Pepperell Hydro Company, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments and Motions To Intervene, 36377-36378 [2010-15385]
Download as PDF
mstockstill on DSKH9S0YB1PROD with NOTICES
Federal Register / Vol. 75, No. 122 / Friday, June 25, 2010 / Notices
Anita R.Wilson, John S. Decker, or
Damien R. Lyster, Vinson & Elkins
L.L.P., 1455 Pennsylvania Avenue, NW.,
Suite 600, Washington, DC 20004–1008,
or by calling (202) 639–6599 (telephone)
or (202) 879–8899 (fax),
jdecker@velaw.com.
Pursuant to section 157.9 of the
Commission’s rules, 18 CFR 157.9,
within 90 days of this Notice the
Commission staff will either: complete
its environmental assessment (EA) and
place it into the Commission’s public
record (eLibrary) for this proceeding; or
issue a Notice of Schedule for
Environmental Review. If a Notice of
Schedule for Environmental Review is
issued, it will indicate, among other
milestones, the anticipated date for the
Commission staff’s issuance of the final
environmental impact statement (FEIS)
or EA for this proposal. The filing of the
EA in the Commission’s public record
for this proceeding or the issuance of a
Notice of Schedule for Environmental
Review will serve to notify Federal and
State agencies of the timing for the
completion of all necessary reviews, and
the subsequent need to complete all
Federal authorizations within 90 days of
the date of issuance of the Commission
staff’s FEIS or EA.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below, file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
14 copies of filings made with the
Commission and must mail a copy to
the applicant and to every other party in
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
VerDate Mar<15>2010
16:23 Jun 24, 2010
Jkt 220001
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commentors will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commentors will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commentors
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: July 1, 2010.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–15387 Filed 6–24–10; 8:45 am]
BILLING CODE 6717–01–P
PO 00000
Frm 00032
Fmt 4703
Sfmt 4703
36377
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12721–004]
Pepperell Hydro Company, LLC; Notice
of Preliminary Permit Application
Accepted for Filing and Soliciting
Comments and Motions To Intervene
June 17, 2010.
On March 9, 2010, the Pepperell
Hydro Company, LLC filed an
application for a preliminary permit,
pursuant to section 4(f) of the Federal
Power Act (FPA), proposing to study the
feasibility of the East Pepperell Project,
located on the Nashua River in
Middlesex County, Massachusetts. The
sole purpose of a preliminary permit, if
issued, is to grant the permit holder
priority to file a license application
during the permit term. A preliminary
permit does not authorize the permit
holder to perform any land-disturbing
activities or otherwise enter upon lands
or waters owned by others without the
owners’ express permission.
The proposed project would consist
of: (1) The existing 27-foot-high, 275foot-long East Pepperell Dam; (2) an
existing intake; (3) an existing 1,465acre impoundment at a normal
maximum water surface elevation of
199.8 feet above mean sea level (with 3foot-high flashboards in place); (4) an
existing 13-foot-diameter, 666-foot-long
wood stave penstock; (5) a powerhouse
containing three existing generating
units and a new low-flow turbine
generator located adjacent to the intake
gates with a total installed capacity of
2,070 kilowatts; (6) an existing tailrace;
(7) an existing switchyard; (8) an
existing 7.5-mile-long, 69-kilovolt
transmission line owned by National
Grid; and (9) appurtenant facilities. The
project would have an estimated average
annual generation of approximately
8,123 megawatt-hours.
Applicant Contact: Peter B. Clark,
Pepperell Hydro Company LLC, P.O.
Box 149, 823 Bay Road, Hamilton, MA
01936, (978) 468–3999.
FERC Contact: Brandon Cherry, (202)
502–8328.
Deadline for filing comments or
motions to intervene: 60 days from the
issuance of this notice. Comments and
motions to intervene may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site (https://www.ferc.gov/docs-filing/
ferconline.asp) under the ‘‘eFiling’’ link.
For a simpler method of submitting text
only comments, click on ‘‘Quick
Comment.’’ For assistance, please
E:\FR\FM\25JNN1.SGM
25JNN1
36378
Federal Register / Vol. 75, No. 122 / Friday, June 25, 2010 / Notices
contact FERC Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and eight copies to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–12721) in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–15385 Filed 6–24–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2503–143]
Notice of Application for Amendment
of License and Soliciting Comments,
Motions To Intervene, and Protests;
Duke Energy Carolinas, LLC
mstockstill on DSKH9S0YB1PROD with NOTICES
June 17, 2010.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Application Type: Non-project use
of project lands.
b. Project No: 2503–143.
c. Date Filed: June 4, 2010.
d. Applicant: Duke Energy Carolinas,
LLC.
e. Name of Project: Keowee-Toxaway
Project.
f. Location: The proposed non-project
use is on Lake Keowee in Pickens
County, South Carolina.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Joe Hall, Duke
Energy Carolinas, LLC, P.O. Box 1006,
Charlotte, NC 28201–1006; (704) 382–
8576.
i. FERC Contact: Shana High, (202)
502–8674.
j. Deadline for filing comments,
motions to intervene, and protests: July
19, 2010.
Comments, protests and interventions
may be filed electronically via the
Internet in lieu of paper. See, 18 CFR
385.2001(a)(1)(iii) and the instructions
VerDate Mar<15>2010
16:23 Jun 24, 2010
Jkt 220001
on the Commission’s Web site at
https://www.ferc.gov under the ‘‘e-Filing’’
link. The Commission strongly
encourages electronic filings.
