Natural Currents Energy Services, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 30388-30389 [2010-12994]
Download as PDF
30388
Federal Register / Vol. 75, No. 104 / Tuesday, June 1, 2010 / Notices
4:30 p.m ...............................
Richard O’Neill, FERC—Conclusion and Next Steps.
[FR Doc. 2010–12990 Filed 5–28–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13682–000]
Natural Currents Energy Services,
LLC; Notice of Preliminary Permit
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, and Competing Applications
erowe on DSK5CLS3C1PROD with NOTICES
May 24, 2010.
On May 5, 2010, Natural Currents
Energy Services, LLC filed an
application for a preliminary permit,
pursuant to section 4(f) of the Federal
Power Act, proposing to study the
feasibility of the Hoffmans Marina Tidal
Energy Project, which would be located
on the Manasquan River, in Monmouth
County, New Jersey. The sole purpose of
a preliminary permit, if issued, is to
grant the permit holder priority to file
a license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
any land-disturbing activities or
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
Natural Currents proposes to develop
this project, in conjunction with
Hoffmans Marina, to install and operate
in-stream tidal turbines to power the
office building and marina on site.
Natural Currents Red Hawk TM Tidal InStream Energy Conversion (TISEC)
modules will generate electricity in the
free flow of the tides. The initial
installations would consist of ten instream 20-kilowatt (kW) turbines with
an initial peak output of 200 kW.
Applicant Contact: Mr. Roger Bason,
Natural Currents Energy Services, LLC,
24 Roxanne Boulevard, Highland, NY
12561; phone (845) 691–4009.
FERC Contact: John M. Mudre, (202)
502–8902.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36. Comments, motions to
intervene, notices of intent, and
competing applications may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
VerDate Mar<15>2010
15:41 May 28, 2010
Jkt 220001
site (https://www.ferc.gov/docs-filing/
ferconline.asp) under the ‘‘eFiling’’ link.
For a simpler method of submitting text
only comments, click on ‘‘Quick
Comment.’’ For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and eight copies to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–13682) in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–12991 Filed 5–28–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13725–000]
Natural Currents Energy Services,
LLC; Notice of Preliminary Permit
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, and Competing Applications
May 24, 2010.
On May 6, 2010, Natural Currents
Energy Services, LLC filed an
application for a preliminary permit,
pursuant to section 4(f) of the Federal
Power Act, proposing to study the
feasibility of the Highlands New Jersey
Tidal Energy Project, which would be
located on the Shrewsbury River, in
Monmouth County, New Jersey. The
sole purpose of a preliminary permit, if
issued, is to grant the permit holder
priority to file a license application
during the permit term. A preliminary
permit does not authorize the permit
holder to perform any land-disturbing
activities or otherwise enter upon lands
or waters owned by others without the
owners’ express permission.
Natural Currents proposes to develop
this project, in conjunction with various
PO 00000
Frm 00025
Fmt 4703
Sfmt 4703
marinas as well as private, public and
commercial properties within the
project footprint, potentially including
42 South Bay Ave, LLC, Twin Lights
Marina, Barhs Marina, and other
property owners in the Highlands, NJ
area. The purpose of this project is to
install and operate in-stream tidal
turbines to power the office buildings
and marinas within the site. Natural
Currents Red Hawk TM Tidal In-Stream
Energy Conversion (TISEC) modules
would generate electricity in the free
flow of the tides. The initial
installations will consist of twenty instream 150-kilowatt (kW) turbines with
an initial peak output of 3,000 kW.
Applicant Contact: Mr. Roger Bason,
Natural Currents Energy Services, LLC,
24 Roxanne Boulevard, Highland, NY
12561; phone (845) 691–4009.
FERC Contact: John M. Mudre, (202)
502–8902.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Competing applications and notices of
intent must meet the requirements of 18
CFR 4.36. Comments, motions to
intervene, notices of intent, and
competing applications may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site (https://www.ferc.gov/docs-filing/
ferconline.asp) under the ‘‘eFiling’’ link.
