Transcontinental Gas Pipe Line Company, LLC; Notice of Intent To Prepare an Environmental Assessment for the Planned Mid-South Expansion Project and Request for Comments on Environmental Issues, 51455-51457 [2010-20652]
Download as PDF
sroberts on DSKD5P82C1PROD with NOTICES
Federal Register / Vol. 75, No. 161 / Friday, August 20, 2010 / Notices
to filings initiating a new proceeding,
interventions or protests submitted on
or before the comment deadline need
not be served on persons other than the
Applicant.
As it relates to any qualifying facility
filings, the notices of self-certification
[or self-recertification] listed above, do
not institute a proceeding regarding
qualifying facility status. A notice of
self-certification [or self-recertification]
simply provides notification that the
entity making the filing has determined
the facility named in the notice meets
the applicable criteria to be a qualifying
facility. Intervention and/or protest do
not lie in dockets that are qualifying
facility self-certifications or selfrecertifications. Any person seeking to
challenge such qualifying facility status
may do so by filing a motion pursuant
to 18 CFR 292.207(d)(iii). Intervention
and protests may be filed in response to
notices of qualifying facility dockets
other than self-certifications and selfrecertifications.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 14 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First St., NE., Washington, DC
20426.
The filings in the above proceedings
are accessible in the Commission’s
eLibrary system by clicking on the
appropriate link in the above list. They
are also available for review in the
Commission’s Public Reference Room in
Washington, DC. There is an
eSubscription link on the Web site that
enables subscribers to receive e-mail
notification when a document is added
to a subscribed dockets(s). For
assistance with any FERC Online
service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2010–20650 Filed 8–19–10; 8:45 am]
BILLING CODE 6717–01–P
VerDate Mar<15>2010
17:19 Aug 19, 2010
Jkt 220001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. PF10–13–000]
Transcontinental Gas Pipe Line
Company, LLC; Notice of Intent To
Prepare an Environmental Assessment
for the Planned Mid-South Expansion
Project and Request for Comments on
Environmental Issues
August 13, 2010.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Mid-South Expansion Project
(MSEP) involving construction and
operation of facilities by
Transcontinental Gas Pipe Line
Company, LLC (Transco) in Coosa,
Randolph, Dallas, and Marengo
Counties, Alabama; Gaston, Rowan,
Davidson, and Cleveland Counties,
North Carolina; Walton, Coweta, and
Henry Counties, Georgia; and
Spartanburg County, South Carolina.
This EA will be used by the
Commission in its decision-making
process to determine whether the
project is in the public convenience and
necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
Your input will help the Commission
staff determine what issues need to be
evaluated in the EA. Please note that the
scoping period will close on September
13, 2010.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives are
asked to notify their constituents of this
planned project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, you may be contacted by a
pipeline company representative about
the acquisition of an easement to
construct, operate, and maintain the
planned facilities. The company would
seek to negotiate a mutually acceptable
agreement. However, if the project is
approved by the Commission, that
approval conveys with it the right of
eminent domain. Therefore, if easement
negotiations fail to produce an
agreement, the pipeline company could
initiate condemnation proceedings
where compensation would be
determined in accordance with state
law.
PO 00000
Frm 00019
Fmt 4703
Sfmt 4703
51455
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ is available for viewing on
the FERC Web site (https://
www.ferc.gov). This fact sheet addresses
a number of typically-asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings.
Summary of the Planned Project
Transco is proposing to construct and
operate five new pipeline loops,1
construct one new compressor station,
add compression at two existing
compressor stations, and perform other
modifications to five compressor
stations. The MSEP would provide
about 451 million standard cubic feet of
natural gas per day to Transco’s existing
mainline system from the Clean Energy
LNG import terminal currently under
construction in Pascagoula, Mississippi,
with existing capacity on Transco’s
Mobile Bay Lateral, down to existing
Compressor Station 85. According to
Transco, its project would expand
delivery capacity on its existing
pipeline system to growing markets in
the east as far downstream as
Rockingham County, North Carolina.
