate alternative actions to restructure the existing range boundary for improved efficiency in the management of the CMAGR and adjacent lands. DATES AND ADDRESSES: DoN is initiating a 90-day public scoping process to identify community interests and specific issues to be addressed in the L–EIS, which starts with the publication of this Notice of Intent (NOI). Four public scoping meetings have been scheduled to enlist written and oral comments regarding the scope of the Draft L–EIS analysis: 1. Monday, December 6, 2010, 5:30 p.m. to 8 p.m., Yuma County Library, Rooms B–C, 2951 S. 21st Drive, Yuma, Arizona 85364; 2. Tuesday, December 7, 2010, 5:30 p.m. to 8 p.m., Holiday Inn Express—El Centro, Conference Room B, 350 Smoketree Drive, El Centro, California 92243; 3. Wednesday, December 8, 2010, 5:30 p.m. to 8 p.m., Holiday Inn, 1800 E. Palm Canyon, Palm Springs, California 92264; and 4. Thursday, December 9, 2010, 5:30 p.m. to 8 p.m., San Diego Planning Commission Hearing Room, 5201 Ruffin Road, Suite B, San Diego, California 92123. FOR FURTHER INFORMATION CONTACT: CMAGR L–EIS Project Manager (Attn: Kelly Finn), NAVFAC Southwest, 1220 Pacific Highway, San Diego, CA 92132– 5190; phone 619–532–4452. Additional supplementary information regarding the CMAGR Draft L–EIS is available at https:// www.chocolatemountainrenewal.com. Please submit requests for special assistance, sign language interpretation for the hearing impaired, or other auxiliary aids needed at the scoping meeting to the L–EIS Project Manager by November 26, 2010. SUPPLEMENTARY INFORMATION: Public scoping meeting schedules and locations will also be published in local newspapers. The public is invited to attend these meetings to view projectrelated displays, speak with DoN and USMC representatives, and submit public comment forms at information stations. A court reporter will be available at the meetings to accept oral comments. The scoping meetings will be conducted in an informal, open E:\FR\FM\24SEN1.SGM 24SEN1 srobinson on DSKHWCL6B1PROD with NOTICES Federal Register / Vol. 75, No. 185 / Friday, September 24, 2010 / Notices house style meeting format. All comments regarding the scope of issues that should be considered in the Draft L–EIS must be received within 90 days of the publication date of this notice to ensure full consideration in the Draft L–EIS analysis. Submitting Comments: Federal, state, and local agencies and interested parties are encouraged to provide oral and/or written comments regarding the scope of the L–EIS, reasonable alternatives and/or specific issues or topics of interest to the public. Comments may be submitted by: (1) Attending one of the public scoping open houses and providing oral or written comments, (2) submitting a comment form on the project’s public website at https:// www.chocolatemountainrenewal.com, or (3) mail. Written comments should be submitted to the L–EIS Project Manager listed below under FOR FURTHER INFORMATION CONTACT. All written comments on the scope of the L–EIS should be submitted and/or postmarked no later than December 23, 2010. The USMC will consider all comments received during the scoping period. A mailing list has been assembled to facilitate preparation of the L–EIS. Those on this list will receive notices and information related to L–EIS preparation. This list includes local, state, and federal agencies with jurisdiction or other interests in the alternatives. In addition, the mailing list includes affected municipalities and other interested parties. Anyone wishing to be added to the mailing list may request to be added by contacting the L–EIS project manager at the address provided below. Before including your address, telephone number, email address, or other personal identifying information in your comment, please be aware that your entire comment—including any personal identifying information—may be made publicly available at any time. Although requests can be made to withhold personal identifying information from public review, it may not be possible to keep this information from disclosure. The CMAGR has served as an aerial bombing and gunnery training range since the 1940s. The CMAGR currently provides more than 700 square miles (459,000 