Public Utility District No. 1 of Pend Orielle County; Notice of Application for Surrender of License Accepted for Filing, Soliciting Comments, Motions To Intervene and Protests, and Ready for Environmental Analysis, 40800-40801 [2010-17099]
Download as PDF
40800
Federal Register / Vol. 75, No. 134 / Wednesday, July 14, 2010 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2225–013]
Public Utility District No. 1 of Pend
Orielle County; Notice of Application
for Surrender of License Accepted for
Filing, Soliciting Comments, Motions
To Intervene and Protests, and Ready
for Environmental Analysis
emcdonald on DSK2BSOYB1PROD with NOTICES
July 6, 2010.
Take notice that the following
hydroelectric application has been with
the Commission and is available for
public inspection.
a. Type of Application: Surrender of
License.
b. Project No.: Sullivan Creek: P–
2225–013.
c. Date Filed: March 29, 2010.
d. Applicant: Public Utility District
No. 1 of Pend Oreille County (Pend
Oreille PUD).
e. Location: The existing project is
located on Sullivan Creek and Outlet
Creek, tributaries to the Pend Oreille
River, in northeast Washington. The
project occupies lands within the
Colville National Forest.
f. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
g. Applicant Contact: Mark J Cauchy,
Public Utility District No. 1 of Pend
Oreille, County, Washington, PO Box
190, Newport, WA 99156–0190; 509 447
9331.
h. FERC Contact: David Turner (202)
502–6091 or via e-mail at
david.turner@ferc.gov.
i. Cooperating agencies: Federal, state,
local, and tribal agencies with
jurisdiction and/or special expertise
with respect to environmental issues
that wish to cooperate in the
preparation of the environmental
document should follow the
instructions for filing such requests
described in item J below. Cooperating
agencies should note the Commission’s
policy that agencies that cooperate in
the preparation of the environmental
document cannot also intervene. See, 94
FERC ¶ 1,076 (2001).
j. Deadline for filing comments,
motions to intervene, protests, and
requests for cooperating agency status is
60 days from the issuance date of this
notice; reply comments are due 105
days from the issuance date of this
notice.
All documents may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site (https://www.ferc.gov/docs-filing/
ferconline.asp) under the ‘‘eFiling’’ link.
VerDate Mar<15>2010
16:07 Jul 13, 2010
Jkt 220001
For a simpler method of submitting text
only comments, click on ‘‘Quick
Comment.’’ For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659.
Although the Commission strongly
encourages electronic filing, documents
may also be paper-filed. To paper-file,
mail an original and eight copies to:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
All documents (original and eight
copies) should be filed with: Kimberly
D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
require all interveners filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervener files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted
for filing and is now ready for
environmental analysis.
l. The Sullivan Creek Project works
include: (1) A 172-foot-long, 34-foothigh concrete and earth-filed Sullivan
Lake dam; (2) the 1,240-acre Sullivan
Lake; (3) a 134-foot-long, 55-foot-high
concrete, gravity Mill Pond dam; and (4)
the 80.5-acre Mill Pond. Other
abandoned project works include: (5) a
0.8-mile-long Sullivan Creek diversion
conduit, (6) a 12,500-foot-long wooden
flume, (7) a 2,200-foot-long earthen
canal, (8) a 1,150-foot-long, 8-foot
diameter horseshoe tunnel, and (9) a
100-foot by 8-foot masonry brick
powerhouse. The turbines were
removed from the powerhouse in 1958
and the turbine bays filled with rock
and gravel.
The Pend Orielle PUD proposes to (1)
retain and operate under a Forest
Service Special Use Authorization the
Sullivan Lake dam and lake; (2) install
a new cold-water release facility at
Sullivan Lake dam; and (3) remove Mill
Pond dam and restore the site and
downstream stream channel and
conduct short-term monitoring and
maintenance in accordance with its
filed Mill Pond Decommissioning Plan.
No action is proposed for the remaining
abandoned project works.
m. A copy of the surrender
application is available for review at the
Commission in the Public Reference
Room or may be viewed on the
PO 00000
Frm 00031
Fmt 4703
Sfmt 4703
Commission’s website at https://
www.ferc.gov, using the ‘‘e-Library’’ link.
