Gresham Municipal Utilities provided
public notice of its request on July 6,
2010. In a letter issued on August 23,
2010, Ms. Ann F. Miles, the Director of
the Division of Hydropower Licensing,
approved Gresham Municipal Utilities
request to use the Traditional Licensing
Process.
k. With this notice, we are initiating
informal consultation with: (a) The U.S.
Fish and Wildlife under section 7 of the
Endangered Species Act and the joint
agency regulations thereunder at 50
CFR, part 402; and (b) the Wisconsin
State Historic Preservation Officer, as
required by section 106, National
Historical Preservation Act, and the
implementing regulations of the
Advisory Council on Historic
Preservation at 36 CFR 800.2.
l. Gresham Municipal Utilities filed a
Pre-Application Document (PAD;
including a proposed process plan and
schedule) with the Commission,
pursuant to 18 CFR 5.6 of the
Commission’s regulations.
m. A copy of the PAD is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site (https://
www.ferc.gov), using the ‘‘eLibrary’’ link.
Enter the docket number, excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at
FERCONlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in paragraph h.
n. The licensee states its unequivocal
intent to submit an application for a
new license for Project No. 2464.
Pursuant to 18 CFR 16.8, 16.9, and 16.10
each application for a new license and
any competing license applications
must be filed with the Commission at
least 24 months prior to the expiration
of the existing license. All applications
for license for this project must be filed
by June 30, 2013.
o. Register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filing and issuances related
to this or other pending projects. For
assistance, contact FERC Online
Support.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–21794 Filed 8–31–10; 8:45 am]
BILLING CODE 6717–01–P
VerDate Mar<15>2010
18:24 Aug 31, 2010
Jkt 220001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EL10–82–000]
Southern Montana Electric Generation
& Transmission Cooperative, Inc. v.
NorthWestern Corporation; Notice of
Complaint
August 25, 2010.
Take notice that on August 20, 2010,
pursuant to section 206 of the Federal
Power Act, 16 U.S.C. 824c, and Rule 206
of the Federal Energy Regulatory
Commission’s (Commission) Rules of
Practice and Procedure, 18 CFR 385.206,
Southern Montana Electric Generation &
Transmission Cooperative, Inc.
(Complainant) filed a complaint against
NorthWestern Corporation
(Respondent), alleging that the
Respondent violated Commission
policies and its Open Access
Transmission Tariff by (1) using an
‘‘umbrella’’ or ‘‘enabling’’ agreement as
the contractual basis for a long-term
point-to-point transmission service and
(2) billing the Complainant with respect
to a transmission service for which they
had not contracted.
Complainant certifies that copies of
the complaint were served on the
contacts listed for Respondent as listed
on the Commission’s list of Corporate
Officials.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. The Respondent’s answer
and all interventions, or protests must
be filed on or before the comment date.
The Respondent’s answer, motions to
intervene, and protests must be served
on the Complainants.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible online at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
PO 00000
Frm 00058
Fmt 4703
Sfmt 4703
53687
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on September 9, 2010.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–21790 Filed 8–31–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2106–059]
Pacific Gas and Electric Company,
California; Notice Correcting Times for
Public Draft Environmental Impact
Statement Meetings
August 25, 2010.
As stated in the July 30, 2010 Notice
of Availability for the McCloud-Pit
Hydroelectric Project draft
Environmental Impact Statement (EIS),
Commission staff will be conducting
two public meetings to receive
comments on the draft EIS. The July 30,
2010 notice, however, incorrectly listed
the time for the morning meeting as 9
a.m.–11 p.m.. This notice corrects that
error to indicate the meeting is from 9
a.m.–11 a.m.
The time and location of the meetings
are as follows:
Morning Meeting:
Date: September 9, 2010.
Time: 9 a.m.–11 a.m.
Place: Holiday Inn Hotel,
Address: 1900 Hilltop Dr.,
Redding, CA.
Evening Meeting:
Date: September 9, 2010.
Time: 7 p.m.–9 p.m.
Place: Holiday Inn Hotel,
Address: 1900 Hilltop Dr.,
Redding, CA.
At these meetings, resource agency
personnel and other interested persons
will have the opportunity to provide
oral and written comments and
recommendations regarding the draft
EIS. The meetings will be recorded by
a court reporter, and all statements
(verbal and written) will become part of
the Commission’s public record for the
project. This meeting is posted on the
Commission’s calendar located at
https://www.ferc.gov/EventCalendar/
E:\FR\FM\01SEN1.SGM
01SEN1
53688
Federal Register / Vol. 75, No. 169 / Wednesday, September 1, 2010 / Notices
EventsList.aspx along with other related
information.
Whether or not you attend one of
these meetings, you are invited to
submit written comments on the draft
EIS. Comments should be filed with
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
All comments must be filed by
September 28, 2010, and should
reference Project No. 2106–059.
Comments may be filed electronically
via the Internet in lieu of paper. The
Commission strongly encourages
electronic filings. See 18 CFR
385.2001(a)(1)(iii) and instructions on
the Commission’s Web site at https://
www.ferc.gov under the ‘‘e-Library’’ link.
The Commission staff will consider
comments made on the draft EIS in
preparing a final EIS for the project.
Before the Commission makes a
licensing decision, it will take into
account all concerns relevant to the
public interest. The final EIS will be
part of the record from which the
Commission will make its decision.
For further information, please
contact Emily Carter at (202) 502–6512.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–21792 Filed 8–31–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER10–2281–000]
Constellation Mystic Power, LLC;
Supplemental Notice That Initial
Market-Based Rate Filing Includes
Request for Blanket Section 204
Authorization
intervene or protest must serve a copy
of that document on the Applicant.
