University of Maryland; Notice of Acceptance for Docketing and Opportunity for Hearing on the Application Regarding Renewal of Facility Operating License for an Additional 20-Year Period for the Maryland University Training Reactor and Order Imposing Procedures for Access to Safeguards Information and Sensitive Unclassified Non-Safeguards Information, 43566-43571 [2010-18221]

Download as PDF jlentini on DSKJ8SOYB1PROD with NOTICES 43566 Federal Register / Vol. 75, No. 142 / Monday, July 26, 2010 / Notices copies of the proposed information collection and supporting statement should be directed to Tamee Fechhelm at telephone number 301–837–1694 or fax number 301–713–7409. SUPPLEMENTARY INFORMATION: Pursuant to the Paperwork Reduction Act of 1995 (Pub. L. 104–13), NARA invites the general public and other Federal agencies to comment on proposed information collections. NARA published a notice of proposed collection for this information collection on May 10, 2010 (75 FR 25886). No comments were received. NARA has submitted the described information collection to OMB for approval. In response to this notice, comments and suggestions should address one or more of the following points: (a) Whether the proposed collection information is necessary for the proper performance of the functions of NARA; (b) the accuracy of NARA’s estimate of the burden of the proposed information collection; (c) ways to enhance the quality, utility, and clarity of the information to be collected; and (d) ways to minimize the burden of the collection of information on respondents, including the use of information technology; and (e) whether small businesses are affected by this collection. In this notice, NARA is soliciting comments concerning the following information collection: Title: Microfilm Order. OMB Number: 3095–0046. Agency Form Number: NATF Form 36. Type of Review: Regular. Affected Public: Business or for-profit, nonprofit organizations and institutions, federal, state and local government agencies, and individuals or households. Estimated Number of Respondents: 600. Estimated Time per Response: 10 minutes. Frequency of Response: On occasion. Estimated Total Annual Burden Hours: 100 hours. Abstract: The information collection is prescribed by 36 CFR 1254.72. The collection is prepared by researchers who cannot visit the appropriate NARA research room or who request copies of records as a result of visiting a research room. NARA offers limited provisions to obtain copies of records by mail and requires requests to be made on prescribed forms for certain bodies of records. The National Archives Trust Fund (NATF) Form 36 (5–10), Microfilm Order, is used by customers/researchers for ordering a roll, rolls, or a microfiche of a microfilm publication. VerDate Mar<15>2010 16:04 Jul 23, 2010 Jkt 220001 Dated: July 16, 2010. Charles K. Piercy, Acting Assistant Archivist for Information Services. [FR Doc. 2010–18347 Filed 7–23–10; 8:45 am] BILLING CODE 7515–01–P NUCLEAR REGULATORY COMMISSION [Facility Operating License No. R–70; Docket No. 50–166; NRC–2010–0250] University of Maryland; Notice of Acceptance for Docketing and Opportunity for Hearing on the Application Regarding Renewal of Facility Operating License for an Additional 20-Year Period for the Maryland University Training Reactor and Order Imposing Procedures for Access to Safeguards Information and Sensitive Unclassified Non-Safeguards Information Nuclear Regulatory Commission. ACTION: Notice of acceptance for docketing. AGENCY: FOR FURTHER INFORMATION CONTACT: Spyros A. Traiforos, Project Manager, Research and Test Reactors Projects Branch, Division of Policy and Rulemaking, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Rockville, MD 20852. Telephone: (301) 415–3965; fax number: (301) 415–1032; e-mail: Spyros.Traiforos@nrc.gov. SUPPLEMENTARY INFORMATION: I. Introduction The U.S. Nuclear Regulatory Commission (NRC) is considering an application for the renewal of Facility Operating License No. R–70 (‘‘Application’’), which currently authorizes the University of Maryland (the licensee, UMD) to operate the Maryland University Training Reactor (MUTR) at a maximum steady-state thermal power of 250 kilowatts (kW). The renewed license would authorize the applicant to operate the MUTR up to a steady-state thermal power of 250 kW for an additional 20 years from the date of issuance. By letter dated May 12, 2000, as supplemented by letters dated June 7, August 4, September 17, and October 7, 2004; April 18, 2005, April 25 (two letters), August 28 (two letters), November 9, and December 18, 2006; and May 27, 2010, the licensee submitted an application to the NRC filed pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Section PO 00000 Frm 00082 Fmt 4703 Sfmt 4703 50.51(a), to renew Facility Operating License No. R–70 for the MUTR. The application contains sensitive unclassified non-safeguards information (SUNSI) and Safeguards Information (SGI). Based on its initial review of the application and the supplemental information, the Commission’s staff determined that UMD submitted sufficient information in accordance with 10 CFR 50.33 and 10 CFR 50.34 so that the application is acceptable for docketing. The current Docket No. 50– 166 for Facility Operating License No. R–70 will be retained. The docketing of the renewal application does not preclude requests for additional information as the review proceeds, nor does it predict whether the Commission will grant or deny the application. Prior to a decision to renew the license, the Commission will make the findings required by the Atomic Energy Act of 1954, as amended (the Act), and the Commission’s rules and regulations. II. Opportunity To Request a Hearing or Petition to Intervene Within 60 days of this notice, any person(s) whose interest may be affected may file a request for hearing/petition to intervene. As required by 10 CFR 2.309, a petition for leave to intervene shall set forth with particularity the interest of the petitioner/requestor in the proceeding, and how that interest may be affected by the results of the proceeding. The petition should specifically explain the reasons why intervention should be permitted with particular reference to the following general requirements: (1) The name, address and telephone number of the requestor or petitioner; (2) the nature of the requestor’s/petitioner’s right under the Act to be made a party to the proceeding; (3) the nature and extent of the requestor’s/petitioner’s property, financial, or other interest in the proceeding; and (4) the possible effect of any decision or order which may be entered in the proceeding on the requestor’s/petitioner’s interest. The petition must also identify the specific contentions which the petitioner/ requestor seeks to have litigated at the proceeding. Each contention must consist of a specific statement of the issue of law or fact to be raised or controverted. In addition, the petitioner/requestor shall provide a brief explanation of the bases for the contention and a concise statement of the alleged facts or expert opinion which support the contention and on which the petitioner intends to rely in proving the contention at the hearing. The petitioner must also E:\FR\FM\26JYN1.SGM 26JYN1 jlentini on DSKJ8SOYB1PROD with NOTICES Federal Register / Vol. 75, No. 142 / Monday, July 26, 2010 / Notices provide references to those specific sources and documents of which the petitioner is aware and on which the petitioner intends to rely to establish those facts or expert opinion. The petition must include sufficient information to show that a genuine dispute exists with the applicant on a material issue of law or fact. Contentions shall be limited to matters within the scope of the amendment under consideration. The contention must be one which, if proven, would entitle the petitioner/requestor to relief. A petitioner/requestor who fails to satisfy these requirements with respect to at least one contention will not be permitted to participate as a party. Those permitted to intervene become parties to the proceeding, subject to any limitations in the order granting leave to intervene, and have the opportunity to participate fully in the conduct of the hearing. Non-timely requests and/or petitions and contentions will not be entertained absent a determination by the Commission, the presiding officer, or the Atomic Safety and Licensing Board that the petition and/or request should be granted and/or the contentions should be admitted, based on a balancing of the factors specified in 10 CFR 2.309(c)(1)(i)–(viii). A State, county, municipality, Federally-recognized Indian Tribe, or agencies thereof, may submit a petition to the Commission to participate as a party under 10 CFR 2.309(d)(2). The petition should state the nature and extent of the petitioner’s interest in the proceeding. The petition should be submitted to the Commission by September 24, 2010. The petition must be filed in accordance with the filing instructions in section IV, and should meet the requirements for petitions for leave to intervene set forth in section III.A, except that State and Federallyrecognized Indian Tribes do not need to address the standing requirements in 10 CFR 2.309(d)(1) if the facility is located within its boundaries. The entities listed above could also seek to participate in a hearing as a nonparty pursuant to 10 CFR 2.315(c). Any person who does not wish, or is not qualified, to become a party to this proceeding may request permission to make a limited appearance pursuant to the provisions of 10 CFR 2.315(a). A person making a limited appearance may make an oral or written statement of position on the issues, but may not otherwise participate in the proceeding. A limited appearance may be made at any session of the hearing or at any prehearing conference, subject to such limits and conditions as may be VerDate Mar<15>2010 16:04 Jul 23, 2010 Jkt 220001 imposed by the Licensing Board. Persons desiring to make a limited appearance are requested to inform the Secretary of the Commission by September 24, 2010. III. Electronic Submissions (E-Filing) All documents filed in NRC adjudicatory proceedings, including a request for hearing, a petition for leave to intervene, any motion or other document filed in the proceeding prior to the submission of a request for hearing or petition to intervene, and documents filed by interested governmental entities participating under 10 CFR 2.315(c), must be filed in accordance with the NRC E-Filing rule (72 FR 49139, August 28, 2007). The EFiling process requires participants to submit and serve all adjudicatory documents over the Internet, or in some cases to mail copies on electronic storage media. Participants may not submit paper copies of their filings unless they seek an exemption in accordance with the procedures described below. To comply with the procedural requirements of E-Filing, at least ten (10) days prior to the filing deadline, the participant should contact the Office of the Secretary by