Download as PDF 40804 Federal Register / Vol. 75, No. 134 / Wednesday, July 14, 2010 / Notices emcdonald on DSK2BSOYB1PROD with NOTICES or waters owned by others without the owners’ express permission. The proposed Sardis Lake Hydroelectric Project consists of: (1) An existing 15,300-foot-long dam and dike; (2) a control tower containing four vertical gates connected to a 550-footlong outlet tunnel; (3) a proposed 75foot-wide intake structure; (4) a proposed 800-foot-long, 16-foot diameter steel penstock; (5) a proposed reinforced concrete powerhouse containing a 8.0-megawatt turbine/ generator; (6) a proposed 1 and 0.25mile-long 138-kilovolt three-phase overhead transmission line; and (7) appurtenant facilities. The FFP Missouri 2, LLC, project would have an average annual generation of 40-gigawatt-hours. Applicant Contact: Ms. Ramya Swaminathan, FFP Missouri 2, LLC, 33 Commercial Street, Gloucester, MA 01930, phone (978) 283–2822. FERC Contact: Pennie Lewis-Partee, (202) 502–6018. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance date of this notice. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. If unable to be filed electronically, documents may be paperfiled. To paper-file, an original and eight copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For more information on how to submit these types of filings please go to the Commission’s Web site located at https://www.ferc.gov/filingcomments.asp. More information about this project can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https://www.ferc.gov/docsfiling/elibrary.asp. Enter the docket number (P–13701) in the docket number field to access the document. For assistance, call toll-free 1–866–208– 3372. Kimberly D. Bose, Secretary. [FR Doc. 2010–17106 Filed 7–13–10; 8:45 am] BILLING CODE 6717–01–P VerDate Mar<15>2010 16:07 Jul 13, 2010 Jkt 220001 DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13704–000] FFP Missouri 2, LLC; Notice of Preliminary Permit Applications Accepted for Filing and Soliciting Comment, Motions To Intervene, and Competing Applications July 7, 2010. On April 5, 2010, FFP Missouri 2, LLC filed an application, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of the Arkabutla Lake Hydroelectric Project, to be located on the Coldwater River, Tate and DeSoto Counties, Mississippi. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land-disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed Arkabutla Lake Hydroelectric Project consists of: (1) An existing 11,500-foot-long dam and dike; (2) a control tower containing four vertical gates connected to a 400-footlong outlet tunnel; (3) a proposed 50foot-wide intake structure; (4) a proposed 900-foot-long, 12-foot diameter steel penstock; (5) a proposed reinforced concrete powerhouse containing a 3.5-megawatt turbine/ generator; (6) a proposed 0.5-mile-long, 12.5-kilovolt three-phase overhead transmission line; and (7) appurtenant facilities. The FFP Missouri 2, LLC, project would have an average annual generation of 17.5 gigawatt-hours. Applicant Contact: Ms. Ramya Swaminathan, FFP Missouri 2, LLC, 33 Commercial Street, Gloucester, MA 01930, phone (978) 283–2822. FERC Contact: Pennie Lewis-Partee, (202) 502–6018. Deadline for filing comments, motions to intervene, competing applications (without notices of intent), or notices of intent to file competing applications: 60 days from the issuance date of this notice. Comments, motions to intervene, notices of intent, and competing applications may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site under the ‘‘e-Filing’’ link. If unable to be filed electronically, documents may be paperfiled. To paper-file, an original and eight copies should be mailed to: Kimberly D. Bose, Secretary, Federal Energy PO 00000 Frm 00035 Fmt 4703 Sfmt 4703 Regulatory Commission, 888 First Street, NE., Washington, DC 20426. For more information on how to submit these types of filings please go to the Commission’s Web site located at https://www.ferc.gov/filingcomments.asp. More information about this project can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https://www.ferc.gov/docsfiling/elibrary.asp. Enter the docket number (P–13704) in the docket number field to access the document. For assistance, call toll-free 1–866–208– 3372. Kimberly D. Bose, Secretary. [FR Doc. 2010–17092 Filed 7–13–10; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 13591–000] McGinnis, Inc.; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications July 6, 2010. On September 29, 2009, McGinnis, Inc. filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of the Kentucky Hydrokinetic Project, to be located on the Tennessee River downstream of the Tennessee Valley Authority (TVA) and the Corps of Engineers’ (COE) existing Kentucky Lock & Dam in Marshall and Livingston County, Kentucky. