Download as PDF Federal Register / Vol. 75, No. 134 / Wednesday, July 14, 2010 / Notices FERC Contact: Kim Carter, 202–502– 6486. Deadline for filing comments or motions to intervene: 60 days from the issuance of this notice. Comments and motions to intervene may be filed electronically via the internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site (https://www.ferc.gov/docs-filing/ ferconline.asp) under the ‘‘eFiling’’ link. For a simpler method of submitting text only comments, click on ‘‘Quick Comment.’’ For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY, contact (202) 502–8659. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and eight copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https:// www.ferc.gov/docs-filing/elibrary.asp. Enter the docket number (P–13591) in the docket number field to access the document. For assistance, contact FERC Online Support. Kimberly D. Bose, Secretary. [FR Doc. 2010–17096 Filed 7–13–10; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission McGinnis, Inc. Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications emcdonald on DSK2BSOYB1PROD with NOTICES July 6, 2010. On September 29, 2009, McGinnis, Inc. filed an application for a preliminary permit, pursuant to section 4(f) of the Federal Power Act, proposing to study the feasibility of the Pickwick Hydrokinetic Project, to be located on the Tennessee River downstream of the Tennessee Valley Authority (TVA) and the Corps of Engineers’ (COE) existing Pickwick Lock & Dam in Harden County, Tennessee. The sole purpose of a preliminary permit, if issued, is to grant the permit holder priority to file a license application during the permit term. A preliminary permit does not authorize the permit holder to perform any land disturbing activities or otherwise enter upon lands or waters VerDate Mar<15>2010 16:07 Jul 13, 2010 Jkt 220001 owned by others without the owners’ express permission. The proposed Pickwick Hydrokinetic Project consists of: (1) 10 proposed 35 kilowatt axial flow turbine generating units having a total installed capacity of 350 kilowatts; (2) a 1,300-foot-long, 13.2 kilovolt transmission line; and (3) appurtenant facilities. The proposed Pickwick Hydrokinetic Project would have an average annual generation of 1.533 gigawatt-hours. Applicant Contact: Bruce McGinnis, Sr., CEO, McGinnis, Inc., 502 Second Street Ext., South Point, OH 45680; phone: (740) 377–4391. FERC Contact: Kim Carter, 202–502– 6486. Deadline for filing comments or motions to intervene: 60 days from the issuance of this notice. Comments and motions to intervene may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site (https://www.ferc.gov/docs-filing/ ferconline.asp) under the ‘‘eFiling’’ link. For a simpler method of submitting text only comments, click on ‘‘Quick Comment.’’ For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY, contact (202) 502–8659. Although the Commission strongly encourages electronic filing, documents may also be paper-filed. To paper-file, mail an original and eight copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. More information about this project, including a copy of the application, can be viewed or printed on the ‘‘eLibrary’’ link of Commission’s Web site at https://www.ferc.gov/docs-filing/ elibrary.asp. Enter the docket number (P–13594) in the docket number field to access the document. For assistance, contact FERC Online Support. Kimberly D. Bose, Secretary. [FR Doc. 2010–17095 Filed 7–13–10; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Combined Notice of Filings #2 July 2, 2010. Take notice that the Commission received the following electric rate filings: Docket Numbers: ER10–1649–000. PO 00000 Frm 00036 Fmt 4703 Sfmt 4703 40805 Applicants: Midwest Independent Transmission System Operator, Inc. Description: Midwest Independent Transmission System Operator, Inc submits proposed revisions to the Coordination Agreement with Independent Electricity System Operator. Filed Date: 06/30/2010. Accession Number: 20100630–0234. Comment Date: 5 p.m. Eastern Time on Wednesday, July 21, 2010. Docket Numbers: ER10–1650–000. Applicants: New England Power Pool Participants Committee. Description: The New England Power Pool Participants Committee submits transmittal letter along with counterpart signature pages of the Agreement dated 9/1/71 etc. Filed Date: 06/30/2010. Accession Number: 20100630–0233. Comment Date: 5 p.m. Eastern Time on Wednesday, July 21, 2010. Docket Numbers: ER10–1653–000. Applicants: ISO New England and NEPOOL. Description: ISO New England Inc et al submits transmittal letter and Fourth Revised Sheet 7319B et al to FERC Electric Tariff 3- Section III- Market Rule 1- Standard Market Design etc. Filed Date: 06/30/2010. Accession Number: 20100630–0221. Comment Date: 5 p.m. Eastern Time on Wednesday, July 21, 2010. Docket Numbers: ER10–1654–000. Applicants: Connecticut Light & Power Company. Description: The Connecticut Light and Power Company submits Interconnection Agreement with Covanta Projects of Wallingford, LP etc. Filed Date: 06/30/2010. Accession Number: 20100630–0219. Comment Date: 5 p.m. Eastern Time on Wednesday, July 21, 2010. Docket Numbers: ER10–1655–000. Applicants: MATEP, Inc. Description: MATEP Limited Partnership submits Notice of Succession to New MATEP, Inc’s market- based rate tariff. Filed Date: 06/30/2010. Accession Number: 20100630–0220. Comment Date: 5 p.m. Eastern Time on Wednesday, July 21, 2010. Docket Numbers: ER10–1659–000. Applicants: PSEG Nuclear LLC. Description: PSEG Nuclear LLC submits tariff filing per 35.12: Baseline Filing of Market-Based Rates Tariff Under Order No. 714 to be effective 7/ 1/2010. Filed Date: 07/01/2010. Accession Number: 20100701–5008. Comment Date: 5 p.m. Eastern Time on Thursday, July 22, 2010. E:\FR\FM\14JYN1.SGM 14JYN1