e-mail at hearing.docket@nrc.gov, or by telephone at (301) 415–1677, to request (1) a digital ID certificate, which allows the participant (or its counsel or representative) to digitally sign documents and access the E-Submittal server for any proceeding in which it is participating; and (2) advise the Secretary that the participant will be submitting a request or petition for hearing (even in instances in which the participant, or its counsel or representative, already holds an NRCissued digital ID certificate). Based upon this information, the Secretary will establish an electronic docket for the hearing in this proceeding if the Secretary has not already established an electronic docket. Information about applying for a digital ID certificate is available on NRC’s public Web site at https:// www.nrc.gov/site-help/e-submittals/ apply-certificates.html. System requirements for accessing the ESubmittal server are detailed in NRC’s ‘‘Guidance for Electronic Submission,’’ which is available on the agency’s public Web site at https://www.nrc.gov/ site-help/e-submittals.html. Participants may attempt to use other software not listed on the Web site, but should note that the NRC’s E-Filing system does not support unlisted software, and the NRC Meta System Help Desk will not be able PO 00000 Frm 00083 Fmt 4703 Sfmt 4703 43567 to offer assistance in using unlisted software. If a participant is electronically submitting a document to the NRC in accordance with the E-Filing rule, the participant must file the document using the NRC’s online, Web-based submission form. In order to serve documents through EIE, users will be required to install a Web browser plugin from the NRC Web site. Further information on the Web-based submission form, including the installation of the Web browser plug-in, is available on the NRC’s public Web site at https://www.nrc.gov/site-help/esubmittals.html. Once a participant has obtained a digital ID certificate and a docket has been created, the participant can then submit a request for hearing or petition for leave to intervene. Submissions should be in Portable Document Format (PDF) in accordance with NRC guidance available on the NRC public Web site at https://www.nrc.gov/site-help/esubmittals.html. A filing is considered complete at the time the documents are submitted through the NRC’s E-Filing system. To be timely, an electronic filing must be submitted to the E-Filing system no later than 11:59 p.m. Eastern Time on the due date. Upon receipt of a transmission, the E-Filing system time-stamps the document and sends the submitter an e-mail notice confirming receipt of the document. The E-Filing system also distributes an email notice that provides access to the document to the NRC Office of the General Counsel and any others who have advised the Office of the Secretary that they wish to participate in the proceeding, so that the filer need not serve the documents on those participants separately. Therefore, applicants and other participants (or their counsel or representative) must apply for and receive a digital ID certificate before a hearing request/ petition to intervene is filed so that they can obtain access to the document via the E-Filing system. A person filing electronically using the agency’s adjudicatory E-Filing system may seek assistance by contacting the NRC Meta System Help Desk through the ‘‘Contact Us’’ link located on the NRC Web site at https:// www.nrc.gov/site-help/esubmittals.html, by e-mail at MSHD.Resource@nrc.gov, or by a tollfree call at (866) 672–7640. The NRC Meta System Help Desk is available between 8 a.m. and 8 p.m., Eastern Time, Monday through Friday, excluding government holidays. Participants who believe that they have a good cause for not submitting E:\FR\FM\26JYN1.SGM 26JYN1 jlentini on DSKJ8SOYB1PROD with NOTICES 43568 Federal Register / Vol. 75, No. 142 / Monday, July 26, 2010 / Notices documents electronically must file an exemption request, in accordance with 10 CFR 2.302(g), with their initial paper filing requesting authorization to continue to submit documents in paper format. Such filings must be submitted by: (1) First class mail addressed to the Office of the Secretary of the Commission, U.S. Nuclear Regulatory Commission, Washington, DC 20555– 0001, Attention: Rulemaking and Adjudications Staff; or (2) courier, express mail, or expedited delivery service to the Office of the Secretary, Sixteenth Floor, One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852, Attention: Rulemaking and Adjudications Staff. Participants filing a document in this manner are responsible for serving the document on all other participants. Filing is considered complete by first-class mail as of the time of deposit in the mail, or by courier, express mail, or expedited delivery service upon depositing the document with the provider of the service. A presiding officer, having granted an exemption request from using E-Filing, may require a participant or party to use E-Filing if the presiding officer subsequently determines that the reason for granting the exemption from use of E-Filing no longer exists. Documents submitted in adjudicatory proceedings will appear in NRC’s electronic hearing docket which is available to the public at https:// ehd.nrc.gov/EHD_Proceeding/home.asp, unless excluded pursuant to an order of the Commission, or the presiding officer. Participants are requested not to include personal privacy information, such as social security numbers, home addresses, or home phone numbers in their filings, unless an NRC regulation or other law requires submission of such information. With respect to copyrighted works, except for limited excerpts that serve the purpose of the adjudicatory filings and would constitute a Fair Use application, participants are requested not to include copyrighted materials in their submission. Petitions for leave to intervene must be filed no later than 60 days from July 26, 2010. Non-timely filings will not be entertained absent a determination by the presiding officer that the petition or request should be granted or the contentions should be admitted, based on a balancing of the factors specified in 10 CFR 2.309(c)(1)(i)–(viii). The NRC maintains an Agencywide Documents Access and Management System (ADAMS), which provides text and image files of NRC’s public documents. Detailed guidance which the NRC uses to review applications for VerDate Mar<15>2010 16:04 Jul 23, 2010 Jkt 220001 the renewal of non-power reactor licenses can be found in the documents NUREG–1537, entitled ‘‘Guidelines for Preparing and Reviewing Applications for the Licensing of Non-Power Reactors’’ and the ‘‘Interim Staff Guidance on the Streamlined Review Process for License Renewal for Research Reactors’’ (ISG) which can be obtained from the Commission’s public document room (PDR). The detailed review guidance (NUREG–1537 and the ISG) may be accessed through the NRC’s Public Electronic Reading Room on the Internet at https://www.nrc.gov/readingrm/adams.html under ADAMS Accession No. ML042430055 for part one of NUREG–1537, ADAMS Accession No. ML042430048 for part two of NUREG–1537 and ADAMS Accession No. ML092240244 for the ISG. Copies of the application to renew the facility license from the licensee are available for public inspection at the Commission’s PDR, located at One White Flint North, 11555 Rockville Pike (first floor), Rockville, Maryland 20852– 2738. The initial application and other related documents may be accessed through the NRC’s Public Electronic Reading Room, at the address mentioned above, under ADAMS Accession Nos.: May 12, 2000, (ML072210862), June 7, 2004, (ML101970211), August 4, 2004, (ML042240227), September 17, 2004, (ML042940317), October 7, 2004, (ML042940408), April 18, 2005, (ML051160054), April 25, 2006, (two letters ML061250233 and ML061280383), August 28, 2006, (two letters ML101480914 and ML101970209), November 9, 2006, (ML101970210), December 18, 2006, (ML101480913) and May 27, 2010 (ML101670413). Persons who do not have access to ADAMS, or who encounter problems in accessing the documents located in ADAMS, should contact the NRC PDR Reference staff by telephone at 1–800– 397–4209, or (301) 415–4737, or by email to pdr.resource@nrc.gov. Order Imposing Procedures for Access to Sensitive Unclassified NonSafeguards Information and Safeguards Information for Contention Preparation A. This Order contains instructions regarding how potential parties to this proceeding may request access to documents containing sensitive unclassified information (including SUNSI and SGI). Requirements for access to SGI are primarily set forth in 10 CFR Parts 2 and 73. Nothing in this Order is intended to conflict with the SGI regulations. PO 00000 Frm 00084 Fmt 4703 Sfmt 4703 B. Within 10 days after publication of this notice of hearing and opportunity to petition for leave to intervene, any potential party who believes access to SUNSI or SGI is necessary to respond to this notice may request access to SUNSI or SGI. A ‘‘potential party’’ is any person who intends to participate as a party by demonstrating standing and filing an admissible contention under 10 CFR 2.309. Requests for access to SUNSI or SGI submitted later than 10 days after publication will not be considered absent a showing of good cause for the late filing, addressing why the request could not have been filed earlier. C. The requestor shall submit a letter requesting permission to access SUNSI, SGI, or both to the Office of the Secretary, U.S. Nuclear Regulatory Commission, Washington, DC 20555– 0001, Attention: Rulemakings and Adjudications Staff, and provide a copy to the Associate General Counsel for Hearings, Enforcement and Administration, Office of the General Counsel, Washington, DC 20555–0001. The expedited delivery or courier mail address for both offices is: U.S. Nuclear Regulatory Commission, 11555 Rockville Pike, Rockville, Maryland 20852. The e-mail address for the Office of the Secretary and the Office of the General Counsel are Hearing.Docket@nrc.gov and OGCmailcenter@nrc.gov, respectively.1 The request must include the following information: (1) A description of the licensing action with a citation to this Federal Register notice; (2) The name and address of the potential party and a description of the potential party’s particularized interest that could be harmed by the action identified in C.