The MSEP would consist of the
following facilities:
• Five pipeline loops located in Coosa
and Randolph Counties, Alabama,
and Gaston, Rowan and Davidson
Counties, North Carolina;
• One new compressor station, Station
95, to be located in Dallas County,
Alabama;
• Additional new compression at two
existing compressor stations:
Æ Station 90 in Marengo County,
Alabama; and
Æ Station 125 in Walton County,
Georgia;
• Modifications at the following
existing compressor stations:
Æ Station 105 in Coosa County,
Alabama;
Æ Station 115 in Coweta County,
Georgia;
Æ Station 120 in Henry County,
Georgia;
Æ Station 140 in Spartanburg County,
South Carolina; and
Æ Station 145 in Cleveland County,
North Carolina.
The planned loops would be
constructed with 42-inch-diameter steel
pipe and would have a combined total
length of about 22.6 miles.
1 A pipeline loop is constructed parallel to an
existing pipeline to increase capacity.
E:\FR\FM\20AUN1.SGM
20AUN1
51456
Federal Register / Vol. 75, No. 161 / Friday, August 20, 2010 / Notices
The general location of the project
facilities is shown in appendix 1.2
Land Requirements for Construction
Construction of the planned facilities
would disturb approximately 287.9
acres of land for the aboveground
facilities and the pipeline. Following
construction, approximately 144.6 acres
would be maintained for permanent
operation of the project’s facilities; the
remaining acreage would be restored
and allowed to revert to former uses.
The entire planned pipeline route either
parallels or would be located within
existing pipeline, utility, or road rightsof-way.
The EA Process
sroberts on DSKD5P82C1PROD with NOTICES
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us 3 to
discover and address concerns the
public may have about proposals. This
process is referred to as scoping. The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
notice, the Commission requests public
comments on the scope of the issues to
address in the EA. All comments
received will be considered during the
preparation of the EA.
In the EA we will discuss impacts that
could occur as a result of the
construction and operation of the
planned project under these general
headings:
• Geology and soils;
• land use;
• water resources, fisheries, and
wetlands;
• cultural resources;
• vegetation and wildlife;
• air quality and noise;
• endangered and threatened species;
and
• public safety.
We will also evaluate possible
alternatives to the planned project or
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
2 The appendices referenced in this notice are not
being printed in the Federal Register. Copies of
appendices were sent to all those receiving this
notice in the mail and are available at https://
www.ferc.gov using the link called ‘‘eLibrary’’ or
from the Commission’s Public Reference Room, 888
First Street NE., Washington, DC 20426, or call
(202) 502–8371. For instructions on connecting to
eLibrary, refer to the last page of this notice.
3 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the environmental
staff of the Commission’s Office of Energy Projects.
VerDate Mar<15>2010
17:19 Aug 19, 2010
Jkt 220001
Although no formal application has
been filed, we have already initiated our
NEPA review under the Commission’s
pre-filing process. The purpose of the
pre-filing process is to encourage early
involvement of interested stakeholders
and to identify and resolve issues before
an application is filed with the FERC.
As part of our pre-filing review, we have
begun to contact some Federal and State
agencies to discuss their involvement in
the scoping process and the preparation
of the EA.
Our independent analysis of the
issues will be presented in the EA. The
EA will be placed in the public record
and, depending on the comments
received during the scoping process,
may be published and distributed to the
public. A comment period will be
allotted if the EA is published for
review. We will consider all comments
on the EA before we make our
recommendations to the Commission.
To ensure your comments are
considered, please carefully follow the
instructions in the Public Participation
section beginning on page 5.
With this notice, we are asking
agencies with jurisdiction and/or
special expertise with respect to
environmental issues to formally
cooperate with us in the preparation of
the EA. These agencies may choose to
participate once they have evaluated the
proposal relative to their
responsibilities. Agencies that would
like to request cooperating agency status
should follow the instructions for filing
comments provided under the Public
Participation section of this notice.