Enter the docket number, excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item h above. A copy of the
application may be obtained by agencies
directly from the applicant.
Register online at https://
www.ferc.gov/esubscribenow.htm to be
notified via e-mail of new filings and
issuances related to this or other
pending projects. For assistance, contact
FERC Online Support.
n. Anyone may submit comments, a
protest, or a motion to intervene in
accordance with the requirements of
Rules of Practice and Procedure, 18 CFR
385.210, .211, .214. In determining the
appropriate action to take, the
Commission will consider all protests or
other comments filed, but only those
who file a motion to intervene in
accordance with the Commission’s
Rules may become a party to the
proceeding. Any comments, protests, or
motions to intervene must be received
on or before the specified comment date
in item j.
All filings must (1) bear in all capital
letters the title ‘‘COMMENTS’’,
‘‘PROTEST’’, ‘‘MOTION TO
INTERVENE’’, or ‘‘REQUEST TO BE
COOPERATING AGENCY’’; as
appropriate; (2) set forth in the heading
the name of the applicant and the
project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. All
comments, motions to intervene or
protests should relate to project works
which are the subject of the license
surrender. A copy of any protest or
motion to intervene must be served
upon each representative of the
applicant specified in the particular
application. A copy of all other filings
in reference to this application must be
accompanied by proof of service on all
persons listed in the service list
prepared by the Commission in this
proceeding, in accordance with 18 CFR
385.2010.
o. A copy of the application for water
quality certification was filed on April
8, 2010.
p. Procedural schedule and final
amendments: The application will be
processed according to the following
E:\FR\FM\14JYN1.SGM
14JYN1
Federal Register / Vol. 75, No. 134 / Wednesday, July 14, 2010 / Notices
schedule. Revisions to the schedule will
be made if the Commission determines
it necessary to do so:
Milestone
Target date
Filing of comments, motions to intervene, protests, and requests for cooperating agency status.
Reply Comments due ............................................................................................
Issue Draft EA .......................................................................................................
Comments on Draft EA Due .................................................................................
Issue Final EA .......................................................................................................
Final amendments to the application
must be filed with the Commission no
later than 30 days from the issuance
date of this notice.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–17099 Filed 7–13–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12642–003]
Wilkesboro Hydropower, LLC; Notice
of Application Accepted for Filing and
Soliciting Motions To Intervene and
Protests
emcdonald on DSK2BSOYB1PROD with NOTICES
July 6, 2010.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Original Major
License.
b. Project No.: P–12642–003.
c. Date filed: September 29, 2009.
d. Applicant: Wilkesboro
Hydroelectric Company, LLC.
e. Name of Project: W. Kerr Scott
Hydropower Project.
f. Location: The proposed project
would be located at the existing U.S.
Army Corps of Engineers’ (Corps) W.
Kerr Scott dam on the Yadkin River,
near Wilkesboro in Wilkes County,
North Carolina. A total of 3.5 acres of
federal lands, administered by the
Corps, would be occupied by the
proposed project.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contacts: Mr. Kevin
Edwards, P.O. Box 143, Mayodan, NC
27027; Mr. Dean Edwards, P.O. Box
1565, Dover, FL 33527;
i. FERC Contact: Jennifer Adams at
(202) 502–8087, or
jennifer.adams@ferc.gov.
j. Deadline for filing motions to
intervene and protests: 60 days from the
issuance date of this notice, or
September 4, 2010.
VerDate Mar<15>2010
16:07 Jul 13, 2010
Jkt 220001
40801
September 6, 2010.
October 19, 2010.
March 3, 2011.
April 4, 2011.
September 2, 2011.
All documents may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s
website (https://www.ferc.gov/docsfiling/ferconline.asp) under the ‘‘eFiling’’
link. For a simpler method of submitting
text only comments, click on ‘‘Quick
Comment.’’ For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and eight copies to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
and Procedure require all interveners
filing documents with the Commission
to serve a copy of that document on
each person on the official service list
for the project. Further, if an intervener
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
k. This application has been accepted
for filing, but is not ready for
environmental analysis at this time.
l. The proposed project would use the
existing Kerr Scott dam, which is
federally owned and administered by
the Corps. The proposed project would
use releases from the reservoir, as
directed by the Corps, which would
normally be released directly to the
Yadkin River downstream from the
dam. All existing facilities would
remain, but some features would be
modified and new facilities would be
constructed.
