Takes of Marine Mammals Incidental to Specified Activities; Manette Bridge Replacement in Bremerton, Washington, 38783-38791 [2010-16370]
Download as PDF
Federal Register / Vol. 75, No. 128 / Tuesday, July 6, 2010 / Notices
wwoods2 on DSK1DXX6B1PROD with NOTICES_PART 1
provide to the Department a reasonable
basis to believe or suspect that the
products are being utilized in a covered
application. If such information is
provided, we will require end-use
certification only for the product(s) (or
specification(s)) for which evidence is
provided that such products are being
used in a covered application as
described above. For example, if, based
on evidence provided by petitioner, the
Department finds a reasonable basis to
believe or suspect that seamless pipe
produced to the A–335 specification is
being used in an A–106 application, we
will require end-use certifications for
imports of that specification. Normally
we will require only the importer of
record to certify to the end use of the
imported merchandise. If it later proves
necessary for adequate implementation,
we may also require producers who
export such products to the United
States to provide such certification on
invoices accompanying shipments to
the United States.
Although the HTSUS subheadings are
provided for convenience and customs
purposes, our written description of the
merchandise subject to this scope is
dispositive.
Rescission of the Administrative
Review
As noted above, all four of the
potential respondents submitted letters
to the Department indicating that they
did not make any shipments or entries
of subject merchandise to the United
States during the POR. In response to
the Department’s query to CBP, CBP
data showed subject merchandise
manufactured by one of the respondent
companies, SMI, was entered for
consumption into the United States
during the POR from third countries. On
December 31, 2009, the Department
placed on the record of this review
copies of the entry documents in
question.
Additionally, on December 31, 2009,
the Department sent a letter to SMI
requesting that SMI further substantiate
its claim of no shipments. On January
28, 2010, SMI responded that it had no
knowledge of the entries in question. In
its response, SMI explained in detail
how its claim of no knowledge is
supported by the record evidence. See
Memorandum to the File, from Mary
Kolberg, International Trade
Compliance Analyst, ‘‘Intent to Rescind
the Antidumping Duty Administrative
Review on Certain Large Diameter
Carbon and Alloy Seamless Standard,
Line, and Pressure Pipe from Japan,’’
March 12, 2010 (‘‘Intent to Rescind
Memo’’). On the basis of these
documents and SMI’s submission, the
VerDate Mar<15>2010
14:52 Jul 02, 2010
Jkt 220001
Department concluded that there is no
evidence on the record that, at the time
of the sale, SMI had knowledge that any
of these entries of subject merchandise
entered the United States during the
POR. Specifically, subject merchandise
produced by SMI entered the United
States during the POR under its
antidumping case number, but without
the company’s knowledge by way of
intermediaries.
On March 12, 2010, the Department
notified interested parties of its intent to
rescind this administrative review and
gave parties until March 22, 2010 to
provide comments. No comments were
received. See Intent to Rescind Memo.
Subsequent to that, in response to the
Department’s earlier no shipments
inquiry, CBP notified us on March 31,
2010, of additional POR entries of
consumption of subject merchandise,
shipped from a third country that were
manufactured by respondent company,
JFE Steel. On April 14, 2010, the
Department placed on the record copies
of these entry documents and asked JFE
Steel to comment on the company’s no
shipment claim in light of the CBP data.
On May 13, 2010, JFE Steel responded
to the Department. In its response, JFE
Steel addressed each entry in detail,
explained how JFE Steel’s claim of no
knowledge is supported by the evidence
on record, and reiterated that JFE Steel
had no knowledge of the entries in
question. See Memorandum to the File,
from Mary Kolberg, International Trade
Compliance Analyst, ‘‘Reiteration of
Intent to Rescind the Antidumping Duty
Administrative Review on Certain Large
Diameter Carbon and Alloy Seamless
Standard, Line, and Pressure Pipe from
Japan,’’ June 3, 2010 (‘‘Reiteration of
Intent to Rescind Memo’’).
On the basis of these documents and
JFE Steel’s submission, the Department
concluded that there is no evidence on
the record that, at the time of the sale,
JFE Steel had knowledge that those
entries were destined for the United
States, nor is there evidence that JFE
Steel had knowledge that any of these
entries of subject merchandise entered
the United States during the POR.
Specifically, subject merchandise
produced by JFE Steel entered the
United States during the POR under its
antidumping case number, but without
the company’s knowledge by way of
intermediaries.
The Department reiterated this intent
to rescind on June 3, 2010, giving
parties until June 14, 2010 to provide
comments. Again, no comments were
received. See Reiteration of Intent to
Rescind Memo.
Thus, the Department finds that the
respondents’ claims of no shipments or
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
38783
entries for consumption to be
substantiated. Based upon the
certifications and the evidence on the
record, we are satisfied that no
respondent had shipments of subject
merchandise to the United States during
the POR. Pursuant to 19 CFR
351.213(d)(3), the Department may
rescind an administrative review, in
whole or with respect to a particular
exporter or producer, if the Secretary
concludes that, during the period
covered by the review, there were no
entries, exports, or sales of the subject
merchandise. Therefore, the Department
is rescinding this review in accordance
with 19 CFR 351.213(d)(3).
The Department intends to instruct
CBP 15 days after the publication of this
notice to liquidate such entries.
Antidumping duties shall be assessed at
rates equal to the cash deposit of
estimated antidumping duties required
at the time of entry, or withdrawal from
warehouse, for consumption, in
accordance with 19 CFR 351.212(c)(2).
We are issuing and publishing this
notice in accordance with sections
751(a)(1) 777 (i) of the Act and 19 CFR
351.213(d)(4).
Dated: June 29, 2010.
John M. Andersen
Acting Deputy Assistant Secretary for
Antidumping and Countervailing Duty
Operations.
[FR Doc. 2010–16354 Filed 7–2–10; 8:45 am]
BILLING CODE 3510–DS–P
DEPARTMENT OF COMMERCE
National Oceanic and Atmospheric
Administration
RIN 0648–XU03
Takes of Marine Mammals Incidental to
Specified Activities; Manette Bridge
Replacement in Bremerton,
Washington
AGENCY: National Marine Fisheries
Service (NMFS), National Oceanic and
Atmospheric Administration (NOAA),
Commerce.
ACTION: Notice; issuance of incidental
harassment authorization.
SUMMARY: In accordance with the
regulations implementing the Marine
Mammal Protection Act (MMPA) as
amended, notification is hereby given
that NMFS has issued an Incidental
Harassment Authorization (IHA) to the
Washington State Department of
Transportation (WSDOT), to
incidentally harass, by Level B
harassment only, small numbers of
marine mammals during the specified
activity.
E:\FR\FM\06JYN1.SGM
06JYN1
38784
Federal Register / Vol. 75, No. 128 / Tuesday, July 6, 2010 / Notices
wwoods2 on DSK1DXX6B1PROD with NOTICES_PART 1
DATES: This authorization is effective
from June 29, 2010, through June 28,
2011.
ADDRESSES: A copy of the IHA and the
application are available by writing to P.
Michael Payne, Chief, Permits,
Conservation and Education Division,
Office of Protected Resources, National
Marine Fisheries Service, 1315 EastWest Highway, Silver Spring, MD
20910–3225. A copy of the application
may be obtained by writing to this
address, by telephoning the contact
listed here (FOR FURTHER
INFORMATION CONTACT) or online
at: https://www.nmfs.noaa.gov/pr/
permits/incidental.htm#applications
Documents cited in this notice may be
viewed, by appointment, during regular
business hours, at the aforementioned
address.
FOR FURTHER INFORMATION CONTACT:
Shane Guan, Office of Protected
Resources, NMFS, (301) 713–2289, ext
137.
SUPPLEMENTARY INFORMATION:
Background
Section 101(a)(5)(D) of the MMPA (16
U.S.C. 1371 (a)(5)(D)) directs the
Secretary of Commerce to authorize,
upon request, the incidental, but not
intentional, taking by harassment of
small numbers of marine mammals of a
species or population stock, for periods
of not more than one year, by United
States citizens who engage in a specified
activity (other than commercial fishing)
within a specific geographic region if
certain findings are made and, a notice
of a proposed authorization is provided
to the public for review.
Authorization for incidental takings
shall be granted if NMFS finds that the
taking will have a negligible impact on
the species or stock(s), will not have an
unmitigable adverse impact on the
availability of the species or stock(s) for
subsistence uses (where relevant), and if
the permissible methods of taking and
requirements pertaining to the
mitigation, monitoring and reporting of
such takings are set forth. NMFS has
defined ‘‘negligible impact’’ in 50 CFR
216.103 as ’’...an impact resulting from
the specified activity that cannot be
reasonably expected to, and is not
reasonably likely to, adversely affect the
species or stock through effects on
annual rates of recruitment or survival.’’
Section 101(a)(5)(D) of the MMPA
established an expedited process by
which citizens of the United States can
apply for an authorization to
incidentally take small numbers of
marine mammals by harassment.
Section 101(a)(5)(D) establishes a 45–
day time limit for NMFS review of an
VerDate Mar<15>2010
14:52 Jul 02, 2010
Jkt 220001
application followed by a 30–day public
notice and comment period on any
proposed authorizations for the
incidental harassment of marine
mammals. Within 45 days of the close
of the comment period, NMFS must
either issue or deny the authorization.
Except with respect to certain
activities not pertinent here, the MMPA
defines ‘‘harassment’’ as:
any act of pursuit, torment, or annoyance
which (i) has the potential to injure a marine
mammal or marine mammal stock in the wild
[Level A harassment]; or (ii) has the potential
to disturb a marine mammal or marine
mammal stock in the wild by causing
disruption of behavioral patterns, including,
but not limited to, migration, breathing,
nursing, breeding, feeding, or sheltering
[Level B harassment].
Summary of Request
NMFS received an application on
December 24, 2009, from WSDOT for
the taking, by harassment, of marine
mammals incidental to construction and
demolition work related to the Manette
Bridge replacement in Bremerton,
Washington, starting in early June 2010.
The Manette Bridge is located within
the Puget Sound of Washington State, at
the outlet to the Port Washington
Narrows. The Port Washington Narrows
provides the only outlet from Dyes Inlet
to Sinclair Inlet, and connection to the
greater Puget Sound. The Manette
Bridge is determined to be a
functionally obsolete and structurally
deficient bridge that requires
replacement, and the WSDOT is
planning to have it replaced. The
proposed bridge replacement work
includes the following activities:
• Construction of temporary work
trestles, which involves steel pile
installation using both vibratory and
impact driving methods;
• Construction of new bridge piers,
which involves excavation of benthic
material;
• Barge anchoring and usage;
• Removal of existing bridge; and
• Removal of temporary work
platforms.
Since marine mammal species and
stocks in the proposed action area could
be affected by the proposed bridge
replacement activities, the WSDOT is
seeking an IHA that would allow the
incidental, but not intentional, take of
marine mammals by Level B behavioral
harassment during the construction of
the new Manette Bridge and removal of
the existing bridge. The WSDOT states
that small numbers of three species of
marine mammals could potentially be
taken by pile driving or other
construction activities associated with
the bridge replacement work. However,
with the required mitigation and
PO 00000
Frm 00021
Fmt 4703
Sfmt 4703
monitoring measures, the numbers and
levels of marine mammal takes would
be reduced to the least amount
practicable.
Description of the Specific Activity
WSDOT will conduct construction
and demolishing activities associated
with the Manette Bridge replacement
project in Bremerton, WA, starting from
June 2010 and lasting for approximately
three years. However, no in-water
activities will be planned between
March 1 and June 14 in water below the
ordinary high water line.
NMFS provided a detailed overview
of the activity in the notice of the
proposed IHA (75 FR 13502, March 22,
2010) and in the WSDOT’s IHA
application. No changes have been
made to the proposed activities.
The following is a summarized
description of the sequence of
anticipated work activities associated
with the Manette Bridge replacement
project.
1. Construction of Work Trestles and
Falsework Towers
Separate work trestles would be
constructed for the new bridge
construction and existing bridge
removal processes. The south trestles for
access to the new bridge site would be
constructed prior to the installation of
the north trestles for bridge removal.
The work trestles and associated
falsework towers would be supported
on steel pilings with diameters of 24 to
36 in. (0.61 to 0.91 m). The construction
of the work trestles is estimated to take
up to 9 months. The work trestles and
falsework towers would be in place
throughout the project duration,
approximately 3 years.
The trestles would be located a few
feet above the high water mark, with the
exact height determined by the
contractor and work site conditions. The
trestles would be supported by steel
girders attached to the piles and the
deck would be composed of timbers.
The new bridge construction work
trestle would be supported by up to 360
piles and could cover an area of up to
40,000 ft2 (3,716 m2). The bridge
removal work trestle will be supported
by up to 170 piles and could cover an
area of up to 15,900 ft2 (1,477 m2). Up
to 12 additional piles may be used for
project related moorage.
