Questar Pipeline Company; Notice of Intent to Prepare an Environmental Assessment for the Planned Mainline 104 Expansion Project and Request for Comments on Environmental Issues, 24938-24940 [2010-10641]
Download as PDF
24938
Federal Register / Vol. 75, No. 87 / Thursday, May 6, 2010 / Notices
assistance, call toll-free 1–866–208–
3372.
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–10635 Filed 5–5–10; 8:45 am]
[Project No. 12667–029]
BILLING CODE 6717–01–P
City of Hamilton, Ohio American
Municipal Power, Inc.; Notice of
Application for Transfer of License and
Soliciting Comments and Motions To
Intervene
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
mstockstill on DSKH9S0YB1PROD with NOTICES
April 28, 2010.
On February 26, 2010, City of
Hamilton, Ohio (Hamilton) and
American Municipal Power, Inc. (AMP)
filed an application for a partial transfer
of license of the Meldahl Hydroelectric
Project No. 12677. The project would be
located at the U.S. Army Corps of
Engineers’ (Corps) Captain Anthony
Meldahl Lock and Dam on the Ohio
River, near the City of Augusta, Bracken
County, Kentucky.
Applicants seek Commission approval
to transfer the license for the Meldahl
Project from Hamilton to Hamilton and
AMP.
Applicants’ Contacts: City of
Hamilton—Mr. Mark Brandenburger,
City Manager, City of Hamilton, 345
High Street, Hamilton, OH 45011–6071
(513) 785–7000 e-mail:
brandenb@ci.hamilton.oh.us. American
Municipal Power, Inc.—Mr. Mark S.
Gerken, P.E., President and CEO,
American Municipal Power, Inc., 1111
Schrock Road, Suite 100, Columbus, OH
43229, phone (614) 540–0855, e-mail:
mgerken@amppartners.org.
FERC Contact: Patricia W. Gillis, (202)
502–8735.
Deadline for filing comments and
motions to intervene: 30 days from the
issuance of this notice. Comments and
motions to intervene may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii)(2009) and the
instructions on the Commission’s Web
site under the ‘‘e-Filing’’ link. If unable
to be filed electronically, documents
may be paper-filed. To paper-file, an
original and eight copies should be
mailed to: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426. For more information on how to
submit these types of filings please go
to the Commission’s Web site located at
https://www.ferc.gov/filingcomments.asp. More information about
this project can be viewed or printed on
the eLibrary link of Commission’s Web
site at https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–12667–029) in the docket number
field to access the document. For
VerDate Mar<15>2010
16:53 May 05, 2010
Jkt 220001
[Docket No. PF10–7–000]
Questar Pipeline Company; Notice of
Intent to Prepare an Environmental
Assessment for the Planned Mainline
104 Expansion Project and Request for
Comments on Environmental Issues
April 29, 2010.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Mainline 104 Expansion Project,
involving construction and operation of
facilities by Questar Pipeline Company
(Questar) in Uintah County, Utah. This
EA will be used by the Commission in
its decision-making process to
determine whether the project is in the
public convenience and necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
Your input will help the Commission
staff determine what issues need to be
evaluated in the EA. Please note that the
scoping period will close on May 29,
2010.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives are
asked to notify their constituents of this
planned project and encourage them to
comment on their areas of concern.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ is available for viewing on
the FERC Web site (https://
www.ferc.gov). This fact sheet addresses
a number of typically-asked questions,
including the use of eminent domain
and how to participate in the
Commission’s proceedings.
Summary of the Planned Project
Questar plans to construct and
operate about 23.3 miles of 24-inchdiameter pipeline in Uintah County,
Utah. The Mainline 104 Expansion
PO 00000
Frm 00074
Fmt 4703
Sfmt 4703
Project would loop 1 the western end of
Questar’s existing Mainline 40 between
its existing Green River Block Valve and
its Fidlar Compressor Staiton.
According to Questar, its project would
allow existing shippers to amend the
primary receipt-point capacity eastward
to Fidlar.
The Mainline 104 Expansion Project
would consist of the following facilities:
• 23.5 miles of 24-inch-diameter
looping pipeline;
• four mainline block valves;
• two pig launchers/receivers; 2
• six taps; and
• minor modifications at the existing
Fidlar Compressor Station.
