Transcontinental Gas Pipe Line Company, LLC; Notice of Intent To Prepare an Environmental Assessment for the Planned Mid-Atlantic Connector Expansion Project, Request for Comments on Environmental Issues, and Notice of Public Scoping Meeting, 42738-42740 [2010-17885]
Download as PDF
42738
Federal Register / Vol. 75, No. 140 / Thursday, July 22, 2010 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. PF10–16–000]
Transcontinental Gas Pipe Line
Company, LLC; Notice of Intent To
Prepare an Environmental Assessment
for the Planned Mid-Atlantic Connector
Expansion Project, Request for
Comments on Environmental Issues,
and Notice of Public Scoping Meeting
sroberts on DSKD5P82C1PROD with NOTICES
July 15, 2010.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Mid-Atlantic Connector Expansion
Project involving construction and
operation of facilities by
Transcontinental Gas Pipe Line
Company, LLC (Transco) in Fairfax,
Prince William, Pittsylvania, and
Fluvanna Counties, Virginia. This EA
will be used by the Commission in its
decision-making process to determine
whether the project is in the public
convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
Your input will help the Commission
staff determine what issues need to be
evaluated in the EA. Please note that the
scoping period will close on August 16,
2010.
Comments may be submitted in
written form or verbally. Further details
on how to submit written comments are
provided in the Public Participation
section of this notice. In lieu of or in
addition to sending written comments,
we invite you to attend the public
scoping meeting scheduled as follows:
FERC Public Scoping Meeting, MidAtlantic Connector Expansion Project,
August 4, 2010, 7 p.m., Virginia Run
Community Center, 15355 Wetherburn
Court, Centerville, VA 20120.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives are
asked to notify their constituents of this
planned project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, you may be contacted by a
pipeline company representative about
the acquisition of an easement to
construct, operate, and maintain the
planned facilities. The company would
seek to negotiate a mutually acceptable
agreement. However, if the project is
approved by the Commission, that
VerDate Mar<15>2010
18:46 Jul 21, 2010
Jkt 220001
approval conveys with it the right of
eminent domain. Therefore, if easement
negotiations fail to produce an
agreement, the pipeline company could
initiate condemnation proceedings
where compensation would be
determined in accordance with State
law.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ is available for viewing on
the FERC Web site (https://
www.ferc.gov). This fact sheet addresses
a number of typically-asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings.
Summary of the Planned Project
Transco’s planned Mid-Atlantic
Connector Expansion Project would
increase capacity by 142,000
dekatherms per day from Transco’s
Cascade Creek Interconnect in
Rockingham County, North Carolina, to
delivery points in Virginia and
Maryland. The project would consist of
the following facilities in Virginia:
• Construction of about 1.44 miles of
new 42-inch-diameter pipeline loop 1
(Mainline D) and appurtenant facilities
from Transco’s Compressor Station 185
in Prince William County to milepost
(MP) 1584.83 in Fairfax County;
• Replacement of about 1.35 miles of
Mainline B pipeline with the new
Mainline D pipeline from MP 1584.83 to
MP 1586.17 in Fairfax County;
• New and replacement compressor
units at Transco’s existing Compressor
Stations 165 and 175 in Pittsylvania and
Fluvanna Counties, respectively; and
• Relocation of a pig launcher 2 in
Fairfax County to Transco’s existing
Compressor Station 185 in Prince
William County.
The general location of the project
facilities is shown in appendix 1.3
Land Requirements for Construction
The new pipeline loop and pipeline
replacement would primarily be
installed within Transco’s existing
rights-of-way. Installation of the new
Mainline D loop would be between
1 A pipeline loop is constructed parallel to an
existing pipeline to increase capacity.
2 A ‘‘pig’’ is a tool that is inserted into and moves
through the pipeline, and is used for cleaning the
pipeline, internal inspections, or other purposes.
3 The appendices referenced in this notice are not
being printed in the Federal Register. Copies of
appendices were sent to all those receiving this
notice in the mail and are available at https://
www.ferc.gov using the link called ‘‘eLibrary’’ or
from the Commission’s Public Reference Room, 888
First Street, NE., Washington, DC 20426, or call
(202) 502–8371. For instructions on connecting to
eLibrary, refer to the last page of this notice.
PO 00000
Frm 00061
Fmt 4703
Sfmt 4703
Transco’s Mainline B and C pipeline
rights-of-way. Transco would replace
the Mainline B pipeline with the new
Mainline D pipeline between Transco’s
existing Mainline A and C pipelines.