Consultations Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations for section
106 of the National Historic
Preservation Act, we are using this
notice to initiate consultation with
applicable State Historic Preservation
Office(s), and to solicit their views and
those of other government agencies,
interested Indian tribes, and the public
on the project’s potential effects on
historic properties.4 We will define the
project-specific Area of Potential Effects
(APE) in consultation with the SHPO(s)
as the project is further developed. On
natural gas facility projects, the APE at
a minimum encompasses all areas
subject to ground disturbance (examples
4 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Historic properties are
defined in those regulations as any prehistoric or
historic district, site, building, structure, or object
included in or eligible for inclusion in the National
Register for Historic Places.
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
include construction right-of-way,
contractor/pipe storage yards,
compressor stations, and access roads).
Our EA for this project will document
our findings on the impacts on historic
properties and summarize the status of
consultations under section 106.
Currently Identified Environmental
Issues
We have already identified several
issues that we think deserve attention
based on a preliminary review of the
planned facilities and the
environmental information provided by
Transco. This preliminary list of issues
may be changed based on your
comments and our analysis.
• Cultural resources;
• Water resources, fisheries, and
wetlands; and
• Threatened and endangered species.
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the project.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
The more specific your comments, the
more useful they will be. To ensure that
your comments are timely and properly
recorded, please send your comments so
that they will be received in
Washington, DC on or before September
13, 2010.
For your convenience, there are three
methods you can use to submit your
comments to the Commission. In all
instances, please reference the project
docket number (PF10–13–000) with
your submission. The Commission
encourages electronic filing of
comments and has expert eFiling staff
available to assist you at (202) 502–8258
or efiling@ferc.gov.
(1) You may file your comments
electronically by using the eComment
feature, which is located on the
Commission’s Web site at https://
www.ferc.gov under the link to
Documents and Filings. An eComment
is an easy method for interested persons
to submit brief, text-only comments on
a project;
(2) You may file your comments
electronically by using the eFiling
feature, which is located on the
Commission’s Web site at https://
www.ferc.gov under the link to
Documents and Filings. With eFiling
you can provide comments in a variety
of formats by attaching them as a file
with your submission. New eFiling
users must first create an account by
clicking on ‘‘eRegister.’’ You will be
asked to select the type of filing you are
E:\FR\FM\20AUN1.SGM
20AUN1
Federal Register / Vol. 75, No. 161 / Friday, August 20, 2010 / Notices
making. A comment on a particular
project is considered a ‘‘Comment on a
Filing’’; or
(3) You may file a paper copy of your
comments at the following address:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street, NE., Room 1A, Washington,
DC 20426.
sroberts on DSKD5P82C1PROD with NOTICES
Environmental Mailing List
The environmental mailing list
includes Federal, State, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project. We will
update the environmental mailing list as
the analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the planned project.
If the EA is published for distribution,
copies will be sent to the environmental
mailing list for public review and
comment. If you would prefer to receive
a paper copy of the document instead
of the CD version or would like to
remove your name from the mailing
list, please return the attached
Information Request (appendix 2).
Becoming an Intervenor
Once Transco files its application
with the Commission, you may want to
become an ‘‘intervenor’’ which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in
the proceeding by filing a request to
intervene. Instructions for becoming an
intervenor are included in the User’s
Guide under the ‘‘e-filing’’ link on the
Commission’s Web site. Please note that
the Commission will not accept requests
for intervenor status at this time. You
must wait until a formal application for
the project is filed with the
Commission.