The general location of the project
facilities is shown in appendix 1.3
Land Requirements for Construction
Construction of the planned facilities
would disturb about 336 acres of land
for the above ground facilities and the
pipeline. Following construction, about
142 acres would be maintained for
permanent operation of the project’s
facilities; the remaining acreage would
be restored and allowed to revert to
former uses. About 70 percent of the
planned pipeline route parallels existing
pipeline, utility, or road rights-of-way.
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us 4 to
discover and address concerns the
public may have about proposals. This
process is referred to as scoping. The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
notice, the Commission requests public
comments on the scope of the issues to
address in the EA. All comments
received will be considered during the
preparation of the EA.
In the EA, we will discuss impacts
that could occur as a result of the
construction and operation of the
1 A pipeline loop is constructed parallel to an
existing pipeline to increase capacity.
2 A ‘‘pig’’ is a tool that is inserted into and moves
through the pipeline, and is used for cleaning the
pipeline, internal inspections, or other purposes.
3 The appendices referenced in this notice are not
being printed in the Federal Register. Copies of
appendices were sent to all those receiving this
notice in the mail and are available at https://
www.ferc.gov using the link called ‘‘eLibrary’’ or
from the Commission’s Public Reference Room, 888
First Street, NE., Washington, DC 20426, or call
(202) 502–8371. For instructions on connecting to
eLibrary, refer to the last page of this notice.
4 ‘‘We’’, ‘‘us’’, and ‘‘our’’ refer to the environmental
staff of the Commission’s Office of Energy Projects.
E:\FR\FM\06MYN1.SGM
06MYN1
mstockstill on DSKH9S0YB1PROD with NOTICES
Federal Register / Vol. 75, No. 87 / Thursday, May 6, 2010 / Notices
planned project under these general
headings:
• Geology and soils;
• land use;
• water resources, fisheries, and
wetlands;
• cultural resources;
• vegetation and wildlife;
• air quality and noise;
• endangered and threatened species;
and
• public safety.
We will also evaluate possible
alternatives to the planned project or
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
Although no formal application has
been filed, we have already initiated our
NEPA review under the Commission’s
pre-filing process. The purpose of the
pre-filing process is to encourage early
involvement of interested stakeholders
and to identify and resolve issues before
an application is filed with the FERC.
As part of our pre-filing review, we have
begun to contact some federal and state
agencies to discuss their involvement in
the scoping process and the preparation
of the EA.
Our independent analysis of the
issues will be presented in the EA. The
EA will be placed in the public record
and, depending on the comments
received during the scoping process,
may be published and distributed to the
public. A comment period will be
allotted if the EA is published for
review. We will consider all comments
on the EA before we make our
recommendations to the Commission.
To ensure your comments are
considered, please carefully follow the
instructions in the Public Participation
section beginning on page 4.
With this notice, we are asking
agencies with jurisdiction and/or
special expertise with respect to
environmental issues to formally
cooperate with us in the preparation of
the EA. These agencies may choose to
participate once they have evaluated the
proposal relative to their
responsibilities. Agencies that would
like to request cooperating agency status
should follow the instructions for filing
comments provided under the Public
Participation section of this notice.
Currently, the U.S. Department of
Interior’s Bureau of Indian Affairs,
Bureau of Land Management (BLM), and
U.S. Fish and Wildlife Service have
expressed their intention to participate
as cooperating agencies in the
preparation of the EA to satisfy their
NEPA responsibilities related to this
project.
VerDate Mar<15>2010
16:53 May 05, 2010
Jkt 220001
Consultations Under Section 106 of the
National Historic Preservation Act
In accordance with the Advisory
Council on Historic Preservation’s
implementing regulations, we are using
this notice to solicit the views of the
public on the project’s potential effects
on historic properties.5 We will
document our findings on the impacts
on cultural resources and summarize
the status of consultations under section
106 of the National Historic
Preservation Act in our EA.
Currently Identified Environmental
Issues
We have already identified several
issues that we think deserve attention
based on a preliminary review of the
planned facilities and the
environmental information provided by
Questar. This preliminary list of issues
may be changed based on your
comments and our analysis.