Transco would install the new Mainline
D pipeline within the same trench of
Mainline B. Following construction,
permanent operation of the pipelines
would remain within Transco’s existing
rights-of-way. The modifications at
Compressor Stations 165 and 175 would
take place entirely within the existing
fenced stations.
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us 4 to
discover and address concerns the
public may have about proposals. This
process is referred to as scoping. The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
notice, the Commission requests public
comments on the scope of the issues to
address in the EA. All comments
received will be considered during the
preparation of the EA.
In the EA we will discuss impacts that
could occur as a result of the
construction and operation of the
planned project under these general
headings:
• Geology and soils;
• Land use;
• Water resources, fisheries, and
wetlands;
• Cultural resources;
• Vegetation and wildlife;
• Air quality and noise;
• Endangered and threatened species;
and
• Public safety.
We will also evaluate possible
alternatives to the planned project or
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
Although no formal application has
been filed, we have already initiated our
NEPA review under the Commission’s
pre-filing process. The purpose of the
pre-filing process is to encourage early
involvement of interested stakeholders
and to identify and resolve issues before
an application is filed with the FERC.
As part of our pre-filing review, we have
begun to contact some Federal and State
agencies to discuss their involvement in
4 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the environmental
staff of the Commission’s Office of Energy Projects.
E:\FR\FM\22JYN1.SGM
22JYN1
Federal Register / Vol. 75, No. 140 / Thursday, July 22, 2010 / Notices
the scoping process and the preparation
of the EA.
Our independent analysis of the
issues will be presented in the EA. The
EA will be placed in the public record
and, depending on the comments
received during the scoping process,
may be published and distributed to the
public. A comment period will be
allotted if the EA is published for
review. We will consider all comments
on the EA before we make our
recommendations to the Commission.
To ensure your comments are
considered, please carefully follow the
instructions in the Public Participation
section beginning on page 5.
FERC staff will be involved in
discussions with other jurisdictional
agencies to identify their issues and
concerns. These agencies include, but
are not limited to, the National Park
Service; U.S. Fish and Wildlife Service;
Virginia State Historic Preservation
Office; and Virginia Department of
Environmental Quality. With this
notice, we are asking agencies with
jurisdiction and/or special expertise
with respect to environmental issues to
formally cooperate with us in the
preparation of the EA. These agencies
may choose to participate once they
have evaluated the proposal relative to
their responsibilities. Agencies that
would like to request cooperating
agency status should follow the
instructions for filing comments
provided under the Public Participation
section of this notice.
sroberts on DSKD5P82C1PROD with NOTICES
Consultations Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations, we are using
this notice to solicit the views of the
public on the project’s potential effects
on historic properties.5 We will
document our findings on the impacts
on cultural resources and summarize
the status of consultations under section
106 of the National Historic
Preservation Act in our EA.
Currently Identified Environmental
Issues
We have already identified several
issues that we think deserve attention
based on a preliminary review of the
planned facilities and the
environmental information provided by
Transco. This preliminary list of issues
5 The Advisory Council on Historic Preservation’s
regulations are at Title 36, Code of Federal
Regulations, Part 800. Historic properties are
defined in those regulations as any prehistoric or
historic district, site, building, structure, or object
included in or eligible for inclusion in the National
Register for Historic Places.
VerDate Mar<15>2010
18:46 Jul 21, 2010
Jkt 220001
may be changed based on your
comments and our analysis.
• Impacts on residential and
commercial areas; and
• Impacts from the new loop pipeline
on the Manassas National Battlefield
Park in Manassas, Virginia.
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the project.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
The more specific your comments, the
more useful they will be. To ensure that
your comments are timely and properly
recorded, please send your comments so
that they will be received in
Washington, DC on or before August 16,
2010.
For your convenience, there are three
methods you can use to submit your
comments to the Commission. In all
instances, please reference the project
docket number (PF10–16–000) with
your submission. The Commission
encourages electronic filing of
comments and has expert eFiling staff
available to assist you at (202) 502–8258
or efiling@ferc.gov.
(1) You may file your comments
electronically by using the Quick
Comment feature, which is located at
https://www.ferc.gov under the link
called Documents and Filings. A Quick
Comment is an easy method for
interested persons to submit text-only
comments on a project;
(2) You may file your comments
electronically by using the ‘‘eFiling’’
feature that is listed under the
Documents and Filings link. eFiling
involves preparing your submission in
the same manner as you would if filing
on paper, and then saving the file on
your computer’s hard drive. You will
attach that file to your submission. New
eFiling users must first create an
account by clicking on the links called
Sign up or eRegister. You will be asked
to select the type of filing you are
making. A comment on a particular
project is considered a ‘‘Comment on a
Filing’’; or
(3) You may file a paper copy of your
comments at the following address:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Room 1A, Washington,
DC 20426.
