Cellu Tissue Corporation; Notice of Application Tendered for Filing With the Commission and Establishing Procedural Schedule for Licensing and Deadline for Submission of Final Amendments, 28000-28001 [2010-11910]
Download as PDF
jlentini on DSKJ8SOYB1PROD with NOTICES
28000
Federal Register / Vol. 75, No. 96 / Wednesday, May 19, 2010 / Notices
toll-free, (886) 208–3676 or TTY, (202)
502–8659.
Any questions concerning this
application may be directed to Michelle
Willis, Manager, Regulatory &
Compliance, CenterPoint Energy Gas
Transmission Company, P.O. Box
21734, Shreveport, Louisiana 71151, at
(318) 429–3708.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below, file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
14 copies of filings made in the
proceeding with the Commission and
must mail a copy to the applicant and
to every other party. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: June 2, 2010.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–11912 Filed 5–18–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 2851–016]
Cellu Tissue Corporation; Notice of
Application Tendered for Filing With
the Commission and Establishing
Procedural Schedule for Licensing and
Deadline for Submission of Final
Amendments
May 12, 2010.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: New Major
License.
b. Project No.: 2851–016.
c. Date Filed: April 29, 2010.
d. Applicant: Cellu Tissue
Corporation.
e. Name of Project: Natural Dam
Hydroelectric Project.
f. Location: On the Oswegatchie River
in the town of Gouverneur, St. Lawrence
County, New York. The project would
not occupy any Federal lands.
g. Filed Pursuant to: 18 CFR part 5 of
the Commission’s Regulations.
h. Agent Contact: Chris Fiedler or
Robin Gaumes, Cellu Tissue Corp.,
Natural Dam Mill, 4921 Route 58N,
Gouverneur, NY 13642, (315) 287–7190.
i. FERC Contact: John Baummer, (202)
502–6837.
j. This application is not ready for
environmental analysis at this time.
k. Project Description: The existing
project consists of: (1) A 155 foot-longdam and spillway with a inflatable
rubber crest at a deflated crest elevation
of 394.0 feet National Geodetic Vertical
Datum (NGVD); (2) a 180-foot-long
auxiliary dam/spillway with a crest
elevation of 397.3 feet NGVD; (3) a 570acre impoundment with a normal water
surface elevation of 396.0 feet NGVD; (4)
a 152-foot-long gated headpond
structure leading to an intake structure
and a 412-foot-long flume along the
west bank of the river; (5) a 570-footlong bypass reach; (6) a powerhouse
containing three turbine generating
units with a total installed capacity of
1,020 kW; and (7) electrical transformers
located in a transformer yard adjacent to
the north wall of the powerhouse that
supply power for use at the Natural Dam
Mill to produce specialty paper
products.
Cellu Tissue Corporation proposes to:
(1) Operate the project in a run-of river
mode with a minimum impoundment
elevation of 395.85 feet; (2) maintain a
minimum bypass flow of 77 cubic feet
per second (cfs) or inflow, whichever is
less; (3) upgrade water level monitoring
equipment for the impoundment; and
(4) install equipment to allow for
automatic pond level control.
l. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the ‘‘eLibrary’’
link. Enter the docket number excluding
the last three digits in the docket
number field to access the document.
For assistance, contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item (h) above.
m. You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Procedural Schedule: The
application will be processed according
to the following Hydro Licensing
Schedule. Revisions to the schedule
may be made as appropriate.
Milestone
Target date
Notice of Acceptance/Notice of Ready for Environmental Analysis .......................................................................................
Filing of Recommendations, preliminary terms and conditions, and fishway prescriptions ...................................................
Commission issues Non-Draft EA ...........................................................................................................................................
Comments on EA ....................................................................................................................................................................
VerDate Mar<15>2010
16:07 May 18, 2010
Jkt 220001
PO 00000
Frm 00022
Fmt 4703
Sfmt 4703
E:\FR\FM\19MYN1.SGM
19MYN1
June 29, 2010.
August 28, 2010.
December 26, 2010.
January 25, 2011.
Federal Register / Vol. 75, No. 96 / Wednesday, May 19, 2010 / Notices
Milestone
Target date
Modified Terms and Conditions ...............................................................................................................................................
o. Final amendments to the
application must be filed with the
Commission no later than 30 days from
the issuance date of the notice of ready
for environmental analysis.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–11910 Filed 5–18–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 1992–003]
Ken Willis; Notice of Authorization for
Continued Project Operation
jlentini on DSKJ8SOYB1PROD with NOTICES
May 12, 2010.