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land disturbing activities or otherwise enter upon lands or waters owned by others without the owners’ express permission. The proposed Kentucky Hydrokinetic Project consists of: (1) 10 proposed 35 kilowatt axial flow turbine generating units having a total installed capacity of 350 kilowatts; (2) a 700-foot-long, 13.2 kilovolt transmission line; and (3) appurtenant facilities. The proposed Kentucky Hydrokinetic Project would have an average annual generation of 1.533 gigawatt-hours. Applicant Contact: Bruce McGinnis, Sr., CEO, McGinnis, Inc., 502 Second Street Ext., South Point, OH 45680; phone: (740) 377–4391. E:\FR\FM\14JYN1.SGM 14JYN1 Federal Register / Vol. 75, No. 134 / Wednesday, July 14, 2010 / Notices FERC Contact: Kim Carter, 202–502– 6486. Deadline for filing comments or motions to intervene: 60 days from the issuance of this notice. Comments and motions to intervene may be filed electronically via the internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site (https://www.ferc.gov/docs-filing/ ferconline.asp) under the ‘‘eFiling’’ link. For a simpler method of submitting text only comments, click on ‘‘Quick Comment.’’ For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY, contact (202) 502–8659. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and eight copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https:// www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number (P–13591) in the docket number field to access the document. For assistance, contact FERC Online Support. Kimberly D. Bose, Secretary. [FR Doc. 2010–17096 Filed 7–13–10; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission McGinnis, Inc. Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications emcdonald on DSK2BSOYB1PROD with NOTICES July 6, 2010. On September 29, 2009, McGinnis, Inc. filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of the Pickwick Hydrokinetic Project, to be located on the Tennessee River downstream of the Tennessee Valley Authority (TVA) and the Corps of Engineers’ (COE) existing Pickwick Lock & Dam in Harden County, Tennessee. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land disturbing activities or otherwise enter upon lands or waters VerDate Mar<15>2010 16:07 Jul 13, 2010 Jkt 220001 owned by others without the owners’ express permission. The proposed Pickwick Hydrokinetic Project consists of: (1) 10 proposed 35 kilowatt axial flow turbine generating units having a total installed capacity of 350 kilowatts; (2) a 1,300-foot-long, 13.2 kilovolt transmission line; and (3) appurtenant facilities. The proposed Pickwick Hydrokinetic Project would have an average annual generation of 1.533 gigawatt-hours. Applicant Contact: Bruce McGinnis, Sr., CEO, McGinnis, Inc., 502 Second Street Ext., South Point, OH 45680; phone: (740) 377–4391. FERC Contact: Kim Carter, 202–502– 6486. Deadline for filing comments or motions to intervene: 60 days from the issuance of this notice. Comments and motions to intervene may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site (https://www.ferc.gov/docs-filing/ ferconline.asp) under the ‘‘eFiling’’ link. For a simpler method of submitting text only comments, click on ‘‘Quick Comment.’’ For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY, contact (202) 502–8659. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and eight copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–13594) in the docket number field to access the document. For assistance, contact FERC Online Support. Kimberly D. Bose, Secretary. [FR Doc. 2010–17095 Filed 7–13–10; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #2 July 2, 2010. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER10–1649–000. PO 00000 Frm 00036 Fmt 4703 Sfmt 4703 40805 Applicants: Midwest Independent Transmission System Operator, Inc. Description: Midwest Independent Transmission System Operator, Inc submits proposed revisions to the Coordination Agreement with Independent Electricity System Operator. Filed Date: 06/30/2010. Accession Number: 20100630–0234. Comment Date: 5 p.m. Eastern Time on Wednesday, July 21, 2010. Docket Numbers: ER10–1650–000. Applicants: New England Power Pool Participants Committee. Description: The New England Power Pool Participants Committee submits transmittal letter along with counterpart signature pages of the Agreement dated 9/1/71 etc. Filed Date: 06/30/2010. Accession Number: 20100630–0233. Comment Date: 5 p.m. Eastern Time on Wednesday, July 21, 2010. Docket Numbers: ER10–1653–000. Applicants: ISO New England and NEPOOL. Description: ISO New England Inc et al submits transmittal letter and Fourth Revised Sheet 7319B et al to FERC Electric Tariff 3- Section III- Market Rule 1- Standard Market Design etc. Filed Date: 06/30/2010. Accession Number: 20100630–0221. Comment Date: 5 p.m. Eastern Time on Wednesday, July 21, 2010. Docket Numbers: ER10–1654–000. Applicants: Connecticut Light & Power Company. Description: The Connecticut Light and Power Company submits Interconnection Agreement with Covanta Projects of Wallingford, LP etc. Filed Date: 06/30/2010. Accession Number: 20100630–0219. Comment Date: 5 p.m. Eastern Time on Wednesday, July 21, 2010. Docket Numbers: ER10–1655–000. Applicants: MATEP, Inc. Description: MATEP Limited Partnership submits Notice of Succession to New MATEP, Inc’s market- based rate tariff. Filed Date: 06/30/2010. Accession Number: 20100630–0220. Comment Date: 5 p.m. Eastern Time on Wednesday, July 21, 2010. Docket Numbers: ER10–1659–000. Applicants: PSEG Nuclear LLC. Description: PSEG Nuclear LLC submits tariff filing per 35.12: Baseline Filing of Market-Based Rates Tariff Under Order No. 714 to be effective 7/ 1/2010. Filed Date: 07/01/2010. Accession Number: 20100701–5008. Comment Date: 5 p.m. Eastern Time on Thursday, July 22, 2010. E:\FR\FM\14JYN1.SGM 14JYN1