acres) of land, and overlying and adjacent special-use airspace that extends laterally for several thousands of square miles that, among other activities, supports training in air combat maneuvering and tactics; close air support (where air-to-ground ordnance is fired to directly support friendly forces engaged in ground combat); airborne laser system VerDate Mar<15>2010 16:12 Sep 23, 2010 Jkt 220001 operations; air-to-air gunnery; and airto-ground bombing, rocketry, and strafing. Artillery, demolitions, small arms, and Navy Special Warfare training are also conducted within the range. The CMAGR is a centerpiece in a much larger training complex that incorporates adjacent and nearby special use airspaces and ranges to support full-spectrum combat operations so that Marines can realistically train as they will fight. Purpose and Need: The purpose of and need for the proposed CMAGR renewal is for the DoN to retain a military aircrew training range for nearand long-term preparedness of United States tactical air forces. Extending the land withdrawal will provide for the continued effective implementation of ongoing aircrew training while maintaining the flexibility to adapt to the training needs of new technologies as they develop. The performance of air operations in combat is directly related to the quality and depth of training. The CMAGR provides a unique combination of attributes that serve this training requirement, including the favorable location and flying weather; sufficient land and airspace; diverse terrain; and developed training support facilities. The CMAGR consists of approximately 459,000 acres of desert mountain terrain in Imperial and Riverside counties, California. The land jurisdiction map of the CMAGR closely resembles a checkerboard where every other section (640 acres or 1 square mile) is managed by either the DoN or the Bureau of Land Management (BLM). The DoN owns 232,116 acres of the checkerboard, while the alternate sections of the range (226,711 acres) are made up of withdrawn lands managed by the BLM. Since the CMAGR comprises DoNowned and BLM-managed public lands, environmental stewardship for the CMAGR is implemented through the Sikes Act for DoN land and the Federal Land Policy and Management Act for BLM land. Because the management goals and procedures of these acts differ, two separate regulatory schemes are required to administer the checkerboard land jurisdiction pattern of the range. Currently, DoN has full administrative jurisdiction to manage military training and resource management on DoNowned lands within the CMAGR, and the BLM is responsible for resource management on the alternating sections of public lands withdrawn and reserved for DoN use. Preliminary Alternatives: A range of alternatives, including the no-action alternative required by NEPA, will be considered. The L–EIS will also PO 00000 Frm 00025 Fmt 4703 Sfmt 4703 58371 consider other reasonable alternatives that are identified during scoping or the preparation of the L–EIS. Four preliminary action alternatives have been identified. Alternatives 2, 3 and 4 would include restructuring the CMAGR boundaries to more closely follow certain prominent geographic features, such as aligning part of the CMAGR boundary to closely parallel but no longer cross features such as the Bradshaw Trail and Coachella Canal. 1. Alternative 1 would extend the current withdrawal with no boundary or jurisdictional changes, for a period of 25 years. 2. Alternative 2 would extend the land withdrawal for a period of 25 years with restructured boundaries and would allocate full administrative jurisdiction for resource management to DoN, in addition to the military activities. 