(1); (3) If the request is for SUNSI, the identity of the individual or entity requesting access to SUNSI and the requestor’s basis for the need for the information in order to meaningfully participate in this adjudicatory proceeding. In particular, the request must explain why publicly-available versions of the information requested would not be sufficient to provide the basis and specificity for a proffered contention; (4) If the request is for SGI, the identity of each individual who would have access to SGI if the request is granted, including the identity of any expert, consultant, or assistant who will 1 While a request for hearing or petition to intervene in this proceeding must comply with the filing requirements of the NRC’s ‘‘E-Filing Rule,’’ the initial request to access SUNSI and/or SGI under these procedures should be submitted as described in this paragraph. E:\FR\FM\26JYN1.SGM 26JYN1 Federal Register / Vol. 75, No. 142 / Monday, July 26, 2010 / Notices jlentini on DSKJ8SOYB1PROD with NOTICES aid the requestor in evaluating the SGI. In addition, the request must contain the following information: (a) A statement that explains each individual’s ‘‘need to know’’ the SGI, as required by 10 CFR 73.2 and 10 CFR 73.22(b)(1). Consistent with the definition of ‘‘need to know’’ as stated in 10 CFR 73.2, the statement must explain: (i) Specifically why the requestor believes that the information is necessary to enable the requestor to proffer and/or adjudicate a specific contention in this proceeding; 2 and (ii) The technical competence (demonstrable knowledge, skill, training or education) of the requestor to effectively utilize the requested SGI to provide the basis and specificity for a proffered contention. The technical competence of a potential party or its counsel may be shown by reliance on a qualified expert, consultant, or assistant who satisfies these criteria. (b) A completed Form SF–85, ‘‘Questionnaire for Non-Sensitive Positions’’ for each individual who would have access to SGI. The completed Form SF–85 will be used by the Office of Administration to conduct the background check required for access to SGI, as required by 10 CFR Part 2, Subpart G and 10 CFR 73.22(b)(2), to determine the requestor’s trustworthiness and reliability. For security reasons, Form SF–85 can only be submitted electronically through the electronic questionnaire for investigations processing (e-QIP) Web site, a secure Web site that is owned and operated by the Office of Personnel Management. To obtain online access to the form, the requestor should contact the NRC’s Office of Administration at (301) 492–3524.3 (c) A completed Form FD–258 (fingerprint card), signed in original ink, and submitted in accordance with 10 CFR 73.57(d). Copies of Form FD–258 may be obtained by writing the Office of Information Services, U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001, by calling (301) 415– 7232 or (301) 492–7311, or by e-mail to 2 Broad SGI requests under these procedures are unlikely to meet the standard for need to know; furthermore, staff redaction of information from requested documents before their release may be appropriate to comport with this requirement. These procedures do not authorize unrestricted disclosure or less scrutiny of a requestor’s need to know than ordinarily would be applied in connection with an already-admitted contention or non-adjudicatory access to SGI. 3 The requestor will be asked to provide his or her full name, social security number, date and place of birth, telephone number, and e-mail address. After providing this information, the requestor usually should be able to obtain access to the online form within one business day. VerDate Mar<15>2010 16:04 Jul 23, 2010 Jkt 220001 Forms.Resource@nrc.gov. The fingerprint card will be used to satisfy the requirements of 10 CFR Part 2, 10 CFR 73.22(b)(1), and Section 149 of the Atomic Energy Act of 1954, as amended, which mandates that all persons with access to SGI must be fingerprinted for an FBI identification and criminal history records check; (d) A check or money order payable in the amount of $ 200.00 4 to the U.S. Nuclear Regulatory Commission for each individual for whom the request for access has been submitted, and (e) If the requestor or any individual who will have access to SGI believes they belong to one or more of the categories of individuals that are exempt from the criminal history records check and background check requirements in 10 CFR 73.59, the requestor should also provide a statement identifying which exemption the requestor is invoking and explaining the requestor’s basis for believing that the exemption applies. While processing the request, the Office of Administration, Personnel Security Branch, will make a final determination whether the claimed exemption applies. Alternatively, the requestor may contact the Office of Administration for an evaluation of their exemption status prior to submitting their request. Persons who are exempt from the background check are not required to complete the SF–85 or Form FD–258; however, all other requirements for access to SGI, including the need to know, are still applicable. Note: Copies of documents and materials required by paragraphs C.(4)(b), (c), and (d) of this Order must be sent to the following address: Office of Administration, U.S. Nuclear Regulatory Commission, Personnel Security Branch, Mail Stop TWB–05–B32M, Washington, DC 20555–0001. These documents and materials should not be included with the request letter to the Office of the Secretary, but the request letter should state that the forms and fees have been submitted as required above. D. To avoid delays in processing requests for access to SGI, the requestor should review all submitted materials for completeness and accuracy (including legibility) before submitting them to the NRC. The NRC will return incomplete packages to the sender without processing. E. Based on an evaluation of the information submitted under paragraphs C.(3) or C.(4) above, as applicable, the 4 This fee is subject to change pursuant to the Office of Personnel Management’s adjustable billing rates. PO 00000 Frm 00085 Fmt 4703 Sfmt 4703 43569 NRC staff will determine within 10 days of receipt of the request whether: (1) There is a reasonable basis to believe the petitioner is likely to establish standing to participate in this NRC proceeding; and (2) The requestor has established a legitimate need for access to SUNSI or need to know the SGI requested. F. For requests for access to SUNSI, if the NRC staff determines that the requestor satisfies both E.(1) and E.(2) above, the NRC staff will notify the requestor in writing that access to SUNSI has been granted. The written notification will contain instructions on how the requestor may obtain copies of the requested documents, and any other conditions that may apply to access to those documents. These conditions may include, but are not limited to, the signing of a Non-Disclosure Agreement or Affidavit, or Protective Order 5 setting forth terms and conditions to prevent the unauthorized or inadvertent disclosure of SUNSI by each individual who will be granted access to SUNSI. G. For requests for access to SGI, if the NRC staff determines that the requestor has satisfied both E.(1) and E.(2) above, the Office of Administration will then determine, based upon completion of the background check, whether the proposed recipient is trustworthy and reliable, as required for access to SGI by 10 CFR 73.22(b). If the Office of Administration determines that the individual or individuals are trustworthy and reliable, the NRC will promptly notify the requestor in writing. The notification will provide the names of approved individuals as well as the conditions under which the SGI will be provided. Those conditions may include, but not be limited to, the signing of a Non-Disclosure Agreement or Affidavit, or Protective Order 6 by each individual who will be granted access to SGI. H. Release and Storage of SGI. Prior to providing SGI to the requestor, the NRC staff will conduct (as necessary) an inspection to confirm that the recipient’s information protection system is sufficient to satisfy the requirements of 10 CFR 73.22. Alternatively, recipients may opt to 5 Any motion for Protective Order or draft NonDisclosure Affidavit or Agreement for SUNSI must be filed with the presiding officer or the Chief Administrative Judge if the presiding officer has not yet been designated, within 30 days of the deadline for the receipt of the written access request. 6 Any motion for Protective Order or draft NonDisclosure Affidavit or Agreement for SGI must be filed with the presiding officer or the Chief Administrative Judge if the presiding officer has not yet been designated, within 180 days of the deadline for the receipt of the written access request. E:\FR\FM\26JYN1.SGM 26JYN1 43570 Federal Register / Vol. 75, No. 142 / Monday, July 26, 2010 / Notices view SGI at an approved SGI storage location rather than establish their own SGI protection program to meet SGI protection requirements. I. Filing of Contentions. Any contentions in these proceedings that are based upon the information received as a result of the request made for SUNSI or SGI must be filed by the requestor no later than 25 days after the requestor is granted access to that information. However, if more than 25 days remain between the date the petitioner is granted access to the information and the deadline for filing all other contentions (as established in the notice of hearing or opportunity for hearing), the petitioner may file its SUNSI or SGI contentions by that later deadline. J. Review of Denials of Access. (1) If the request for access to SUNSI or SGI is denied by the NRC staff either after a determination on standing and requisite need, or after a determination on trustworthiness and reliability, the NRC staff shall immediately notify the requestor in writing, briefly stating the reason or reasons for the denial. (2) Before the Office of Administration makes an adverse determination regarding the proposed recipient(s) trustworthiness and reliability for access to SGI, the Office of Administration, in accordance with 10 CFR 2.705(c)(3)(iii), must provide the proposed recipient(s) any records that were considered in the trustworthiness and reliability determination, including those required to be provided under 10 CFR 73.57(e)(1), so that the proposed recipient(s) have an opportunity to correct or explain the record. (3) The requestor may challenge the NRC staff’s adverse determination with respect to access to SUNSI by filing a challenge within 5 days of receipt of that determination with: (a) The presiding officer designated in this proceeding; (b) if no presiding officer has been appointed, the Chief Administrative Judge, or if he or she is unavailable, another administrative judge, or an administrative law judge with jurisdiction pursuant to 10 CFR 2.318(a); or (c) if another officer has been designated to rule on information access issues, with that officer. (4) The requestor may challenge the NRC staff’s or Office of Administration’s adverse determination with respect to access to SGI by filing a request for review in accordance with 10 CFR 2.705(c)(3)(iv). Further appeals of decisions under this paragraph must be made pursuant to 10 CFR 2.311. K. Review of Grants of Access. A party other than the requestor may challenge an NRC staff determination granting access to SUNSI or SGI whose release would harm that party’s interest independent of the proceeding. Such a challenge must be filed with the Chief Administrative Judge within 5 