For a simpler method of submitting text
only comments, click on ‘‘Quick
Comment.’’ For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and eight copies to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–13725) in
the docket number field to access the
E:\FR\FM\01JNN1.SGM
01JNN1
Federal Register / Vol. 75, No. 104 / Tuesday, June 1, 2010 / Notices
document. For assistance, contact FERC
Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–12994 Filed 5–28–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13727–000]
City of Santa Fe, NM; Notice of
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, Protests,
Recommendations, and Terms and
Conditions
erowe on DSK5CLS3C1PROD with NOTICES
May 24, 2010.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Conduit
Exemption.
b. Project No.: 13727–000.
c. Date filed: May 10, 2010.
d. Applicant: City of Santa Fe, New
Mexico.
e. Name of Project: Santa Fe Canyon
Hydroelectric Project.
f. Location: The proposed Santa Fe
Canyon Hydroelectric Project would be
located on a pipeline in the City of
Santa Fe’s water distribution system
located in Santa Fe County, New
Mexico. The land on which all the
project structures are located is owned
by the applicant.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791a–825r.
h. Applicant Contact: Mr. Dale Lyons,
Water Resources Coordinator, City of
Santa Fe Water Division, 801 West San
Mateo Road, Santa Fe, New Mexico
87505; telephone (505) 955–4204.
i. FERC Contact: Linda Stewart,
telephone (202) 502–6680, and e-mail
address linda.stewart@ferc.gov.
j. Status of Environmental Analysis:
This application is ready for
environmental analysis at this time, and
the Commission is requesting
comments, reply comments,
recommendations, terms and
conditions, and prescriptions.
k. Deadline for filing responsive
documents: Due to the small size and
location of the proposed project in a
closed system, as well as the resource
agency consultation letters filed with
the application, the 60-day timeframe
specified in 18 CFR 4.43(b) for filing all
comments, motions to intervene,
protests, recommendations, terms and
VerDate Mar<15>2010
15:41 May 28, 2010
Jkt 220001
conditions, and prescriptions is
shortened to 30 days from the issuance
date of this notice. All reply comments
filed in response to comments
submitted by any resource agency,
Indian tribe, or person, must be filed
with the Commission within 45 days
from the issuance date of this notice.
Comments, protests, and
interventions may be filed electronically
via the Internet in lieu of paper; see 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site under the ‘‘e-Filing’’ link. The
Commission strongly encourages
electronic filings.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person in the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
l. Description of Project: The proposed
Santa Fe Canyon Hydroelectric Project
would consist of: (1) A proposed new
concrete vault containing one turbine
generating unit having an installed
capacity of 90 kilowatts; and (2)
appurtenant facilities. The project
would have an estimated annual
generation of 394,900 kilowatt-hours
that would be sold to a local utility.
m. This filing is available for review
and reproduction at the Commission in
the Public Reference Room, Room 2A,
888 First Street, NE., Washington, DC
20426. The filing may also be viewed on
the Web at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number, here P–13727, in the docket
number field to access the document.
For assistance, call toll-free 1–866–208–
3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659. A copy is also
available for review and reproduction at
the address in item h above.
n. Development Application—Any
qualified applicant desiring to file a
competing application must submit to
the Commission, on or before the
specified deadline date for the
particular application, a competing
development application, or a notice of
intent to file such an application.
Submission of a timely notice of intent
allows an interested person to file the
competing development application no
later than 120 days after the specified
deadline date for the particular
application. Applications for
preliminary permits will not be
accepted in response to this notice.
PO 00000
Frm 00026
Fmt 4703
Sfmt 4703
30389
o. Notice of Intent—A notice of intent
must specify the exact name, business
address, and telephone number of the
prospective applicant, and must include
an unequivocal statement of intent to
submit a competing development
application. A notice of intent must be
served on the applicant(s) named in this
public notice.
p. Protests or Motions to Intervene—
Anyone may submit a protest or a
motion to intervene in accordance with
the requirements of Rules of Practice
and Procedure, 18 CFR 385.210,
385.211, and 385.214. In determining
the appropriate action to take, the
Commission will consider all protests
filed, but only those who file a motion
to intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any protests or
motions to intervene must be received
on or before the specified deadline date
for the particular application.
q. All filings must (1) Bear in all
capital letters the title ‘‘PROTEST’’,
‘‘MOTION TO INTERVENE’’, ‘‘NOTICE
OF INTENT TO FILE COMPETING
APPLICATION’’, ‘‘COMPETING
APPLICATION’’, ‘‘COMMENTS’’,
‘‘REPLY COMMENTS,’’
‘‘RECOMMENDATIONS,’’ ‘‘TERMS AND
CONDITIONS,’’ or ‘‘PRESCRIPTIONS;’’
(2) set forth in the heading the name of
the applicant and the project number of
the application to which the filing
responds; (3) furnish the name, address,
and telephone number of the person
protesting or intervening; and (4)
otherwise comply with the requirements
of 18 CFR 385.2001 through 385.2005.