• Approach and crossing of the Green
River;
• Crossing the Uintah and Ouray
Reservation; and
• Crossing state and federal lands.
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the project.
Your comments should focus on the
potential environmental effects,
reasonable alternatives, and measures to
avoid or lessen environmental impacts.
The more specific your comments, the
more useful they will be. To ensure that
your comments are timely and properly
recorded, please send your comments so
that they will be received in
Washington, DC on or before May 29,
2010.
For your convenience, there are three
methods you can use to submit your
comments to the Commission. In all
instances, please reference the project
docket number PF10–7–000 with your
submission. The Commission
encourages electronic filing of
comments and has expert eFiling staff
available to assist you at (202) 502–8258
or efiling@ferc.gov.
(1) You may file your comments
electronically by using the Quick
Comment feature, which is located at
https://www.ferc.gov under the link
called ‘‘Documents and Filings’’. A
Quick Comment is an easy method for
5 The Advisory Council on Historic Preservation’s
regulations are at Title 36 of the Code of Federal
Regulations, Part 800. Historic properties are
defined in those regulations as any prehistoric or
historic district, site, building, structure, or object
included in or eligible for inclusion in the National
Register for Historic Places.
PO 00000
Frm 00075
Fmt 4703
Sfmt 4703
24939
interested persons to submit text-only
comments on a project;
(2) You may file your comments
electronically by using the ‘‘eFiling’’
feature that is listed under the
‘‘Documents and Filings’’ link. eFiling
involves preparing your submission in
the same manner as you would if filing
on paper, and then saving the file on
your computer’s hard drive. You will
attach that file to your submission. New
eFiling users must first create an
account by clicking on the links called
‘‘Sign up’’ or ‘‘eRegister’’. You will be
asked to select the type of filing you are
making. A comment on a particular
project is considered a ‘‘Comment on a
Filing’’; or
(3) You may file a paper copy of your
comments at the following address:
Kimberly D. Bose, Secretary, Federal
Energy Regulatory Commission, 888
First Street, NE., Room 1A, Washington,
DC 20426.
Environmental Mailing List
The environmental mailing list
includes federal, state, and local
government representatives and
agencies; elected officials;
environmental and public interest
groups; Native American Tribes; and
local libraries and newspapers. This list
includes all affected landowners (as
defined in the Commission’s
regulations) who are potential right-ofway grantors, whose property may be
used temporarily for project purposes,
or who own homes within certain
distances of aboveground facilities, and
anyone who submits comments on the
project. We will update the
environmental mailing list as the
analysis proceeds to ensure that we
send the information related to this
environmental review to all individuals,
organizations, and government entities
interested in and/or potentially affected
by the planned project.
If the EA is published for distribution,
copies will be sent to the environmental
mailing list for public review and
comment. If you would prefer to receive
a paper copy of the document instead of
the CD version or would like to remove
your name from the mailing list, please
return the attached Information Request
(appendix 2).
Becoming an Intervenor
Once Questar files its application
with the Commission, you may want to
become an ‘‘intervenor’’ which is an
official party to the Commission’s
proceeding. Intervenors play a more
formal role in the process and are able
to file briefs, appear at hearings, and be
heard by the courts if they choose to
appeal the Commission’s final ruling.
E:\FR\FM\06MYN1.SGM
06MYN1
24940
Federal Register / Vol. 75, No. 87 / Thursday, May 6, 2010 / Notices
An intervenor formally participates in
the proceeding by filing a request to
intervene. Instructions for becoming an
intervenor are included in the User’s
Guide under the ‘‘e-filing’’ link on the
Commission’s Web site. Please note that
the Commission will not accept requests
for intervenor status at this time. You
must wait until a formal application for
the project is filed with the
Commission.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at (866) 208–FERC, or on the FERC Web
site (https://www.ferc.gov) using the
eLibrary link. Click on the eLibrary link,
click on ‘‘General Search’’ and enter the
docket number, excluding the last three
digits in the Docket Number field (i.e.,
PF10–7). Be sure you have selected an
appropriate date range. For assistance,
please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free
at (866) 208–3676, or for TTY, contact
(202) 502–8659. The eLibrary link also
provides access to the texts of formal
documents issued by the Commission,
such as orders, notices, and
rulemakings.