All piles would be installed using a
vibratory hammer unless an impact
hammer is needed to drive a pile
through consolidated material or meet
bearing. Currently, pile driving is
scheduled to occur July 1 to August 20,
2010, and October 6, 2010, to January
31, 2011, with an estimated 45 minutes
E:\FR\FM\06JYN1.SGM
06JYN1
Federal Register / Vol. 75, No. 128 / Tuesday, July 6, 2010 / Notices
per pile and 410 total hours of pile
driving using a vibratory hammer. Pile
driving activities would occur daily two
hours after sunrise to two hours before
sunset between April 1 and September
15, 2010. No pile driving will occur
during nighttime hours.
2. Barge Anchoring and Usage
Barges would be used extensively
throughout the project duration to
provide access to work areas, support
machinery, deliver and stage materials,
and as a collection surface for spoils,
construction debris, and materials from
demolition. The actual number and
dimensions of barges to be used would
be determined by the contractor and
work site conditions. However, it is
estimated that up to 6 barges would be
used at one time. A typical barge
dimension is approximately 290 ft (88.4
m) in length and 50 ft (15.2 m) in width.
Typical barge draft is 4 to 8 ft (1.22 to
2.44 m) and typical freeboard is 3 to 6
ft (0.91 to 1.83 m). Barges would be used
throughout the construction period,
approximately 3 years.
During working hours, barges would
be attached to mooring lines, the work
trestles, or to other portions of the
project area, depending on the
construction and access needs. Up to 6
temporary buoys may be installed to
moor barges during non-working hours.
These buoys would be attached to one
or more anchors, which may need to be
driven, or excavated, due to hard
ground and strong currents in the
project area. If the contractor chooses to
deploy a dynamic barge positioning
system, it is expected that the hours the
system is in use would coincide closely
with pile driving activities.
wwoods2 on DSK1DXX6B1PROD with NOTICES_PART 1
3. Construction of New Piers
Eight piers would support the new
bridge, six in-water and two upland.
The existing bridge has 13 piers, nine
in-water and three upland. The total
footprint of the piers would be 1,416 ft2
(131.6 m2). The footprint of the nine inwater piers supporting the existing
bridge is 8,726 ft2 (810.7 m2).
Piers 1 and 8 are the bridge abutments
and are located well above the mean
high water line (MHW). Piers 2 through
7 are located below the MLLW line. The
construction of the in-water piers (2
through 7) would take up to 18 months.
The construction of the abutment piers
(1 and 8) would occur during the bridge
closure period (targeted duration of 3
months). The construction of each
would include excavation of up to 3
shafts to support each pier, concrete
pouring of each shaft, and construction
of piers on top of new shafts.
VerDate Mar<15>2010
14:52 Jul 02, 2010
Jkt 220001
Shaft casings would be installed and
the shafts will be excavated using
equipment positioned on the work
trestles or barges.
To create a drilled shaft, a steel casing
approximately 6 to 10 ft (1.8 to 3 m) in
diameter is driven into the substrate
using a vibratory hammer, and the
material inside the casing is excavated
using an auger or a clamshell dredge.
During excavation a premixed bentonite
or synthetic polymer slurry is
sometimes added to stabilize the walls
of the shaft. Spoils from shaft
excavation would be placed in a large
steel containment box located on a barge
or on the work trestle for offsite
transport. During the drilling, polymer
slurry is typically placed into the hole
to keep side walls of the shaft from
caving.
After completion of the excavation, a
steel reinforcing cage is placed into the
hole to specified elevations. Concrete is
then pumped into the hole using a
tremie tube placed at the bottom of the
excavation. As concrete is placed the
tremie tube is raised but is maintained
within the concrete. As the concrete is
pumped into the hole, the slurry is
displaced upward and removed from
the top concrete using a vacuum hose.
The slurry is pumped from the hole into
large tanks located on the work trestle
or on a barge, which is either recycled
for use in the next shaft or transported
off site. This procedure would be used
on all shafts at each pier.
After shafts are completed, pre-cast
concrete, stay-in-place forms would be
stacked on top of the shafts up to the
crossbeam elevation. A steel reinforcing
cage would be placed inside the
concrete forms and the columns would
be filled with concrete. A pre-cast
concrete crossbeam or a cast-in-place
crossbeam, or some combination of both
would be constructed on top of the
columns. Girders would be fabricated
off site and would be shipped to the site
on barges. The girders would then be
placed on the piers and falsework
towers between piers 2 and 7.
After completion of the girder
placement and casting of diaphragms
connecting the girders, post-tensioning
strands would be placed into ducts cast
in the girders. The post-tensioning
strands will then be stressed. The
roadway deck would then be formed
and cast between piers 2 and 7.
4. Installation of Girders and Decking
Girders and decking would be
installed using the work trestles,
falsework towers, and cranes deployed
on work barges. The roadway deck
would be made of concrete and would
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
38785
be poured in place. This work is
expected to take 3 to 4 months.
5. Reconfiguration of Abutments and
Roadway Approaches
The existing bridge abutments would
be removed, along with the associated
retaining walls. New retaining walls and
abutments would be constructed. These
activities, and associated construction
access would require the temporary
disturbance of 0.75 acre of land, of
which 0.15 acre are vegetated, and
permanent removal of 0.15 acre of
vegetation. This work, all in upland
areas, includes 2000 cubic yards of fill.
Once the abutments are complete, the
new bridge approach roadways will be
constructed. Disturbed areas on the east
shore of the Port Washington Narrows
would be restored with a mix of native
trees and shrubs including marine
riparian vegetation and shoreline
enhancement.
6. Demolition of Existing Bridge
The demolition of the existing bridge
would occur in phases over a period of
18 months. After the central portion of
the new bridge is constructed, the
outermost spans and abutments of the
existing bridge would be demolished.
Once the new abutments and outer
spans are constructed, the demolition of
the remainder of the existing bridge will
proceed. Conceptual demolition plan
sheets are included in Appendix D of
the WSDOT IHA application.
The bridge structure above the water
line would be cut into manageable
sections, using conventional concrete
and metal cutting tools, or a wire saw,
and placed on barges for transport to
approved waste or recycling sites. The
portions of the piers below the water
line would be cut into pieces using a
wire saw. All slurry from wire cutting
operations above the water line would
be contained and removed. All slurry
from wire cutting operations below the
water line would be dispersed by the
current. Piers would be cut off at the
ground level except for one, Pier 4. Pier
4 was built up to encapsulate original
creosote treated timbers. Complete
removal of the pier is not feasible and
if it is cut at the ground level, many
creosote treated timbers may be
exposed. To minimize the risk of
contamination, Pier 4 would be cut two
feet above ground level.
7. Removal of Falsework Towers and
Work Trestles
Once the demolition of the existing
bridge is complete, the falsework towers
and work trestles would be removed.
Decking and girders would be placed on
barges for transportation off-site. Piles
E:\FR\FM\06JYN1.SGM
06JYN1
38786
Federal Register / Vol. 75, No. 128 / Tuesday, July 6, 2010 / Notices
would be removed using vibratory
hammers, based on barges. The removal
of the falsework towers and work
trestles is expected to occur over 4 to 6
months.
Vibratory extraction is a common
method for removing steel piling. The
pile is unseated from the sediments by
engaging the hammer and slowly lifting
up on the hammer with the aid of the
crane. Once unseated, the crane would
continue to raise the hammer and pull
the pile from the sediment. When the
pile is released from the sediment, the
vibratory hammer is disengaged and the
pile is pulled from the water and placed
on a barge for transfer upland.
wwoods2 on DSK1DXX6B1PROD with NOTICES_PART 1
Comments and Responses
NMFS published a notice of receipt of
the WSDPT application and proposed
IHA in the Federal Register on March
22, 2010 (75 FR 13502). During the 30–
day comment period, NMFS received a
letter from the Marine Mammal
Commission (Commission) and a private
citizen. Both the Commission and the
private citizen recommended that
NMFS issue the requested
authorization. The Commission further
states that the authorization should be
issued provided that the required
monitoring and mitigation measures are
carried out (e.g., establishing of the
safety zones and take zones, marine
mammal monitoring during in-water
construction activities, and ramp-up for
pile driving) as described in NMFS’
March 22, 2010 (75 FR 13502), notice of
the proposed IHA and the application.
All measures proposed in the initial
Federal Register notice are included in
the authorization and NMFS has
determined that they will effect the least
practicable impact on the species or
stocks and their habitats.
Description of Marine Mammals in the
Area of the Specified Activity
Six marine mammal species/stocks
occur in the area where the proposed
Manette Bridge replacement work is
planned. These six species/stocks are:
Pacific harbor seal (Phoca vitulina
richardsi), California sea lion (Zalophus
californianus), Steller sea lion
(Eumetopias ubatus), transient and
Southern Resident killer whales
(Orcinus orca), and gray whale
(Eschrichtius robustus). All these
marine mammals have been observed in
southern Puget Sound during certain
periods of the year and may occur in
Sinclair Inlet, Port Washington Narrows
and Dyes Inlet, although direct
observation in the vicinity of the
Manette Bridge may not be documented.
General information on these marine
mammal species can be found in Caretta
VerDate Mar<15>2010
14:52 Jul 02, 2010
Jkt 220001
et al. (2008), which is available at the
following URL: https://
www.nmfs.noaa.gov/pr/pdfs/sars/
po2009.pdf. Refer to that document for
information on these species.
To further gather information on the
occurrence of these marine mammal
species in the vicinity of the proposed
project area, the WSDOT contracted ten
surveys between the months of July
2006 and January 2007. This time
period was chosen for sampling because
it represents the time period when most
in-water work activities would occur.
Two pinniped species and zero
cetaceans were observed. Thirty four
harbor seals, one California sea lion and
one unidentified pinniped, likely a
California sea lion, were observed over
the six month period. In general,
cetacean observations are infrequent in
the Puget Sound (Calambokidis and
Baird 1994, Jefferies 2007). During ten
surveys for marine mammals in Sinclair
Inlet and Port Washington Narrows
between July 2006 and January 2007, no
cetaceans were observed. No marine
mammals were observed during two of
the ten surveys. Detailed results of the
surveys are provided in a final report,
which is included in Appendix E of the
WSDOT IHA application.
Additional information on these
species, particularly in relation to their
occurrence in the proposed project area,
is provided in the March 22, 2010,
Federal Register notice (75 FR 13502).
Please refer to that document for this
information.
Potential Effects on Marine Mammals
and Their Habitat
Anticipated impacts resulting from
the Manette Bridge Replacement project
include disturbance from increased
human presence and marine traffic if
marine mammals are in the vicinity of
the proposed project area, Level B
harassment by noises generated from the
construction work such as pile driving
and dredging activities, and the effect of
the new bridge and stormwater system
on water quality. A detailed discussion
of these effects from various
construction and demolishing activity
components is provided in the March
22, 2010, Federal Register notice (75 FR
13502). These potential effects are
expected to be localized and short-term.
In addition, none of these potential
impacts is believed to be biologically
significant to the survival and
reproduction of marine mammals and
their habitat in the vicinity of the
proposed project. Please refer to that
document for this information.
PO 00000
Frm 00023
Fmt 4703
Sfmt 4703
Mitigation Measures
In order to issue an incidental take
authorization under Section 101(a)(5)(D)
of the MMPA, NMFS must set forth the
permissible methods of taking pursuant
to such activity, and other means of
effecting the least practicable adverse
impact on such species or stock and its
habitat, paying particular attention to
rookeries, mating grounds, and areas of
similar significance, and on the
availability of such species or stock for
taking for certain subsistence uses.
For the proposed Manette Bridge
replacement project, the WSDOT
worked with NMFS and formulated the
following mitigation measures to
minimize the potential impacts to
marine mammals in the project vicinity
as a result of the construction activities.
1. Overall Construction Activities
All construction shall be performed in
accordance with the current WSDOT
Standard Specifications for Road,
Bridge, and Municipal Construction.
Special Provisions contained in
contracts are used in conjunction with,
and supersede, any conflicting
provisions of the Standard
Specifications.
WSDOT activities are subject to state
and local permit conditions. WSDOT
shall use the best guidance available
(e.g., best management practices and
conservation measures) to accomplish
the necessary work while avoiding and
minimizing environmental impacts to
the greatest extent possible.
The WSDOT contractor is expected to
be responsible for the preparation of a
Spill Prevention, Control, and
Countermeasures plan to be used for the
duration of the project. The plan would
be submitted to the WSDOT Project
Engineer prior to the commencement of
any construction activities. A copy of
the plan with any updates will be
maintained at the work site by the
contractor. A detailed discussion of the
plan is provided in the WSDOT’s IHA
application.
2. Equipment Noise Standards
To mitigate noise levels and,
therefore, impacts to marine mammals,
all the construction equipment shall
comply with applicable equipment
noise standards of the U.S.
Environmental Protection Agency, and
all construction equipment shall have
noise control devices no less effective
than those provided on the original
equipment.
3. Timing Windows
Timing restrictions are used to avoid
construction activities that generate
relatively intense underwater noises
E:\FR\FM\06JYN1.SGM
06JYN1
Federal Register / Vol. 75, No. 128 / Tuesday, July 6, 2010 / Notices
wwoods2 on DSK1DXX6B1PROD with NOTICES_PART 1
(i.e., pile driving, dredging, and
dynamic positioning) when ESA-listed
species are most likely to be present. If
an ESA-listed marine mammal species
is detected in the vicinity of the project
area, pile driving and dredging
operations shall be halted and stationing
construction vessels will turn off
dynamic positioning systems. WSDOT
shall comply with all in-water timing
restrictions as determined through the
MMPA take authorization. Pile driving
activities shall only be conducted
during daylight hours. If the safety zone
(see below) is obscured by fog or poor
lighting conditions, impact pile driving
will not be initiated until the entire
safety zone is visible. In addition, no inwater work shall be conducted between
March 1 and June 14 in water below the
ordinary high water line.