days of the notification by the NRC staff of its grant of access. If challenges to the NRC staff determinations are filed, these procedures give way to the normal process for litigating disputes concerning access to information. The availability of interlocutory review by the Commission of orders ruling on such NRC staff determinations (whether granting or denying access) is governed by 10 CFR 2.311.7 L. The Commission expects that the NRC staff and presiding officers (and any other reviewing officers) will consider and resolve requests for access to SUNSI or SGI, and motions for protective orders, in a timely fashion in order to minimize any unnecessary delays in identifying those petitioners who have standing and who have propounded contentions meeting the specificity and basis requirements in 10 CFR Part 2. Attachment 1 to this Order summarizes the general target schedule for processing and resolving requests under these procedures. It is so ordered. Dated at Rockville, Maryland this 19th day of July 2010. For the Commission. Annette L. Vietti-Cook, Secretary of the Commission. ATTACHMENT 1—GENERAL TARGET SCHEDULE FOR PROCESSING AND RESOLVING REQUESTS FOR ACCESS TO SENSITIVE UNCLASSIFIED NON-SAFEGUARDS INFORMATION AND SAFEGUARDS INFORMATION IN THIS PROCEEDING Day Event/activity 0 ............... Publication of Federal Register notice of hearing and opportunity to petition for leave to intervene, including order with instructions for access requests. Deadline for submitting requests for access to Sensitive Unclassified Non-Safeguards Information (SUNSI) and/or Safeguards Information (SGI) with information: supporting the standing of a potential party identified by name and address; describing the need for the information in order for the potential party to participate meaningfully in an adjudicatory proceeding; demonstrating that access should be granted (e.g., showing technical competence for access to SGI); and, for SGI, including application fee for fingerprint/background check. Deadline for submitting petition for intervention containing: (i) Demonstration of standing; (ii) all contentions whose formulation does not require access to SUNSI and/or SGI (+25 Answers to petition for intervention; +7 petitioner/requestor reply). Nuclear Regulatory Commission (NRC) staff informs the requester of the staff’s determination whether the request for access provides a reasonable basis to believe standing can be established and shows (1) need for SUNSI or (2) need to know for SGI. (For SUNSI, NRC staff also informs any party to the proceeding whose interest independent of the proceeding would be harmed by the release of the information.) If NRC staff makes the finding of need for SUNSI and likelihood of standing, NRC staff begins document processing (preparation of redactions or review of redacted documents). If NRC staff makes the finding of need to know for SGI and likelihood of standing, NRC staff begins background check (including fingerprinting for a criminal history records check), information processing (preparation of redactions or review of redacted documents), and readiness inspections. 10 ............. 60 ............. 20 ............. jlentini on DSKJ8SOYB1PROD with NOTICES 25 30 ............. 40 ............. 190 ........... Deadline for NRC staff reply to motions to reverse NRC staff determination(s). (Receipt +30) If NRC staff finds standing and need for SUNSI, deadline for NRC staff to complete information processing and file motion for Protective Order and draft Non-Disclosure Affidavit. Deadline for applicant/licensee to file Non-Disclosure Agreement for SUNSI. (Receipt +180) If NRC staff finds standing, need to know for SGI, and trustworthiness and reliability, deadline for NRC staff to file motion for Protective Order and draft Non-disclosure Affidavit (or to make a determination that the proposed recipient of SGI is not trustworthy or reliable). Note: Before the Office of Administration makes an adverse determination regarding access to SGI, the proposed recipient must be provided an opportunity to correct or explain information. 7 Requestors should note that the filing requirements of the NRC’s E-Filing Rule (72 FR 49139; August 28, 2007) apply to appeals of NRC VerDate Mar<15>2010 16:04 Jul 23, 2010 Jkt 220001 staff determinations (because they must be served on a presiding officer or the Commission, as PO 00000 Frm 00086 Fmt 4703 Sfmt 4703 applicable), but not to the initial SUNSI/SGI request submitted to the NRC staff under these procedures. E:\FR\FM\26JYN1.SGM 26JYN1 Federal Register / Vol. 75, No. 142 / Monday, July 26, 2010 / Notices 43571 ATTACHMENT 1—GENERAL TARGET SCHEDULE FOR PROCESSING AND RESOLVING REQUESTS FOR ACCESS TO SENSITIVE UNCLASSIFIED NON-SAFEGUARDS INFORMATION AND SAFEGUARDS INFORMATION IN THIS PROCEEDING—Continued Day Event/activity 205 ........... Deadline for petitioner to seek reversal of a final adverse NRC staff trustworthiness or reliability determination either before the presiding officer or another designated officer under 10 CFR 2.705(c)(3)(iv). If access granted: Issuance of presiding officer or other designated officer decision on motion for protective order for access to sensitive information (including schedule for providing access and submission of contentions) or decision reversing a final adverse determination by the NRC staff. Deadline for filing executed Non-Disclosure Affidavits. Access provided to SUNSI and/or SGI consistent with decision issuing the protective order. Deadline for submission of contentions whose development depends upon access to SUNSI and/or SGI. However, if more than 25 days remain between the petitioner’s receipt of (or access to) the information and the deadline for filing all other contentions (as established in the notice of hearing or opportunity for hearing), the petitioner may file its SUNSI or SGI contentions by that later deadline. (Contention receipt +25) Answers to contentions whose development depends upon access to SUNSI and/or SGI. (Answer receipt +7) Petitioner/Intervenor reply to answers. Decision on contention admission. A .............. A + 3 ........ A + 28 ...... A + 53 ...... A + 60 ...... >A + 60 .... burnup to as high as 62 GWD/MTU. The licensee has procedures in place to ensure that maximum rod burnup will not exceed 62 GWD/MTU. The proposed action is in accordance with the licensee’s application dated October 29, 2009. [FR Doc. 2010–18221 Filed 7–23–10; 8:45 am] BILLING CODE 7590–01–P NUCLEAR REGULATORY COMMISSION [Docket Nos. 50–413 and 50–414; NRC– 2010–0260] The Need for the Proposed Action Duke Energy Carolinas, LLC; Catawba Nuclear Station, Units 1 and 2; Environmental Assessment And Finding of No Significant Impact The U.S. Nuclear Regulatory Commission (NRC) is considering issuance of amendments to Renewed Facility Operating License No. NPF–35 and Renewed Facility Operating License No. NPF–52, issued to Duke Energy Carolinas, LLC (the licensee), for operation of the Catawba Nuclear Station, Units 1 and 2 (Catawba 1 and 2), respectively, located in York County, South Carolina, in accordance with Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Section 50.90. In accordance with 10 CFR 51.21, the NRC performed an environmental assessment documenting its findings. The NRC concluded that the proposed action would have no significant environmental impact. Environmental Assessment jlentini on DSKJ8SOYB1PROD with NOTICES Identification of the Proposed Action The proposed action would revise the Renewed Facility Operating Licenses by removing a condition in Appendix B of the Renewed Facility Operating Licenses for Catawba 1 and 2 which had limited the peak rod average burnup to 60 gigawatt-days per metric ton uranium (GWD/MTU) until completion of an NRC environmental assessment supporting an increased limit. The proposed action would allow an increase of the maximum rod average VerDate Mar<15>2010 16:04 Jul 23, 2010 Jkt 220001 The proposed action to delete the license condition for fuel burnup is needed to allow a higher maximum rod average burnup of 62 GWD/MTU, which would allow for more effective fuel management. If the amendment is not approved, the licensee will not be provided the opportunity to increase maximum rod average burnup to as high as 62 GWD/MTU and allow fuel management flexibility. Environmental Impacts of the Proposed Action In this environmental assessment regarding the impacts of the use of extended burnup fuel beyond 60 GWD/ MTU, the Commission is relying on the results of the updated study conducted for the NRC by the Pacific Northwest National Laboratory (PNNL), entitled ‘‘Environmental Effects of Extending Fuel Burnup Above 60 GWD/MTU’’ (NUREG/CR–6703, PNNL–13257, January 2001). Environmental impacts of high burnup fuel up to 75 GWD/MTU were evaluated in the study, but some aspects of the review were limited to evaluating the impacts of the extended burnup up to 62 GWD/MTU, because of the need for additional data on the effect of extended burnup on gap release fractions. All the aspects of the fuelcycle were considered during the study, from mining, milling, conversion, enrichment and fabrication through normal reactor operation, transportation, waste management, and storage of spent fuel. PO 00000 Frm 00087 Fmt 4703 Sfmt 4703 The amendment would allow Catawba 1 and 2 to extend lead rod average burnup to 62 GWD/MTU. The NRC staff has completed its evaluation of the proposed action and concludes that such changes would not adversely affect plant safety, and would have no adverse affect on the probability of any accident. For the accidents that involve damage or melting of the fuel in the reactor core, fuel rod integrity has been shown to be unaffected by extended burnup under consideration; therefore, the probability of an accident will not be affected. For the accidents in which core remains intact, the increased burnup may slightly change the mix of fission products that could be released in the event of a serious accident, but because the radionuclides contributing most to the dose are short-lived, increased burnup would not have an effect on the consequences of a serious accident beyond the previously evaluated accident scenarios. Increases in projected dose consequences of postulated accidents associated with fuel burnup up to 62 GWD/MTU are not considered significant, and remain well below regulatory limits. Regulatory limits on radiological effluent releases are independent of burnup. The requirements of 10 CFR Part 20, 10 CFR 50.36a, and Appendix I to 10 CFR Part 50 ensure that routine releases of gaseous, liquid or solid radiological effluents to unrestricted areas is kept ‘‘As Low As is Reasonably Achievable.’’ Therefore, NRC staff concludes that during routine operations, there would be no significant increase in the amount of gaseous radiological effluents released into the environment as a result of the proposed action, nor will there be a significant increase in the amount of liquid radiological effluents or solid E:\FR\FM\26JYN1.SGM 26JYN1

