Southern Nuclear Operating Company et al.; Notice of Availability of Environmental Assessment and Finding of No Significant Impact for License Amendment to Early Site Permit Issued to Southern Nuclear Operating Company et al., for Vogtle Electric Generating Plant ESP Site Located In Burke County, GA, 39284 [2010-16631]
Download as PDF
39284
Federal Register / Vol. 75, No. 130 / Thursday, July 8, 2010 / Notices
at the NRC Public Document Room, One
White Flint North, 11555 Rockville
Pike, Room O–1 F21, Rockville, MD
20852. OMB clearance requests are
available at the NRC worldwide Web
site: http://www.nrc.gov/public-involve/
doc-comment/omb/index.html. The
document will be available on the NRC
home page site for 60 days after the
signature date of this notice.
Comments and questions should be
directed to the OMB reviewer listed
below by August 9, 2010. Comments
received after this date will be
considered if it is practical to do so, but
assurance of consideration cannot be
given to comments received after this
date. Christine J. Kymn, Desk Officer,
Office of Information and Regulatory
Affairs (3150–0046), NEOB–10202,
Office of Management and Budget,
Washington, DC 20503.
Comments can also be e-mailed to
Christine.J.Kymn@omb.eop.gov or
submitted by telephone at (202) 395–
4638.
The NRC Clearance Officer is
Tremaine Donnell, (301) 415–6258.
Dated at Rockville, Maryland, this 1st day
of July 2010.
For the Nuclear Regulatory Commission.
Tremaine Donnell,
NRC Clearance Officer, Office of Information
Services.
[FR Doc. 2010–16624 Filed 7–7–10; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
I. Introduction
The Nuclear Regulatory Commission
(NRC) is considering issuance of an
amendment to Early Site Permit (ESP)
No. ESP–004, issued on August 26,
2009, to Southern Nuclear Operating
Company (SNC) and several coapplicants (Georgia Power Company,
Oglethorpe Power Corporation,
Municipal Electric Authority of Georgia,
and the City of Dalton, Georgia), for the
Vogtle Electric Generating Plant (VEGP)
ESP site located in Burke County,
Georgia. The license amendment request
(LAR) was submitted by letter dated
May 24, 2010, and was supplemented
by a letter dated June 2, 2010. In
particular, pursuant to Title 10 of the
Code of Federal Regulations (10 CFR)
Section 52.39(e), the request seeks to
amend the ESP Site Safety Analysis
Report (SSAR) to change the
classification of backfill over the slopes
of the Units 3 and 4 excavations from
Category 1 and 2 backfill to engineered
granular backfill (EGB).
NRC has prepared an Environmental
Assessment (EA) in support of this
amendment in accordance with the
requirements of 10 CFR Part 51. Based
on the EA, the NRC has concluded that
a Finding of No Significant Impact
(FONSI) is appropriate. The NRC staff’s
review of the safety aspects of the
amendment request will be documented
in a separate safety evaluation report
(SER); if warranted by the results of that
evaluation, the amendment would be
issued following the publication of this
Notice.
II. EA Summary
[Docket No. 52–011; NRC–2008–0252]
Southern Nuclear Operating Company
et al.; Notice of Availability of
Environmental Assessment and
Finding of No Significant Impact for
License Amendment to Early Site
Permit Issued to Southern Nuclear
Operating Company et al., for Vogtle
Electric Generating Plant ESP Site
Located In Burke County, GA
srobinson on DSKHWCL6B1PROD with NOTICES
AGENCY: Nuclear Regulatory
Commission.
ACTION: Notice of availability.
FOR FURTHER INFORMATION CONTACT:
Terri Spicher, Project Manager, AP1000
Branch 1, Division of New Reactors
Licensing, Office of New Reactors, U.S.
Nuclear Regulatory Commission,
Washington, DC 20555–0001.
Telephone: (301) 415–1670; fax number:
(301) 415–6323; e-mail:
Terri.Spicher@nrc.gov.
