McGinnis, Inc.; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 40799 [2010-17100]
Download as PDF
Federal Register / Vol. 75, No. 134 / Wednesday, July 14, 2010 / Notices
planned generator rewinds and step-up
transformer replacements.
m. Locations of the Application: A
copy of the application is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item (h) above.
Register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. All filings must (1) Bear in all
capital letters the title ‘‘COMMENTS,’’
‘‘REPLY COMMENTS,’’
‘‘RECOMMENDATIONS,’’
‘‘PRELIMINARY TERMS AND
CONDITIONS,’’ or ‘‘PRELIMINARY
FISHWAY PRESCRIPTIONS;’’ (2) set
forth in the heading the name of the
applicant and the project number of the
application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
submitting the filing; and (4) otherwise
comply with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, recommendations, terms and
conditions or prescriptions must set
forth their evidentiary basis and
otherwise comply with the requirements
of 18 CFR 4.34(b). Agencies may obtain
copies of the application directly from
the applicant. Each filing must be
accompanied by proof of service on all
persons listed on the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
4.34(b), and 385.2010.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
o. A license applicant must file no
later than 60 days following the date of
issuance of the notice of acceptance and
ready for environmental analysis
provided for in § 5.22: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
p. Procedural Schedule: The
application will be processed according
to the following Hydro Licensing
Schedule. Revisions to the schedule
may be made as appropriate.
Milestone
Target date
Filing of Recommendations, Preliminary Terms and Conditions, and Fishway Prescriptions ...............................................
Reply Comments due ..............................................................................................................................................................
Issue Draft EA .........................................................................................................................................................................
Comments on Draft EA Due ....................................................................................................................................................
Filing of Modified Mandatory Terms and Conditions ..............................................................................................................
Issue Final EA .........................................................................................................................................................................
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–17111 Filed 7–13–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13597–000]
McGinnis, Inc.; Notice of Preliminary
Permit Application Accepted for Filing
and Soliciting Comments, Motions To
Intervene, and Competing Applications
emcdonald on DSK2BSOYB1PROD with NOTICES
July 6, 2010.
On September 29, 2009, McGinnis,
Inc. filed an application for a
preliminary permit, pursuant to section
4(f) of the Federal Power Act, proposing
to study the feasibility of the Wilson
Hydrokinetic Project, to be located on
the Tennessee River downstream of the
Tennessee Valley Authority (TVA) and
the Corps of Engineers’ (COE) existing
Wilson Lock & Dam in Lauderdale and
Colbert County, Alabama. The sole
purpose of a preliminary permit, if
issued, is to grant the permit holder
priority to file a license application
during the permit term. A preliminary
VerDate Mar<15>2010
16:07 Jul 13, 2010
Jkt 220001
permit does not authorize the permit
holder to perform any land disturbing
activities or otherwise enter upon lands
or waters owned by others without the
owners’ express permission.
The proposed Wilson Hydrokinetic
Project consists of: (1) 10 proposed 35
kilowatt axial flow turbine generating
units having a total installed capacity of
350 kilowatts; (2) a 700-foot-long, 13.2
kilovolt transmission line; and (3)
appurtenant facilities. The proposed
Wilson Hydrokinetic Project would
have an average annual generation of
1.533 gigawatt-hours.
Applicant Contact: Bruce McGinnis,
Sr., CEO, McGinnis, Inc., 502 Second
Street Ext., South Point, OH 45680;
phone: (740) 377–4391.
FERC Contact: Kim Carter, 202–502–
6486.
Deadline for filing comments or
motions to intervene: 60 days from the
issuance of this notice. Comments and
motions to intervene may be filed
electronically via the internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site (https://www.ferc.gov/docs-filing/
ferconline.asp) under the ‘‘eFiling’’ link.
For a simpler method of submitting text
only comments, click on ‘‘Quick
Comment.’’ For assistance, please
PO 00000
Frm 00030
Fmt 4703
40799
Sfmt 9990
September 6, 2010.
October 19, 2010.
March 3, 2011.
April 4, 2011.
June 3, 2011.
September 2, 2011.
contact FERC Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and eight copies to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–13597) in the docket number field to
access the document. For assistance,
contact FERC Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–17100 Filed 7–13–10; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\14JYN1.SGM
14JYN1
Agencies
[Federal Register Volume 75, Number 134 (Wednesday, July 14, 2010)]
[Notices]
[Page 40799]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-17100]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 13597-000]
McGinnis, Inc.; Notice of Preliminary Permit Application Accepted
for Filing and Soliciting Comments, Motions To Intervene, and Competing
Applications
July 6, 2010.
On September 29, 2009, McGinnis, Inc. filed an application for a
preliminary permit, pursuant to section 4(f) of the Federal Power Act,
proposing to study the feasibility of the Wilson Hydrokinetic Project,
to be located on the Tennessee River downstream of the Tennessee Valley
Authority (TVA) and the Corps of Engineers' (COE) existing Wilson Lock
& Dam in Lauderdale and Colbert County, Alabama. The sole purpose of a
preliminary permit, if issued, is to grant the permit holder priority
to file a license application during the permit term. A preliminary
permit does not authorize the permit holder to perform any land
disturbing activities or otherwise enter upon lands or waters owned by
others without the owners' express permission.
The proposed Wilson Hydrokinetic Project consists of: (1) 10
proposed 35 kilowatt axial flow turbine generating units having a total
installed capacity of 350 kilowatts; (2) a 700-foot-long, 13.2 kilovolt
transmission line; and (3) appurtenant facilities. The proposed Wilson
Hydrokinetic Project would have an average annual generation of 1.533
gigawatt-hours.
Applicant Contact: Bruce McGinnis, Sr., CEO, McGinnis, Inc., 502
Second Street Ext., South Point, OH 45680; phone: (740) 377-4391.
FERC Contact: Kim Carter, 202-502-6486.
Deadline for filing comments or motions to intervene: 60 days from
the issuance of this notice. Comments and motions to intervene may be
filed electronically via the internet. See 18 CFR 385.2001(a)(1)(iii)
and the instructions on the Commission's Web site (https://www.ferc.gov/docs-filing/ferconline.asp) under the ``eFiling'' link. For a simpler
method of submitting text only comments, click on ``Quick Comment.''
For assistance, please contact FERC Online Support at
FERCOnlineSupport@ferc.gov; call toll-free at (866) 208-3676; or, for
TTY, contact (202) 502-8659. Although the Commission strongly
encourages electronic filing, documents may also be paper-filed. To
paper-file, mail an original and eight copies to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426.
More information about this project, including a copy of the
application, can be viewed or printed on the ``eLibrary'' link of
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P-13597) in the docket number field to access
the document. For assistance, contact FERC Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010-17100 Filed 7-13-10; 8:45 am]
BILLING CODE 6717-01-P