The proposed project would consist
of: (1) Modifying the existing low-level
intake tower to be a multilevel intake
structure with trashracks; (2) placing a
580-foot-long, 11-foot-diameter steel
liner in the downstream portion of the
existing 749-foot-long reinforced
concrete water conduit to enable
pressurization of the conduit; (3) a
PO 00000
Frm 00032
Fmt 4703
Sfmt 4703
penstock bifurcation and two 8-footdiameter steel penstocks; (4) a gate at
the end of the water conduit, with a
Howell-Bunger-ring-jet-type fixed cone
valve installed in the gate; (5) an 80foot-long by 30-foot-wide powerhouse
containing one 2.0–MW Kaplan unit
and one 2.0–MW propeller-type unit; (6)
an 80-foot-wide by 30-foot-long
discharge channel that joins the Yadkin
River at the downstream end of the
existing stilling basin; (7) a substation;
(8) a new underground 12.47-kilovolt
(kV) transmission line that extends 150
feet from the proposed powerhouse to
an existing utility pole to the south of
the powerhouse, and an upgraded
3,600-foot-long, 12.47-kV three-phase
line that connects the utility pole to a
Duke Energy substation; and (9)
appurtenant facilities. The Kerr Scott
project would generate approximately
22,400 megawatt-hours of energy
annually.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room, or may be
viewed on the Commission’s website at
https://www.ferc.gov, using the
‘‘eLibrary’’ link. Enter the docket
number, excluding the last three digits
in the docket number field, to access the
document. For help, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h.
You may also register online at https://
www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Any qualified applicant desiring to
file a competing application must
submit to the Commission, on or before
the specified intervention deadline date,
a competing development application
no later than 120 days after the specified
intervention deadline date. Applications
for preliminary permits will not be
accepted in response to this notice.
A notice of intent must specify the
exact name, business address, and
telephone number of the prospective
applicant, and must include an
E:\FR\FM\14JYN1.SGM
14JYN1
Agencies
[Federal Register Volume 75, Number 134 (Wednesday, July 14, 2010)]
[Notices]
[Pages 40800-40801]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-17099]
[[Page 40800]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2225-013]
Public Utility District No. 1 of Pend Orielle County; Notice of
Application for Surrender of License Accepted for Filing, Soliciting
Comments, Motions To Intervene and Protests, and Ready for
Environmental Analysis
July 6, 2010.
Take notice that the following hydroelectric application has been
with the Commission and is available for public inspection.
a. Type of Application: Surrender of License.
b. Project No.: Sullivan Creek: P-2225-013.
c. Date Filed: March 29, 2010.
d. Applicant: Public Utility District No. 1 of Pend Oreille County
(Pend Oreille PUD).
e. Location: The existing project is located on Sullivan Creek and
Outlet Creek, tributaries to the Pend Oreille River, in northeast
Washington. The project occupies lands within the Colville National
Forest.
f. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
g. Applicant Contact: Mark J Cauchy, Public Utility District No. 1
of Pend Oreille, County, Washington, PO Box 190, Newport, WA 99156-
0190; 509 447 9331.
h. FERC Contact: David Turner (202) 502-6091 or via e-mail at
david.turner@ferc.gov.
i. Cooperating agencies: Federal, state, local, and tribal agencies
with jurisdiction and/or special expertise with respect to
environmental issues that wish to cooperate in the preparation of the
environmental document should follow the instructions for filing such
requests described in item J below. Cooperating agencies should note
the Commission's policy that agencies that cooperate in the preparation
of the environmental document cannot also intervene. See, 94 FERC ]
1,076 (2001).
j. Deadline for filing comments, motions to intervene, protests,
and requests for cooperating agency status is 60 days from the issuance
date of this notice; reply comments are due 105 days from the issuance
date of this notice.