4. Establishment of Zones of Safety and
Influence
For impact pile driving, the safety
zones are defined as the areas where
received SPLs from the noise source
exceed 180 dB re 1 μPa (rms) for
cetaceans or 190 dB re 1 μPa (rms) for
pinnipeds. Repeated and prolonged
exposure to SPLs above these values
may cause TTS to cetaceans and
pinnipeds, respectively. The radii of the
safety zones shall be determined
through empirical measurements of
acoustic data. Prior to acquiring acoustic
data, the safety zones shall be
established based on the worst-case
scenario measured from impact pile
driving of 36–inch (0.91 m) steel pile
conducted elsewhere, such as the
Anacortes or Mukiteo ferry terminals.
Acoustic measurements indicate that
source levels are approximately 201 dB
re 1 μPa (rms) at 10 m for both pile
driving activities for Anacortes and
Mukiteo ferry terminal constructions
when the 36–inch (0.91 m) piles were
hammered in (Laughlin 2007; Sexton
2007). Approximation of the received
levels of 180 and 190 dB re 1 μPa (rms)
by using an acoustic propagation
spreading model between spherical and
cylindrical propagation,
TL = 15log(R]/RSL),
where TL is the transmission loss (in
dB), RRL is the distance at received
levels (either 180 or 190 dB), and RSL
is the distance (10 m) at source level
(201 dB). The results show that the
distances for received levels 180 and
190 dB re 1 μPa (rms) are approximately
251 m and 54 m, respectively. NMFS
expects that the modeled safety zones
are reasonably conservative as the
propagation model does not take into
consideration other transmission loss
factors such as sound absorption in the
water column.
VerDate Mar<15>2010
14:52 Jul 02, 2010
Jkt 220001
Once impact pile driving begins,
NMFS requires that the contractor
adjust the size of the safety zones based
on actual measurements of SPLs at
various distances to determine the most
conservative (the largest) safety zones at
which the received levels are 180 and
190 dB re 1 μPa (rms).
Since the source levels for vibratory
pile driving are expected to be under
180 dB re 1 μPa (rms) at 10 m, no safety
zones would be established for vibratory
pile driving.
In addition, WSDOT and its
contractor shall establish zones of
influence (ZOIs) at received levels of
160 and 120 dB re 1 μPa (rms) for
impulse noise (noise from impact pile
driving) and non-impulse noise (such as
noise from vibratory pile driving and
dynamic positioning system),
respectively. These SPLs are expected to
cause Level B behavioral harassment to
marine mammals. The model based
approximation for the distance at 160
dB received level is 5,412 m from pile
driving based on the most conservative
measurements from the Anacortes or
Mukiteo ferry terminal construction
(201 dB re 1 μPa (rms) at 10 m; Laughlin
2007; Sexton 2007), using the same
spreading model discussed above. Once
impact pile driving starts, the contractor
shall conduct empirical acoustic
measurements to determine the most
conservative distance (the largest
distance from the pile) where the
received levels begin to fall below 160
dB re 1 μPa (rms).
As far as non-pulse noises are
concerned, for which the Level B
behavioral harassment is set at a
received level of 120 dB re 1 μPa, no
simple modeling is available to
approximate the distance (though direct
calculation using the spreading model
puts the 120 dB received level at 100
km, this simple approximation no
longer works at this long distance due
to range-dependent propagation
involving complex sound propagation
behavior that cannot be ignored). NMFS
uses the empirical underwater acoustic
measurements from vibratory pile
driving of 42 48–inch (1.06 1.22 m)
diameter piles at the San FranciscoOakland Bay Bridge construction as a
model and expects that the distance at
a received level of 120 dB is less than
1,900 m from the pile (CALTRANS
2009). Likewise, WSDOT and its
contractor shall conduct empirical
acoustic measurements to determine the
actual distance of 120 dB re 1 μPa (rms)
from the pile.
All safety and influence zones shall
be monitored for marine mammals prior
to and during construction activities.
Please refer to the Monitoring and
PO 00000
Frm 00024
Fmt 4703
Sfmt 4703
38787
Reporting Measures section for a
detailed description of monitoring
measures.
5. Shutdown Measures
To prevent marine mammals from
exposure to intense sounds that could
potentially lead to TTS (i.e., received
levels above 180 dB and 190 dB re 1 μPa
(rms) for cetaceans and pinnipeds,
respectively), no impact pile driving
shall be initiated when marine
mammals are detected within these
safety zones. In addition, during impact
driving, when a marine mammal is
detected within the respective safety
zones or is about to enter the safety
zones, impact pile driving shall be
halted and shall not be resumed until
the animal is seen to leave the safety
zone on its own, or 30 minutes has
elapsed until the animal is last seen.
Pile driving and dredging activities
shall be suspended when ESA-listed
marine mammals (Steller sea lion and
killer whale) are detected within the
zone of behavioral harassment (160 dB
re 1 μPa for impulse sources and 120 dB
re 1 μPa for non-impulse sources) and
that all vessels’ dynamic positioning
systems would be turned off. Therefore,
no take of ESA-listed marine mammal
species or stocks is expected.
6. ‘‘Soft Start’’ Impact Pile Driving or
Ramp-up
Although marine mammals will be
protected from Level A harassment by
establishment of an air-bubble curtain
during impact pile driving and marine
mammal observers monitoring a safety
zone, monitoring may not be 100
percent effective at all times in locating
marine mammals. Therefore, a ‘‘softstart’’ technique shall be used at the
beginning of each day’s in-water pile
driving activities or if pile driving has
ceased for more than one hour to allow
any marine mammal that may be in the
immediate area to leave before pile
driving reaches full energy.
For vibratory pile driving, the soft
start requires contractors to initiate
noise from vibratory hammers for 15
seconds at reduced energy followed by
a one minute waiting period. The
procedure shall be repeated two
additional times. If an impact hammer
is used on a pile greater than 10 inches
in diameter, contractors shall be
required to provide an initial set of three
strikes from the impact hammer at 40
percent energy, followed by a one
minute waiting period, then two
subsequent 3–strike sets. This should
expose fewer animals to loud sounds
both underwater and above water noise.
This would also ensure that, although
not expected, any pinnipeds and
E:\FR\FM\06JYN1.SGM
06JYN1
38788
Federal Register / Vol. 75, No. 128 / Tuesday, July 6, 2010 / Notices
cetaceans that are missed during safety
zone monitoring will not be injured.
wwoods2 on DSK1DXX6B1PROD with NOTICES_PART 1
7. Sound Attenuation Measures
All steel piles shall be installed using
a vibratory hammer until an impact
hammer is needed for bearing or if a pile
encounters consolidated material. If
vibratory installation is not possible due
to the substrate, an impact pile driver
would be used. An air bubble curtain(s)
shall be employed during impact
installation of all steel piles. Detailed
description and specification of the air
bubble curtain system is provided in
Appendix C of the WSDOT’s IHA
application.
WSDOT shall provide bubble curtain
performance criteria to the contractor,
which include:
• Piling shall be completely engulfed
in bubbles over the full depth of the
water column at all times when an
impact pile driver is in use.
• The lowest bubble ring shall be in
contact with the mud line for the full
circumference of the ring. The weights
attached to the bottom ring shall ensure
complete mud line contact. No parts of
the ring or other objects shall prevent
the full mud line contact.
• Bubblers shall be constructed of
minimum 2–inch (5.1–cm) inside
diameter aluminum pipe with 1/16–
inch (0.16–cm) diameter bubble release
holes in four rows with 3/4–inch (1.9–
cm) spacing in the radial and axial
directions. Bubblers shall be durable
enough to withstand repeated
deployment during pile driving and
shall be constructed to facilitate
underwater setup, knockdown, and
reuse on the next pile.
• One or more compressors shall be
provided to supply air in sufficient
volume and pressure to self-purge water
from the bubblers and maintain the
required bubble flux for the duration of
pile driving. Compressors shall be of a
type that prevents the introduction of
oil or fine oil mist by the compressed air
into the water. If there is presence of oil
film or sheen on the water surface in the
vicinity of the operating bubbler, the
contractor shall immediately stop work
until the source of oil film or sheen is
identified and corrected.
• The system shall provide a bubble
flux of 3.0 cubic meters (m3) per minute
per linear meter of pipe in each layer
(32.91 cubic feet, or 0.93 m3, per minute
per linear foot of pipe in each layer).
The total volume of air per layer is the
product of the bubble flux and the
circumference of the ring:
Vt=3.0 m3/min/m x Circum of the
aeration ring in meters.
or
VerDate Mar<15>2010
14:52 Jul 02, 2010
Jkt 220001
Vt=32.91 ft3/min/ft x Circum of the
aeration ring in meters.
• The bubble ring manifold shall
incorporate a shut off valve, flow meter,
and a throttling globe valve with a
pressure gauge for each bubble ring
supply.
• Prior to first use of the bubble
curtain during pile driving, the fullyassembled system shall be test-operated
to demonstrate proper function and to
train personnel in the proper balancing
of the air flow to the bubblers. The test
shall also confirm the calculated
pressures and flow rates at each
manifold ring. The Contractor shall
submit an inspection/performance
report to WSDOT within 72 hours
following the performance test.
The WSDOT Office of Air Quality and
Noise has prepared a noise monitoring
plan for the Manette Bridge
Replacement Project (Appendix H). To
comply with the provisions of the plan,
the State will conduct hydroacoustic
monitoring during construction to
evaluate in water noise levels.
8. Ensure Regulation Compliance
Finally, a WSDOT inspector shall be
on site during construction. The role of
the inspector is to ensure contract
compliance. The inspector and the
contractor each have a copy of the
Contract Plans and Specifications on
site and are aware of all requirements.
The inspector is also trained in
environmental provisions and
compliance.
NMFS has carefully evaluated the
applicant’s proposed mitigation
measures and considered a range of
other measures in the context of
ensuring that NMFS prescribes the
means of effecting the least practicable
adverse impact on the affected marine
mammal species and stocks and their
habitat. Our evaluation of potential
measures included consideration of the
following factors in relation to one
another:
• the manner in which, and the
degree to which, the successful
implementation of the measure is
expected to minimize adverse impacts
to marine mammals
• the proven or likely efficacy of the
specific measure to minimize adverse
impacts as planned
• the practicability of the measure for
applicant implementation, including
consideration of personnel safety, and
practicality of implementation.
Based on our evaluation of the
applicant’s proposed measures, as well
as other measures considered by NMFS
or recommended by the public, NMFS
has determined that the required
mitigation measures provide the means
PO 00000
Frm 00025
Fmt 4703
Sfmt 4703
of effecting the least practicable adverse
impacts on marine mammals species or
stocks and their habitat, paying
particular attention to rookeries, mating
grounds, and areas of similar
significance.
Monitoring and Reporting Measures
In order to issue an ITA for an
activity, Section 101(a)(5)(D) of the
MMPA states that NMFS must set forth
‘‘requirements pertaining to the
monitoring and reporting of such
taking’’. The MMPA implementing
regulations at 50 CFR § 216.104 (a)(13)
indicate that requests for IHAs must
include the suggested means of
accomplishing the necessary monitoring
and reporting that will result in
increased knowledge of the species and
of the level of taking or impacts on
populations of marine mammals that are
expected to be present. The requireed
monitoring and reporting measures for
the Manette Bridge replacement project
are provided below.
1. Marine Mammal Observers
A minimum of two qualified and
NMFS-approved marine mammal
observers (MMOs) would be present on
site at all times during steel pile driving.
In order to be considered qualified,
WSDOT lists the following requirements
for prospective MMOs:
• Visual acuity in both eyes
(correction is permissible) sufficient for
discernment of moving targets at the
water’s surface with ability to estimate
target size and distance. MMOs shall
use binoculars to correctly identify the
target.
• Advanced education in biological
science, wildlife management,
mammalogy or related fields (Bachelors
degree or higher is preferred).
• Experience and ability to conduct
field observations and collect data
according to assigned protocols (this
may include academic experience).
• Experience or training in the field
identification of marine mammals
(cetaceans and pinnipeds), including
the identification of behaviors.
• Sufficient training, orientation or
experience with the construction
operation to provide for personal safety
during observations.
• Writing skills sufficient to prepare a
report of observations.
• Ability to communicate orally, by
radio or in person, with project
personnel to provide real-time
information on marine mammals
observed in the area as necessary.
2. Marine Mammal Monitoring
WSDOT has developed a monitoring
plan (Appendix G of the WSDOT IHA
E:\FR\FM\06JYN1.SGM
06JYN1
Federal Register / Vol. 75, No. 128 / Tuesday, July 6, 2010 / Notices
wwoods2 on DSK1DXX6B1PROD with NOTICES_PART 1
application) in conjunction with NMFS
that will collect sighting data for each
distinct marine mammal species
observed during the proposed Manette
Bridge replacement construction
activities that generate intense
underwater noise. These activities
include, but are not limited to, impact
and vibratory pile driving, use of
dynamic positioning system by
construction and supporting vessels,
and sediment dredging. Marine mammal
behavior, overall numbers of
individuals observed, frequency of
observation, and the time corresponding
to the daily tidal cycle will also be
included. An example of a marine
mammal sighting form is included in
Appendix I of the WSDOT’s IHA
application.