Additional Information
Additional information about the
project is available from the
VerDate Mar<15>2010
17:19 Aug 19, 2010
Jkt 220001
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site (https://www.ferc.gov) using the
eLibrary link. Click on the eLibrary link,
click on ‘‘General Search’’ and enter the
docket number, excluding the last three
digits in the Docket Number field (i.e.,
PF10–13). Be sure you have selected an
appropriate date range. For assistance,
please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free
at (866) 208–3676, or for TTY, contact
(202) 502–8659. The eLibrary link also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to https://www.ferc.gov/
esubscribenow.htm.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at https://www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–20652 Filed 8–19–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. AC10–146–000]
Delaware Pipeline Company LLC;
Notice of Filing
August 13, 2010.
Take notice that on July 13, 2010,
Delaware Pipeline Company LLC (DPC)
submitted a request for waiver of the
requirement to file the FERC Form No.
6–Q for the second quarter of 2010.
On June 1, 2010, DPC acquired oil
pipeline assets associated with an idled
refinery in Delaware City, Delaware
from The Premcor Refining Group, Inc.,
a subsidiary of Valero Energy
Corporation. For the thirty days in June
2010 during which the pipeline was
under DPC’s ownership, the pipeline
was not in operation and DPC had no
revenue. The pipeline is currently in
standby mode while the refinery, which
is the origin for products shipped on the
pipeline, is shutdown for a complete
turnaround until early next year, and
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
51457
the pipeline also undergoes checks of
certain operational systems.
On July 1, 2010, Delaware Pipeline
Company adopted the tariffs of The
Premcor Pipeline Co. (‘‘Premcor’’)
including FERC Nos. 2.0, 3.0 and 4.0 in
their entirety. FERC Nos. 2.0.0, 3.0.0,
and 4.0.0 implement a change in
ownership effective June 1, 2010 of the
pipeline facilities used to perform the
services stated in the Premcor tariffs
that are being adopted and brought
forward under DPC’s name. DPC is
adopting these tariffs to reflect its
purchase of the Premcor pipeline
system associated with the Delaware
City Refinery, located in New Castle
County, Delaware, which originates at
the Delaware City Refinery and extends
to Sunoco Pipeline L.P.’s Twin Oaks
Pump Station, located in Delaware
County, Pennsylvania.
Since DPC had no operations during
the 30-day period in June, it requests
waiver of the quarter 2 6–Q reporting
requirement of 18 CFR 357.4.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211 or 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. On or before the
comment date, it is not necessary to
serve motions to intervene or protests
on persons other than the Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
E:\FR\FM\20AUN1.SGM
20AUN1
Agencies
[Federal Register Volume 75, Number 161 (Friday, August 20, 2010)]
[Notices]
[Pages 51455-51457]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-20652]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. PF10-13-000]
Transcontinental Gas Pipe Line Company, LLC; Notice of Intent To
Prepare an Environmental Assessment for the Planned Mid-South Expansion
Project and Request for Comments on Environmental Issues
August 13, 2010.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Mid-South Expansion Project
(MSEP) involving construction and operation of facilities by
Transcontinental Gas Pipe Line Company, LLC (Transco) in Coosa,
Randolph, Dallas, and Marengo Counties, Alabama; Gaston, Rowan,
Davidson, and Cleveland Counties, North Carolina; Walton, Coweta, and
Henry Counties, Georgia; and Spartanburg County, South Carolina. This
EA will be used by the Commission in its decision-making process to
determine whether the project is in the public convenience and
necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the project. Your input will help the Commission staff
determine what issues need to be evaluated in the EA. Please note that
the scoping period will close on September 13, 2010.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives are asked to notify their constituents of this planned
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, you may be contacted
by a pipeline company representative about the acquisition of an
easement to construct, operate, and maintain the planned facilities.
The company would seek to negotiate a mutually acceptable agreement.
However, if the project is approved by the Commission, that approval
conveys with it the right of eminent domain. Therefore, if easement
negotiations fail to produce an agreement, the pipeline company could
initiate condemnation proceedings where compensation would be
determined in accordance with state law.