3. Alternative 3 would extend the land withdrawal for a period of 25 years and transfer all custody and accountability for the real property within both the current withdrawal and the restructured boundaries from BLM to DoN. All responsibility for resource management and use of the lands would then reside with DoN. 4. Alternative 4 would extend the land withdrawal for a period of 25 years with the restructured boundaries; management of the military activities would remain with DoN and the resource management would remain with BLM. 5. Under Alternative 5, the No Action Alternative, the existing land withdrawal for the CMAGR, provided by the California Military Lands Withdrawal and Overflights Act of 1994, would expire. The capability to support existing and future training activities at the CMAGR that rely on these lands would cease. No alternative range is located in the operational region that has the weapons training capacity of the CMAGR. Consequently, aircrew and other training terminated at the CMAGR by the No Action Alternative would have to be relocated to ranges elsewhere in the country or curtailed. Range cleanup operations at CMAGR would be required. Environmental Issues and Resources To Be Examined: The Draft L–EIS will evaluate the potential environmental effects associated with each of the above alternatives and any additional alternatives developed during the scoping period. Issues to be addressed include, but are not limited to, biological resources, cultural resources, geology and soils, hydrology, noise, air quality, safety, hazardous materials and waste, socioeconomics and environmental justice. Relevant and E:\FR\FM\24SEN1.SGM 24SEN1 srobinson on DSKHWCL6B1PROD with NOTICES 58372 Federal Register / Vol. 75, No. 185 / Friday, September 24, 2010 / Notices reasonable measures that would avoid or mitigate environmental effects will also be analyzed. Additionally, the USMC will undertake any consultations required by the Endangered Species Act, Clean Water Act, National Historic Preservation Act, and any other applicable law or regulation. In accordance with the Engle Act of 1958, and the Federal Lands Policy and Management Act of 1976, the DoN is required to file an application with the BLM requesting the Secretary of the Interior process a proposed legislative withdrawal and reservation of public land to continue military training exercises at the CMAGR. The proposed alternatives would withdraw at least 222,041 but not more than 242,058 acres of public land. As a result of the proposed boundary restructuring, approximately 15,347 acres of public land not in the existing 226,711 acre withdrawal would be withdrawn. The restructured boundary would offer the best opportunities to define and manage a secure boundary for the CMAGR, safeguard public use of adjacent public land, and consolidate holdings for more efficient environmental stewardship. The public land would be withdrawn from all forms of appropriation under the public land laws, including surface entry, mining, mineral leasing, and the Materials Act of 1947. L–EIS Schedule: This notice is the first phase of the L–EIS process and announces the 90-day public comment period and public scoping meetings to identify community concerns and local issues that should be addressed in the L–EIS. The next phase occurs when a Notice of Availability (NOA) is published in the Federal Register and local media to publicly announce the release of the Draft L–EIS. A minimum 45-day public comment period for the Draft L–EIS will commence upon publication of the NOA in the Federal Register. The USMC will consider and respond to all comments received on the Draft L–EIS when preparing the Final L– EIS. After publication of the Draft L– EIS, one or more public hearings will be held, and public notice will be given regarding the time and place of the hearing(s). The Draft L–EIS will be available for public and agency review and comment before the public hearing(s). Dated: September 17, 2010. D.J. Werner, Lieutenant Commander, Office of the Judge Advocate General, U.S. Navy, Federal Register Liaison Officer. [FR Doc. 2010–23984 Filed 9–23–10; 8:45 am] BILLING CODE 3810–FF–P VerDate Mar<15>2010 16:12 Sep 23, 2010 Jkt 220001 DEPARTMENT OF DEFENSE Department of the Army; Corps of Engineers Notice of Intent To Prepare an Environmental Impact Statement for Skokomish General Investigation Study, Mason County, WA Department of the Army, U.S. Army Corps of Engineers, DoD. ACTION: Notice of intent. AGENCY: Pursuant to Section 102(2)(C) of the National Environmental Policy Act (NEPA) of 1969, as amended, the U.S. Army Corps of Engineers (USACE) will prepare an Integrated Feasibility Report/Environmental Impact Statement (FR/EIS) for proposed