In addition, for impact pile driving,
the following Marine Mammal
Monitoring Plan and shut down
procedures shall be implemented:
• At least two MMOs shall be on site
to monitor the safety and influence
zones by using a range finder or hand
held global positioning system (GPS)
device. The zone will be monitored by
driving a boat along and within the
radius while visually scanning the area,
and/or monitored from shore if there is
a vantage point that will allow full
observation of the zone.
• If the safety zone is obscured by fog
or poor lighting conditions, pile driving
shall not be initiated until the entire
safety zone is visible.
• The safety zone shall be monitored
for the presence of marine mammals for
30 minutes prior to impact pile driving,
during pile driving, and 20 minutes
after pile driving activities.
• No impact pile driving shall be
started if a marine mammal is detected
within the respective safety zones. Pile
driving may begin if a marine mammal
is seen leaving the safety zone, or 30
minutes has elapsed since the marine
mammal is last seen inside the safety
zone.
• If marine mammals are observed,
their location in relation to the safety
and influence zones, and their reaction
(if any) to pile driving activities shall be
documented.
3. Reporting
WSDOT shall submit weekly marine
mammal monitoring reports from the
time when in-water construction
activities are commenced to NMFS
Office of Protected Resources (OPR).
These weekly reports shall include a
summary of the previous week’s
monitoring activities and an estimate of
the number of marine mammals that
may have been disturbed as a result of
in-water construction activities.
VerDate Mar<15>2010
14:52 Jul 02, 2010
Jkt 220001
In addition, WSDOT shall provide
NMFS OPR with a draft final report
within 90 days after the expiration of
the IHA. This report should detail the
in-water construction and demolishing
activities being conducted, empirically
measured safety zones for pile driving,
and the monitoring protocol; summarize
the data recorded during monitoring;
and estimate the number of marine
mammals that may have been harassed
due to the construction activities. If no
comments are received from NMFS OPR
within 30 days, the draft final report
will be considered the final report. If
comments are received, a final report
must be submitted within 30 days after
receipt of comments.
Estimated Take by Incidental
Harassment
As mentioned earlier in the March 22,
2010, Federal Register (75 FR 13502),
the potential effects to marine mammals
from the proposed activities include
disturbance from increased human
presence and marine traffic and from
noises generated from the construction
work such as pile driving and dredging
activities. The required mitigation
measures of using air bubble curtain
systems would prevent marine
mammals from onset of TTS by impact
pile driving and reduce Level B
behavioral harassment due to the
effective attenuation by the air bubble
systems. Therefore, the following
analyses focus on potential noise
impacts that could cause Level B
behavioral harassment, based on the
WSDOT contracted surveys for the
entire proposed project area (WSDOT
2009).
1. Harbor Seal
There are no harbor seal haulouts
within 3 miles (4.8 km) of the project.
The nearest haulout is in Dyes Inlet and
animals must move through the Port
Washington Narrows to access Sinclair
Inlet and the greater Puget Sound.
Individual harbor seals moving between
Sinclair and Dyes Inlets would be
exposed to project activities.
A total of 34 harbor seals were
detected during ten surveys conducted
during the same time of year pile
driving will occur, between July and
January. The age, sex and reproductive
condition of the animals was not
determined. For the proposed Manette
Bridge replacement activities, it is
reasonable to assume that similar
numbers of animals would be
encountered during an average 10–day
period. WSDOT anticipates that for
every day of construction activities,
between 3 and 4 harbor seals may be
encountered, although it is possible that
PO 00000
Frm 00026
Fmt 4703
Sfmt 4703
38789
some of these animals will be the same
individuals. If in-water construction
activities occur every day of the year
(258 days between June 15 and February
28), approximately 877 harbor seals (or
about 6% of the Washington inland
waters stock of harbor seals) could be
encountered in the vicinity of the
proposed bridge replacement work.
However, it is not likely that every
harbor seal would be taken by Level B
behavioral harassment since not every
animal would be exposed to received
levels above 160 dB re 1 μPa (rms) from
an impulse source (such as impact pile
driving) or above 120 dB re 1 μPa (rms)
from a non-impulse source (such as
vibratory pile driving or dredging).
Likewise, not every single harbor seal
would respond to the sight of human or
vessel traffic in the vicinity of the
project area. Therefore, the estimated
number of 877 represents the upperlimit of the number of harbor seals that
could be affected by Level B behavioral
harassment as a result of exposure to
Manette Bridge replacement related
construction activities.
2. California Sea Lion
There are no California sea lion
haulouts within three miles of the
project. The nearest haulout is in Rich
Passage, east of the Port Washington
Narrows in more open water. Individual
California sea lions moving between
Sinclair and Dyes Inlets could be
exposed to project activities.
A total of one, possibly two California
sea lions were detected during ten
surveys conducted during the same time
of year pile driving would occur,
between July and January. The age, sex
and reproductive condition of the
animals was not determined. For the
proposed Manette Bridge replacement
activities, it is reasonable to assume that
similar numbers of animals would be
encountered during an average 10–day
period. WSDOT anticipates that for
every 10 days of construction activities,
between 1 and 2 California sea lions
may be encountered, although it is
possible that some of these animals will
be the same individuals. If in-water
construction activities occur every day
of the year (258 days between June 15
and February 28), up to 516 California
sea lions (or about 0.2% of the US stock
of California sea lions) could be
encountered in the vicinity of the
proposed bridge replacement work.
However, it is not likely that every
California sea lion would be taken by
Level B behavioral harassment since not
every animal would be exposed to
received levels above 160 dB re 1 μPa
(rms) from an impulse source (such as
impact pile driving) or above 120 dB re
E:\FR\FM\06JYN1.SGM
06JYN1
38790
Federal Register / Vol. 75, No. 128 / Tuesday, July 6, 2010 / Notices
1 μPa (rms) from a non-impulse source
(such as vibratory pile driving or
dredging). Likewise, not every single
California sea lion would respond to the
sight of human or vessel traffic in the
vicinity of the project area. Therefore,
the estimated number of 516 represents
the upper-limit of the number of harbor
seals that could be affected by Level B
behavioral harassment as a result of
exposure to Manette Bridge replacement
related construction activities.
wwoods2 on DSK1DXX6B1PROD with NOTICES_PART 1
3. Steller Sea Lion
As stated earlier, the nearest Steller
sea lion haulout is approximately 12
miles (19.3 km) northeast of the
proposed project area in Shilshole Bay
on the east side of the Puget Sound,
adjacent to the city of Seattle. No Steller
sea lions were sighted during the ten
surveys contracted by WSDOT, and
NMFS considers it is very unlikely that
a Steller sea lion would occur in the
vicinity of the proposed project area.
The implementation of the
aforementioned mitigation measures,
including halting all pile driving and
dredging activities and turning off
construction vessels’ dynamic
positioning systems when a Steller sea
lion is detected about to enter the zone
of influence (received levels at or above
160 dB re 1 μPa (rms) for impulse noise
or 120 dB re 1 μPa (rms) for nonimpulse noise). Therefore, NMFS does
not believe Steller sea lions would be
affected.
4. Killer Whale
Killer whales (southern resident) have
been documented in the project vicinity
once in the last ten years (WSDOT
2009). No killer whales were sighted
during the ten surveys contracted by
WSDOT, and NMFS considers it rare
that a killer whale would occur in the
vicinity of the proposed project area.
The implementation of the
aforementioned mitigation measures,
including halting all pile driving and
dredging activities and turning off
construction vessels’ dynamic
positioning systems when a killer whale
is detected about to enter the zone of
influence (received levels at or above
160 dB re 1 μPa (rms) for impulse noise
or 120 dB re 1 μPa (rms) for nonimpulse noise). Therefore, NMFS does
not believe killer whales would be
affected.
5. Gray Whale
Individual gray whales have been
observed near the project area in four of
the last eight years (WSDOT 2009). No
gray whales were sighted during the ten
surveys contracted by WSDOT, and
NMFS considers it rare that a gray
VerDate Mar<15>2010
14:52 Jul 02, 2010
Jkt 220001
whale would occur in the vicinity of the
proposed project area. Most grays
whales spend winters in their breeding/
calving grounds around Baja California
and summers in feeding grounds around
the Bering Sea and the Arctic. The few
gray whales that occur in the vicinity of
the proposed project area are likely the
ones visiting the area on their northsouth migration route. Based on past
occurrence of gray whales in the area
and using conservative probability
estimate, NMFS considers that no more
than 2 individuals of gray whales
(0.01% of the Eastern North Pacific gray
whale population) would be exposed to
underwater construction noise SPL that
could cause Level B behavioral
harassment annually as a result of the
proposed Manette Bridge replacement
project.
Negligible Impact and Small Numbers
Analysis and Determination
Pursuant to NMFS’ regulations
implementing the MMPA, an applicant
is required to estimate the number of
animals that will be ‘‘taken’’ by the
specified activities (i.e., takes by
harassment only, or takes by
harassment, injury, and/or death). This
estimate informs the analysis that NMFS
must perform to determine whether the
activity will have a ‘‘negligible impact’’
on the species or stock. Level B
(behavioral) harassment occurs at the
level of the individual(s) and does not
assume any resulting population-level
consequences, though there are known
avenues through which behavioral
disturbance of individuals can result in
population-level effects. A negligible
impact finding is based on the lack of
likely adverse effects on annual rates of
recruitment or survival (i.e., populationlevel effects). An estimate of the number
of Level B harassment takes alone is not
enough information on which to base an
impact determination.
In addition to considering estimates of
the number of marine mammals that
might be ‘‘taken’’ through behavioral
harassment, NMFS considers other
factors, such as the likely nature of any
responses (their intensity, duration,
etc.), the context of any responses
(critical reproductive time or location,
migration, etc.), as well as the number
and nature of estimated Level A takes,
the number of estimated mortalities, and
effects on habitat.
The WSDOT’s specified activities
have been described based on best
estimates of the planned Manette Bridge
replacement project within the
proposed project area. Some of the
noises that would be generated as a
result of the proposed bridge
replacement project, such as impact pile
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
driving, are high intensity. However,
WSDOT plans to use vibratory pile
driving and to avoid using impact pile
driving as much as possible, therefore
eliminating the intense impulses that
could cause TTS to marine mammals
when repeatedly exposed in close
proximity. In addition, WSDOT
indicates that if impact pile driving is to
be conducted, an air bubble curtain
system would be used to attenuate the
noise level. Furthermore, shutdown of
pile driving would be implemented
when a marine mammal is spotted
within the 180 dB and 190 dB re 1 μPa
(rms) safety zones for cetaceans and
pinnipeds, respectively. Therefore,
NMFS does not expect that any animals
would receive Level A (including
injury) harassment or Level B TTS from
being exposed to intense construction
noise.
Animals exposed to construction
noise associated with the proposed
bridge replacement work would be
limited to Level B behavioral
harassment only, i.e., the exposure of
received levels for impulse noise
between 160 and 180 dB re 1 μPa (rms)
(from impact pile driving) and for nonimpulse noise between 120 and 180 dB
re 1 μPa (rms) (from vibratory pile
driving, dredging, and dynamic
positioning of construction vessels). In
addition, the potential behavioral
responses from exposed animals are
expected to be localized and short in
duration. The modeled 160 dB isopleths
from impact pile driving is 5,412 m
from the pile, and the estimated 120 dB
isopleths from vibratory pile driving is
approximately 1,900 m from the pile.
However, the actual zone of influence
from impact pile driving is expected to
be much smaller due to other sound
attenuation factors not considered in the
spreading model. Furthermore, although
in-water construction activities are
expected to be conducted everyday
during daylight hours between June 15
and February 28, the total duration for
pile driving is expected to be
approximately 410 hours, or 41 working
days based on 10 hours of daylight for
each working day. WSDOT also plans to
use barge anchoring instead of dynamic
positioning systems for construction
vessels, thus further reducing noise
input into the water column. Therefore,
the underwater noise impacts from the
proposed Manette Bridge replacement
construction is expected to have a low
level of noise intensity, and be of short
duration and localized. These low
intensity, localized, and short-term
noise exposures, when received at
distances of Level B behavioral
harassment (i.e., 160 dB re 1 μPa (rms)
E:\FR\FM\06JYN1.SGM
06JYN1
Federal Register / Vol. 75, No. 128 / Tuesday, July 6, 2010 / Notices
from impulse sources and 120 dB re 1
μPa (rms) from non-impulse sources),
are expected to cause brief startle
reactions or short-term behavioral
modification by the animals. These brief
reactions and behavioral changes are
expected to disappear when the
exposures cease. Therefore, these levels
of received underwater construction
noise from the proposed Manette Bridge
replacement project are not expected to
affect marine mammal annual rates of
recruitment or survival.