On April 25, 2008, Ken Willis,
licensee for the Fire Mountain Lodge
Hydroelectric Project, filed an
Application for a New License pursuant
to the Federal Power Act (FPA) and the
Commission’s regulations thereunder.
The Fire Mountain Lodge Hydroelectric
Project is located in Fern Springs, in
Tehama County, California near the
town of Chester, Plumas County,
California.
The license for Project No. 1992 was
issued for a period ending April 30,
2010. Section 15(a)(1) of the FPA, 16
U.S.C. 808(a)(1), requires the
Commission, at the expiration of a
license term, to issue from year-to-year
an annual license to the then licensee
under the terms and conditions of the
prior license until a new license is
issued, or the project is otherwise
disposed of as provided in section 15 or
any other applicable section of the FPA.
If the project’s prior license waived the
applicability of section 15 of the FPA,
then, based on section 9(b) of the
Administrative Procedure Act, 5 U.S.C.
558(c), and as set forth at 18 CFR
16.21(a), if the licensee of such project
has filed an application for a subsequent
license, the licensee may continue to
operate the project in accordance with
the terms and conditions of the license
after the minor or minor part license
expires, until the Commission acts on
its application. If the licensee of such a
project has not filed an application for
a subsequent license, then it may be
required, pursuant to 18 CFR 16.21(b),
to continue project operations until the
Commission issues someone else a
VerDate Mar<15>2010
16:07 May 18, 2010
Jkt 220001
license for the project or otherwise
orders disposition of the project.
If the project is subject to section 15
of the FPA, notice is hereby given that
an annual license for Project No. 1992
is issued to Ken Willis for a period
effective May 1, 2010 through April 30,
2011, or until the issuance of a new
license for the project or other
disposition under the FPA, whichever
comes first. If issuance of a new license
(or other disposition) does not take
place on or before April 30, 2011, notice
is hereby given that, pursuant to 18 CFR
16.18(c), an annual license under
section 15(a)(1) of the FPA is renewed
automatically without further order or
notice by the Commission, unless the
Commission orders otherwise. If the
project is not subject to section 15 of the
FPA, notice is hereby given that Ken
Willis is authorized to continue
operation of the Fire Mountain Lodge
Hydroelectric Project, until such time as
the Commission acts on its application
for a subsequent license.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–11909 Filed 5–18–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings #1
May 10, 2010.
Take notice that the Commission
received the following electric corporate
filings:
Docket Numbers: EC10–66–000.
Applicants: Black Hills Power, Inc.
Description: Application of Black
Hills Power, Inc.
Filed Date: 05/07/2010.
Accession Number: 20100507–5116.
Comment Date: 5 p.m. Eastern Time
on Friday, May 28, 2010.
Take notice that the Commission
received the following electric rate
filings:
Docket Numbers: ER05–1232–024;
ER07–1358–014.
Applicants: J.P. Morgan Ventures
Energy Corporation, BE Louisiana LLC.
Description: J.P. Morgan Ventures
Energy Corporation and BE Louisiana
LLC’s Supplement to Updated Market
Power Analysis and Order No. 697
Compliance Filing.
PO 00000
Frm 00023
Fmt 4703
28001
Sfmt 4703
March 26, 2011.
Filed Date: 05/05/2010.
Accession Number: 20100505–5111.
Comment Date: 5 p.m. Eastern Time
on Wednesday, May 26, 2010.
Docket Numbers: ER07–930–002;
ER06–146–004; ER98–2782–017; ER98–
2782–018; ER98–2782–019.
Applicants: AER NY–Gen, LLC;
Alliance Energy Marketing, LLC; AG–
Energy, LP.
Description: AER NY–Gen, LLC et al.
submits market power update for the
Northeast Region in compliance with
Order No 697.
Filed Date: 05/06/2010.
Accession Number: 20100510–0205.
Comment Date: 5 p.m. Eastern Time
on Tuesday, July 06, 2010.
Docket Numbers: ER10–1052–000.
Applicants: Public Service Electric
and Gas Company.
Description: Public Service Electric
and Gas Company submits an executed
transmission facilities agreement with
Atlantic City Electric Company
substituting Original Service Agreement
1877 etc.
Filed Date: 04/29/2010.
Accession Number: 20100429–0073.
Comment Date: 5 p.m. Eastern Time
on Thursday, May 20, 2010.