ecosystem restoration and flood risk management in the Skokomish River Basin which empties into Hood Canal, near Shelton, Washington. The Skokomish Indian Tribe and Mason County are the nonFederal sponsors for the project. The Skokomish River General Investigation (GI) Feasibility Study for the Skokomish River Basin is being conducted under the authority of Section 209 of the Flood Control Act of 1962 (Pub. L. 87–874). The Skokomish River channel has been filling with sediment for several decades, resulting in frequent flooding and decreasing natural ecosystem structures, functions, and processes necessary to support critical fish and wildlife habitat throughout the Skokomish River Basin. Increased sediment load, reduced flows, and encroachment of the floodplain by manmade structures are leading to continued degradation of natural ecosystem functions and habitat. The degraded riverine and estuarine aquatic habitat has caused a decline in the population of critical fish and wildlife species, including multiple ESA listed species. Additionally, the channel capacity of the Skokomish River varies significantly. Limited channel capacity causes floodwater to leave the banks at various locations, ultimately causing frequent flooding of local roads, two state highways, agricultural fields, residences, and other structures. The Skokomish River GI is a basinwide study; however, work by others, constrain the limit of Corps’ involvement to actions primarily in the lower Skokomish River Valley. Problems, opportunities, and objectives will be examined within the context of the entire watershed. Recognizing the relationships between the upper and lower watershed will ensure a comprehensive study overview. SUMMARY: PO 00000 Frm 00026 Fmt 4703 Sfmt 4703 The purpose of the FR/EIS and feasibility study is to evaluate if there is a federal interest in aquatic ecosystem restoration and flood risk management in the Skokomish River Basin. DATES: Submit comments by October 25, 2010 on the scope of issues to be addressed in the draft FR/EIS. ADDRESSES: Address all comments concerning this notice to Mr. Patrick Cagney, Environmental Resources Section, U.S. Army Corps of Engineers, Seattle District, P.O. Box 3755, Seattle, WA 98124–3755. Submit electronic comments and supporting data to patrick.t.cagney@usace.army.mil FOR FURTHER INFORMATION CONTACT: Questions regarding the scoping process or preparation of the draft EIS may be directed to Mr. Patrick Cagney, telephone (206) 764–3654, e-mail patrick.t.cagney@usace.army.mil SUPPLEMENTARY INFORMATION: 1. Study Area: The Skokomish River Basin (Basin) is located in northwest Washington, predominantly in Mason County. The project study area is comprised of the entire drainage basin, including the estuary at Annas Bay. The river collects drainage from an approximate 240 square mile drainage basin, and eventually flows into southern Hood Canal, an arm of Puget Sound. The river flows out of three subbasins (South Fork, North Fork, and Vance Creek) into a broad, flat alluvial plain known as the Skokomish River Valley. The Skokomish Indian Reservation is located within the lower valley and extends along the southeast portion of the Olympic Peninsula. The Basin is defined by the Water Resource Inventory Area (WRIA) 16 and is located within U.S. Congressional District #6 of Washington State. 2. Alternatives: The EIS will separately evaluate alternatives for aquatic ecosystem restoration and flood risk management. Alternatives that will be evaluated under aquatic ecosystem restoration will include an alternative that uses physical actions to restore the Basin’s habitat-forming processes and/or create habitats that have been lost as a result of historic alterations. Example of actions that could occur under this alternative include: increasing floodplain habitat and connectivity, restoring off-channel habitat for juvenile fish, improving estuarine functions and processes, and increasing emergent and riparian vegetation. Another alternative that will be considered will focus on benefits to the several aquatic species listed under the Endangered Species Act. Actions under this alternative could include creation of spawning and E:\FR\FM\24SEN1.SGM 24SEN1