In addition, the Commission offers a
free service called eSubscription which
allows you to keep track of all formal
issuances and submittals in specific
dockets. This can reduce the amount of
time you spend researching proceedings
by automatically providing you with
notification of these filings, document
summaries, and direct links to the
documents. Go to https://www.ferc.gov/
esubscribenow.htm.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at https://www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–10641 Filed 5–5–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Kimberly D. Bose,
Secretary.
[Docket No. PR10–16–000]
mstockstill on DSKH9S0YB1PROD with NOTICES
the interruptible transportation services
provided under section 311(a)(2) of the
Natural Gas Policy Act of 1978 (NGPA).
Any person desiring to participate in
this rate proceeding must file a motion
to intervene or to protest this filing must
file in accordance with Rules 211 and
214 of the Commission’s Rules of
Practice and Procedure (18 CFR 385.211
and 385.214). Protests will be
considered by the Commission in
determining the appropriate action to be
taken, but will not serve to make
protestants parties to the proceeding.
Any person wishing to become a party
must file a notice of intervention or
motion to intervene, as appropriate.
Such notices, motions, or protests must
be filed on or before the date as
indicated below. Anyone filing an
intervention or protest must serve a
copy of that document on the Applicant.
Anyone filing an intervention or protest
on or before the intervention or protest
date need not serve motions to intervene
or protests on persons other than the
Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible online at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern time
on Friday, May 7, 2010.
[FR Doc. 2010–10642 Filed 5–5–10; 8:45 am]
BILLING CODE 6717–01–P
Acacia Natural Gas Corporation;
Notice of Baseline Filing
April 29, 2010.
16:53 May 05, 2010
Jkt 220001
PO 00000
Federal Energy Regulatory
Commission
[Docket No. EL05–15–010]
Entergy Services, Inc.; Notice of Filing
April 29, 2010.
Take notice that on April 28, 2010,
Entergy Services, Inc. filed a compliance
refund report, pursuant to the Federal
Energy Regulatory Commission’s, Order
Conditionally Accepting Refund Report
and Ordering Further Funds, issued on
January 8, 2010, Arkansas Electric
Cooperative Corp. v. Entergy Arkansas,
Inc. 130 FERC ¶ 61,020 (2010).
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. Anyone filing a motion
to intervene or protest must serve a copy
of that document on the Applicant and
all the parties in this proceeding.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on May 19, 2010.
Kimberly D. Bose,
Secretary.
Take notice that on April 27, 2010,
Acacia Natural Gas Corporation (Acacia)
submitted its baseline filing of its
Statement of Operating Conditions for
VerDate Mar<15>2010
DEPARTMENT OF ENERGY
[FR Doc. 2010–10637 Filed 5–5–10; 8:45 am]
BILLING CODE 6717–01–P
Frm 00076
Fmt 4703
Sfmt 9990
E:\FR\FM\06MYN1.SGM
06MYN1
Agencies
[Federal Register Volume 75, Number 87 (Thursday, May 6, 2010)]
[Notices]
[Pages 24938-24940]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-10641]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. PF10-7-000]
Questar Pipeline Company; Notice of Intent to Prepare an
Environmental Assessment for the Planned Mainline 104 Expansion Project
and Request for Comments on Environmental Issues
April 29, 2010.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Mainline 104 Expansion
Project, involving construction and operation of facilities by Questar
Pipeline Company (Questar) in Uintah County, Utah. This EA will be used
by the Commission in its decision-making process to determine whether
the project is in the public convenience and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the project. Your input will help the Commission staff
determine what issues need to be evaluated in the EA. Please note that
the scoping period will close on May 29, 2010.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives are asked to notify their constituents of this planned
project and encourage them to comment on their areas of concern.
A fact sheet prepared by the FERC entitled ``An Interstate Natural
Gas Facility On My Land? What Do I Need To Know?'' is available for
viewing on the FERC Web site (https://www.ferc.gov). This fact sheet
addresses a number of typically-asked questions, including the use of
eminent domain and how to participate in the Commission's proceedings.