Environmental Mailing List
The environmental mailing list
includes Federal, State, and local
government representatives and
agencies; elected officials;
PO 00000
Frm 00062
Fmt 4703
Sfmt 4703
42739
environmental and public interest
groups; Native American Tribes; other
interested parties; and local libraries
and newspapers. This list also includes
all affected landowners (as defined in
the Commission’s regulations) who are
potential right-of-way grantors, whose
property may be used temporarily for
project purposes, or who own homes
within certain distances of aboveground
facilities, and anyone who submits
comments on the project. We will
update the environmental mailing list as
the analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the planned project.
If the EA is published for distribution,
copies will be sent to the environmental
mailing list for public review and
comment. If you would prefer to receive
a paper copy of the document instead of
the CD version or would like to remove
your name from the mailing list, please
return the attached Information Request
(appendix 2).
Becoming an Intervenor
Once Transco files its application
with the Commission, you may want to
become an ‘‘intervenor’’ which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
An intervenor formally participates in
the proceeding by filing a request to
intervene. Instructions for becoming an
intervenor are included in the User’s
Guide under the ‘‘e-filing’’ link on the
Commission’s Web site. Please note that
the Commission will not accept requests
for intervenor status at this time. You
must wait until a formal application for
the project is filed with the
Commission.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site (https://www.ferc.gov) using the
eLibrary link. Click on the eLibrary link,
click on ‘‘General Search’’ and enter the
docket number, excluding the last three
digits in the Docket Number field (i.e.,
PF10–16). Be sure you have selected an
appropriate date range. For assistance,
please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free
at (866) 208–3676, or for TTY, contact
(202) 502–8659. The eLibrary link also
provides access to the texts of formal
documents issued by the Commission,
E:\FR\FM\22JYN1.SGM
22JYN1
42740
Federal Register / Vol. 75, No. 140 / Thursday, July 22, 2010 / Notices
such as orders, notices, and
rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to https://www.ferc.gov/
esubscribenow.htm.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at https://www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–17885 Filed 7–21–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. PF10–18–000]
Ryckman Creek Resources, LLC;
Notice of Intent To Prepare an
Environmental Assessment for the
Planned Ryckman Creek Storage
Project and Request for Comments on
Environmental Issues
sroberts on DSKD5P82C1PROD with NOTICES
July 15, 2010.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA). The EA
will discuss the environmental impacts
of the Ryckman Creek Storage Project
(Project) involving construction and
operation of facilities by Ryckman Creek
Resources, LLC (Ryckman Creek) in
Uinta County, Wyoming. This EA will
be used by the Commission in its
decisionmaking process to determine
whether the project is in the public
convenience and necessity.
This notice announces the opening of
the scoping process that will be used to
gather input from the public and
interested agencies on the Project. Your
input will help the Commission staff
and cooperating agencies determine
which issues need to be evaluated in the
EA. Please note that the scoping period
for this Project will close on August 16,
2010. This is not your only public input
opportunity; please refer to the
Environmental Review Process flow
chart in Appendix 1.
The FERC will be the lead Federal
agency for the preparation of the EA.
The EA will satisfy the requirements of
VerDate Mar<15>2010
18:46 Jul 21, 2010
Jkt 220001
the National Environmental Policy Act
(NEPA) and will be used by the FERC
to consider the environmental impacts
that could result if it issues Ryckman
Creek Certificate of Public Convenience
and Necessity under section 7 of the
Natural Gas Act.