Based on the analysis contained
herein of the likely effects of the
specified activity on marine mammals
and their habitat, and taking into
consideration the implementation of the
required mitigation and monitoring
measures, NMFS finds that the Manette
Bridge replacement project will result in
the incidental take of small numbers of
Pacific harbor seals, California sea lions,
and gray whales by Level B harassment
only, and that the total taking from
harassment will have a negligible
impact on the affected species or stocks.
wwoods2 on DSK1DXX6B1PROD with NOTICES_PART 1
Impact on Availability of Affected
Species for Taking for Subsistence Uses
There are no relevant subsistence uses
of marine mammals implicated by this
action.
Endangered Species Act (ESA)
There are two marine mammal
species and two fish species that are
listed as endangered or threatened
under the ESA with confirmed or
possible occurrence in the study area:
Eastern North Pacific Southern Resident
killer whale, Eastern U.S. Steller sea
lion, Chinook salmon, and steelhead
trout. Under section 7 of the ESA, the
Federal Highway Administration
(FHWA) and WSDOT have consulted
with NMFS Northwest Regional Office
(NWRO) on the proposed Manette
Bridge replacement project. In a memo
issued with its August 3, 2009,
Biological Opinion, NMFS NWRO
stated that the proposed bridge
replacement may affect, but is not likely
to adversely affect the listed marine
mammal species and stocks. On May 28,
2010, FHWA requested the reinitiation
of section 7 consultation with NMFS
NWRO on the newly ESA-listed three
Puget Sound rockfish species. The
consultation is expected to be
completed in July 2010.
The issuance of an IHA to WSDOT
constitutes an agency action that
authorizes an activity that may affect
ESA-listed species and, therefore, is
subject to section 7 of the ESA. As the
effects of the activities on listed marine
mammals and salmonids were analyzed
during a formal consultation between
VerDate Mar<15>2010
14:52 Jul 02, 2010
Jkt 220001
the FHWA and NMFS, and as the
underlying action has not changed from
that considered in the consultation, the
discussion of effects that are contained
in the Biological Opinion and
accompanying memo issued to the
FHWA on August 3, 2009, pertains also
to this action. Therefore, NMFS has
determined that issuance of an IHA for
this activity would not lead to any
effects to listed marine mammal species
apart from those that were considered in
the consultation on FHWA’s action.
Although the reinitiation of section 7
consultation by FHWA on three Puget
Sound rockfish species is still on-going,
NMFS does not expect that the outcome
would affect NMFS’ action in issuing an
IHA for the incidental take of marine
mammals.
National Environmental Policy Act
(NEPA)
To meet NMFS’ NEPA requirements
for the issuance of an IHA to the
WSDOT, NMFS has prepared an
Environmental Assessment (EA) that is
specific to the construction and
demolishing activities associated with
the Manette Bridge replacement project
in Bremerton, WA. NMFS has prepared
an EA titled Issuance of an Incidental
Harassment Authorization to the
Washington State Department of
Transportation to Take Marine
Mammals by Harassment Incidental to
Manette Bridge Replacement Project in
Bremerton, Washington, that evaluates
the impacts on the human environment
of NMFS’ authorization of incidental
Level B harassment resulting from the
specified activity in the specified
geographic region. The NMFS has made
a Finding of No Significant Impact
(FONSI) and, therefore, it is not
necessary to prepare an environmental
impact statement for the issuance of an
IHA to WSDOT for this activity. A copy
of the EA and the NMFS FONSI for this
activity is available upon request (see
ADDRESSES).
As a result of these determinations,
NMFS has issued an IHA to the WSDOT
to conduct construction and
demolishing activities associated with
the Manette Bridge replacement project
in Bremerton, WA, provided the
previously mentioned mitigation,
monitoring, and reporting requirements
are incorporated.
Dated: June 29, 2010.
Helen Golde,
Deputy Director, Office of Protected
Resources, National Marine Fisheries Service.
[FR Doc. 2010–16370 Filed 7–2–10; 8:45 am]
BILLING CODE 3510–22–S
PO 00000
Frm 00028
Fmt 4703
Sfmt 4703
38791
CONSUMER PRODUCT SAFETY
COMMISSION
Sunshine Act Meetings
TIME AND DATE: Wednesday, July 7, 2010;
2 p.m.–3 p.m.
PLACE: Hearing Room 420, Bethesda
Towers, 4330 East West Highway,
Bethesda, Maryland.
STATUS: Closed to the Public.
MATTERS TO BE CONSIDERED:
Compliance Status Report
The Commission staff will brief the
Commission on the status of compliance
matters.
For a recorded message containing the
latest agenda information, call (301)
504–7948.
CONTACT PERSON FOR MORE INFORMATION:
Todd A. Stevenson, Office of the
Secretary, U.S. Consumer Product
Safety Commission, 4330 East West
Highway, Bethesda, MD 20814, (301)
504–7923.
Dated: June 29, 2010.
Todd A. Stevenson,
Secretary.
[FR Doc. 2010–16499 Filed 7–1–10; 4:15 pm]
BILLING CODE 6355–01–P
CONSUMER PRODUCT SAFETY
COMMISSION
Sunshine Act Meetings
TIME AND DATE: Wednesday, July 7, 2010,
10 a.m.–12:30 p.m.
PLACE: Hearing Room 420, Bethesda
Towers, 4330 East West Highway,
Bethesda, Maryland.
STATUS: Commission Meeting—Open to
the Public.
MATTERS TO BE CONSIDERED:
1. Decisional Matters: (a)
Accreditation for Third Party
Conformity Assessment Bodies for
Testing for Children’s Products: Carpets
and Rugs; and (b) Accreditation for
Third Party Conformity Assessment
Bodies for Testing for Children’s
Products: Vinyl Plastic Film.
2. Cribs—Notice of Proposed
Rulemaking (NPR).
3. Interim Policy and Partial Lifting of
the Stay on Component Testing and
Certification of Children’s Toys and
Child Care Articles to the Phthalates
Limits.
A live Webcast of the Meeting can be
viewed at https://www.cpsc.gov/webcast.
For a recorded message containing the
latest agenda information, call (301)
504–7948.
CONTACT PERSON FOR MORE INFORMATION:
Todd A. Stevenson, Office of the
E:\FR\FM\06JYN1.SGM
06JYN1
Agencies
[Federal Register Volume 75, Number 128 (Tuesday, July 6, 2010)]
[Notices]
[Pages 38783-38791]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-16370]
-----------------------------------------------------------------------
DEPARTMENT OF COMMERCE
National Oceanic and Atmospheric Administration
RIN 0648-XU03
Takes of Marine Mammals Incidental to Specified Activities;
Manette Bridge Replacement in Bremerton, Washington
AGENCY: National Marine Fisheries Service (NMFS), National Oceanic and
Atmospheric Administration (NOAA), Commerce.
ACTION: Notice; issuance of incidental harassment authorization.
-----------------------------------------------------------------------
SUMMARY: In accordance with the regulations implementing the Marine
Mammal Protection Act (MMPA) as amended, notification is hereby given
that NMFS has issued an Incidental Harassment Authorization (IHA) to
the Washington State Department of Transportation (WSDOT), to
incidentally harass, by Level B harassment only, small numbers of
marine mammals during the specified activity.
[[Page 38784]]
DATES: This authorization is effective from June 29, 2010, through
June 28, 2011.
ADDRESSES: A copy of the IHA and the application are available by
writing to P. Michael Payne, Chief, Permits, Conservation and Education
Division, Office of Protected Resources, National Marine Fisheries
Service, 1315 East-West Highway, Silver Spring, MD 20910-3225. A copy
of the application may be obtained by writing to this address, by
telephoning the contact listed here (FOR FURTHER INFORMATION CONTACT)
or online at: https://www.nmfs.noaa.gov/pr/permits/incidental.htm#applications
Documents cited in this notice may be viewed, by appointment,
during regular business hours, at the aforementioned address.
FOR FURTHER INFORMATION CONTACT: Shane Guan, Office of Protected
Resources, NMFS, (301) 713-2289, ext 137.
SUPPLEMENTARY INFORMATION:
Background
Section 101(a)(5)(D) of the MMPA (16 U.S.C. 1371 (a)(5)(D)) directs
the Secretary of Commerce to authorize, upon request, the incidental,
but not intentional, taking by harassment of small numbers of marine
mammals of a species or population stock, for periods of not more than
one year, by United States citizens who engage in a specified activity
(other than commercial fishing) within a specific geographic region if
certain findings are made and, a notice of a proposed authorization is
provided to the public for review.
Authorization for incidental takings shall be granted if NMFS finds
that the taking will have a negligible impact on the species or
stock(s), will not have an unmitigable adverse impact on the
availability of the species or stock(s) for subsistence uses (where
relevant), and if the permissible methods of taking and requirements
pertaining to the mitigation, monitoring and reporting of such takings
are set forth. NMFS has defined ``negligible impact'' in 50 CFR 216.103
as ''...an impact resulting from the specified activity that cannot be
reasonably expected to, and is not reasonably likely to, adversely
affect the species or stock through effects on annual rates of
recruitment or survival.''
Section 101(a)(5)(D) of the MMPA established an expedited process
by which citizens of the United States can apply for an authorization
to incidentally take small numbers of marine mammals by harassment.
Section 101(a)(5)(D) establishes a 45-day time limit for NMFS review of
an application followed by a 30-day public notice and comment period on
any proposed authorizations for the incidental harassment of marine
mammals. Within 45 days of the close of the comment period, NMFS must
either issue or deny the authorization.
Except with respect to certain activities not pertinent here, the
MMPA defines ``harassment'' as:
any act of pursuit, torment, or annoyance which (i) has the
potential to injure a marine mammal or marine mammal stock in the
wild [Level A harassment]; or (ii) has the potential to disturb a
marine mammal or marine mammal stock in the wild by causing
disruption of behavioral patterns, including, but not limited to,
migration, breathing, nursing, breeding, feeding, or sheltering
[Level B harassment].
Summary of Request
NMFS received an application on December 24, 2009, from WSDOT for
the taking, by harassment, of marine mammals incidental to construction
and demolition work related to the Manette Bridge replacement in
Bremerton, Washington, starting in early June 2010.
The Manette Bridge is located within the Puget Sound of Washington
State, at the outlet to the Port Washington Narrows. The Port
Washington Narrows provides the only outlet from Dyes Inlet to Sinclair
Inlet, and connection to the greater Puget Sound. The Manette Bridge is
determined to be a functionally obsolete and structurally deficient
bridge that requires replacement, and the WSDOT is planning to have it
replaced. The proposed bridge replacement work includes the following
activities:
Construction of temporary work trestles, which involves
steel pile installation using both vibratory and impact driving
methods;
Construction of new bridge piers, which involves
excavation of benthic material;
Barge anchoring and usage;
Removal of existing bridge; and
Removal of temporary work platforms.
Since marine mammal species and stocks in the proposed action area
could be affected by the proposed bridge replacement activities, the
WSDOT is seeking an IHA that would allow the incidental, but not
intentional, take of marine mammals by Level B behavioral harassment
during the construction of the new Manette Bridge and removal of the
existing bridge. The WSDOT states that small numbers of three species
of marine mammals could potentially be taken by pile driving or other
construction activities associated with the bridge replacement work.
However, with the required mitigation and monitoring measures, the
numbers and levels of marine mammal takes would be reduced to the least
amount practicable.
Description of the Specific Activity
WSDOT will conduct construction and demolishing activities
associated with the Manette Bridge replacement project in Bremerton,
WA, starting from June 2010 and lasting for approximately three years.
However, no in-water activities will be planned between March 1 and
June 14 in water below the ordinary high water line.
NMFS provided a detailed overview of the activity in the notice of
the proposed IHA (75 FR 13502, March 22, 2010) and in the WSDOT's IHA
application. No changes have been made to the proposed activities.
The following is a summarized description of the sequence of
anticipated work activities associated with the Manette Bridge
replacement project.
1. Construction of Work Trestles and Falsework Towers
Separate work trestles would be constructed for the new bridge
construction and existing bridge removal processes. The south trestles
for access to the new bridge site would be constructed prior to the
installation of the north trestles for bridge removal. The work
trestles and associated falsework towers would be supported on steel
pilings with diameters of 24 to 36 in. (0.61 to 0.91 m). The
construction of the work trestles is estimated to take up to 9 months.
The work trestles and falsework towers would be in place throughout the
project duration, approximately 3 years.
The trestles would be located a few feet above the high water mark,
with the exact height determined by the contractor and work site
conditions. The trestles would be supported by steel girders attached
to the piles and the deck would be composed of timbers. The new bridge
construction work trestle would be supported by up to 360 piles and
could cover an area of up to 40,000 ft\2\ (3,716 m\2\). The bridge
removal work trestle will be supported by up to 170 piles and could
cover an area of up to 15,900 ft\2\ (1,477 m\2\). Up to 12 additional
piles may be used for project related moorage.
All piles would be installed using a vibratory hammer unless an
impact hammer is needed to drive a pile through consolidated material
or meet bearing. Currently, pile driving is scheduled to occur July 1
to August 20, 2010, and October 6, 2010, to January 31, 2011, with an
estimated 45 minutes
[[Page 38785]]
per pile and 410 total hours of pile driving using a vibratory hammer.