Agencies

[Federal Register Volume 75, Number 185 (Friday, September 24, 2010)]
[Notices]
[Pages 58370-58372]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-23984]


-----------------------------------------------------------------------

DEPARTMENT OF DEFENSE

Department of the Navy


Notice of Intent To Prepare a Legislative Environmental Impact 
Statement for the Proposed Extension of the Chocolate Mountain Aerial 
Gunnery Range Land Withdrawal

    Lead Agency: Department of the Navy, DoD.
    Cooperating Agency: Bureau of Land Management, Department of the 
Interior.

ACTION: Notice.

-----------------------------------------------------------------------

SUMMARY: Pursuant to Section 102(2)(c) of the National Environmental 
Policy Act (NEPA) of 1969 and regulations implemented by the Council on 
Environmental Quality (40 Code of Federal Regulations [CFR] Parts 1500-
1508), the Department of the Navy (DoN) and the United States Marine 
Corps (USMC), with the cooperation of the Bureau of Land Management 
(BLM), intends to prepare a Legislative Environmental Impact Statement 
(L-EIS) and conduct public scoping meetings for the proposed extension 
of the withdrawal of approximately 226,711 acres of public land in 
Imperial and Riverside counties, California, for continued military use 
of the Chocolate Mountain Aerial Gunnery Range (CMAGR).
    The California Military Lands Withdrawal and Overflights Act of 
1994 (Pub. L. 103-433) withdrew 226,711 acres of public land to DoN, 
reserving these lands for defense-related purposes for a period of 20 
years (until October 31, 2014). The Act provides that the DoN may seek 
extension of the CMAGR withdrawal. As part of the withdrawal process, 
the Secretary of the Navy is required to publish a Draft L-EIS 
addressing legislative alternatives and the effects of continued 
withdrawal. The CMAGR Draft L-EIS will evaluate the environmental 
effects of the proposal to extend the land withdrawal for an additional 
25 years (through 2039) and will evaluate alternative actions to 
restructure the existing range boundary for improved efficiency in the 
management of the CMAGR and adjacent lands.

DATES AND ADDRESSES: DoN is initiating a 90-day public scoping process 
to identify community interests and specific issues to be addressed in 
the L-EIS, which starts with the publication of this Notice of Intent 
(NOI). Four public scoping meetings have been scheduled to enlist 
written and oral comments regarding the scope of the Draft L-EIS 
analysis:
    1. Monday, December 6, 2010, 5:30 p.m. to 8 p.m., Yuma County 
Library, Rooms B-C, 2951 S. 21st Drive, Yuma, Arizona 85364;
    2. Tuesday, December 7, 2010, 5:30 p.m. to 8 p.m., Holiday Inn 
Express--El Centro, Conference Room B, 350 Smoketree Drive, El Centro, 
California 92243;
    3. Wednesday, December 8, 2010, 5:30 p.m. to 8 p.m., Holiday Inn, 
1800 E. Palm Canyon, Palm Springs, California 92264; and
    4. Thursday, December 9, 2010, 5:30 p.m. to 8 p.m., San Diego 
Planning Commission Hearing Room, 5201 Ruffin Road, Suite B, San Diego, 
California 92123.

FOR FURTHER INFORMATION CONTACT: CMAGR L-EIS Project Manager (Attn: 
Kelly Finn), NAVFAC Southwest, 1220 Pacific Highway, San Diego, CA 
92132-5190; phone 619-532-4452. Additional supplementary information 
regarding the CMAGR Draft L-EIS is available at https://www.chocolatemountainrenewal.com. Please submit requests for special 
assistance, sign language interpretation for the hearing impaired, or 
other auxiliary aids needed at the scoping meeting to the L-EIS Project 
Manager by November 26, 2010.

SUPPLEMENTARY INFORMATION: Public scoping meeting schedules and 
locations will also be published in local newspapers. The public is 
invited to attend these meetings to view project-related displays, 
speak with DoN and USMC representatives, and submit public comment 
forms at information stations. A court reporter will be available at 
the meetings to accept oral comments. The scoping meetings will be 
conducted in an informal, open

[[Page 58371]]