Agencies

[Federal Register Volume 75, Number 142 (Monday, July 26, 2010)]
[Notices]
[Pages 43566-43571]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-18221]


=======================================================================
-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Facility Operating License No. R-70; Docket No. 50-166; NRC-2010-0250]


University of Maryland; Notice of Acceptance for Docketing and 
Opportunity for Hearing on the Application Regarding Renewal of 
Facility Operating License for an Additional 20-Year Period for the 
Maryland University Training Reactor and Order Imposing Procedures for 
Access to Safeguards Information and Sensitive Unclassified Non-
Safeguards Information

AGENCY: Nuclear Regulatory Commission.

ACTION: Notice of acceptance for docketing.

-----------------------------------------------------------------------

FOR FURTHER INFORMATION CONTACT: Spyros A. Traiforos, Project Manager, 
Research and Test Reactors Projects Branch, Division of Policy and 
Rulemaking, Office of Nuclear Reactor Regulation, U.S. Nuclear 
Regulatory Commission, Rockville, MD 20852. Telephone: (301) 415-3965; 
fax number: (301) 415-1032; e-mail: Spyros.Traiforos@nrc.gov.

SUPPLEMENTARY INFORMATION: 

I. Introduction

    The U.S. Nuclear Regulatory Commission (NRC) is considering an 
application for the renewal of Facility Operating License No. R-70 
(``Application''), which currently authorizes the University of 
Maryland (the licensee, UMD) to operate the Maryland University 
Training Reactor (MUTR) at a maximum steady-state thermal power of 250 
kilowatts (kW). The renewed license would authorize the applicant to 
operate the MUTR up to a steady-state thermal power of 250 kW for an 
additional 20 years from the date of issuance.
    By letter dated May 12, 2000, as supplemented by letters dated June 
7, August 4, September 17, and October 7, 2004; April 18, 2005, April 
25 (two letters), August 28 (two letters), November 9, and December 18, 
2006; and May 27, 2010, the licensee submitted an application to the 
NRC filed pursuant to Title 10 of the Code of Federal Regulations (10 
CFR) Section 50.51(a), to renew Facility Operating License No. R-70 for 
the MUTR.
    The application contains sensitive unclassified non-safeguards 
information (SUNSI) and Safeguards Information (SGI).
    Based on its initial review of the application and the supplemental 
information, the Commission's staff determined that UMD submitted 
sufficient information in accordance with 10 CFR 50.33 and 10 CFR 50.34 
so that the application is acceptable for docketing. The current Docket 
No. 50-166 for Facility Operating License No. R-70 will be retained. 
The docketing of the renewal application does not preclude requests for 
additional information as the review proceeds, nor does it predict 
whether the Commission will grant or deny the application. Prior to a 
decision to renew the license, the Commission will make the findings 
required by the Atomic Energy Act of 1954, as amended (the Act), and 
the Commission's rules and regulations.

II. Opportunity To Request a Hearing or Petition to Intervene

    Within 60 days of this notice, any person(s) whose interest may be 
affected may file a request for hearing/petition to intervene. As 
required by 10 CFR 2.309, a petition for leave to intervene shall set 
forth with particularity the interest of the petitioner/requestor in 
the proceeding, and how that interest may be affected by the results of 
the proceeding. The petition should specifically explain the reasons 
why intervention should be permitted with particular reference to the 
following general requirements: (1) The name, address and telephone 
number of the requestor or petitioner; (2) the nature of the 
requestor's/petitioner's right under the Act to be made a party to the 
proceeding; (3) the nature and extent of the requestor's/petitioner's 
property, financial, or other interest in the proceeding; and (4) the 
possible effect of any decision or order which may be entered in the 
proceeding on the requestor's/petitioner's interest. The petition must 
also identify the specific contentions which the petitioner/requestor 
seeks to have litigated at the proceeding.
    Each contention must consist of a specific statement of the issue 
of law or fact to be raised or controverted. In addition, the 
petitioner/requestor shall provide a brief explanation of the bases for 
the contention and a concise statement of the alleged facts or expert 
opinion which support the contention and on which the petitioner 
intends to rely in proving the contention at the hearing. The 
petitioner must also

[[Page 43567]]

provide references to those specific sources and documents of which the 
petitioner is aware and on which the petitioner intends to rely to 
establish those facts or expert opinion. The petition must include 
sufficient information to show that a genuine dispute exists with the 
applicant on a material issue of law or fact. Contentions shall be 
limited to matters within the scope of the amendment under 
consideration. The contention must be one which, if proven, would 
entitle the petitioner/requestor to relief. A petitioner/requestor who 
fails to satisfy these requirements with respect to at least one 
contention will not be permitted to participate as a party.
    Those permitted to intervene become parties to the proceeding, 
subject to any limitations in the order granting leave to intervene, 
and have the opportunity to participate fully in the conduct of the 
hearing.
    Non-timely requests and/or petitions and contentions will not be 
entertained absent a determination by the Commission, the presiding 
officer, or the Atomic Safety and Licensing Board that the petition 
and/or request should be granted and/or the contentions should be 
admitted, based on a balancing of the factors specified in 10 CFR 
2.309(c)(1)(i)-(viii).
    A State, county, municipality, Federally-recognized Indian Tribe, 
or agencies thereof, may submit a petition to the Commission to 
participate as a party under 10 CFR 2.309(d)(2). The petition should 
state the nature and extent of the petitioner's interest in the 
proceeding. The petition should be submitted to the Commission by 
September 24, 2010. The petition must be filed in accordance with the 
filing instructions in section IV, and should meet the requirements for 
petitions for leave to intervene set forth in section III.A, except 
that State and Federally-recognized Indian Tribes do not need to 
address the standing requirements in 10 CFR 2.309(d)(1) if the facility 
is located within its boundaries. The entities listed above could also 
seek to participate in a hearing as a nonparty pursuant to 10 CFR 
2.315(c).
    Any person who does not wish, or is not qualified, to become a 
party to this proceeding may request permission to make a limited 
appearance pursuant to the provisions of 10 CFR 2.315(a). A person 
making a limited appearance may make an oral or written statement of 
position on the issues, but may not otherwise participate in the 
proceeding. A limited appearance may be made at any session of the 
hearing or at any prehearing conference, subject to such limits and 
conditions as may be imposed by the Licensing Board. Persons desiring 
to make a limited appearance are requested to inform the Secretary of 
the Commission by September 24, 2010.

