Dogwood Energy, LLC; Notice of Institution of Section 206 Proceeding and Refund Effective Date, 51033 [2010-20457]

Download as PDF Federal Register / Vol. 75, No. 159 / Wednesday, August 18, 2010 / Notices BILLING CODE 6717–01–P remains just and reasonable. Dogwood Energy, LLC, 132 FERC ¶ 61,120 (2010). The refund effective date in Docket No. EL10–74–000, established pursuant to section 206(b) of the FPA, will be the date of publication of this notice in the Federal Register. DEPARTMENT OF ENERGY Kimberly J. Bose, Secretary. Comment Date: 5 p.m. Eastern time on Monday, August 23, 2010. Kimberly D. Bose, Secretary. [FR Doc. 2010–20462 Filed 8–17–10; 8:45 am] [FR Doc. 2010–20457 Filed 8–17–10; 8:45 am] Federal Energy Regulatory Commission BILLING CODE 6717–01–P [Docket No. EL10–73–000] DEPARTMENT OF ENERGY BE Louisiana, LLC; Notice of Institution of Section 206 Proceeding and Refund Effective Date [Docket No. CP10–459–000] August 12, 2010. On August 11, 2010, the Commission issued an order that instituted a proceeding in Docket No. EL10–73–000, pursuant to section 206 of the Federal Power Act (FPA), 16 USC 824e, to determine whether the J.P. Morgan Sellers’ 1 market-based rate authority in the Cleco Corporation, Inc. balancing authority area remains just and reasonable. BE Louisiana, LLC, 132 FERC ¶ 61,118 (2010). The refund effective date in Docket No. EL10–73–000, established pursuant to section 206(b) of the FPA, will be the date of publication of this notice in the Federal Register. Kimberly J. Bose, Secretary. [FR Doc. 2010–20456 Filed 8–17–10; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. EL10–74–000] Dogwood Energy, LLC; Notice of Institution of Section 206 Proceeding and Refund Effective Date sroberts on DSKD5P82C1PROD with NOTICES August 12, 2010. On August 11, 2010, the Commission issued an order that instituted a proceeding in Docket No. EL10–74–000, pursuant to section 206 of the Federal Power Act (FPA), 16 U.S.C. 824e, to determine whether Dogwood Energy, LLC’s market-based rate authority in the KCP&L Greater Missouri Operations Company balancing authority area 1 For purposes of this notice, the J.P. Morgan Sellers are BE Louisiana, LLC, Cedar Brakes I, L.L.C., Cedar Brakes II, L.L.C., J.P. Morgan Commodities Canada Corporation, J.P. Morgan Ventures Energy Corporation, and Utility Contract Funding, L.L.C. VerDate Mar<15>2010 18:40 Aug 17, 2010 Federal Energy Regulatory Commission Jkt 220001 ETC Tiger Pipeline, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed ETC Tiger Pipeline Expansion Project— Phase I and Request for Comments on Environmental Issues August 12, 2010. The staff of the Federal Energy Regulatory Commission (FERC or Commission) will prepare an environmental assessment (EA) that will discuss the environmental impacts of the ETC Tiger Pipeline Expansion Project—Phase I, involving construction and operation of facilities by ETC Tiger Pipeline, LLC (Tiger) in Bienville, Jackson, Ouachita, and Red River Parishes in Louisiana. This EA will be used by the Commission in its decisionmaking process to determine whether the project is in the public convenience and necessity. This notice announces the opening of the scoping process the Commission will use to gather input from the public and interested agencies on the project. Your input will help the Commission staff determine what issues need to be evaluated in the EA. Please note that the scoping period will close on September 13, 2010. This notice is being sent to the Commission’s current environmental mailing list for this project. State and local government representatives are asked to notify their constituents of this planned project and encourage them to comment on their areas of concern. If you are a landowner receiving this notice, you may be contacted by a pipeline company representative about the acquisition of an easement to construct, operate, and maintain the proposed facilities. The company would seek to negotiate a mutually acceptable agreement. However, if the project is approved by the Commission, that approval conveys with it the right of PO 00000 Frm 00051 Fmt 4703 Sfmt 4703 51033 eminent domain. Therefore, if easement negotiations fail to produce an agreement, the pipeline company could initiate condemnation proceedings where compensation would be determined in accordance with state law. A fact sheet prepared by the FERC entitled ‘‘An Interstate Natural Gas Facility On My Land? What Do I Need To Know?’’ was attached to the project notice Tiger provided to landowners. This fact sheet addresses a number of typically-asked questions, including the use of eminent domain and how to participate in the Commission’s proceedings. It is also available for viewing on the FERC Web site (https:// www.ferc.gov). Summary of the Proposed Project Tiger has proposed Phase I of the ETC Tiger Pipeline Expansion Project to construct two pipeline loops of the ETC Tiger Pipeline and add compression at three compressor stations. The pipeline construction would consist of: Loop 1— approximately 8.2 miles of new 42-inch diameter loop 1 in Bienville Parish, Louisiana (LA); and Loop 2— approximately 12.3 miles of new 42inch diameter pipeline in Jackson and Ouachita Parishes, LA. Associated aboveground facilities consisting of side valves, crossover piping, pig launchers 2 and receivers would be constructed at each end of the pipeline loops. In addition, Tiger would install additional compression at the following existing compressor stations: Approximately 4,735 horsepower (hp) at the Cannisnia Compressor Station in Red River Parish, LA; approximately 8,180 hp of compression at the Bienville Compressor Station in Bienville Parish, LA; and approximately 17,650 hp of compression at the Chatham Compressor Station in Jackson Parish, LA. The Project would add 0.4 billion cubic feet/day of natural gas capacity to Tiger’s system. The general location of the project facilities is shown in Appendix 1.3 1 A pipeline loop is a segment of new pipeline constructed parallel to an existing pipeline to increase capacity. 2 A ‘‘pig’’ is a tool that is inserted into and moves through the pipeline, and is used for cleaning the pipeline, internal inspections, or other purposes. 3 The appendices referenced in this notice are not being printed in the Federal Register. Copies of appendices were sent to all those receiving this notice in the mail and are available at https:// www.ferc.gov using the link called ‘‘eLibrary’’ or from the Commission’s Public Reference Room, 888 First Street, NE., Washington, DC 20426, or call (202) 502–8371. For instructions on connecting to eLibrary, refer to the last page of this notice. E:\FR\FM\18AUN1.SGM 18AUN1

Agencies

[Federal Register Volume 75, Number 159 (Wednesday, August 18, 2010)]
[Notices]
[Page 51033]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-20457]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. EL10-74-000]


Dogwood Energy, LLC; Notice of Institution of Section 206 
Proceeding and Refund Effective Date

August 12, 2010.
    On August 11, 2010, the Commission issued an order that instituted 
a proceeding in Docket No. EL10-74-000, pursuant to section 206 of the 
Federal Power Act (FPA), 16 U.S.C. 824e, to determine whether Dogwood 
Energy, LLC's market-based rate authority in the KCP&L Greater Missouri 
Operations Company balancing authority area remains just and 
reasonable. Dogwood Energy, LLC, 132 FERC ] 61,120 (2010).
    The refund effective date in Docket No. EL10-74-000, established 
pursuant to section 206(b) of the FPA, will be the date of publication 
of this notice in the Federal Register.

Kimberly J. Bose,
Secretary.
[FR Doc. 2010-20457 Filed 8-17-10; 8:45 am]
BILLING CODE 6717-01-P