The Bureau of Land Management
(BLM) is participating as a cooperating
agency in the preparation of the EA to
satisfy its respective NEPA and
planning responsibilities since the
Project would cross Federal land under
the jurisdiction of the Kemmerer Field
Office in Wyoming. Under sections 17
and 28 of the Mineral Leasing Act of
1920 (30 U.S.C. 185(f) and 226(m)), the
BLM has the authority to issue
underground gas storage agreements and
right-of-way grants for all affected
Federal lands. This would be in
accordance with title 43 Code of Federal
Regulations (CFR) parts 2800, 2880, and
5105.5 subsequent 2800, 2880, and
3160–11 Manuals, and Handbook 2801–
1. As a cooperating agency, the BLM
would adopt the EA per Title 40 CFR
1506.3 to meet its responsibilities under
NEPA in considering Ryckman Creek’s
application for a Right-of-Way Grant
and Temporary Use Permit for the
portion of the Project on Federal land,
by the Kemmerer Field Office, High
Desert District; and the issuance of an
Underground Gas Storage Agreement by
the Wyoming State Office, Reservoir
Management Group, Casper, Wyoming.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives are
asked to notify their constituents of this
planned project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, you may be contacted by a
pipeline company representative about
the acquisition of an easement to
construct, operate, and maintain the
planned facilities. The company would
seek to negotiate a mutually acceptable
agreement. However, if the project is
approved by the Commission, that
approval conveys with it the right of
eminent domain. Therefore, if easement
negotiations fail to produce an
agreement, the pipeline company could
initiate condemnation proceedings in
accordance with state law.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ is available for viewing on
the FERC Web site (https://
www.ferc.gov). This fact sheet addresses
a number of typically asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings.
PO 00000
Frm 00063
Fmt 4703
Sfmt 4703
Summary of the Planned Project
Ryckman Creek plans to convert a
partially depleted oil field, known as
the Ryckman Nugget Unit (Unit), into a
natural gas storage field offering
approximately 25 to 30 billion cubic feet
(Bcf) of high deliverability working gas
capacity in Uinta County, Wyoming.
Ryckman Creek would also construct
and operate about 3.9 miles of 16- to 20inch-diameter pipeline header system
connecting the existing Canyon Creek
Compressor Station with the Unit. The
Project will provide for the injection
and withdrawal of natural gas into and
out of the Unit via interconnects with
the existing Kern River, Questar, and
Overthrust/REX pipelines directly
adjacent to the Canyon Creek
Compressor Station. Combined, these
three interconnect pipelines provide a
total of 1.55 Bcf per day of take-away
capacity. Prior to and concurrent with
the development of the storage field,
Ryckman Creek proposes to initiate
enhanced oil recovery (EOR) operations
of the petroleum reserves remaining in
the Unit.
The Ryckman Creek Storage Project
would consist of the following facilities,
all in Unita County, Wyoming:
• Drill and complete up to five new
horizontal injection/withdrawal (I/W)
wells and convert an EOR horizontal
withdrawal well, to be drilled in the
initial EOR phase in 2010, to an I/W
well for storage operations.
• The Project would require an
additional 6,000 to 9,000 horsepower
(hp), for a total of 28,000 to 31,000 hp
at the existing Canyon Creek
Compressor Station. One or two new
electric-driven compressors would be
added and four of the existing
compressor units would be retrofitted.
• Create a central gas/liquids
separation facility (Ryckman Plant)
where all of the gas pipelines meet. It
would contain a small electric-driven
compressor to compress casing head
gas, liquids separation equipment, and
water and gas handling equipment.
• Construct a 3.9-mile-long high
pressure header pipeline between the
Ryckman Plant at the storage field and
the Canyon Creek Compressor Station.
• Construct 4 mile(s) of new 8-inchdiameter storage field I/W lines.
• Convert one previously re-entered
well to an observation well.
• Construct ancillary facilities, as
necessary to operate the Project (e.g.,
valves, meters, filtration, safety,
cleaning and inspection equipment).
• Construct temporary laydown and
temporary support facilities. To the
extent feasible, some of these would be
located within the existing disturbed,
E:\FR\FM\22JYN1.SGM
22JYN1
Agencies
[Federal Register Volume 75, Number 140 (Thursday, July 22, 2010)]
[Notices]
[Pages 42738-42740]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-17885]
[[Page 42738]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. PF10-16-000]
Transcontinental Gas Pipe Line Company, LLC; Notice of Intent To
Prepare an Environmental Assessment for the Planned Mid-Atlantic
Connector Expansion Project, Request for Comments on Environmental
Issues, and Notice of Public Scoping Meeting
July 15, 2010.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Mid-Atlantic Connector
Expansion Project involving construction and operation of facilities by
Transcontinental Gas Pipe Line Company, LLC (Transco) in Fairfax,
Prince William, Pittsylvania, and Fluvanna Counties, Virginia. This EA
will be used by the Commission in its decision-making process to
determine whether the project is in the public convenience and
necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the project. Your input will help the Commission staff
determine what issues need to be evaluated in the EA. Please note that
the scoping period will close on August 16, 2010.