Agencies

[Federal Register Volume 75, Number 134 (Wednesday, July 14, 2010)]
[Notices]
[Page 40805]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-17095]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission


McGinnis, Inc. Notice of Preliminary Permit Application Accepted 
for Filing and Soliciting Comments, Motions To Intervene, and Competing 
Applications

July 6, 2010.
    On September 29, 2009, McGinnis, Inc. filed an application for a 
preliminary permit, pursuant to section 4(f) of the Federal Power Act, 
proposing to study the feasibility of the Pickwick Hydrokinetic 
Project, to be located on the Tennessee River downstream of the 
Tennessee Valley Authority (TVA) and the Corps of Engineers' (COE) 
existing Pickwick Lock & Dam in Harden County, Tennessee. The sole 
purpose of a preliminary permit, if issued, is to grant the permit 
holder priority to file a license application during the permit term. A 
preliminary permit does not authorize the permit holder to perform any 
land disturbing activities or otherwise enter upon lands or waters 
owned by others without the owners' express permission.
    The proposed Pickwick Hydrokinetic Project consists of: (1) 10 
proposed 35 kilowatt axial flow turbine generating units having a total 
installed capacity of 350 kilowatts; (2) a 1,300-foot-long, 13.2 
kilovolt transmission line; and (3) appurtenant facilities. The 
proposed Pickwick Hydrokinetic Project would have an average annual 
generation of 1.533 gigawatt-hours.
    Applicant Contact: Bruce McGinnis, Sr., CEO, McGinnis, Inc., 502 
Second Street Ext., South Point, OH 45680; phone: (740) 377-4391.
    FERC Contact: Kim Carter, 202-502-6486.
    Deadline for filing comments or motions to intervene: 60 days from 
the issuance of this notice. Comments and motions to intervene may be 
filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) 
and the instructions on the Commission's Web site (https://www.ferc.gov/docs-filing/ferconline.asp) under the ``eFiling'' link. For a simpler 
method of submitting text only comments, click on ``Quick Comment.'' 
For assistance, please contact FERC Online Support at 
FERCOnlineSupport@ferc.gov; call toll-free at (866) 208-3676; or, for 
TTY, contact (202) 502-8659. Although the Commission strongly 
encourages electronic filing, documents may also be paper-filed. To 
paper-file, mail an original and eight copies to: Kimberly D. Bose, 
Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., 
Washington, DC 20426.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of 
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-13594) in the docket number field to access 
the document. For assistance, contact FERC Online Support.

Kimberly D. Bose,
Secretary.