EasTrans, LLC; Notice of Filing, 45110-45111 [2010-18848]
Download as PDF
45110
Federal Register / Vol. 75, No. 147 / Monday, August 2, 2010 / Notices
erowe on DSK5CLS3C1PROD with NOTICES
• Approximately 27.6 miles of 36inch-diameter natural gas pipeline
loop 1 extending southwest in Utah from
Morgan County, through Davis to Salt
Lake County;
• One new 30,000-horsepower
compressor station (known as the
Milford Compressor Station) in Beaver
County, Utah;
• Modifications to four existing
compressor stations to add additional
compression: The Coyote Creek
Compressor Station located in Uinta
County, Wyoming; the Elberta
Compressor Station located in Utah
County, Utah; the Fillmore Compressor
Station located in Millard County, Utah;
and the Dry Lake Compressor Station
located in Clark County, Nevada;
• Six mainline valves; and
• Three pig 2 launcher and two pig
receiver facilities.
The final EIS has been placed in the
public files of the FERC and is available
for public viewing on the FERC’s Web
site at https://www.ferc.gov. A limited
number of copies are available for
distribution and public inspection at:
Federal Energy Regulatory Commission,
Public Reference Room, 888 First Street,
NE., Room 2A, Washington, DC 20426,
(202) 502–8371.
Copies of the EIS have been mailed to
federal, state, and local government
representatives and agencies; elected
officials; environmental and public
interest groups; Native American tribes;
local newspapers and libraries in the
project area; parties to this proceeding;
and potentially affected landowners and
other interested individuals and groups.
Paper copy versions of this EIS were
mailed to those specifically requesting
them; all others received a CD version.
Questions?
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC or on the FERC
(https://www.ferc.gov) using the eLibrary
link. Click on the eLibrary link, click on
‘‘General Search,’’ and enter the docket
number excluding the last three digits in
the Docket Number field (i.e., CP10–14).
Be sure you have selected an
appropriate date range. For assistance,
please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free
at (866) 208–3676; for TTY, contact
(202) 502–8659. The eLibrary link also
provides access to the texts of formal
1 A loop is a segment of pipe that is usually
installed adjacent to an existing pipeline and
connected to it at both ends. The loop allows more
gas to be moved through the system.
2 A pig is an internal tool that can be used to
clean and dry a pipeline and/or to inspect it for
damage or corrosion.
VerDate Mar<15>2010
15:04 Jul 30, 2010
Jkt 220001
DEPARTMENT OF ENERGY
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern time
on Monday, August 9, 2010.
Federal Energy Regulatory
Commission
Kimberly D. Bose,
Secretary.
[Docket No. PR10–62–000]
[FR Doc. 2010–18847 Filed 7–30–10; 8:45 am]
documents issued by the Commission,
such as orders, notices, and
rulemakings.
In addition, the Commission offers a
free service called eSubscription that
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to https://www.ferc.gov/
esubscribenow.htm.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–18838 Filed 7–30–10; 8:45 am]
BILLING CODE 6717–01–P
BILLING CODE 6717–01–P
Pelico Pipeline, LLC; Notice of Filing
July 26, 2010.
Take notice that on July 15, 2010,
Pelico Pipeline, LLC (Pelico) filed a
revised Statement of Operating
conditions to modify several gas quality
specifications to be consistent with the
downstream pipeline specifications. In
addition, the imbalance cash out section
has been revised to modify the pipeline
indices used for the cash out to be
aligned with recent market conditions
and pipeline activity and the pressure
base has been updated to current
practice.
Any person desiring to participate in
this rate filing must file in accordance
with Rules 211 and 214 of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.211 and
385.214). Protests will be considered by
the Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
date as indicated below. Anyone filing
an intervention or protest must serve a
copy of that document on the Applicant.
Anyone filing an intervention or protest
on or before the intervention or protest
date need not serve motions to intervene
or protests on persons other than the
Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. PR10–65–000]
EasTrans, LLC; Notice of Filing
July 26, 2010.