SUPPLEMENTARY INFORMATION:
VerDate Mar<15>2010
17:09 Jul 07, 2010
Jkt 220001
The purpose of the proposed
amendment is to authorize a change to
the early site permit issued to SNC for
the Vogtle Electric Generating Plant ESP
site located in Burke County, Georgia.
Specifically, the proposed amendment
would modify the Vogtle Electric
Generating Plant ESP SSAR to change
the classification of backfill over the
slopes of the Units 3 and 4 excavations
from Category 1 and 2 backfill to EGB.
The NRC staff has prepared an EA in
support of its review of the proposed
action. On the basis of this EA, the NRC
finds that there are no significant
environmental impacts from the
proposed action. The LAR would not
change the total quantity or locations of
backfill material to be obtained from
onsite sources, and the impacts of
acquiring EGB from the specified areas
located within the VEGP site would
remain within the scope of
environmental impacts previously
analyzed in the Final Environmental
Impact Statement (FEIS) for the VEGP
PO 00000
Frm 00084
Fmt 4703
Sfmt 9990
ESP and in the EAs for Amendments 1
and 2 to the VEGP ESP and LWA, and
found not to be significant. Accordingly,
the NRC staff has determined that there
would be no significant environmental
impacts associated with granting the
LAR request.
III. Finding of No Significant Impact
On the basis of the EA, the NRC has
concluded that there are no significant
environmental impacts from the
proposed amendment and has
determined not to prepare an
environmental impact statement.
IV. Further Information
The ESP amendment request is
available electronically at the NRC’s
Electronic Reading Room at http://
www.nrc.gov/reading-rm/adams.html.
From this site, persons can access the
NRC’s Agency-wide Documents Access
and Management System (ADAMS). The
ADAMS accession number for the May
24, 2010, amendment request is
ML101470213 and the accession
number for the June 2 supplement is
ML101550510. The ADAMS accession
number for the EA is ML101660076.
The ADAMS accession numbers for the
ESP FEIS are ML082240145 and
ML082240165, ML082260203, and
ML082550040. The ADAMS accession
numbers for the EAs for Amendment 1
and Amendment 2 to the ESP are
ML101380114 and ML101670592,
respectively. If persons do not have
access to ADAMS or have problems
accessing the documents located in
ADAMS, contact the NRC Public
Document Room Reference staff at 1–
800–397–4209, or 301–415–4737, or via
e-mail to pdr.resource@nrc.gov.
These documents may also be viewed
electronically on the public computers
located at the NRC’s Public Document
Room (PDR), O 1 F21, One White Flint
North, 11555 Rockville Pike, Rockville,
MD 20852. The PDR reproduction
contractor will copy documents for a
fee.
Dated at Rockville, Maryland, this 28th day
of June 2010.
For the Nuclear Regulatory Commission,
Jeffrey Cruz,
Chief, AP1000 Branch 1, Division of New
Reactors Licensing, Office of New Reactors.
[FR Doc. 2010–16631 Filed 7–7–10; 8:45 am]
BILLING CODE 7590–01–P
E:\FR\FM\08JYN1.SGM
08JYN1
Agencies
[Federal Register Volume 75, Number 130 (Thursday, July 8, 2010)]
[Notices]
[Page 39284]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-16631]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 52-011; NRC-2008-0252]
Southern Nuclear Operating Company et al.; Notice of Availability
of Environmental Assessment and Finding of No Significant Impact for
License Amendment to Early Site Permit Issued to Southern Nuclear
Operating Company et al., for Vogtle Electric Generating Plant ESP Site
Located In Burke County, GA
AGENCY: Nuclear Regulatory Commission.
ACTION: Notice of availability.
-----------------------------------------------------------------------
FOR FURTHER INFORMATION CONTACT: Terri Spicher, Project Manager, AP1000
Branch 1, Division of New Reactors Licensing, Office of New Reactors,
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001.