Pile driving activities would occur daily two hours after sunrise to
two hours before sunset between April 1 and September 15, 2010. No pile
driving will occur during nighttime hours.
2. Barge Anchoring and Usage
Barges would be used extensively throughout the project duration to
provide access to work areas, support machinery, deliver and stage
materials, and as a collection surface for spoils, construction debris,
and materials from demolition. The actual number and dimensions of
barges to be used would be determined by the contractor and work site
conditions. However, it is estimated that up to 6 barges would be used
at one time. A typical barge dimension is approximately 290 ft (88.4 m)
in length and 50 ft (15.2 m) in width. Typical barge draft is 4 to 8 ft
(1.22 to 2.44 m) and typical freeboard is 3 to 6 ft (0.91 to 1.83 m).
Barges would be used throughout the construction period, approximately
3 years.
During working hours, barges would be attached to mooring lines,
the work trestles, or to other portions of the project area, depending
on the construction and access needs. Up to 6 temporary buoys may be
installed to moor barges during non-working hours. These buoys would be
attached to one or more anchors, which may need to be driven, or
excavated, due to hard ground and strong currents in the project area.
If the contractor chooses to deploy a dynamic barge positioning system,
it is expected that the hours the system is in use would coincide
closely with pile driving activities.
3. Construction of New Piers
Eight piers would support the new bridge, six in-water and two
upland. The existing bridge has 13 piers, nine in-water and three
upland. The total footprint of the piers would be 1,416 ft\2\ (131.6
m\2\). The footprint of the nine in-water piers supporting the existing
bridge is 8,726 ft\2\ (810.7 m\2\).
Piers 1 and 8 are the bridge abutments and are located well above
the mean high water line (MHW). Piers 2 through 7 are located below the
MLLW line. The construction of the in-water piers (2 through 7) would
take up to 18 months. The construction of the abutment piers (1 and 8)
would occur during the bridge closure period (targeted duration of 3
months). The construction of each would include excavation of up to 3
shafts to support each pier, concrete pouring of each shaft, and
construction of piers on top of new shafts.
Shaft casings would be installed and the shafts will be excavated
using equipment positioned on the work trestles or barges.
To create a drilled shaft, a steel casing approximately 6 to 10 ft
(1.8 to 3 m) in diameter is driven into the substrate using a vibratory
hammer, and the material inside the casing is excavated using an auger
or a clamshell dredge. During excavation a premixed bentonite or
synthetic polymer slurry is sometimes added to stabilize the walls of
the shaft. Spoils from shaft excavation would be placed in a large
steel containment box located on a barge or on the work trestle for
offsite transport. During the drilling, polymer slurry is typically
placed into the hole to keep side walls of the shaft from caving.
After completion of the excavation, a steel reinforcing cage is
placed into the hole to specified elevations. Concrete is then pumped
into the hole using a tremie tube placed at the bottom of the
excavation. As concrete is placed the tremie tube is raised but is
maintained within the concrete. As the concrete is pumped into the
hole, the slurry is displaced upward and removed from the top concrete
using a vacuum hose. The slurry is pumped from the hole into large
tanks located on the work trestle or on a barge, which is either
recycled for use in the next shaft or transported off site. This
procedure would be used on all shafts at each pier.
After shafts are completed, pre-cast concrete, stay-in-place forms
would be stacked on top of the shafts up to the crossbeam elevation. A
steel reinforcing cage would be placed inside the concrete forms and
the columns would be filled with concrete. A pre-cast concrete
crossbeam or a cast-in-place crossbeam, or some combination of both
would be constructed on top of the columns. Girders would be fabricated
off site and would be shipped to the site on barges. The girders would
then be placed on the piers and falsework towers between piers 2 and 7.
After completion of the girder placement and casting of diaphragms
connecting the girders, post-tensioning strands would be placed into
ducts cast in the girders. The post-tensioning strands will then be
stressed. The roadway deck would then be formed and cast between piers
2 and 7.
4. Installation of Girders and Decking
Girders and decking would be installed using the work trestles,
falsework towers, and cranes deployed on work barges. The roadway deck
would be made of concrete and would be poured in place. This work is
expected to take 3 to 4 months.
5. Reconfiguration of Abutments and Roadway Approaches
The existing bridge abutments would be removed, along with the
associated retaining walls. New retaining walls and abutments would be
constructed. These activities, and associated construction access would
require the temporary disturbance of 0.75 acre of land, of which 0.15
acre are vegetated, and permanent removal of 0.15 acre of vegetation.
This work, all in upland areas, includes 2000 cubic yards of fill. Once
the abutments are complete, the new bridge approach roadways will be
constructed. Disturbed areas on the east shore of the Port Washington
Narrows would be restored with a mix of native trees and shrubs
including marine riparian vegetation and shoreline enhancement.
6. Demolition of Existing Bridge
The demolition of the existing bridge would occur in phases over a
period of 18 months. After the central portion of the new bridge is
constructed, the outermost spans and abutments of the existing bridge
would be demolished. Once the new abutments and outer spans are
constructed, the demolition of the remainder of the existing bridge
will proceed. Conceptual demolition plan sheets are included in
Appendix D of the WSDOT IHA application.
The bridge structure above the water line would be cut into
manageable sections, using conventional concrete and metal cutting
tools, or a wire saw, and placed on barges for transport to approved
waste or recycling sites. The portions of the piers below the water
line would be cut into pieces using a wire saw. All slurry from wire
cutting operations above the water line would be contained and removed.
All slurry from wire cutting operations below the water line would be
dispersed by the current. Piers would be cut off at the ground level
except for one, Pier 4. Pier 4 was built up to encapsulate original
creosote treated timbers. Complete removal of the pier is not feasible
and if it is cut at the ground level, many creosote treated timbers may
be exposed. To minimize the risk of contamination, Pier 4 would be cut
two feet above ground level.
7. Removal of Falsework Towers and Work Trestles
Once the demolition of the existing bridge is complete, the
falsework towers and work trestles would be removed. Decking and
girders would be placed on barges for transportation off-site. Piles
[[Page 38786]]
would be removed using vibratory hammers, based on barges. The removal
of the falsework towers and work trestles is expected to occur over 4
to 6 months.
Vibratory extraction is a common method for removing steel piling.
The pile is unseated from the sediments by engaging the hammer and
slowly lifting up on the hammer with the aid of the crane. Once
unseated, the crane would continue to raise the hammer and pull the
pile from the sediment. When the pile is released from the sediment,
the vibratory hammer is disengaged and the pile is pulled from the
water and placed on a barge for transfer upland.
Comments and Responses
NMFS published a notice of receipt of the WSDPT application and
proposed IHA in the Federal Register on March 22, 2010 (75 FR 13502).
During the 30-day comment period, NMFS received a letter from the
Marine Mammal Commission (Commission) and a private citizen. Both the
Commission and the private citizen recommended that NMFS issue the
requested authorization. The Commission further states that the
authorization should be issued provided that the required monitoring
and mitigation measures are carried out (e.g., establishing of the
safety zones and take zones, marine mammal monitoring during in-water
construction activities, and ramp-up for pile driving) as described in
NMFS' March 22, 2010 (75 FR 13502), notice of the proposed IHA and the
application. All measures proposed in the initial Federal Register
notice are included in the authorization and NMFS has determined that
they will effect the least practicable impact on the species or stocks
and their habitats.
Description of Marine Mammals in the Area of the Specified Activity
Six marine mammal species/stocks occur in the area where the
proposed Manette Bridge replacement work is planned. These six species/
stocks are: Pacific harbor seal (Phoca vitulina richardsi), California
sea lion (Zalophus californianus), Steller sea lion (Eumetopias
ubatus), transient and Southern Resident killer whales (Orcinus orca),
and gray whale (Eschrichtius robustus). All these marine mammals have
been observed in southern Puget Sound during certain periods of the
year and may occur in Sinclair Inlet, Port Washington Narrows and Dyes
Inlet, although direct observation in the vicinity of the Manette
Bridge may not be documented. General information on these marine
mammal species can be found in Caretta et al. (2008), which is
available at the following URL: https://www.nmfs.noaa.gov/pr/pdfs/sars/po2009.pdf. Refer to that document for information on these species.
To further gather information on the occurrence of these marine
mammal species in the vicinity of the proposed project area, the WSDOT
contracted ten surveys between the months of July 2006 and January
2007. This time period was chosen for sampling because it represents
the time period when most in-water work activities would occur. Two
pinniped species and zero cetaceans were observed. Thirty four harbor
seals, one California sea lion and one unidentified pinniped, likely a
California sea lion, were observed over the six month period. In
general, cetacean observations are infrequent in the Puget Sound
(Calambokidis and Baird 1994, Jefferies 2007). During ten surveys for
marine mammals in Sinclair Inlet and Port Washington Narrows between
July 2006 and January 2007, no cetaceans were observed. No marine
mammals were observed during two of the ten surveys. Detailed results
of the surveys are provided in a final report, which is included in
Appendix E of the WSDOT IHA application.
Additional information on these species, particularly in relation
to their occurrence in the proposed project area, is provided in the
March 22, 2010, Federal Register notice (75 FR 13502). Please refer to
that document for this information.
Potential Effects on Marine Mammals and Their Habitat
Anticipated impacts resulting from the Manette Bridge Replacement
project include disturbance from increased human presence and marine
traffic if marine mammals are in the vicinity of the proposed project
area, Level B harassment by noises generated from the construction work
such as pile driving and dredging activities, and the effect of the new
bridge and stormwater system on water quality. A detailed discussion of
these effects from various construction and demolishing activity
components is provided in the March 22, 2010, Federal Register notice
(75 FR 13502). These potential effects are expected to be localized and
short-term. In addition, none of these potential impacts is believed to
be biologically significant to the survival and reproduction of marine
mammals and their habitat in the vicinity of the proposed project.
Please refer to that document for this information.
Mitigation Measures
In order to issue an incidental take authorization under Section
101(a)(5)(D) of the MMPA, NMFS must set forth the permissible methods
of taking pursuant to such activity, and other means of effecting the
least practicable adverse impact on such species or stock and its
habitat, paying particular attention to rookeries, mating grounds, and
areas of similar significance, and on the availability of such species
or stock for taking for certain subsistence uses.
For the proposed Manette Bridge replacement project, the WSDOT
worked with NMFS and formulated the following mitigation measures to
minimize the potential impacts to marine mammals in the project
vicinity as a result of the construction activities.
1. Overall Construction Activities
All construction shall be performed in accordance with the current
WSDOT Standard Specifications for Road, Bridge, and Municipal
Construction. Special Provisions contained in contracts are used in
conjunction with, and supersede, any conflicting provisions of the
Standard Specifications.
WSDOT activities are subject to state and local permit conditions.
WSDOT shall use the best guidance available (e.g., best management
practices and conservation measures) to accomplish the necessary work
while avoiding and minimizing environmental impacts to the greatest
extent possible.
The WSDOT contractor is expected to be responsible for the
preparation of a Spill Prevention, Control, and Countermeasures plan to
be used for the duration of the project. The plan would be submitted to
the WSDOT Project Engineer prior to the commencement of any
construction activities. A copy of the plan with any updates will be
maintained at the work site by the contractor. A detailed discussion of
the plan is provided in the WSDOT's IHA application.
2. Equipment Noise Standards
To mitigate noise levels and, therefore, impacts to marine mammals,
all the construction equipment shall comply with applicable equipment
noise standards of the U.S. Environmental Protection Agency, and all
construction equipment shall have noise control devices no less
effective than those provided on the original equipment.
3. Timing Windows
Timing restrictions are used to avoid construction activities that
generate relatively intense underwater noises
[[Page 38787]]
(i.e., pile driving, dredging, and dynamic positioning) when ESA-listed
species are most likely to be present. If an ESA-listed marine mammal
species is detected in the vicinity of the project area, pile driving
and dredging operations shall be halted and stationing construction
vessels will turn off dynamic positioning systems. WSDOT shall comply
with all in-water timing restrictions as determined through the MMPA
take authorization. Pile driving activities shall only be conducted
during daylight hours. If the safety zone (see below) is obscured by
fog or poor lighting conditions, impact pile driving will not be
initiated until the entire safety zone is visible. In addition, no in-
water work shall be conducted between March 1 and June 14 in water
below the ordinary high water line.
4. Establishment of Zones of Safety and Influence
For impact pile driving, the safety zones are defined as the areas
where received SPLs from the noise source exceed 180 dB re 1 microPa
(rms) for cetaceans or 190 dB re 1 microPa (rms) for pinnipeds.
