Lock+ Hydro Friends Fund VII; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 27769 [2010-11790]
Download as PDF
Federal Register / Vol. 75, No. 95 / Tuesday, May 18, 2010 / Notices
document. For assistance, contact FERC
Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–11784 Filed 5–17–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13697–000]
Mississippi 16 Hydro, LLC; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
mstockstill on DSKH9S0YB1PROD with NOTICES
May 11, 2010.
On April 5, 2010 Mississippi 16
Hydro, LLC filed an application for a
preliminary permit, pursuant to section
4(f) of the Federal Power Act, proposing
to study the feasibility of the
Mississippi River Lock and Dam #16
Hydroelectric Project, located on the
Mississippi River, in Rock Island
County, Iowa. The sole purpose of a
preliminary permit, if issued, is to grant
the permit holder priority to file a
license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
any land-disturbing activities or
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
The proposed project would consist
of: (1) The powerhouse; (2) installation
of four 5.2 megawatt bulb turbines; (3)
a proposed 1.5-mile-long, 69-kilovolt
transmission line; (4) switchyard; and
(5) appurtenant facilities. The proposed
Mississippi River Lock and Dam #16
Hydroelectric Project would have an
average annual generation of 95.5
gigawatt-hours.
Applicant Contact: Brent L. Smith,
COO, Symbiotics, LLC, P.O. Box 535,
Rigby, Idaho 83442; phone: (208) 745–
0834.
FERC Contact: Bryan Roden-Reynolds
at (202) 502–6618, or via e-mail at
bryan.roden-reynolds@ferc.gov.
The deadline for filing comments,
motions to intervene, competing
applications (without notices of intent),
or notices of intent to file competing
applications is 60 days from the
issuance of this notice. Competing
applications and notices of intent must
meet the requirements of 18 CFR 4.36.
Comments, motions to intervene,
notices of intent, and competing
applications may be filed electronically
via the Internet. See 18 CFR
VerDate Mar<15>2010
17:22 May 17, 2010
Jkt 220001
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site (https://
www.ferc.gov/docs-filing/ferconline.
asp), under the ‘‘eFiling’’ link. For a
simpler method of submitting text only
comments, click on ‘‘Quick Comment.’’
For assistance, please contact FERC
Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and eight copies of the
correspondence to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the
Commission’s ‘‘eLibrary’’ link at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–13697) in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–11786 Filed 5–17–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13711–000]
Lock+ Hydro Friends Fund VII; Notice
of Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
May 11, 2010.
On April 13, 2010 Lock+ Hydro
Friends Fund VII filed an application
for a preliminary permit, pursuant to
section 4(f) of the Federal Power Act,
proposing to study the feasibility of the
Green Wave Project, located on the
Mississippi River, in Pike County,
Missouri. The sole purpose of a
preliminary permit, if issued, is to grant
the permit holder priority to file a
license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
any land-disturbing activities or
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
The proposed project would consist
of: (1) One lock frame module of ten
hydropower turbines, which will be
installed in a single row; (2) a new gate;
PO 00000
Frm 00069
Fmt 4703
Sfmt 9990
27769
(3) a proposed 3.5-mile-long, 69-kilovolt
transmission line; (4) flow control door
assemblies; and (5) appurtenant
facilities. The proposed Domage Project
would have an average annual
generation of 65.745 gigawatt-hours.
Applicant Contact: Wayne F. Krouse,
Chairman & CEO, Hydro Green Energy,
LLC, 5090 Richmond Ave, #390,
Houston, Texas, 77056.
FERC Contact: Bryan Roden-Reynolds
at (202) 502–6618, or via e-mail at
bryan.roden-reynolds@ferc.gov.
The deadline for filing comments,
motions to intervene, competing
applications (without notices of intent),
or notices of intent to file competing
applications is 60 days from the
issuance of this notice. Competing
applications and notices of intent must
meet the requirements of 18 CFR 4.36.
Comments, motions to intervene,
notices of intent, and competing
applications may be filed electronically
via the Internet. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site (https://
www.ferc.gov/docs-filing/ferconline
.asp), under the ‘‘eFiling’’ link. For a
simpler method of submitting text only
comments, click on ‘‘Quick Comment.’’
For assistance, please contact FERC
Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and eight copies of the
correspondence to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the
Commission’s ‘‘eLibrary’’ link at https://
www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P–13711) in
the docket number field to access the
document. For assistance, contact FERC
Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–11790 Filed 5–17–10; 8:45 am]
BILLING CODE 6717–01–P
E:\FR\FM\18MYN1.SGM
18MYN1
Agencies
[Federal Register Volume 75, Number 95 (Tuesday, May 18, 2010)]
[Notices]
[Page 27769]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-11790]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 13711-000]
Lock+ Hydro Friends Fund VII; Notice of Preliminary Permit
Application Accepted for Filing and Soliciting Comments, Motions To
Intervene, and Competing Applications
May 11, 2010.
On April 13, 2010 Lock+ Hydro Friends Fund VII filed an application
for a preliminary permit, pursuant to section 4(f) of the Federal Power
Act, proposing to study the feasibility of the Green Wave Project,
located on the Mississippi River, in Pike County, Missouri. The sole
purpose of a preliminary permit, if issued, is to grant the permit
holder priority to file a license application during the permit term. A
preliminary permit does not authorize the permit holder to perform any
land-disturbing activities or otherwise enter upon lands or waters
owned by others without the owners' express permission.
The proposed project would consist of: (1) One lock frame module of
ten hydropower turbines, which will be installed in a single row; (2) a
new gate; (3) a proposed 3.5-mile-long, 69-kilovolt transmission line;
(4) flow control door assemblies; and (5) appurtenant facilities. The
proposed Domage Project would have an average annual generation of
65.745 gigawatt-hours.
Applicant Contact: Wayne F. Krouse, Chairman & CEO, Hydro Green
Energy, LLC, 5090 Richmond Ave, 390, Houston, Texas, 77056.
FERC Contact: Bryan Roden-Reynolds at (202) 502-6618, or via e-mail
at bryan.roden-reynolds@ferc.gov.
The deadline for filing comments, motions to intervene, competing
applications (without notices of intent), or notices of intent to file
competing applications is 60 days from the issuance of this notice.
Competing applications and notices of intent must meet the requirements
of 18 CFR 4.36. Comments, motions to intervene, notices of intent, and
competing applications may be filed electronically via the Internet.
See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's
Web site (https://www.ferc.gov/docs-filing/ferconline.asp), under the
``eFiling'' link. For a simpler method of submitting text only
comments, click on ``Quick Comment.'' For assistance, please contact
FERC Online Support at FERCOnlineSupport@ferc.gov; call toll-free at
(866) 208-3676; or, for TTY, contact (202) 502-8659. Although the
Commission strongly encourages electronic filing, documents may also be
paper-filed. To paper-file, mail an original and eight copies of the
correspondence to: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street, NE., Washington, DC 20426.
More information about this project, including a copy of the
application, can be viewed or printed on the Commission's ``eLibrary''
link at https://www.ferc.gov/docs-filing/elibrary.asp. Enter the docket
number (P-13711) in the docket number field to access the document. For
assistance, contact FERC Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010-11790 Filed 5-17-10; 8:45 am]
BILLING CODE 6717-01-P