house style meeting format. All comments regarding the scope of issues 
that should be considered in the Draft L-EIS must be received within 90 
days of the publication date of this notice to ensure full 
consideration in the Draft L-EIS analysis.
    Submitting Comments: Federal, state, and local agencies and 
interested parties are encouraged to provide oral and/or written 
comments regarding the scope of the L-EIS, reasonable alternatives and/
or specific issues or topics of interest to the public. Comments may be 
submitted by: (1) Attending one of the public scoping open houses and 
providing oral or written comments, (2) submitting a comment form on 
the project's public website at https://www.chocolatemountainrenewal.com, or (3) mail. Written comments should 
be submitted to the L-EIS Project Manager listed below under FOR 
FURTHER INFORMATION CONTACT. All written comments on the scope of the 
L-EIS should be submitted and/or postmarked no later than December 23, 
2010.
    The USMC will consider all comments received during the scoping 
period. A mailing list has been assembled to facilitate preparation of 
the L-EIS. Those on this list will receive notices and information 
related to L-EIS preparation. This list includes local, state, and 
federal agencies with jurisdiction or other interests in the 
alternatives. In addition, the mailing list includes affected 
municipalities and other interested parties. Anyone wishing to be added 
to the mailing list may request to be added by contacting the L-EIS 
project manager at the address provided below.
    Before including your address, telephone number, email address, or 
other personal identifying information in your comment, please be aware 
that your entire comment--including any personal identifying 
information--may be made publicly available at any time. Although 
requests can be made to withhold personal identifying information from 
public review, it may not be possible to keep this information from 
disclosure.
    The CMAGR has served as an aerial bombing and gunnery training 
range since the 1940s. The CMAGR currently provides more than 700 
square miles (459,000 acres) of land, and overlying and adjacent 
special-use airspace that extends laterally for several thousands of 
square miles that, among other activities, supports training in air 
combat maneuvering and tactics; close air support (where air-to-ground 
ordnance is fired to directly support friendly forces engaged in ground 
combat); airborne laser system operations; air-to-air gunnery; and air-
to-ground bombing, rocketry, and strafing. Artillery, demolitions, 
small arms, and Navy Special Warfare training are also conducted within 
the range. The CMAGR is a centerpiece in a much larger training complex 
that incorporates adjacent and nearby special use airspaces and ranges 
to support full-spectrum combat operations so that Marines can 
realistically train as they will fight.
    Purpose and Need: The purpose of and need for the proposed CMAGR 
renewal is for the DoN to retain a military aircrew training range for 
near- and long-term preparedness of United States tactical air forces. 
Extending the land withdrawal will provide for the continued effective 
implementation of ongoing aircrew training while maintaining the 
flexibility to adapt to the training needs of new technologies as they 
develop. The performance of air operations in combat is directly 
related to the quality and depth of training. The CMAGR provides a 
unique combination of attributes that serve this training requirement, 
including the favorable location and flying weather; sufficient land 
and airspace; diverse terrain; and developed training support 
facilities.
    The CMAGR consists of approximately 459,000 acres of desert 
mountain terrain in Imperial and Riverside counties, California. The 
land jurisdiction map of the CMAGR closely resembles a checkerboard 
where every other section (640 acres or 1 square mile) is managed by 
either the DoN or the Bureau of Land Management (BLM). The DoN owns 
232,116 acres of the checkerboard, while the alternate sections of the 
range (226,711 acres) are made up of withdrawn lands managed by the 
BLM.
    Since the CMAGR comprises DoN-owned and BLM-managed public lands, 
environmental stewardship for the CMAGR is implemented through the 
Sikes Act for DoN land and the Federal Land Policy and Management Act 
for BLM land. Because the management goals and procedures of these acts 
differ, two separate regulatory schemes are required to administer the 
checkerboard land jurisdiction pattern of the range. Currently, DoN has 
full administrative jurisdiction to manage military training and 
resource management on DoN-owned lands within the CMAGR, and the BLM is 
responsible for resource management on the alternating sections of 
public lands withdrawn and reserved for DoN use.
    Preliminary Alternatives: A range of alternatives, including the 
no-action alternative required by NEPA, will be considered. The L-EIS 
will also consider other reasonable alternatives that are identified 
during scoping or the preparation of the L-EIS. Four preliminary action 
alternatives have been identified. Alternatives 2, 3 and 4 would 
include restructuring the CMAGR boundaries to more closely follow 
certain prominent geographic features, such as aligning part of the 
CMAGR boundary to closely parallel but no longer cross features such as 
the Bradshaw Trail and Coachella Canal.
    1. Alternative 1 would extend the current withdrawal with no 
boundary or jurisdictional changes, for a period of 25 years.
    2. Alternative 2 would extend the land withdrawal for a period of 
25 years with restructured boundaries and would allocate full 
administrative jurisdiction for resource management to DoN, in addition 
to the military activities.
    3. Alternative 3 would extend the land withdrawal for a period of 
25 years and transfer all custody and accountability for the real 
property within both the current withdrawal and the restructured 
boundaries from BLM to DoN. All responsibility for resource management 
and use of the lands would then reside with DoN.
    4. Alternative 4 would extend the land withdrawal for a period of 
25 years with the restructured boundaries; management of the military 
activities would remain with DoN and the resource management would 
remain with BLM.
    5. Under Alternative 5, the No Action Alternative, the existing 
land withdrawal for the CMAGR, provided by the California Military 
Lands Withdrawal and Overflights Act of 1994, would expire. The 
capability to support existing and future training activities at the 
CMAGR that rely on these lands would cease. No alternative range is 
located in the operational region that has the weapons training 
capacity of the CMAGR. Consequently, aircrew and other training 
terminated at the CMAGR by the No Action Alternative would have to be 
relocated to ranges elsewhere in the country or curtailed. Range clean-
up operations at CMAGR would be required.
    Environmental Issues and Resources To Be Examined: The Draft L-EIS 
will evaluate the potential environmental effects associated with each 
of the above alternatives and any additional alternatives developed 
during the scoping period. Issues to be addressed include, but are not 
limited to, biological resources, cultural resources, geology and 
soils, hydrology, noise, air quality, safety, hazardous materials and 
waste, socioeconomics and environmental justice. Relevant and