A fact sheet prepared by the FERC entitled ``An Interstate Natural
Gas Facility On My Land? What Do I Need To Know?'' is available for
viewing on the FERC Web site (https://www.ferc.gov). This fact sheet
addresses a number of typically-asked questions, including the use of
eminent domain and how to participate in the Commission's proceedings.
Summary of the Planned Project
Transco is proposing to construct and operate five new pipeline
loops,\1\ construct one new compressor station, add compression at two
existing compressor stations, and perform other modifications to five
compressor stations. The MSEP would provide about 451 million standard
cubic feet of natural gas per day to Transco's existing mainline system
from the Clean Energy LNG import terminal currently under construction
in Pascagoula, Mississippi, with existing capacity on Transco's Mobile
Bay Lateral, down to existing Compressor Station 85. According to
Transco, its project would expand delivery capacity on its existing
pipeline system to growing markets in the east as far downstream as
Rockingham County, North Carolina.
---------------------------------------------------------------------------
\1\ A pipeline loop is constructed parallel to an existing
pipeline to increase capacity.
---------------------------------------------------------------------------
The MSEP would consist of the following facilities:
Five pipeline loops located in Coosa and Randolph Counties,
Alabama, and Gaston, Rowan and Davidson Counties, North Carolina;
One new compressor station, Station 95, to be located in
Dallas County, Alabama;
Additional new compression at two existing compressor
stations:
[cir] Station 90 in Marengo County, Alabama; and
[cir] Station 125 in Walton County, Georgia;
Modifications at the following existing compressor stations:
[cir] Station 105 in Coosa County, Alabama;
[cir] Station 115 in Coweta County, Georgia;
[cir] Station 120 in Henry County, Georgia;
[cir] Station 140 in Spartanburg County, South Carolina; and
[cir] Station 145 in Cleveland County, North Carolina.
The planned loops would be constructed with 42-inch-diameter steel
pipe and would have a combined total length of about 22.6 miles.
[[Page 51456]]
The general location of the project facilities is shown in appendix
1.\2\
---------------------------------------------------------------------------
\2\ The appendices referenced in this notice are not being
printed in the Federal Register. Copies of appendices were sent to
all those receiving this notice in the mail and are available at
https://www.ferc.gov using the link called ``eLibrary'' or from the
Commission's Public Reference Room, 888 First Street NE.,
Washington, DC 20426, or call (202) 502-8371. For instructions on
connecting to eLibrary, refer to the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the planned facilities would disturb approximately
287.9 acres of land for the aboveground facilities and the pipeline.
Following construction, approximately 144.6 acres would be maintained
for permanent operation of the project's facilities; the remaining
acreage would be restored and allowed to revert to former uses. The
entire planned pipeline route either parallels or would be located
within existing pipeline, utility, or road rights-of-way.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
\3\ to discover and address concerns the public may have about
proposals. This process is referred to as scoping. The main goal of the
scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EA. All comments
received will be considered during the preparation of the EA.
---------------------------------------------------------------------------
\3\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the planned project under these
general headings:
Geology and soils;
land use;
water resources, fisheries, and wetlands;
cultural resources;
vegetation and wildlife;
air quality and noise;
endangered and threatened species; and
public safety.
We will also evaluate possible alternatives to the planned project
or portions of the project, and make recommendations on how to lessen
or avoid impacts on the various resource areas.
Although no formal application has been filed, we have already
initiated our NEPA review under the Commission's pre-filing process.
The purpose of the pre-filing process is to encourage early involvement
of interested stakeholders and to identify and resolve issues before an
application is filed with the FERC. As part of our pre-filing review,
we have begun to contact some Federal and State agencies to discuss
their involvement in the scoping process and the preparation of the EA.
Our independent analysis of the issues will be presented in the EA.
The EA will be placed in the public record and, depending on the
comments received during the scoping process, may be published and
distributed to the public. A comment period will be allotted if the EA
is published for review. We will consider all comments on the EA before
we make our recommendations to the Commission. To ensure your comments
are considered, please carefully follow the instructions in the Public
Participation section beginning on page 5.