III. Electronic Submissions (E-Filing)

    All documents filed in NRC adjudicatory proceedings, including a 
request for hearing, a petition for leave to intervene, any motion or 
other document filed in the proceeding prior to the submission of a 
request for hearing or petition to intervene, and documents filed by 
interested governmental entities participating under 10 CFR 2.315(c), 
must be filed in accordance with the NRC E-Filing rule (72 FR 49139, 
August 28, 2007). The E-Filing process requires participants to submit 
and serve all adjudicatory documents over the Internet, or in some 
cases to mail copies on electronic storage media. Participants may not 
submit paper copies of their filings unless they seek an exemption in 
accordance with the procedures described below.
    To comply with the procedural requirements of E-Filing, at least 
ten (10) days prior to the filing deadline, the participant should 
contact the Office of the Secretary by e-mail at 
hearing.docket@nrc.gov, or by telephone at (301) 415-1677, to request 
(1) a digital ID certificate, which allows the participant (or its 
counsel or representative) to digitally sign documents and access the 
E-Submittal server for any proceeding in which it is participating; and 
(2) advise the Secretary that the participant will be submitting a 
request or petition for hearing (even in instances in which the 
participant, or its counsel or representative, already holds an NRC-
issued digital ID certificate). Based upon this information, the 
Secretary will establish an electronic docket for the hearing in this 
proceeding if the Secretary has not already established an electronic 
docket.
    Information about applying for a digital ID certificate is 
available on NRC's public Web site at https://www.nrc.gov/site-help/e-submittals/apply-certificates.html. System requirements for accessing 
the E-Submittal server are detailed in NRC's ``Guidance for Electronic 
Submission,'' which is available on the agency's public Web site at 
https://www.nrc.gov/site-help/e-submittals.html. Participants may 
attempt to use other software not listed on the Web site, but should 
note that the NRC's E-Filing system does not support unlisted software, 
and the NRC Meta System Help Desk will not be able to offer assistance 
in using unlisted software.
    If a participant is electronically submitting a document to the NRC 
in accordance with the E-Filing rule, the participant must file the 
document using the NRC's online, Web-based submission form. In order to 
serve documents through EIE, users will be required to install a Web 
browser plug-in from the NRC Web site. Further information on the Web-
based submission form, including the installation of the Web browser 
plug-in, is available on the NRC's public Web site at https://www.nrc.gov/site-help/e-submittals.html.
    Once a participant has obtained a digital ID certificate and a 
docket has been created, the participant can then submit a request for 
hearing or petition for leave to intervene. Submissions should be in 
Portable Document Format (PDF) in accordance with NRC guidance 
available on the NRC public Web site at https://www.nrc.gov/site-help/e-submittals.html. A filing is considered complete at the time the 
documents are submitted through the NRC's E-Filing system. To be 
timely, an electronic filing must be submitted to the E-Filing system 
no later than 11:59 p.m. Eastern Time on the due date. Upon receipt of 
a transmission, the E-Filing system time-stamps the document and sends 
the submitter an e-mail notice confirming receipt of the document. The 
E-Filing system also distributes an e-mail notice that provides access 
to the document to the NRC Office of the General Counsel and any others 
who have advised the Office of the Secretary that they wish to 
participate in the proceeding, so that the filer need not serve the 
documents on those participants separately. Therefore, applicants and 
other participants (or their counsel or representative) must apply for 
and receive a digital ID certificate before a hearing request/petition 
to intervene is filed so that they can obtain access to the document 
via the E-Filing system.
    A person filing electronically using the agency's adjudicatory E-
Filing system may seek assistance by contacting the NRC Meta System 
Help Desk through the ``Contact Us'' link located on the NRC Web site 
at https://www.nrc.gov/site-help/e-submittals.html, by e-mail at 
MSHD.Resource@nrc.gov, or by a toll-free call at (866) 672-7640. The 
NRC Meta System Help Desk is available between 8 a.m. and 8 p.m., 
Eastern Time, Monday through Friday, excluding government holidays.
    Participants who believe that they have a good cause for not 
submitting

[[Page 43568]]

documents electronically must file an exemption request, in accordance 
with 10 CFR 2.302(g), with their initial paper filing requesting 
authorization to continue to submit documents in paper format. Such 
filings must be submitted by: (1) First class mail addressed to the 
Office of the Secretary of the Commission, U.S. Nuclear Regulatory 
Commission, Washington, DC 20555-0001, Attention: Rulemaking and 
Adjudications Staff; or (2) courier, express mail, or expedited 
delivery service to the Office of the Secretary, Sixteenth Floor, One 
White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852, 
Attention: Rulemaking and Adjudications Staff. Participants filing a 
document in this manner are responsible for serving the document on all 
other participants. Filing is considered complete by first-class mail 
as of the time of deposit in the mail, or by courier, express mail, or 
expedited delivery service upon depositing the document with the 
provider of the service. A presiding officer, having granted an 
exemption request from using E-Filing, may require a participant or 
party to use E-Filing if the presiding officer subsequently determines 
that the reason for granting the exemption from use of E-Filing no 
longer exists.
    Documents submitted in adjudicatory proceedings will appear in 
NRC's electronic hearing docket which is available to the public at 
https://ehd.nrc.gov/EHD_Proceeding/home.asp, unless excluded pursuant 
to an order of the Commission, or the presiding officer. Participants 
are requested not to include personal privacy information, such as 
social security numbers, home addresses, or home phone numbers in their 
filings, unless an NRC regulation or other law requires submission of 
such information. With respect to copyrighted works, except for limited 
excerpts that serve the purpose of the adjudicatory filings and would 
constitute a Fair Use application, participants are requested not to 
include copyrighted materials in their submission. Petitions for leave 
to intervene must be filed no later than 60 days from July 26, 2010. 
Non-timely filings will not be entertained absent a determination by 
the presiding officer that the petition or request should be granted or 
the contentions should be admitted, based on a balancing of the factors 
specified in 10 CFR 2.309(c)(1)(i)-(viii).
    The NRC maintains an Agencywide Documents Access and Management 
System (ADAMS), which provides text and image files of NRC's public 
documents. Detailed guidance which the NRC uses to review applications 
for the renewal of non-power reactor licenses can be found in the 
documents NUREG-1537, entitled ``Guidelines for Preparing and Reviewing 
Applications for the Licensing of Non-Power Reactors'' and the 
``Interim Staff Guidance on the Streamlined Review Process for License 
Renewal for Research Reactors'' (ISG) which can be obtained from the 
Commission's public document room (PDR). The detailed review guidance 
(NUREG-1537 and the ISG) may be accessed through the NRC's Public 
Electronic Reading Room on the Internet at https://www.nrc.gov/reading-rm/adams.html under ADAMS Accession No. ML042430055 for part one of 
NUREG-1537, ADAMS Accession No. ML042430048 for part two of NUREG-1537 
and ADAMS Accession No. ML092240244 for the ISG. Copies of the 
application to renew the facility license from the licensee are 
available for public inspection at the Commission's PDR, located at One 
White Flint North, 11555 Rockville Pike (first floor), Rockville, 
Maryland 20852-2738. The initial application and other related 
documents may be accessed through the NRC's Public Electronic Reading 
Room, at the address mentioned above, under ADAMS Accession Nos.: May 
12, 2000, (ML072210862), June 7, 2004, (ML101970211), August 4, 2004, 
(ML042240227), September 17, 2004, (ML042940317), October 7, 2004, 
(ML042940408), April 18, 2005, (ML051160054), April 25, 2006, (two 
letters ML061250233 and ML061280383), August 28, 2006, (two letters 
ML101480914 and ML101970209), November 9, 2006, (ML101970210), December 
18, 2006, (ML101480913) and May 27, 2010 (ML101670413).
    Persons who do not have access to ADAMS, or who encounter problems 
in accessing the documents located in ADAMS, should contact the NRC PDR 
Reference staff by telephone at 1-800-397-4209, or (301) 415-4737, or 
by e-mail to pdr.resource@nrc.gov.