Repeated and prolonged exposure to SPLs above these values may cause
TTS to cetaceans and pinnipeds, respectively. The radii of the safety
zones shall be determined through empirical measurements of acoustic
data. Prior to acquiring acoustic data, the safety zones shall be
established based on the worst-case scenario measured from impact pile
driving of 36-inch (0.91 m) steel pile conducted elsewhere, such as the
Anacortes or Mukiteo ferry terminals. Acoustic measurements indicate
that source levels are approximately 201 dB re 1 microPa (rms) at 10 m
for both pile driving activities for Anacortes and Mukiteo ferry
terminal constructions when the 36-inch (0.91 m) piles were hammered in
(Laughlin 2007; Sexton 2007). Approximation of the received levels of
180 and 190 dB re 1 microPa (rms) by using an acoustic propagation
spreading model between spherical and cylindrical propagation,
TL = 15log(R]/RSL),
where TL is the transmission loss (in dB), RRL is the distance at
received levels (either 180 or 190 dB), and RSL is the distance (10 m)
at source level (201 dB). The results show that the distances for
received levels 180 and 190 dB re 1 microPa (rms) are approximately 251
m and 54 m, respectively. NMFS expects that the modeled safety zones
are reasonably conservative as the propagation model does not take into
consideration other transmission loss factors such as sound absorption
in the water column.
Once impact pile driving begins, NMFS requires that the contractor
adjust the size of the safety zones based on actual measurements of
SPLs at various distances to determine the most conservative (the
largest) safety zones at which the received levels are 180 and 190 dB
re 1 microPa (rms).
Since the source levels for vibratory pile driving are expected to
be under 180 dB re 1 microPa (rms) at 10 m, no safety zones would be
established for vibratory pile driving.
In addition, WSDOT and its contractor shall establish zones of
influence (ZOIs) at received levels of 160 and 120 dB re 1 microPa
(rms) for impulse noise (noise from impact pile driving) and non-
impulse noise (such as noise from vibratory pile driving and dynamic
positioning system), respectively. These SPLs are expected to cause
Level B behavioral harassment to marine mammals. The model based
approximation for the distance at 160 dB received level is 5,412 m from
pile driving based on the most conservative measurements from the
Anacortes or Mukiteo ferry terminal construction (201 dB re 1 microPa
(rms) at 10 m; Laughlin 2007; Sexton 2007), using the same spreading
model discussed above. Once impact pile driving starts, the contractor
shall conduct empirical acoustic measurements to determine the most
conservative distance (the largest distance from the pile) where the
received levels begin to fall below 160 dB re 1 microPa (rms).
As far as non-pulse noises are concerned, for which the Level B
behavioral harassment is set at a received level of 120 dB re 1
microPa, no simple modeling is available to approximate the distance
(though direct calculation using the spreading model puts the 120 dB
received level at 100 km, this simple approximation no longer works at
this long distance due to range-dependent propagation involving complex
sound propagation behavior that cannot be ignored). NMFS uses the
empirical underwater acoustic measurements from vibratory pile driving
of 42 48-inch (1.06 1.22 m) diameter piles at the San Francisco-Oakland
Bay Bridge construction as a model and expects that the distance at a
received level of 120 dB is less than 1,900 m from the pile (CALTRANS
2009). Likewise, WSDOT and its contractor shall conduct empirical
acoustic measurements to determine the actual distance of 120 dB re 1
microPa (rms) from the pile.
All safety and influence zones shall be monitored for marine
mammals prior to and during construction activities. Please refer to
the Monitoring and Reporting Measures section for a detailed
description of monitoring measures.
5. Shutdown Measures
To prevent marine mammals from exposure to intense sounds that
could potentially lead to TTS (i.e., received levels above 180 dB and
190 dB re 1 microPa (rms) for cetaceans and pinnipeds, respectively),
no impact pile driving shall be initiated when marine mammals are
detected within these safety zones. In addition, during impact driving,
when a marine mammal is detected within the respective safety zones or
is about to enter the safety zones, impact pile driving shall be halted
and shall not be resumed until the animal is seen to leave the safety
zone on its own, or 30 minutes has elapsed until the animal is last
seen.
Pile driving and dredging activities shall be suspended when ESA-
listed marine mammals (Steller sea lion and killer whale) are detected
within the zone of behavioral harassment (160 dB re 1 microPa for
impulse sources and 120 dB re 1 microPa for non-impulse sources) and
that all vessels' dynamic positioning systems would be turned off.
Therefore, no take of ESA-listed marine mammal species or stocks is
expected.
6. ``Soft Start'' Impact Pile Driving or Ramp-up
Although marine mammals will be protected from Level A harassment
by establishment of an air-bubble curtain during impact pile driving
and marine mammal observers monitoring a safety zone, monitoring may
not be 100 percent effective at all times in locating marine mammals.
Therefore, a ``soft-start'' technique shall be used at the beginning of
each day's in-water pile driving activities or if pile driving has
ceased for more than one hour to allow any marine mammal that may be in
the immediate area to leave before pile driving reaches full energy.
For vibratory pile driving, the soft start requires contractors to
initiate noise from vibratory hammers for 15 seconds at reduced energy
followed by a one minute waiting period. The procedure shall be
repeated two additional times. If an impact hammer is used on a pile
greater than 10 inches in diameter, contractors shall be required to
provide an initial set of three strikes from the impact hammer at 40
percent energy, followed by a one minute waiting period, then two
subsequent 3-strike sets. This should expose fewer animals to loud
sounds both underwater and above water noise. This would also ensure
that, although not expected, any pinnipeds and
[[Page 38788]]
cetaceans that are missed during safety zone monitoring will not be
injured.
7. Sound Attenuation Measures
All steel piles shall be installed using a vibratory hammer until
an impact hammer is needed for bearing or if a pile encounters
consolidated material. If vibratory installation is not possible due to
the substrate, an impact pile driver would be used. An air bubble
curtain(s) shall be employed during impact installation of all steel
piles. Detailed description and specification of the air bubble curtain
system is provided in Appendix C of the WSDOT's IHA application.
WSDOT shall provide bubble curtain performance criteria to the
contractor, which include:
Piling shall be completely engulfed in bubbles over the
full depth of the water column at all times when an impact pile driver
is in use.
The lowest bubble ring shall be in contact with the mud
line for the full circumference of the ring. The weights attached to
the bottom ring shall ensure complete mud line contact. No parts of the
ring or other objects shall prevent the full mud line contact.
Bubblers shall be constructed of minimum 2-inch (5.1-cm)
inside diameter aluminum pipe with 1/16-inch (0.16-cm) diameter bubble
release holes in four rows with 3/4-inch (1.9-cm) spacing in the radial
and axial directions. Bubblers shall be durable enough to withstand
repeated deployment during pile driving and shall be constructed to
facilitate underwater setup, knockdown, and reuse on the next pile.
One or more compressors shall be provided to supply air in
sufficient volume and pressure to self-purge water from the bubblers
and maintain the required bubble flux for the duration of pile driving.
Compressors shall be of a type that prevents the introduction of oil or
fine oil mist by the compressed air into the water. If there is
presence of oil film or sheen on the water surface in the vicinity of
the operating bubbler, the contractor shall immediately stop work until
the source of oil film or sheen is identified and corrected.
The system shall provide a bubble flux of 3.0 cubic meters
(m3) per minute per linear meter of pipe in each layer (32.91 cubic
feet, or 0.93 m3, per minute per linear foot of pipe in each layer).
The total volume of air per layer is the product of the bubble flux and
the circumference of the ring:
Vt=3.0 m\3\/min/m x Circum of the aeration ring in meters.
or
Vt=32.91 ft\3\/min/ft x Circum of the aeration ring in meters.
The bubble ring manifold shall incorporate a shut off
valve, flow meter, and a throttling globe valve with a pressure gauge
for each bubble ring supply.
Prior to first use of the bubble curtain during pile
driving, the fully-assembled system shall be test-operated to
demonstrate proper function and to train personnel in the proper
balancing of the air flow to the bubblers. The test shall also confirm
the calculated pressures and flow rates at each manifold ring. The
Contractor shall submit an inspection/performance report to WSDOT
within 72 hours following the performance test.
The WSDOT Office of Air Quality and Noise has prepared a noise
monitoring plan for the Manette Bridge Replacement Project (Appendix
H). To comply with the provisions of the plan, the State will conduct
hydroacoustic monitoring during construction to evaluate in water noise
levels.
8. Ensure Regulation Compliance
Finally, a WSDOT inspector shall be on site during construction.
The role of the inspector is to ensure contract compliance. The
inspector and the contractor each have a copy of the Contract Plans and
Specifications on site and are aware of all requirements. The inspector
is also trained in environmental provisions and compliance.
NMFS has carefully evaluated the applicant's proposed mitigation
measures and considered a range of other measures in the context of
ensuring that NMFS prescribes the means of effecting the least
practicable adverse impact on the affected marine mammal species and
stocks and their habitat. Our evaluation of potential measures included
consideration of the following factors in relation to one another:
the manner in which, and the degree to which, the
successful implementation of the measure is expected to minimize
adverse impacts to marine mammals
the proven or likely efficacy of the specific measure to
minimize adverse impacts as planned
the practicability of the measure for applicant
implementation, including consideration of personnel safety, and
practicality of implementation.
Based on our evaluation of the applicant's proposed measures, as
well as other measures considered by NMFS or recommended by the public,
NMFS has determined that the required mitigation measures provide the
means of effecting the least practicable adverse impacts on marine
mammals species or stocks and their habitat, paying particular
attention to rookeries, mating grounds, and areas of similar
significance.
Monitoring and Reporting Measures
In order to issue an ITA for an activity, Section 101(a)(5)(D) of
the MMPA states that NMFS must set forth ``requirements pertaining to
the monitoring and reporting of such taking''. The MMPA implementing
regulations at 50 CFR Sec. 216.104 (a)(13) indicate that requests for
IHAs must include the suggested means of accomplishing the necessary
monitoring and reporting that will result in increased knowledge of the
species and of the level of taking or impacts on populations of marine
mammals that are expected to be present. The requireed monitoring and
reporting measures for the Manette Bridge replacement project are
provided below.
1. Marine Mammal Observers
A minimum of two qualified and NMFS-approved marine mammal
observers (MMOs) would be present on site at all times during steel
pile driving. In order to be considered qualified, WSDOT lists the
following requirements for prospective MMOs:
Visual acuity in both eyes (correction is permissible)
sufficient for discernment of moving targets at the water's surface
with ability to estimate target size and distance. MMOs shall use
binoculars to correctly identify the target.
Advanced education in biological science, wildlife
management, mammalogy or related fields (Bachelors degree or higher is
preferred).
Experience and ability to conduct field observations and
collect data according to assigned protocols (this may include academic
experience).
Experience or training in the field identification of
marine mammals (cetaceans and pinnipeds), including the identification
of behaviors.
Sufficient training, orientation or experience with the
construction operation to provide for personal safety during
observations.
Writing skills sufficient to prepare a report of
observations.
Ability to communicate orally, by radio or in person, with
project personnel to provide real-time information on marine mammals
observed in the area as necessary.
2. Marine Mammal Monitoring
WSDOT has developed a monitoring plan (Appendix G of the WSDOT IHA
[[Page 38789]]
application) in conjunction with NMFS that will collect sighting data
for each distinct marine mammal species observed during the proposed
Manette Bridge replacement construction activities that generate
intense underwater noise. These activities include, but are not limited
to, impact and vibratory pile driving, use of dynamic positioning
system by construction and supporting vessels, and sediment dredging.
Marine mammal behavior, overall numbers of individuals observed,
frequency of observation, and the time corresponding to the daily tidal
cycle will also be included. An example of a marine mammal sighting
form is included in Appendix I of the WSDOT's IHA application.
In addition, for impact pile driving, the following Marine Mammal
Monitoring Plan and shut down procedures shall be implemented:
At least two MMOs shall be on site to monitor the safety
and influence zones by using a range finder or hand held global
positioning system (GPS) device. The zone will be monitored by driving
a boat along and within the radius while visually scanning the area,
and/or monitored from shore if there is a vantage point that will allow
full observation of the zone.
If the safety zone is obscured by fog or poor lighting
conditions, pile driving shall not be initiated until the entire safety
zone is visible.
The safety zone shall be monitored for the presence of
marine mammals for 30 minutes prior to impact pile driving, during pile
driving, and 20 minutes after pile driving activities.
No impact pile driving shall be started if a marine mammal
is detected within the respective safety zones. Pile driving may begin
if a marine mammal is seen leaving the safety zone, or 30 minutes has
elapsed since the marine mammal is last seen inside the safety zone.
If marine mammals are observed, their location in relation
to the safety and influence zones, and their reaction (if any) to pile
driving activities shall be documented.
3. Reporting
WSDOT shall submit weekly marine mammal monitoring reports from the
time when in-water construction activities are commenced to NMFS Office
of Protected Resources (OPR). These weekly reports shall include a
summary of the previous week's monitoring activities and an estimate of
the number of marine mammals that may have been disturbed as a result
of in-water construction activities.
In addition, WSDOT shall provide NMFS OPR with a draft final report
within 90 days after the expiration of the IHA. This report should
detail the in-water construction and demolishing activities being
conducted, empirically measured safety zones for pile driving, and the
monitoring protocol; summarize the data recorded during monitoring; and
estimate the number of marine mammals that may have been harassed due
to the construction activities. If no comments are received from NMFS
OPR within 30 days, the draft final report will be considered the final
report. If comments are received, a final report must be submitted
within 30 days after receipt of comments.
Estimated Take by Incidental Harassment
As mentioned earlier in the March 22, 2010, Federal Register (75 FR
13502), the potential effects to marine mammals from the proposed
activities include disturbance from increased human presence and marine
traffic and from noises generated from the construction work such as
pile driving and dredging activities. The required mitigation measures
of using air bubble curtain systems would prevent marine mammals from
onset of TTS by impact pile driving and reduce Level B behavioral
harassment due to the effective attenuation by the air bubble systems.