[[Page 58372]]

reasonable measures that would avoid or mitigate environmental effects 
will also be analyzed. Additionally, the USMC will undertake any 
consultations required by the Endangered Species Act, Clean Water Act, 
National Historic Preservation Act, and any other applicable law or 
regulation.
    In accordance with the Engle Act of 1958, and the Federal Lands 
Policy and Management Act of 1976, the DoN is required to file an 
application with the BLM requesting the Secretary of the Interior 
process a proposed legislative withdrawal and reservation of public 
land to continue military training exercises at the CMAGR. The proposed 
alternatives would withdraw at least 222,041 but not more than 242,058 
acres of public land. As a result of the proposed boundary 
restructuring, approximately 15,347 acres of public land not in the 
existing 226,711 acre withdrawal would be withdrawn. The restructured 
boundary would offer the best opportunities to define and manage a 
secure boundary for the CMAGR, safeguard public use of adjacent public 
land, and consolidate holdings for more efficient environmental 
stewardship. The public land would be withdrawn from all forms of 
appropriation under the public land laws, including surface entry, 
mining, mineral leasing, and the Materials Act of 1947.
    L-EIS Schedule: This notice is the first phase of the L-EIS process 
and announces the 90-day public comment period and public scoping 
meetings to identify community concerns and local issues that should be 
addressed in the L-EIS. The next phase occurs when a Notice of 
Availability (NOA) is published in the Federal Register and local media 
to publicly announce the release of the Draft L-EIS. A minimum 45-day 
public comment period for the Draft L-EIS will commence upon 
publication of the NOA in the Federal Register. The USMC will consider 
and respond to all comments received on the Draft L-EIS when preparing 
the Final L-EIS. After publication of the Draft L-EIS, one or more 
public hearings will be held, and public notice will be given regarding 
the time and place of the hearing(s). The Draft L-EIS will be available 
for public and agency review and comment before the public hearing(s).

    Dated: September 17, 2010.
D.J. Werner,
Lieutenant Commander, Office of the Judge Advocate General, U.S. Navy, 
Federal Register Liaison Officer.
[FR Doc. 2010-23984 Filed 9-23-10; 8:45 am]
BILLING CODE 3810-FF-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.