All comments, recommendations, terms
and conditions or prescriptions must set
forth their evidentiary basis and
otherwise comply with the requirements
of 18 CFR 4.34(b). Agencies may obtain
copies of the application directly from
the applicant. Any of these documents
must be filed by providing the original
and eight copies to: The Secretary,
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426. An additional copy must be sent
to Director, Division of Hydropower
Administration and Compliance, Office
of Energy Projects, Federal Energy
Regulatory Commission, at the above
address. A copy of any protest or motion
to intervene must be served upon each
representative of the applicant specified
in the particular application. A copy of
all other filings in reference to this
application must be accompanied by
proof of service on all persons listed in
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
E:\FR\FM\01JNN1.SGM
01JNN1
Agencies
[Federal Register Volume 75, Number 104 (Tuesday, June 1, 2010)]
[Notices]
[Pages 30388-30389]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-12994]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 13725-000]
Natural Currents Energy Services, LLC; Notice of Preliminary
Permit Application Accepted for Filing and Soliciting Comments, Motions
To Intervene, and Competing Applications
May 24, 2010.
On May 6, 2010, Natural Currents Energy Services, LLC filed an
application for a preliminary permit, pursuant to section 4(f) of the
Federal Power Act, proposing to study the feasibility of the Highlands
New Jersey Tidal Energy Project, which would be located on the
Shrewsbury River, in Monmouth County, New Jersey. The sole purpose of a
preliminary permit, if issued, is to grant the permit holder priority
to file a license application during the permit term. A preliminary
permit does not authorize the permit holder to perform any land-
disturbing activities or otherwise enter upon lands or waters owned by
others without the owners' express permission.
Natural Currents proposes to develop this project, in conjunction
with various marinas as well as private, public and commercial
properties within the project footprint, potentially including 42 South
Bay Ave, LLC, Twin Lights Marina, Barhs Marina, and other property
owners in the Highlands, NJ area. The purpose of this project is to
install and operate in-stream tidal turbines to power the office
buildings and marinas within the site. Natural Currents Red Hawk \TM\
Tidal In-Stream Energy Conversion (TISEC) modules would generate
electricity in the free flow of the tides. The initial installations
will consist of twenty in-stream 150-kilowatt (kW) turbines with an
initial peak output of 3,000 kW.
Applicant Contact: Mr. Roger Bason, Natural Currents Energy
Services, LLC, 24 Roxanne Boulevard, Highland, NY 12561; phone (845)
691-4009.
FERC Contact: John M. Mudre, (202) 502-8902.
Deadline for filing comments, motions to intervene, competing
applications (without notices of intent), or notices of intent to file
competing applications: 60 days from the issuance of this notice.
Competing applications and notices of intent must meet the requirements
of 18 CFR 4.36. Comments, motions to intervene, notices of intent, and
competing applications may be filed electronically via the Internet.
See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's
Web site (https://www.ferc.gov/docs-filing/ferconline.asp) under the
``eFiling'' link. For a simpler method of submitting text only
comments, click on ``Quick Comment.'' For assistance, please contact
FERC Online Support at FERCOnlineSupport@ferc.gov; call toll-free at
(866) 208-3676; or, for TTY, contact (202) 502-8659. Although the
Commission strongly encourages electronic filing, documents may also be
paper-filed. To paper-file, mail an original and eight copies to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
More information about this project, including a copy of the
application, can be viewed or printed on the ``eLibrary'' link of
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P-13725) in the docket number field to access
the
[[Page 30389]]
document. For assistance, contact FERC Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010-12994 Filed 5-28-10; 8:45 am]