Therefore, the following analyses focus on potential noise impacts that
could cause Level B behavioral harassment, based on the WSDOT
contracted surveys for the entire proposed project area (WSDOT 2009).
1. Harbor Seal
There are no harbor seal haulouts within 3 miles (4.8 km) of the
project. The nearest haulout is in Dyes Inlet and animals must move
through the Port Washington Narrows to access Sinclair Inlet and the
greater Puget Sound. Individual harbor seals moving between Sinclair
and Dyes Inlets would be exposed to project activities.
A total of 34 harbor seals were detected during ten surveys
conducted during the same time of year pile driving will occur, between
July and January. The age, sex and reproductive condition of the
animals was not determined. For the proposed Manette Bridge replacement
activities, it is reasonable to assume that similar numbers of animals
would be encountered during an average 10-day period. WSDOT anticipates
that for every day of construction activities, between 3 and 4 harbor
seals may be encountered, although it is possible that some of these
animals will be the same individuals. If in-water construction
activities occur every day of the year (258 days between June 15 and
February 28), approximately 877 harbor seals (or about 6% of the
Washington inland waters stock of harbor seals) could be encountered in
the vicinity of the proposed bridge replacement work. However, it is
not likely that every harbor seal would be taken by Level B behavioral
harassment since not every animal would be exposed to received levels
above 160 dB re 1 microPa (rms) from an impulse source (such as impact
pile driving) or above 120 dB re 1 microPa (rms) from a non-impulse
source (such as vibratory pile driving or dredging). Likewise, not
every single harbor seal would respond to the sight of human or vessel
traffic in the vicinity of the project area. Therefore, the estimated
number of 877 represents the upper-limit of the number of harbor seals
that could be affected by Level B behavioral harassment as a result of
exposure to Manette Bridge replacement related construction activities.
2. California Sea Lion
There are no California sea lion haulouts within three miles of the
project. The nearest haulout is in Rich Passage, east of the Port
Washington Narrows in more open water. Individual California sea lions
moving between Sinclair and Dyes Inlets could be exposed to project
activities.
A total of one, possibly two California sea lions were detected
during ten surveys conducted during the same time of year pile driving
would occur, between July and January. The age, sex and reproductive
condition of the animals was not determined. For the proposed Manette
Bridge replacement activities, it is reasonable to assume that similar
numbers of animals would be encountered during an average 10-day
period. WSDOT anticipates that for every 10 days of construction
activities, between 1 and 2 California sea lions may be encountered,
although it is possible that some of these animals will be the same
individuals. If in-water construction activities occur every day of the
year (258 days between June 15 and February 28), up to 516 California
sea lions (or about 0.2% of the US stock of California sea lions) could
be encountered in the vicinity of the proposed bridge replacement work.
However, it is not likely that every California sea lion would be taken
by Level B behavioral harassment since not every animal would be
exposed to received levels above 160 dB re 1 microPa (rms) from an
impulse source (such as impact pile driving) or above 120 dB re
[[Page 38790]]
1 microPa (rms) from a non-impulse source (such as vibratory pile
driving or dredging). Likewise, not every single California sea lion
would respond to the sight of human or vessel traffic in the vicinity
of the project area. Therefore, the estimated number of 516 represents
the upper-limit of the number of harbor seals that could be affected by
Level B behavioral harassment as a result of exposure to Manette Bridge
replacement related construction activities.
3. Steller Sea Lion
As stated earlier, the nearest Steller sea lion haulout is
approximately 12 miles (19.3 km) northeast of the proposed project area
in Shilshole Bay on the east side of the Puget Sound, adjacent to the
city of Seattle. No Steller sea lions were sighted during the ten
surveys contracted by WSDOT, and NMFS considers it is very unlikely
that a Steller sea lion would occur in the vicinity of the proposed
project area. The implementation of the aforementioned mitigation
measures, including halting all pile driving and dredging activities
and turning off construction vessels' dynamic positioning systems when
a Steller sea lion is detected about to enter the zone of influence
(received levels at or above 160 dB re 1 microPa (rms) for impulse
noise or 120 dB re 1 microPa (rms) for non-impulse noise). Therefore,
NMFS does not believe Steller sea lions would be affected.
4. Killer Whale
Killer whales (southern resident) have been documented in the
project vicinity once in the last ten years (WSDOT 2009). No killer
whales were sighted during the ten surveys contracted by WSDOT, and
NMFS considers it rare that a killer whale would occur in the vicinity
of the proposed project area. The implementation of the aforementioned
mitigation measures, including halting all pile driving and dredging
activities and turning off construction vessels' dynamic positioning
systems when a killer whale is detected about to enter the zone of
influence (received levels at or above 160 dB re 1 microPa (rms) for
impulse noise or 120 dB re 1 microPa (rms) for non-impulse noise).
Therefore, NMFS does not believe killer whales would be affected.
5. Gray Whale
Individual gray whales have been observed near the project area in
four of the last eight years (WSDOT 2009). No gray whales were sighted
during the ten surveys contracted by WSDOT, and NMFS considers it rare
that a gray whale would occur in the vicinity of the proposed project
area. Most grays whales spend winters in their breeding/calving grounds
around Baja California and summers in feeding grounds around the Bering
Sea and the Arctic. The few gray whales that occur in the vicinity of
the proposed project area are likely the ones visiting the area on
their north-south migration route. Based on past occurrence of gray
whales in the area and using conservative probability estimate, NMFS
considers that no more than 2 individuals of gray whales (0.01% of the
Eastern North Pacific gray whale population) would be exposed to
underwater construction noise SPL that could cause Level B behavioral
harassment annually as a result of the proposed Manette Bridge
replacement project.
Negligible Impact and Small Numbers Analysis and Determination
Pursuant to NMFS' regulations implementing the MMPA, an applicant
is required to estimate the number of animals that will be ``taken'' by
the specified activities (i.e., takes by harassment only, or takes by
harassment, injury, and/or death). This estimate informs the analysis
that NMFS must perform to determine whether the activity will have a
``negligible impact'' on the species or stock. Level B (behavioral)
harassment occurs at the level of the individual(s) and does not assume
any resulting population-level consequences, though there are known
avenues through which behavioral disturbance of individuals can result
in population-level effects. A negligible impact finding is based on
the lack of likely adverse effects on annual rates of recruitment or
survival (i.e., population-level effects). An estimate of the number of
Level B harassment takes alone is not enough information on which to
base an impact determination.
In addition to considering estimates of the number of marine
mammals that might be ``taken'' through behavioral harassment, NMFS
considers other factors, such as the likely nature of any responses
(their intensity, duration, etc.), the context of any responses
(critical reproductive time or location, migration, etc.), as well as
the number and nature of estimated Level A takes, the number of
estimated mortalities, and effects on habitat.
The WSDOT's specified activities have been described based on best
estimates of the planned Manette Bridge replacement project within the
proposed project area. Some of the noises that would be generated as a
result of the proposed bridge replacement project, such as impact pile
driving, are high intensity. However, WSDOT plans to use vibratory pile
driving and to avoid using impact pile driving as much as possible,
therefore eliminating the intense impulses that could cause TTS to
marine mammals when repeatedly exposed in close proximity. In addition,
WSDOT indicates that if impact pile driving is to be conducted, an air
bubble curtain system would be used to attenuate the noise level.
Furthermore, shutdown of pile driving would be implemented when a
marine mammal is spotted within the 180 dB and 190 dB re 1 microPa
(rms) safety zones for cetaceans and pinnipeds, respectively.
Therefore, NMFS does not expect that any animals would receive Level A
(including injury) harassment or Level B TTS from being exposed to
intense construction noise.
Animals exposed to construction noise associated with the proposed
bridge replacement work would be limited to Level B behavioral
harassment only, i.e., the exposure of received levels for impulse
noise between 160 and 180 dB re 1 microPa (rms) (from impact pile
driving) and for non-impulse noise between 120 and 180 dB re 1 microPa
(rms) (from vibratory pile driving, dredging, and dynamic positioning
of construction vessels). In addition, the potential behavioral
responses from exposed animals are expected to be localized and short
in duration. The modeled 160 dB isopleths from impact pile driving is
5,412 m from the pile, and the estimated 120 dB isopleths from
vibratory pile driving is approximately 1,900 m from the pile. However,
the actual zone of influence from impact pile driving is expected to be
much smaller due to other sound attenuation factors not considered in
the spreading model. Furthermore, although in-water construction
activities are expected to be conducted everyday during daylight hours
between June 15 and February 28, the total duration for pile driving is
expected to be approximately 410 hours, or 41 working days based on 10
hours of daylight for each working day. WSDOT also plans to use barge
anchoring instead of dynamic positioning systems for construction
vessels, thus further reducing noise input into the water column.
Therefore, the underwater noise impacts from the proposed Manette
Bridge replacement construction is expected to have a low level of
noise intensity, and be of short duration and localized. These low
intensity, localized, and short-term noise exposures, when received at
distances of Level B behavioral harassment (i.e., 160 dB re 1 microPa
(rms)
[[Page 38791]]
from impulse sources and 120 dB re 1 microPa (rms) from non-impulse
sources), are expected to cause brief startle reactions or short-term
behavioral modification by the animals. These brief reactions and
behavioral changes are expected to disappear when the exposures cease.
Therefore, these levels of received underwater construction noise from
the proposed Manette Bridge replacement project are not expected to
affect marine mammal annual rates of recruitment or survival.
Based on the analysis contained herein of the likely effects of the
specified activity on marine mammals and their habitat, and taking into
consideration the implementation of the required mitigation and
monitoring measures, NMFS finds that the Manette Bridge replacement
project will result in the incidental take of small numbers of Pacific
harbor seals, California sea lions, and gray whales by Level B
harassment only, and that the total taking from harassment will have a
negligible impact on the affected species or stocks.
Impact on Availability of Affected Species for Taking for Subsistence
Uses
There are no relevant subsistence uses of marine mammals implicated
by this action.
Endangered Species Act (ESA)
There are two marine mammal species and two fish species that are
listed as endangered or threatened under the ESA with confirmed or
possible occurrence in the study area: Eastern North Pacific Southern
Resident killer whale, Eastern U.S. Steller sea lion, Chinook salmon,
and steelhead trout. Under section 7 of the ESA, the Federal Highway
Administration (FHWA) and WSDOT have consulted with NMFS Northwest
Regional Office (NWRO) on the proposed Manette Bridge replacement
project. In a memo issued with its August 3, 2009, Biological Opinion,
NMFS NWRO stated that the proposed bridge replacement may affect, but
is not likely to adversely affect the listed marine mammal species and
stocks. On May 28, 2010, FHWA requested the reinitiation of section 7
consultation with NMFS NWRO on the newly ESA-listed three Puget Sound
rockfish species. The consultation is expected to be completed in July
2010.
The issuance of an IHA to WSDOT constitutes an agency action that
authorizes an activity that may affect ESA-listed species and,
therefore, is subject to section 7 of the ESA. As the effects of the
activities on listed marine mammals and salmonids were analyzed during
a formal consultation between the FHWA and NMFS, and as the underlying
action has not changed from that considered in the consultation, the
discussion of effects that are contained in the Biological Opinion and
accompanying memo issued to the FHWA on August 3, 2009, pertains also
to this action. Therefore, NMFS has determined that issuance of an IHA
for this activity would not lead to any effects to listed marine mammal
species apart from those that were considered in the consultation on
FHWA's action. Although the reinitiation of section 7 consultation by
FHWA on three Puget Sound rockfish species is still on-going, NMFS does
not expect that the outcome would affect NMFS' action in issuing an IHA
for the incidental take of marine mammals.
National Environmental Policy Act (NEPA)
To meet NMFS' NEPA requirements for the issuance of an IHA to the
WSDOT, NMFS has prepared an Environmental Assessment (EA) that is
specific to the construction and demolishing activities associated with
the Manette Bridge replacement project in Bremerton, WA. NMFS has
prepared an EA titled Issuance of an Incidental Harassment
Authorization to the Washington State Department of Transportation to
Take Marine Mammals by Harassment Incidental to Manette Bridge
Replacement Project in Bremerton, Washington, that evaluates the
impacts on the human environment of NMFS' authorization of incidental
Level B harassment resulting from the specified activity in the
specified geographic region. The NMFS has made a Finding of No
Significant Impact (FONSI) and, therefore, it is not necessary to
prepare an environmental impact statement for the issuance of an IHA to
WSDOT for this activity. A copy of the EA and the NMFS FONSI for this
activity is available upon request (see ADDRESSES).
As a result of these determinations, NMFS has issued an IHA to the
WSDOT to conduct construction and demolishing activities associated
with the Manette Bridge replacement project in Bremerton, WA, provided
the previously mentioned mitigation, monitoring, and reporting
requirements are incorporated.
Dated: June 29, 2010.
Helen Golde,
Deputy Director, Office of Protected Resources, National Marine
Fisheries Service.
[FR Doc. 2010-16370 Filed 7-2-10; 8:45 am]
BILLING CODE 3510-22-S