All documents may be filed electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web
site (https://www.ferc.gov/docs-filing/ferconline.asp) under the
``eFiling'' link. For a simpler method of submitting text only
comments, click on ``Quick Comment.'' For assistance, please contact
FERC Online Support at FERCOnlineSupport@ferc.gov; call toll-free at
(866) 208-3676; or, for TTY, contact (202) 502-8659.
Although the Commission strongly encourages electronic filing,
documents may also be paper-filed. To paper-file, mail an original and
eight copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE., Washington, DC 20426. All documents
(original and eight copies) should be filed with: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426.
The Commission's Rules of Practice require all interveners filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervener files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
k. This application has been accepted for filing and is now ready
for environmental analysis.
l. The Sullivan Creek Project works include: (1) A 172-foot-long,
34-foot-high concrete and earth-filed Sullivan Lake dam; (2) the 1,240-
acre Sullivan Lake; (3) a 134-foot-long, 55-foot-high concrete, gravity
Mill Pond dam; and (4) the 80.5-acre Mill Pond. Other abandoned project
works include: (5) a 0.8-mile-long Sullivan Creek diversion conduit,
(6) a 12,500-foot-long wooden flume, (7) a 2,200-foot-long earthen
canal, (8) a 1,150-foot-long, 8-foot diameter horseshoe tunnel, and (9)
a 100-foot by 8-foot masonry brick powerhouse. The turbines were
removed from the powerhouse in 1958 and the turbine bays filled with
rock and gravel.
The Pend Orielle PUD proposes to (1) retain and operate under a
Forest Service Special Use Authorization the Sullivan Lake dam and
lake; (2) install a new cold-water release facility at Sullivan Lake
dam; and (3) remove Mill Pond dam and restore the site and downstream
stream channel and conduct short-term monitoring and maintenance in
accordance with its filed Mill Pond Decommissioning Plan. No action is
proposed for the remaining abandoned project works.
m. A copy of the surrender application is available for review at
the Commission in the Public Reference Room or may be viewed on the
Commission's website at https://www.ferc.gov, using the ``e-Library''
link. Enter the docket number, excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support at FERCOnlineSupport@ferc.gov or toll-free at 1-
866-208-3676, or for TTY, (202) 502-8659. A copy is also available for
inspection and reproduction at the address in item h above. A copy of
the application may be obtained by agencies directly from the
applicant.
Register online at https://www.ferc.gov/esubscribenow.htm to be
notified via e-mail of new filings and issuances related to this or
other pending projects. For assistance, contact FERC Online Support.
n. Anyone may submit comments, a protest, or a motion to intervene
in accordance with the requirements of Rules of Practice and Procedure,
18 CFR 385.210, .211, .214. In determining the appropriate action to
take, the Commission will consider all protests or other comments
filed, but only those who file a motion to intervene in accordance with
the Commission's Rules may become a party to the proceeding. Any
comments, protests, or motions to intervene must be received on or
before the specified comment date in item j.
All filings must (1) bear in all capital letters the title
``COMMENTS'', ``PROTEST'', ``MOTION TO INTERVENE'', or ``REQUEST TO BE
COOPERATING AGENCY''; as appropriate; (2) set forth in the heading the
name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person protesting or intervening; and (4) otherwise
comply with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, motions to intervene or protests should relate to project
works which are the subject of the license surrender. A copy of any
protest or motion to intervene must be served upon each representative
of the applicant specified in the particular application. A copy of all
other filings in reference to this application must be accompanied by
proof of service on all persons listed in the service list prepared by
the Commission in this proceeding, in accordance with 18 CFR 385.2010.
o. A copy of the application for water quality certification was
filed on April 8, 2010.
p. Procedural schedule and final amendments: The application will
be processed according to the following
[[Page 40801]]
schedule. Revisions to the schedule will be made if the Commission
determines it necessary to do so:
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Filing of comments, motions to intervene, September 6, 2010.
protests, and requests for cooperating
agency status.
Reply Comments due....................... October 19, 2010.
Issue Draft EA........................... March 3, 2011.
Comments on Draft EA Due................. April 4, 2011.
Issue Final EA........................... September 2, 2011.
------------------------------------------------------------------------
Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of this notice.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010-17099 Filed 7-13-10; 8:45 am]
BILLING CODE 6717-01-P