Order Imposing Procedures for Access to Sensitive Unclassified Non-
Safeguards Information and Safeguards Information for Contention 
Preparation

    A. This Order contains instructions regarding how potential parties 
to this proceeding may request access to documents containing sensitive 
unclassified information (including SUNSI and SGI). Requirements for 
access to SGI are primarily set forth in 10 CFR Parts 2 and 73. Nothing 
in this Order is intended to conflict with the SGI regulations.
    B. Within 10 days after publication of this notice of hearing and 
opportunity to petition for leave to intervene, any potential party who 
believes access to SUNSI or SGI is necessary to respond to this notice 
may request access to SUNSI or SGI. A ``potential party'' is any person 
who intends to participate as a party by demonstrating standing and 
filing an admissible contention under 10 CFR 2.309. Requests for access 
to SUNSI or SGI submitted later than 10 days after publication will not 
be considered absent a showing of good cause for the late filing, 
addressing why the request could not have been filed earlier.
    C. The requestor shall submit a letter requesting permission to 
access SUNSI, SGI, or both to the Office of the Secretary, U.S. Nuclear 
Regulatory Commission, Washington, DC 20555-0001, Attention: 
Rulemakings and Adjudications Staff, and provide a copy to the 
Associate General Counsel for Hearings, Enforcement and Administration, 
Office of the General Counsel, Washington, DC 20555-0001. The expedited 
delivery or courier mail address for both offices is: U.S. Nuclear 
Regulatory Commission, 11555 Rockville Pike, Rockville, Maryland 20852. 
The e-mail address for the Office of the Secretary and the Office of 
the General Counsel are Hearing.Docket@nrc.gov and 
OGCmailcenter@nrc.gov, respectively.\1\ The request must include the 
following information:
---------------------------------------------------------------------------

    \1\ While a request for hearing or petition to intervene in this 
proceeding must comply with the filing requirements of the NRC's 
``E-Filing Rule,'' the initial request to access SUNSI and/or SGI 
under these procedures should be submitted as described in this 
paragraph.
---------------------------------------------------------------------------

    (1) A description of the licensing action with a citation to this 
Federal Register notice;
    (2) The name and address of the potential party and a description 
of the potential party's particularized interest that could be harmed 
by the action identified in C.(1);
    (3) If the request is for SUNSI, the identity of the individual or 
entity requesting access to SUNSI and the requestor's basis for the 
need for the information in order to meaningfully participate in this 
adjudicatory proceeding. In particular, the request must explain why 
publicly-available versions of the information requested would not be 
sufficient to provide the basis and specificity for a proffered 
contention;
    (4) If the request is for SGI, the identity of each individual who 
would have access to SGI if the request is granted, including the 
identity of any expert, consultant, or assistant who will

[[Page 43569]]

aid the requestor in evaluating the SGI. In addition, the request must 
contain the following information:
    (a) A statement that explains each individual's ``need to know'' 
the SGI, as required by 10 CFR 73.2 and 10 CFR 73.22(b)(1). Consistent 
with the definition of ``need to know'' as stated in 10 CFR 73.2, the 
statement must explain:
    (i) Specifically why the requestor believes that the information is 
necessary to enable the requestor to proffer and/or adjudicate a 
specific contention in this proceeding; \2\ and
---------------------------------------------------------------------------

    \2\ Broad SGI requests under these procedures are unlikely to 
meet the standard for need to know; furthermore, staff redaction of 
information from requested documents before their release may be 
appropriate to comport with this requirement. These procedures do 
not authorize unrestricted disclosure or less scrutiny of a 
requestor's need to know than ordinarily would be applied in 
connection with an already-admitted contention or non-adjudicatory 
access to SGI.
---------------------------------------------------------------------------

    (ii) The technical competence (demonstrable knowledge, skill, 
training or education) of the requestor to effectively utilize the 
requested SGI to provide the basis and specificity for a proffered 
contention. The technical competence of a potential party or its 
counsel may be shown by reliance on a qualified expert, consultant, or 
assistant who satisfies these criteria.
    (b) A completed Form SF-85, ``Questionnaire for Non-Sensitive 
Positions'' for each individual who would have access to SGI. The 
completed Form SF-85 will be used by the Office of Administration to 
conduct the background check required for access to SGI, as required by 
10 CFR Part 2, Subpart G and 10 CFR 73.22(b)(2), to determine the 
requestor's trustworthiness and reliability. For security reasons, Form 
SF-85 can only be submitted electronically through the electronic 
questionnaire for investigations processing (e-QIP) Web site, a secure 
Web site that is owned and operated by the Office of Personnel 
Management. To obtain online access to the form, the requestor should 
contact the NRC's Office of Administration at (301) 492-3524.\3\
---------------------------------------------------------------------------

    \3\ The requestor will be asked to provide his or her full name, 
social security number, date and place of birth, telephone number, 
and e-mail address. After providing this information, the requestor 
usually should be able to obtain access to the online form within 
one business day.
---------------------------------------------------------------------------

    (c) A completed Form FD-258 (fingerprint card), signed in original 
ink, and submitted in accordance with 10 CFR 73.57(d). Copies of Form 
FD-258 may be obtained by writing the Office of Information Services, 
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, by 
calling (301) 415-7232 or (301) 492-7311, or by e-mail to 
Forms.Resource@nrc.gov. The fingerprint card will be used to satisfy 
the requirements of 10 CFR Part 2, 10 CFR 73.22(b)(1), and Section 149 
of the Atomic Energy Act of 1954, as amended, which mandates that all 
persons with access to SGI must be fingerprinted for an FBI 
identification and criminal history records check;
    (d) A check or money order payable in the amount of $ 200.00 \4\ to 
the U.S. Nuclear Regulatory Commission for each individual for whom the 
request for access has been submitted, and
---------------------------------------------------------------------------

    \4\ This fee is subject to change pursuant to the Office of 
Personnel Management's adjustable billing rates.
---------------------------------------------------------------------------

    (e) If the requestor or any individual who will have access to SGI 
believes they belong to one or more of the categories of individuals 
that are exempt from the criminal history records check and background 
check requirements in 10 CFR 73.59, the requestor should also provide a 
statement identifying which exemption the requestor is invoking and 
explaining the requestor's basis for believing that the exemption 
applies. While processing the request, the Office of Administration, 
Personnel Security Branch, will make a final determination whether the 
claimed exemption applies. Alternatively, the requestor may contact the 
Office of Administration for an evaluation of their exemption status 
prior to submitting their request. Persons who are exempt from the 
background check are not required to complete the SF-85 or Form FD-258; 
however, all other requirements for access to SGI, including the need 
to know, are still applicable.

    Note: Copies of documents and materials required by paragraphs 
C.(4)(b), (c), and (d) of this Order must be sent to the following 
address:
    Office of Administration, U.S. Nuclear Regulatory Commission, 
Personnel Security Branch, Mail Stop TWB-05-B32M, Washington, DC 
20555-0001.

    These documents and materials should not be included with the 
request letter to the Office of the Secretary, but the request letter 
should state that the forms and fees have been submitted as required 
above.
    D. To avoid delays in processing requests for access to SGI, the 
requestor should review all submitted materials for completeness and 
accuracy (including legibility) before submitting them to the NRC. The 
NRC will return incomplete packages to the sender without processing.
    E. Based on an evaluation of the information submitted under 
paragraphs C.(3) or C.(4) above, as applicable, the NRC staff will 
determine within 10 days of receipt of the request whether:
    (1) There is a reasonable basis to believe the petitioner is likely 
to establish standing to participate in this NRC proceeding; and
    (2) The requestor has established a legitimate need for access to 
SUNSI or need to know the SGI requested.
    F. For requests for access to SUNSI, if the NRC staff determines 
that the requestor satisfies both E.(1) and E.(2) above, the NRC staff 
will notify the requestor in writing that access to SUNSI has been 
granted. The written notification will contain instructions on how the 
requestor may obtain copies of the requested documents, and any other 
conditions that may apply to access to those documents. These 
conditions may include, but are not limited to, the signing of a Non-
Disclosure Agreement or Affidavit, or Protective Order \5\ setting 
forth terms and conditions to prevent the unauthorized or inadvertent 
disclosure of SUNSI by each individual who will be granted access to 
SUNSI.
---------------------------------------------------------------------------

    \5\ Any motion for Protective Order or draft Non-Disclosure 
Affidavit or Agreement for SUNSI must be filed with the presiding 
officer or the Chief Administrative Judge if the presiding officer 
has not yet been designated, within 30 days of the deadline for the 
receipt of the written access request.
---------------------------------------------------------------------------

    G. For requests for access to SGI, if the NRC staff determines that 
the requestor has satisfied both E.(1) and E.(2) above, the Office of 
Administration will then determine, based upon completion of the 
background check, whether the proposed recipient is trustworthy and 
reliable, as required for access to SGI by 10 CFR 73.22(b). If the 
Office of Administration determines that the individual or individuals 
are trustworthy and reliable, the NRC will promptly notify the 
requestor in writing. The notification will provide the names of 
approved individuals as well as the conditions under which the SGI will 
be provided. Those conditions may include, but not be limited to, the 
signing of a Non-Disclosure Agreement or Affidavit, or Protective Order 
\6\ by each individual who will be granted access to SGI.
---------------------------------------------------------------------------