Comments may be submitted in written form or verbally. Further
details on how to submit written comments are provided in the Public
Participation section of this notice. In lieu of or in addition to
sending written comments, we invite you to attend the public scoping
meeting scheduled as follows: FERC Public Scoping Meeting, Mid-Atlantic
Connector Expansion Project, August 4, 2010, 7 p.m., Virginia Run
Community Center, 15355 Wetherburn Court, Centerville, VA 20120.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives are asked to notify their constituents of this planned
project and encourage them to comment on their areas of concern.
If you are a landowner receiving this notice, you may be contacted
by a pipeline company representative about the acquisition of an
easement to construct, operate, and maintain the planned facilities.
The company would seek to negotiate a mutually acceptable agreement.
However, if the project is approved by the Commission, that approval
conveys with it the right of eminent domain. Therefore, if easement
negotiations fail to produce an agreement, the pipeline company could
initiate condemnation proceedings where compensation would be
determined in accordance with State law.
A fact sheet prepared by the FERC entitled ``An Interstate Natural
Gas Facility On My Land? What Do I Need To Know?'' is available for
viewing on the FERC Web site (https://www.ferc.gov). This fact sheet
addresses a number of typically-asked questions, including the use of
eminent domain and how to participate in the Commission's proceedings.
Summary of the Planned Project
Transco's planned Mid-Atlantic Connector Expansion Project would
increase capacity by 142,000 dekatherms per day from Transco's Cascade
Creek Interconnect in Rockingham County, North Carolina, to delivery
points in Virginia and Maryland. The project would consist of the
following facilities in Virginia:
Construction of about 1.44 miles of new 42-inch-diameter
pipeline loop \1\ (Mainline D) and appurtenant facilities from
Transco's Compressor Station 185 in Prince William County to milepost
(MP) 1584.83 in Fairfax County;
---------------------------------------------------------------------------
\1\ A pipeline loop is constructed parallel to an existing
pipeline to increase capacity.
---------------------------------------------------------------------------
Replacement of about 1.35 miles of Mainline B pipeline
with the new Mainline D pipeline from MP 1584.83 to MP 1586.17 in
Fairfax County;
New and replacement compressor units at Transco's existing
Compressor Stations 165 and 175 in Pittsylvania and Fluvanna Counties,
respectively; and
Relocation of a pig launcher \2\ in Fairfax County to
Transco's existing Compressor Station 185 in Prince William County.
---------------------------------------------------------------------------
\2\ A ``pig'' is a tool that is inserted into and moves through
the pipeline, and is used for cleaning the pipeline, internal
inspections, or other purposes.
---------------------------------------------------------------------------
The general location of the project facilities is shown in appendix
1.\3\
---------------------------------------------------------------------------
\3\ The appendices referenced in this notice are not being
printed in the Federal Register. Copies of appendices were sent to
all those receiving this notice in the mail and are available at
https://www.ferc.gov using the link called ``eLibrary'' or from the
Commission's Public Reference Room, 888 First Street, NE.,
Washington, DC 20426, or call (202) 502-8371. For instructions on
connecting to eLibrary, refer to the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
The new pipeline loop and pipeline replacement would primarily be
installed within Transco's existing rights-of-way. Installation of the
new Mainline D loop would be between Transco's Mainline B and C
pipeline rights-of-way. Transco would replace the Mainline B pipeline
with the new Mainline D pipeline between Transco's existing Mainline A
and C pipelines. Transco would install the new Mainline D pipeline
within the same trench of Mainline B. Following construction, permanent
operation of the pipelines would remain within Transco's existing
rights-of-way. The modifications at Compressor Stations 165 and 175
would take place entirely within the existing fenced stations.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
\4\ to discover and address concerns the public may have about
proposals. This process is referred to as scoping. The main goal of the
scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EA. All comments
received will be considered during the preparation of the EA.
---------------------------------------------------------------------------
\4\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the planned project under these
general headings:
Geology and soils;
Land use;
Water resources, fisheries, and wetlands;
Cultural resources;
Vegetation and wildlife;
Air quality and noise;
Endangered and threatened species; and
Public safety.
We will also evaluate possible alternatives to the planned project
or portions of the project, and make recommendations on how to lessen
or avoid impacts on the various resource areas.
Although no formal application has been filed, we have already
initiated our NEPA review under the Commission's pre-filing process.
The purpose of the pre-filing process is to encourage early involvement
of interested stakeholders and to identify and resolve issues before an
application is filed with the FERC. As part of our pre-filing review,
we have begun to contact some Federal and State agencies to discuss
their involvement in
[[Page 42739]]
the scoping process and the preparation of the EA.