Agencies

[Federal Register Volume 75, Number 134 (Wednesday, July 14, 2010)]
[Notices]
[Pages 40804-40805]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-17096]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 13591-000]


McGinnis, Inc.; Notice of Preliminary Permit Application Accepted 
for Filing and Soliciting Comments, Motions To Intervene, and Competing 
Applications

July 6, 2010.
    On September 29, 2009, McGinnis, Inc. filed an application for a 
preliminary permit, pursuant to section 4(f) of the Federal Power Act, 
proposing to study the feasibility of the Kentucky Hydrokinetic 
Project, to be located on the Tennessee River downstream of the 
Tennessee Valley Authority (TVA) and the Corps of Engineers' (COE) 
existing Kentucky Lock & Dam in Marshall and Livingston County, 
Kentucky. The sole purpose of a preliminary permit, if issued, is to 
grant the permit holder priority to file a license application during 
the permit term. A preliminary permit does not authorize the permit 
holder to perform any land disturbing activities or otherwise enter 
upon lands or waters owned by others without the owners' express 
permission.
    The proposed Kentucky Hydrokinetic Project consists of: (1) 10 
proposed 35 kilowatt axial flow turbine generating units having a total 
installed capacity of 350 kilowatts; (2) a 700-foot-long, 13.2 kilovolt 
transmission line; and (3) appurtenant facilities. The proposed 
Kentucky Hydrokinetic Project would have an average annual generation 
of 1.533 gigawatt-hours.
    Applicant Contact: Bruce McGinnis, Sr., CEO, McGinnis, Inc., 502 
Second Street Ext., South Point, OH 45680; phone: (740) 377-4391.

[[Page 40805]]

    FERC Contact: Kim Carter, 202-502-6486.
    Deadline for filing comments or motions to intervene: 60 days from 
the issuance of this notice. Comments and motions to intervene may be 
filed electronically via the internet. See 18 CFR 385.2001(a)(1)(iii) 
and the instructions on the Commission's Web site (https://www.ferc.gov/docs-filing/ferconline.asp) under the ``eFiling'' link. For a simpler 
method of submitting text only comments, click on ``Quick Comment.'' 
For assistance, please contact FERC Online Support at 
FERCOnlineSupport@ferc.gov; call toll-free at (866) 208-3676; or, for 
TTY, contact (202) 502-8659. Although the Commission strongly 
encourages electronic filing, documents may also be paper-filed. To 
paper-file, mail an original and eight copies to: Kimberly D. Bose, 
Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., 
Washington, DC 20426.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of 
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-13591) in the docket number field to access 
the document. For assistance, contact FERC Online Support.

Kimberly D. Bose,
Secretary.
[FR Doc. 2010-17096 Filed 7-13-10; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.