    \6\ Any motion for Protective Order or draft Non-Disclosure 
Affidavit or Agreement for SGI must be filed with the presiding 
officer or the Chief Administrative Judge if the presiding officer 
has not yet been designated, within 180 days of the deadline for the 
receipt of the written access request.
---------------------------------------------------------------------------

    H. Release and Storage of SGI. Prior to providing SGI to the 
requestor, the NRC staff will conduct (as necessary) an inspection to 
confirm that the recipient's information protection system is 
sufficient to satisfy the requirements of 10 CFR 73.22. Alternatively, 
recipients may opt to

[[Page 43570]]

view SGI at an approved SGI storage location rather than establish 
their own SGI protection program to meet SGI protection requirements.
    I. Filing of Contentions. Any contentions in these proceedings that 
are based upon the information received as a result of the request made 
for SUNSI or SGI must be filed by the requestor no later than 25 days 
after the requestor is granted access to that information. However, if 
more than 25 days remain between the date the petitioner is granted 
access to the information and the deadline for filing all other 
contentions (as established in the notice of hearing or opportunity for 
hearing), the petitioner may file its SUNSI or SGI contentions by that 
later deadline.
    J. Review of Denials of Access.
    (1) If the request for access to SUNSI or SGI is denied by the NRC 
staff either after a determination on standing and requisite need, or 
after a determination on trustworthiness and reliability, the NRC staff 
shall immediately notify the requestor in writing, briefly stating the 
reason or reasons for the denial.
    (2) Before the Office of Administration makes an adverse 
determination regarding the proposed recipient(s) trustworthiness and 
reliability for access to SGI, the Office of Administration, in 
accordance with 10 CFR 2.705(c)(3)(iii), must provide the proposed 
recipient(s) any records that were considered in the trustworthiness 
and reliability determination, including those required to be provided 
under 10 CFR 73.57(e)(1), so that the proposed recipient(s) have an 
opportunity to correct or explain the record.
    (3) The requestor may challenge the NRC staff's adverse 
determination with respect to access to SUNSI by filing a challenge 
within 5 days of receipt of that determination with: (a) The presiding 
officer designated in this proceeding; (b) if no presiding officer has 
been appointed, the Chief Administrative Judge, or if he or she is 
unavailable, another administrative judge, or an administrative law 
judge with jurisdiction pursuant to 10 CFR 2.318(a); or (c) if another 
officer has been designated to rule on information access issues, with 
that officer.
    (4) The requestor may challenge the NRC staff's or Office of 
Administration's adverse determination with respect to access to SGI by 
filing a request for review in accordance with 10 CFR 2.705(c)(3)(iv). 
Further appeals of decisions under this paragraph must be made pursuant 
to 10 CFR 2.311.
    K. Review of Grants of Access. A party other than the requestor may 
challenge an NRC staff determination granting access to SUNSI or SGI 
whose release would harm that party's interest independent of the 
proceeding. Such a challenge must be filed with the Chief 
Administrative Judge within 5 days of the notification by the NRC staff 
of its grant of access.
    If challenges to the NRC staff determinations are filed, these 
procedures give way to the normal process for litigating disputes 
concerning access to information. The availability of interlocutory 
review by the Commission of orders ruling on such NRC staff 
determinations (whether granting or denying access) is governed by 10 
CFR 2.311.\7\
---------------------------------------------------------------------------

    \7\ Requestors should note that the filing requirements of the 
NRC's E-Filing Rule (72 FR 49139; August 28, 2007) apply to appeals 
of NRC staff determinations (because they must be served on a 
presiding officer or the Commission, as applicable), but not to the 
initial SUNSI/SGI request submitted to the NRC staff under these 
procedures.
---------------------------------------------------------------------------

    L. The Commission expects that the NRC staff and presiding officers 
(and any other reviewing officers) will consider and resolve requests 
for access to SUNSI or SGI, and motions for protective orders, in a 
timely fashion in order to minimize any unnecessary delays in 
identifying those petitioners who have standing and who have propounded 
contentions meeting the specificity and basis requirements in 10 CFR 
Part 2. Attachment 1 to this Order summarizes the general target 
schedule for processing and resolving requests under these procedures.
    It is so ordered.

    Dated at Rockville, Maryland this 19th day of July 2010.

    For the Commission.
Annette L. Vietti-Cook,
Secretary of the Commission.

   Attachment 1--General Target Schedule for Processing and Resolving
Requests for Access to Sensitive Unclassified Non-Safeguards Information
              and Safeguards Information in this Proceeding
------------------------------------------------------------------------
          Day                            Event/activity
------------------------------------------------------------------------
0.....................  Publication of Federal Register notice of
                         hearing and opportunity to petition for leave
                         to intervene, including order with instructions
                         for access requests.
10....................  Deadline for submitting requests for access to
                         Sensitive Unclassified Non-Safeguards
                         Information (SUNSI) and/or Safeguards
                         Information (SGI) with information: supporting
                         the standing of a potential party identified by
                         name and address; describing the need for the
                         information in order for the potential party to
                         participate meaningfully in an adjudicatory
                         proceeding; demonstrating that access should be
                         granted (e.g., showing technical competence for
                         access to SGI); and, for SGI, including
                         application fee for fingerprint/background
                         check.
60....................  Deadline for submitting petition for
                         intervention containing: (i) Demonstration of
                         standing; (ii) all contentions whose
                         formulation does not require access to SUNSI
                         and/or SGI (+25 Answers to petition for
                         intervention; +7 petitioner/requestor reply).
20....................  Nuclear Regulatory Commission (NRC) staff
                         informs the requester of the staff's
                         determination whether the request for access
                         provides a reasonable basis to believe standing
                         can be established and shows (1) need for SUNSI
                         or (2) need to know for SGI. (For SUNSI, NRC
                         staff also informs any party to the proceeding
                         whose interest independent of the proceeding
                         would be harmed by the release of the
                         information.) If NRC staff makes the finding of
                         need for SUNSI and likelihood of standing, NRC
                         staff begins document processing (preparation
                         of redactions or review of redacted documents).
                         If NRC staff makes the finding of need to know
                         for SGI and likelihood of standing, NRC staff
                         begins background check (including
                         fingerprinting for a criminal history records
                         check), information processing (preparation of
                         redactions or review of redacted documents),
                         and readiness inspections.
25
30....................  Deadline for NRC staff reply to motions to
                         reverse NRC staff determination(s).
40....................  (Receipt +30) If NRC staff finds standing and
                         need for SUNSI, deadline for NRC staff to
                         complete information processing and file motion
                         for Protective Order and draft Non-Disclosure
                         Affidavit. Deadline for applicant/licensee to
                         file Non-Disclosure Agreement for SUNSI.
190...................  (Receipt +180) If NRC staff finds standing, need
                         to know for SGI, and trustworthiness and
                         reliability, deadline for NRC staff to file
                         motion for Protective Order and draft Non-
                         disclosure Affidavit (or to make a
                         determination that the proposed recipient of
                         SGI is not trustworthy or reliable). Note:
                         Before the Office of Administration makes an
                         adverse determination regarding access to SGI,
                         the proposed recipient must be provided an
                         opportunity to correct or explain information.

[[Page 43571]]

 
205...................  Deadline for petitioner to seek reversal of a
                         final adverse NRC staff trustworthiness or
                         reliability determination either before the
                         presiding officer or another designated officer
                         under 10 CFR 2.705(c)(3)(iv).
A.....................  If access granted: Issuance of presiding officer
                         or other designated officer decision on motion
                         for protective order for access to sensitive
                         information (including schedule for providing
                         access and submission of contentions) or
                         decision reversing a final adverse
                         determination by the NRC staff.
A + 3.................  Deadline for filing executed Non-Disclosure
                         Affidavits. Access provided to SUNSI and/or SGI
                         consistent with decision issuing the protective
                         order.
A + 28................  Deadline for submission of contentions whose
                         development depends upon access to SUNSI and/or
                         SGI. However, if more than 25 days remain
                         between the petitioner's receipt of (or access
                         to) the information and the deadline for filing
                         all other contentions (as established in the
                         notice of hearing or opportunity for hearing),
                         the petitioner may file its SUNSI or SGI
                         contentions by that later deadline.
A + 53................  (Contention receipt +25) Answers to contentions
                         whose development depends upon access to SUNSI
                         and/or SGI.
A + 60................  (Answer receipt +7) Petitioner/Intervenor reply
                         to answers.
>A + 60...............  Decision on contention admission.
------------------------------------------------------------------------