Our independent analysis of the issues will be presented in the EA.
The EA will be placed in the public record and, depending on the
comments received during the scoping process, may be published and
distributed to the public. A comment period will be allotted if the EA
is published for review. We will consider all comments on the EA before
we make our recommendations to the Commission. To ensure your comments
are considered, please carefully follow the instructions in the Public
Participation section beginning on page 5.
FERC staff will be involved in discussions with other
jurisdictional agencies to identify their issues and concerns. These
agencies include, but are not limited to, the National Park Service;
U.S. Fish and Wildlife Service; Virginia State Historic Preservation
Office; and Virginia Department of Environmental Quality. With this
notice, we are asking agencies with jurisdiction and/or special
expertise with respect to environmental issues to formally cooperate
with us in the preparation of the EA. These agencies may choose to
participate once they have evaluated the proposal relative to their
responsibilities. Agencies that would like to request cooperating
agency status should follow the instructions for filing comments
provided under the Public Participation section of this notice.
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations, we are using this notice to solicit the views
of the public on the project's potential effects on historic
properties.\5\ We will document our findings on the impacts on cultural
resources and summarize the status of consultations under section 106
of the National Historic Preservation Act in our EA.
---------------------------------------------------------------------------
\5\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Historic
properties are defined in those regulations as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register for Historic
Places.
---------------------------------------------------------------------------
Currently Identified Environmental Issues
We have already identified several issues that we think deserve
attention based on a preliminary review of the planned facilities and
the environmental information provided by Transco. This preliminary
list of issues may be changed based on your comments and our analysis.
Impacts on residential and commercial areas; and
Impacts from the new loop pipeline on the Manassas
National Battlefield Park in Manassas, Virginia.
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the project. Your comments should focus on
the potential environmental effects, reasonable alternatives, and
measures to avoid or lessen environmental impacts. The more specific
your comments, the more useful they will be. To ensure that your
comments are timely and properly recorded, please send your comments so
that they will be received in Washington, DC on or before August 16,
2010.
For your convenience, there are three methods you can use to submit
your comments to the Commission. In all instances, please reference the
project docket number (PF10-16-000) with your submission. The
Commission encourages electronic filing of comments and has expert
eFiling staff available to assist you at (202) 502-8258 or
efiling@ferc.gov.
(1) You may file your comments electronically by using the Quick
Comment feature, which is located at https://www.ferc.gov under the link
called Documents and Filings. A Quick Comment is an easy method for
interested persons to submit text-only comments on a project;
(2) You may file your comments electronically by using the
``eFiling'' feature that is listed under the Documents and Filings
link. eFiling involves preparing your submission in the same manner as
you would if filing on paper, and then saving the file on your
computer's hard drive. You will attach that file to your submission.
New eFiling users must first create an account by clicking on the links
called Sign up or eRegister. You will be asked to select the type of
filing you are making. A comment on a particular project is considered
a ``Comment on a Filing''; or
(3) You may file a paper copy of your comments at the following
address: Kimberly D. Bose, Secretary, Federal Energy Regulatory
Commission, 888 First Street NE., Room 1A, Washington, DC 20426.
Environmental Mailing List
The environmental mailing list includes Federal, State, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project. We will update the environmental mailing list
as the analysis proceeds to ensure that we send the information related
to this environmental review to all individuals, organizations, and
government entities interested in and/or potentially affected by the
planned project.
If the EA is published for distribution, copies will be sent to the
environmental mailing list for public review and comment. If you would
prefer to receive a paper copy of the document instead of the CD
version or would like to remove your name from the mailing list, please
return the attached Information Request (appendix 2).
Becoming an Intervenor
Once Transco files its application with the Commission, you may
want to become an ``intervenor'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
An intervenor formally participates in the proceeding by filing a
request to intervene. Instructions for becoming an intervenor are
included in the User's Guide under the ``e-filing'' link on the
Commission's Web site. Please note that the Commission will not accept
requests for intervenor status at this time. You must wait until a
formal application for the project is filed with the Commission.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site (https://www.ferc.gov) using the eLibrary link. Click on
the eLibrary link, click on ``General Search'' and enter the docket
number, excluding the last three digits in the Docket Number field
(i.e., PF10-16). Be sure you have selected an appropriate date range.
For assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission,
[[Page 42740]]
such as orders, notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to https://www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at https://www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010-17885 Filed 7-21-10; 8:45 am]
BILLING CODE 6717-01-P