Docket Numbers: ER10–1207–000.
Applicants: Edgewood Energy, LLC.
Description: Edgewood Energy, LLC et
al. submits Notice of Succession and
revised market-based rate wholesale
power sales tariff, FERC Electric Tariff,
Original Volume 1.
Filed Date: 05/07/2010.
Accession Number: 20100510–0201.
Comment Date: 5 p.m. Eastern Time
on Friday, May 28, 2010.
Docket Numbers: ER10–1208–000.
Applicants: Shoreham Energy, LLC.
Description: Edgewood Energy, LLC et
al. submits Notice of Succession and
revised market-based rate wholesale
power sales tariff, FERC Electric Tariff,
Original Volume 1.
Filed Date: 05/07/2010
Accession Number: 20100510–0201.
Comment Date: 5 p.m. Eastern Time
on Friday, May 28, 2010.
Docket Numbers: ER10–1209–000.
Applicants: PPL Electric Utilities
Corporation.
Description: PPL Electric Utilities
Corporation submits revised tariff sheets
to the PJM Interconnection, LLC Open
Access Transmission Tariff.
Filed Date: 05/07/2010.
Accession Number: 20100510–0202.
E:\FR\FM\19MYN1.SGM
19MYN1
Agencies
[Federal Register Volume 75, Number 96 (Wednesday, May 19, 2010)]
[Notices]
[Pages 28000-28001]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-11910]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2851-016]
Cellu Tissue Corporation; Notice of Application Tendered for
Filing With the Commission and Establishing Procedural Schedule for
Licensing and Deadline for Submission of Final Amendments
May 12, 2010.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: 2851-016.
c. Date Filed: April 29, 2010.
d. Applicant: Cellu Tissue Corporation.
e. Name of Project: Natural Dam Hydroelectric Project.
f. Location: On the Oswegatchie River in the town of Gouverneur,
St. Lawrence County, New York. The project would not occupy any Federal
lands.
g. Filed Pursuant to: 18 CFR part 5 of the Commission's
Regulations.
h. Agent Contact: Chris Fiedler or Robin Gaumes, Cellu Tissue
Corp., Natural Dam Mill, 4921 Route 58N, Gouverneur, NY 13642, (315)
287-7190.
i. FERC Contact: John Baummer, (202) 502-6837.
j. This application is not ready for environmental analysis at this
time.
k. Project Description: The existing project consists of: (1) A 155
foot-long-dam and spillway with a inflatable rubber crest at a deflated
crest elevation of 394.0 feet National Geodetic Vertical Datum (NGVD);
(2) a 180-foot-long auxiliary dam/spillway with a crest elevation of
397.3 feet NGVD; (3) a 570-acre impoundment with a normal water surface
elevation of 396.0 feet NGVD; (4) a 152-foot-long gated headpond
structure leading to an intake structure and a 412-foot-long flume
along the west bank of the river; (5) a 570-foot-long bypass reach; (6)
a powerhouse containing three turbine generating units with a total
installed capacity of 1,020 kW; and (7) electrical transformers located
in a transformer yard adjacent to the north wall of the powerhouse that
supply power for use at the Natural Dam Mill to produce specialty paper
products.
Cellu Tissue Corporation proposes to: (1) Operate the project in a
run-of river mode with a minimum impoundment elevation of 395.85 feet;
(2) maintain a minimum bypass flow of 77 cubic feet per second (cfs) or
inflow, whichever is less; (3) upgrade water level monitoring equipment
for the impoundment; and (4) install equipment to allow for automatic
pond level control.
l. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at https://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support at FERCOnlineSupport@ferc.gov or toll-free at 1-
866-208-3676, or for TTY, (202) 502-8659. A copy is also available for
inspection and reproduction at the address in item (h) above.
m. You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via e-mail of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
n. Procedural Schedule: The application will be processed according
to the following Hydro Licensing Schedule. Revisions to the schedule
may be made as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Notice of Acceptance/Notice of Ready June 29, 2010.
for Environmental Analysis.
Filing of Recommendations, August 28, 2010.
preliminary terms and conditions,
and fishway prescriptions.
Commission issues Non-Draft EA...... December 26, 2010.
Comments on EA...................... January 25, 2011.
[[Page 28001]]
Modified Terms and Conditions....... March 26, 2011.
------------------------------------------------------------------------
o. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010-11910 Filed 5-18-10; 8:45 am]