To paper-file, an original and eight
copies should be mailed to: Secretary,
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426. Please include the project
number (P–2503–143) on any comments
or motions filed.
The Commission’s Rules of Practice
and Procedure require all interveners
filing documents with the Commission
to serve a copy of that document on
each person whose name appears on the
official service list for the project.
Further, if an intervener files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency. A copy of any
motion to intervene must also be served
upon each representative of the
Applicant specified in the particular
application.
k. Description of Request: Duke
Energy Carolinas, LLC requests
Commission approval to grant The Cliffs
at Lake Keowee II, LLC permission to
construct a residential marina on project
lands. The licensee requests approval to
lease four areas totaling 1.88 acres for a
courtesy ramp, an access ramp, and four
cluster docks with a total of 58 docking
locations. The application includes 500
feet of shoreline stabilization.
l. Locations of the Application: A
copy of the application is available for
inspection and reproduction at the
Commission’s Public Reference Room,
located at 888 First Street, NE., Room
2A, Washington, DC 20426, or by calling
(202) 502–8371. This filing may also be
viewed on the Commission’s Web site at
https://www.ferc.gov using the ‘‘eLibrary’’
link. Enter the docket number (P–2503)
excluding the last three digits in the
docket number field to access the
document. You may also register online
at https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, call 1–866–208–3376 or
e-mail FERCOnlineSupport@ferc.gov,
for TTY, call (202) 502–8659. A copy is
also available for inspection and
reproduction at the address in item (h)
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Comments, Protests, or Motions to
Intervene: Anyone may submit
comments, a protest, or a motion to
PO 00000
Frm 00033
Fmt 4703
Sfmt 4703
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
o. Any filings must bear in all capital
letters the title ‘‘COMMENTS’’,
‘‘PROTEST’’, or ‘‘MOTION TO
INTERVENE’’, as applicable, and the
Project Number of the particular
application to which the filing refers.
p. Agency Comments: Federal, state,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
Applicant. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
q. Comments, protests and
interventions may be filed electronically
via the Internet in lieu of paper. See, 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site at https://www.ferc.gov under the ‘‘eFiling’’ link.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–15388 Filed 6–24–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13679–000]
JD Products, LLC; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions to Intervene, and
Competing Applications
June 18, 2010.
On March 2, 2010, JD Products, LLC
(JD Products) filed an application for a
preliminary permit, pursuant to section
4(f) of the Federal Power Act, proposing
to study the feasibility of the proposed
San Onofre OWEG Electricity Farm
Project (project). The proposed project
would utilize 11,443 Ocean Wave
Electricity Generation (OWEG) units, an
experimental technology, with an
estimated installed capacity of 3,186
E:\FR\FM\25JNN1.SGM
25JNN1
Agencies
[Federal Register Volume 75, Number 122 (Friday, June 25, 2010)]
[Notices]
[Pages 36377-36378]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-15385]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 12721-004]
Pepperell Hydro Company, LLC; Notice of Preliminary Permit
Application Accepted for Filing and Soliciting Comments and Motions To
Intervene
June 17, 2010.
On March 9, 2010, the Pepperell Hydro Company, LLC filed an
application for a preliminary permit, pursuant to section 4(f) of the
Federal Power Act (FPA), proposing to study the feasibility of the East
Pepperell Project, located on the Nashua River in Middlesex County,
Massachusetts. The sole purpose of a preliminary permit, if issued, is
to grant the permit holder priority to file a license application
during the permit term. A preliminary permit does not authorize the
permit holder to perform any land-disturbing activities or otherwise
enter upon lands or waters owned by others without the owners' express
permission.
The proposed project would consist of: (1) The existing 27-foot-
high, 275-foot-long East Pepperell Dam; (2) an existing intake; (3) an
existing 1,465-acre impoundment at a normal maximum water surface
elevation of 199.8 feet above mean sea level (with 3-foot-high
flashboards in place); (4) an existing 13-foot-diameter, 666-foot-long
wood stave penstock; (5) a powerhouse containing three existing
generating units and a new low-flow turbine generator located adjacent
to the intake gates with a total installed capacity of 2,070 kilowatts;
(6) an existing tailrace; (7) an existing switchyard; (8) an existing
7.5-mile-long, 69-kilovolt transmission line owned by National Grid;
and (9) appurtenant facilities. The project would have an estimated
average annual generation of approximately 8,123 megawatt-hours.
Applicant Contact: Peter B. Clark, Pepperell Hydro Company LLC,
P.O. Box 149, 823 Bay Road, Hamilton, MA 01936, (978) 468-3999.
FERC Contact: Brandon Cherry, (202) 502-8328.
Deadline for filing comments or motions to intervene: 60 days from
the issuance of this notice. Comments and motions to intervene may be
filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii)
and the instructions on the Commission's Web site (https://www.ferc.gov/docs-filing/ferconline.asp) under the ``eFiling'' link. For a simpler
method of submitting text only comments, click on ``Quick Comment.''
For assistance, please
[[Page 36378]]
contact FERC Online Support at FERCOnlineSupport@ferc.gov; call toll-
free at (866) 208-3676; or, for TTY, contact (202) 502-8659. Although
the Commission strongly encourages electronic filing, documents may
also be paper-filed. To paper-file, mail an original and eight copies
to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC 20426.
More information about this project, including a copy of the
application, can be viewed or printed on the ``eLibrary'' link of
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P-12721) in the docket number field to access
the document. For assistance, contact FERC Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010-15385 Filed 6-24-10; 8:45 am]