Take notice that on July 15, 2010,
EasTrans, LLC (EasTrans) filed to
significantly modify its Statement of
Operating Conditions to provide
clarification and reflect the
implementation of a new EasTrans
nomination process.
Any person desiring to participate in
this rate filing must file in accordance
with Rules 211 and 214 of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.211 and
385.214). Protests will be considered by
the Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
date as indicated below. Anyone filing
an intervention or protest must serve a
copy of that document on the Applicant.
Anyone filing an intervention or protest
on or before the intervention or protest
date need not serve motions to intervene
or protests on persons other than the
Applicant.
The Commission encourages
electronic submission of protests and
E:\FR\FM\02AUN1.SGM
02AUN1
Federal Register / Vol. 75, No. 147 / Monday, August 2, 2010 / Notices
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern time
on Monday, August 9, 2010.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–18848 Filed 7–30–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP10–472–000]
Kinder Morgan Interstate Gas
Transmission LLC; Notice of Request
Under Blanket Authorization
erowe on DSK5CLS3C1PROD with NOTICES
July 26, 2010.
Take notice that on July 20, 2010,
Kinder Morgan Interstate Gas
Transmission LLC (KMIGT), PO Box
281304, Lakewood, Colorado 80228–
8304, filed a prior notice request
pursuant to sections 157.205, 157.208,
and 157.210 of the Commission’s
regulations under the Natural Gas Act
(NGA) for authorization to replace,
construct and operate certain mainline
pipeline and ancillary facilities
primarily to serve a new ethanol plant
in Adams County, Nebraska, all as more
fully set forth in the application, which
is on file with the Commission and open
to public inspection. The filing may also
be viewed on the Web at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (866) 208–3676 or TTY, (202)
502–8659.
KMIGT states that as a result of
wrinkle bends, which have caused the
VerDate Mar<15>2010
15:04 Jul 30, 2010
Jkt 220001
pipeline to become physically
deteriorated, approximately 11.4 miles
of its 16-inch Franklin to Hastings
Pipeline needs to be replaced. KMIGT
asserts that, in response to the
developing market for natural gas and to
develop firm transportation to serve
ethanol production facilities in the
Midwest, KMIGT held an open season
from July 2, 2010 through July 9, 2010
seeking support to expand its firm
transportation capacity. As a result of
the open season, KMIGT states that it
has entered into a binding precedent
agreement with Aventine Renewable
Energy—Aurora West, LLC to provide
up to 10,000 dekatherms per day of
natural gas to serve its new ethanol
plant located near Aurora, Nebraska.
Accordingly, KMIGT proposes to
replace 11.4 miles of the Franklin to
Hastings Pipeline with 20-inch pipe to
serve the increase in firm load. In
addition, KMIGT proposes to construct
and operate certain ancillary facilities.
KMIGT estimates cost of constructing
the proposed facilities is $23,511,100.
Any questions regarding the
application should be directed to Robert
F. Harrington, Vice President,
Regulatory, Kinder Morgan Interstate
Gas Transmission LLC, 370 Van Gordon
Street, Lakewood, Colorado 80228–
8304, by telephone (303) 763–3258, or
by facsimile at (303) 984–3272, or by email at
Robert_Harrington@kindermorgan.com.
Any person may, within 60 days after
the issuance of the instant notice by the
Commission, file pursuant to Rule 214
of the Commission’s Procedural Rules
(18 CFR 385.214) a motion to intervene
or notice of intervention. Any person
filing to intervene or the Commission’s
staff may, pursuant to section 157.205 of
the Commission’s regulations under the
NGA (18 CFR 157.205) file a protest to
the request. If no protest is filed within
the time allowed therefore, the proposed
activity shall be deemed to be
authorized effective the day after the
time allowed for protest. If a protest is
filed and not withdrawn within 30 days
after the time allowed for filing a
protest, the instant request shall be
treated as an application for
authorization pursuant to section 7 of
the NGA.
The Commission strongly encourages
electronic filings of comments, protests,
and interventions via the internet in lieu
of paper. See 18 CFR 385.2001(a)(1)(iii)
and the instructions on the
PO 00000
Frm 00025
Fmt 4703
Sfmt 4703
45111
Commission’s Web site (https://
www.ferc.gov) under the ‘‘e-Filing’’ link.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–18845 Filed 7–30–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER02–2001–015; Docket No.