With this notice, we are asking agencies with jurisdiction and/or
special expertise with respect to environmental issues to formally
cooperate with us in the preparation of the EA. These agencies may
choose to participate once they have evaluated the proposal relative to
their responsibilities. Agencies that would like to request cooperating
agency status should follow the instructions for filing comments
provided under the Public Participation section of this notice.
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultation
with applicable State Historic Preservation Office(s), and to solicit
their views and those of other government agencies, interested Indian
tribes, and the public on the project's potential effects on historic
properties.\4\ We will define the project-specific Area of Potential
Effects (APE) in consultation with the SHPO(s) as the project is
further developed. On natural gas facility projects, the APE at a
minimum encompasses all areas subject to ground disturbance (examples
include construction right-of-way, contractor/pipe storage yards,
compressor stations, and access roads). Our EA for this project will
document our findings on the impacts on historic properties and
summarize the status of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Historic
properties are defined in those regulations as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register for Historic
Places.
---------------------------------------------------------------------------
Currently Identified Environmental Issues
We have already identified several issues that we think deserve
attention based on a preliminary review of the planned facilities and
the environmental information provided by Transco. This preliminary
list of issues may be changed based on your comments and our analysis.
Cultural resources;
Water resources, fisheries, and wetlands; and
Threatened and endangered species.
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the project. Your comments should focus on
the potential environmental effects, reasonable alternatives, and
measures to avoid or lessen environmental impacts. The more specific
your comments, the more useful they will be. To ensure that your
comments are timely and properly recorded, please send your comments so
that they will be received in Washington, DC on or before September 13,
2010.
For your convenience, there are three methods you can use to submit
your comments to the Commission. In all instances, please reference the
project docket number (PF10-13-000) with your submission. The
Commission encourages electronic filing of comments and has expert
eFiling staff available to assist you at (202) 502-8258 or
efiling@ferc.gov.
(1) You may file your comments electronically by using the eComment
feature, which is located on the Commission's Web site at https://www.ferc.gov under the link to Documents and Filings. An eComment is an
easy method for interested persons to submit brief, text-only comments
on a project;
(2) You may file your comments electronically by using the eFiling
feature, which is located on the Commission's Web site at https://www.ferc.gov under the link to Documents and Filings. With eFiling you
can provide comments in a variety of formats by attaching them as a
file with your submission. New eFiling users must first create an
account by clicking on ``eRegister.'' You will be asked to select the
type of filing you are
[[Page 51457]]
making. A comment on a particular project is considered a ``Comment on
a Filing''; or
(3) You may file a paper copy of your comments at the following
address: Kimberly D. Bose, Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE., Room 1A, Washington, DC 20426.
Environmental Mailing List
The environmental mailing list includes Federal, State, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project. We will update the environmental mailing list
as the analysis proceeds to ensure that we send the information related
to this environmental review to all individuals, organizations, and
government entities interested in and/or potentially affected by the
planned project.
If the EA is published for distribution, copies will be sent to the
environmental mailing list for public review and comment. If you would
prefer to receive a paper copy of the document instead of the CD
version or would like to remove your name from the mailing list, please
return the attached Information Request (appendix 2).
Becoming an Intervenor
Once Transco files its application with the Commission, you may
want to become an ``intervenor'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
An intervenor formally participates in the proceeding by filing a
request to intervene. Instructions for becoming an intervenor are
included in the User's Guide under the ``e-filing'' link on the
Commission's Web site. Please note that the Commission will not accept
requests for intervenor status at this time. You must wait until a
formal application for the project is filed with the Commission.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site (https://www.ferc.gov) using the eLibrary link. Click on
the eLibrary link, click on ``General Search'' and enter the docket
number, excluding the last three digits in the Docket Number field
(i.e., PF10-13). Be sure you have selected an appropriate date range.
For assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to https://www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at https://www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Kimberly D. Bose,
Secretary.