Telephone: (301) 415-1670; fax number: (301) 415-6323; e-mail:
Terri.Spicher@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Introduction
The Nuclear Regulatory Commission (NRC) is considering issuance of
an amendment to Early Site Permit (ESP) No. ESP-004, issued on August
26, 2009, to Southern Nuclear Operating Company (SNC) and several co-
applicants (Georgia Power Company, Oglethorpe Power Corporation,
Municipal Electric Authority of Georgia, and the City of Dalton,
Georgia), for the Vogtle Electric Generating Plant (VEGP) ESP site
located in Burke County, Georgia. The license amendment request (LAR)
was submitted by letter dated May 24, 2010, and was supplemented by a
letter dated June 2, 2010. In particular, pursuant to Title 10 of the
Code of Federal Regulations (10 CFR) Section 52.39(e), the request
seeks to amend the ESP Site Safety Analysis Report (SSAR) to change the
classification of backfill over the slopes of the Units 3 and 4
excavations from Category 1 and 2 backfill to engineered granular
backfill (EGB).
NRC has prepared an Environmental Assessment (EA) in support of
this amendment in accordance with the requirements of 10 CFR Part 51.
Based on the EA, the NRC has concluded that a Finding of No Significant
Impact (FONSI) is appropriate. The NRC staff's review of the safety
aspects of the amendment request will be documented in a separate
safety evaluation report (SER); if warranted by the results of that
evaluation, the amendment would be issued following the publication of
this Notice.
II. EA Summary
The purpose of the proposed amendment is to authorize a change to
the early site permit issued to SNC for the Vogtle Electric Generating
Plant ESP site located in Burke County, Georgia. Specifically, the
proposed amendment would modify the Vogtle Electric Generating Plant
ESP SSAR to change the classification of backfill over the slopes of
the Units 3 and 4 excavations from Category 1 and 2 backfill to EGB.
The NRC staff has prepared an EA in support of its review of the
proposed action. On the basis of this EA, the NRC finds that there are
no significant environmental impacts from the proposed action. The LAR
would not change the total quantity or locations of backfill material
to be obtained from onsite sources, and the impacts of acquiring EGB
from the specified areas located within the VEGP site would remain
within the scope of environmental impacts previously analyzed in the
Final Environmental Impact Statement (FEIS) for the VEGP ESP and in the
EAs for Amendments 1 and 2 to the VEGP ESP and LWA, and found not to be
significant. Accordingly, the NRC staff has determined that there would
be no significant environmental impacts associated with granting the
LAR request.
III. Finding of No Significant Impact
On the basis of the EA, the NRC has concluded that there are no
significant environmental impacts from the proposed amendment and has
determined not to prepare an environmental impact statement.
IV. Further Information
The ESP amendment request is available electronically at the NRC's
Electronic Reading Room at http://www.nrc.gov/reading-rm/adams.html.
From this site, persons can access the NRC's Agency-wide Documents
Access and Management System (ADAMS). The ADAMS accession number for
the May 24, 2010, amendment request is ML101470213 and the accession
number for the June 2 supplement is ML101550510. The ADAMS accession
number for the EA is ML101660076. The ADAMS accession numbers for the
ESP FEIS are ML082240145 and ML082240165, ML082260203, and ML082550040.
The ADAMS accession numbers for the EAs for Amendment 1 and Amendment 2
to the ESP are ML101380114 and ML101670592, respectively. If persons do
not have access to ADAMS or have problems accessing the documents
located in ADAMS, contact the NRC Public Document Room Reference staff
at 1-800-397-4209, or 301-415-4737, or via e-mail to
pdr.resource@nrc.gov.
These documents may also be viewed electronically on the public
computers located at the NRC's Public Document Room (PDR), O 1 F21, One
White Flint North, 11555 Rockville Pike, Rockville, MD 20852. The PDR
reproduction contractor will copy documents for a fee.
Dated at Rockville, Maryland, this 28th day of June 2010.
For the Nuclear Regulatory Commission,
Jeffrey Cruz,
Chief, AP1000 Branch 1, Division of New Reactors Licensing, Office of
New Reactors.