Notice is hereby given that the
deadline for filing protests with regard
to the applicant’s request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability, is September
14, 2010.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 14 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
The filings in the above-referenced
proceeding are accessible in the
Commission’s eLibrary system by
clicking on the appropriate link in the
above list. They are also available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an eSubscription link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–21791 Filed 8–31–10; 8:45 am]
BILLING CODE 6717–01–P
hsrobinson on DSK69SOYB1PROD with NOTICES
August 25, 2010.
This is a supplemental notice in the
above-referenced proceeding of
Constellation Mystic Power, LLC’s
application for market-based rate
authority, with an accompanying rate
tariff, noting that such application
includes a request for blanket
authorization, under 18 CFR part 34, of
future issuances of securities and
assumptions of liability.
Any person desiring to intervene or to
protest should file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
in accordance with Rules 211 and 214
of the Commission’s Rules of Practice
and Procedure (18 CFR 385.211 and
385.214). Anyone filing a motion to
VerDate Mar<15>2010
18:24 Aug 31, 2010
Jkt 220001
DEPARTMENT OF ENERGY
On June 7, 2010, Southern LNG
Company, L.L.C. (Southern LNG) filed a
tariff sheet to revise its tariff with
respect to gas quality and
interchangeability. On July 28, 2010, the
Commission accepted and suspended
Southern LNG’s proposed tariff sheet, to
become effective January 1, 2011, or an
earlier date set by subsequent
Commission order, subject to conditions
and the outcome of a technical
conference.1 During the technical
conference, Commission Staff and
interested persons will have the
opportunity to discuss all of the issues
raised by Southern LNG’s filing.
Southern LNG should be prepared to
address all concerns raised by South
Carolina Electric & Gas Company in its
protest to the filing, and to provide
additional technical, engineering, and
operational support for its proposed gas
quality and interchangeability
standards. Consistent with the
Commission’s policy statement on gas
quality issues, Southern LNG should
also be prepared to explain how its
proposal conforms with or differs from
the Interim Guidelines and principles.
See Natural Gas Interchangeability,
Policy Statement on Provisions
Governing Natural Gas Quality and
Interchangeability in Interstate Natural
Gas Pipeline Company Tariffs, 115
FERC ¶ 61,325 at P 34, 37 (2006).
FERC conferences are accessible
under section 508 of the Rehabilitation
Act of 1973. For accessibility
accommodations please send an e-mail
to accessibility@ferc.gov or call toll free
(866) 208–3372 (voice) or (202) 502–
8659 (TTY), or send a fax to (202) 208–
2106 with the required
accommodations.
All interested persons are permitted
to attend. For further information please
contact Jennifer Kunz at (202) 502–6102
or e-mail Jennifer.Kunz@ferc.gov.
Kimberly D. Bose,
Secretary.
Federal Energy Regulatory
Commission
[FR Doc. 2010–21793 Filed 8–31–10; 8:45 am]
[Docket No. RP10–829–000]
BILLING CODE 6717–01–P
Southern LNG Company, L.L.C.; Notice
of Technical Conference
August 25, 2010.
Take notice that Commission Staff
will convene a technical conference in
the above-referenced proceeding on
Tuesday, September 14, 2010, at 9 a.m.
(EST), in a room to be designated at the
offices of the Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426.
PO 00000
Frm 00059
Fmt 4703
Sfmt 9990
1 132
E:\FR\FM\01SEN1.SGM
FERC ¶ 61,076 (2010).
01SEN1
Agencies
[Federal Register Volume 75, Number 169 (Wednesday, September 1, 2010)]
[Notices]
[Pages 53687-53688]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-21792]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2106-059]
Pacific Gas and Electric Company, California; Notice Correcting
Times for Public Draft Environmental Impact Statement Meetings
August 25, 2010.
As stated in the July 30, 2010 Notice of Availability for the
McCloud-Pit Hydroelectric Project draft Environmental Impact Statement
(EIS), Commission staff will be conducting two public meetings to
receive comments on the draft EIS. The July 30, 2010 notice, however,
incorrectly listed the time for the morning meeting as 9 a.m.-11 p.m..
This notice corrects that error to indicate the meeting is from 9 a.m.-
11 a.m.
The time and location of the meetings are as follows:
Morning Meeting:
Date: September 9, 2010.
Time: 9 a.m.-11 a.m.
Place: Holiday Inn Hotel,
Address: 1900 Hilltop Dr., Redding, CA.
Evening Meeting:
Date: September 9, 2010.
Time: 7 p.m.-9 p.m.
Place: Holiday Inn Hotel,
Address: 1900 Hilltop Dr., Redding, CA.
At these meetings, resource agency personnel and other interested
persons will have the opportunity to provide oral and written comments
and recommendations regarding the draft EIS. The meetings will be
recorded by a court reporter, and all statements (verbal and written)
will become part of the Commission's public record for the project.
This meeting is posted on the Commission's calendar located at https://
www.ferc.gov/EventCalendar/
[[Page 53688]]
EventsList.aspx along with other related information.
Whether or not you attend one of these meetings, you are invited to
submit written comments on the draft EIS. Comments should be filed with
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426. All comments must be filed by
September 28, 2010, and should reference Project No. 2106-059. Comments
may be filed electronically via the Internet in lieu of paper. The
Commission strongly encourages electronic filings. See 18 CFR
385.2001(a)(1)(iii) and instructions on the Commission's Web site at
https://www.ferc.gov under the ``e-Library'' link.
The Commission staff will consider comments made on the draft EIS
in preparing a final EIS for the project. Before the Commission makes a
licensing decision, it will take into account all concerns relevant to
the public interest. The final EIS will be part of the record from
which the Commission will make its decision.
For further information, please contact Emily Carter at (202) 502-
6512.
Kimberly D. Bose,
Secretary.