ER00–167–000; Docket No. ER03–752–000]
Electric Quarterly Reports; Strategic
Energy Management Corp.; Solaro
Energy Marketing Corporation; Notice
of Revocation of Market-Based Rate
Tariff
July 23, 2010.
On June 25, 2010, the Commission
issued an order announcing its intent to
revoke the market-based rate authority
of the above captioned public utilities,
which had failed to file their required
Electric Quarterly Reports.1 The
Commission provided the utilities
fifteen days in which to file their
overdue Electric Quarterly Reports or
face revocation of their market-based
rate tariffs.
In Order No. 2001, the Commission
revised its public utility filing
requirements and established a
requirement for public utilities,
including power marketers, to file
Electric Quarterly Reports summarizing
the contractual terms and conditions in
their agreements for all jurisdictional
services (including market-based power
sales, cost-based power sales, and
transmission service) and providing
transaction information (including rates)
for short-term and long-term power
sales during the most recent calendar
quarter.2
In the June 25 Order, the Commission
directed Strategic Energy Management
Corp. and Solaro Energy Marketing
Corporation to file the required Electric
Quarterly Reports within 15 days of the
date of issuance of the order or face
revocation of their authority to sell
power at market-based rates and
termination of their electric marketbased rate tariffs.3
1 Electric Quarterly Reports, 131 FERC ¶ 61,272
(2010) (June 25 Order).
2 Revised Public Utility Filing Requirements,
Order No. 2001, 67 Fed. Reg. 31,043, FERC Stats.
& Regs. ¶ 31,127, reh’g denied, Order No. 2001–A,
100 FERC ¶ 61,074, reconsideration and
clarification denied, Order No. 2001–B, 100 FERC
¶ 61,342, order directing filings, Order No. 2001–C,
101 FERC ¶ 61,314 (2002), order directing filing,
Order No. 2001–D, 102 FERC ¶ 61,334 (2003).
3 June 25 Order at Ordering Paragraph A.
E:\FR\FM\02AUN1.SGM
02AUN1
Agencies
[Federal Register Volume 75, Number 147 (Monday, August 2, 2010)]
[Notices]
[Pages 45110-45111]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-18848]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. PR10-65-000]
EasTrans, LLC; Notice of Filing
July 26, 2010.
Take notice that on July 15, 2010, EasTrans, LLC (EasTrans) filed
to significantly modify its Statement of Operating Conditions to
provide clarification and reflect the implementation of a new EasTrans
nomination process.
Any person desiring to participate in this rate filing must file in
accordance with Rules 211 and 214 of the Commission's Rules of Practice
and Procedure (18 CFR 385.211 and 385.214). Protests will be considered
by the Commission in determining the appropriate action to be taken,
but will not serve to make protestants parties to the proceeding. Any
person wishing to become a party must file a notice of intervention or
motion to intervene, as appropriate. Such notices, motions, or protests
must be filed on or before the date as indicated below. Anyone filing
an intervention or protest must serve a copy of that document on the
Applicant. Anyone filing an intervention or protest on or before the
intervention or protest date need not serve motions to intervene or
protests on persons other than the Applicant.
The Commission encourages electronic submission of protests and
[[Page 45111]]
interventions in lieu of paper using the ``eFiling'' link at https://www.ferc.gov. Persons unable to file electronically should submit an
original and 14 copies of the protest or intervention to the Federal
Energy Regulatory Commission, 888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at https://www.ferc.gov, using the
``eLibrary'' link and is available for review in the Commission's
Public Reference Room in Washington, DC. There is an ``eSubscription''
link on the Web site that enables subscribers to receive e-mail
notification when a document is added to a subscribed docket(s). For
assistance with any FERC Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For
TTY, call (202) 502-8659.
Comment Date: 5 p.m. Eastern time on Monday, August 9, 2010.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010-18848 Filed 7-30-10; 8:45 am]
BILLING CODE 6717-01-P