Summary of the Planned Project
Questar plans to construct and operate about 23.3 miles of 24-inch-
diameter pipeline in Uintah County, Utah. The Mainline 104 Expansion
Project would loop \1\ the western end of Questar's existing Mainline
40 between its existing Green River Block Valve and its Fidlar
Compressor Staiton. According to Questar, its project would allow
existing shippers to amend the primary receipt-point capacity eastward
to Fidlar.
---------------------------------------------------------------------------
\1\ A pipeline loop is constructed parallel to an existing
pipeline to increase capacity.
---------------------------------------------------------------------------
The Mainline 104 Expansion Project would consist of the following
facilities:
23.5 miles of 24-inch-diameter looping pipeline;
four mainline block valves;
two pig launchers/receivers; \2\
---------------------------------------------------------------------------
\2\ A ``pig'' is a tool that is inserted into and moves through
the pipeline, and is used for cleaning the pipeline, internal
inspections, or other purposes.
---------------------------------------------------------------------------
six taps; and
minor modifications at the existing Fidlar Compressor
Station.
The general location of the project facilities is shown in appendix
1.\3\
---------------------------------------------------------------------------
\3\ The appendices referenced in this notice are not being
printed in the Federal Register. Copies of appendices were sent to
all those receiving this notice in the mail and are available at
https://www.ferc.gov using the link called ``eLibrary'' or from the
Commission's Public Reference Room, 888 First Street, NE.,
Washington, DC 20426, or call (202) 502-8371. For instructions on
connecting to eLibrary, refer to the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the planned facilities would disturb about 336
acres of land for the above ground facilities and the pipeline.
Following construction, about 142 acres would be maintained for
permanent operation of the project's facilities; the remaining acreage
would be restored and allowed to revert to former uses. About 70
percent of the planned pipeline route parallels existing pipeline,
utility, or road rights-of-way.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
\4\ to discover and address concerns the public may have about
proposals. This process is referred to as scoping. The main goal of the
scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EA. All comments
received will be considered during the preparation of the EA.
---------------------------------------------------------------------------
\4\ ``We'', ``us'', and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA, we will discuss impacts that could occur as a result of
the construction and operation of the
[[Page 24939]]
planned project under these general headings:
Geology and soils;
land use;
water resources, fisheries, and wetlands;
cultural resources;
vegetation and wildlife;
air quality and noise;
endangered and threatened species; and
public safety.
We will also evaluate possible alternatives to the planned project
or portions of the project, and make recommendations on how to lessen
or avoid impacts on the various resource areas.
Although no formal application has been filed, we have already
initiated our NEPA review under the Commission's pre-filing process.
The purpose of the pre-filing process is to encourage early involvement
of interested stakeholders and to identify and resolve issues before an
application is filed with the FERC. As part of our pre-filing review,
we have begun to contact some federal and state agencies to discuss
their involvement in the scoping process and the preparation of the EA.
Our independent analysis of the issues will be presented in the EA.
The EA will be placed in the public record and, depending on the
comments received during the scoping process, may be published and
distributed to the public. A comment period will be allotted if the EA
is published for review. We will consider all comments on the EA before
we make our recommendations to the Commission. To ensure your comments
are considered, please carefully follow the instructions in the Public
Participation section beginning on page 4.
With this notice, we are asking agencies with jurisdiction and/or
special expertise with respect to environmental issues to formally
cooperate with us in the preparation of the EA. These agencies may
choose to participate once they have evaluated the proposal relative to
their responsibilities. Agencies that would like to request cooperating
agency status should follow the instructions for filing comments
provided under the Public Participation section of this notice.
Currently, the U.S. Department of Interior's Bureau of Indian Affairs,
Bureau of Land Management (BLM), and U.S. Fish and Wildlife Service
have expressed their intention to participate as cooperating agencies
in the preparation of the EA to satisfy their NEPA responsibilities
related to this project.
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations, we are using this notice to solicit the views
of the public on the project's potential effects on historic
properties.\5\ We will document our findings on the impacts on cultural
resources and summarize the status of consultations under section 106
of the National Historic Preservation Act in our EA.
---------------------------------------------------------------------------
\5\ The Advisory Council on Historic Preservation's regulations
are at Title 36 of the Code of Federal Regulations, Part 800.
Historic properties are defined in those regulations as any
prehistoric or historic district, site, building, structure, or
object included in or eligible for inclusion in the National
Register for Historic Places.
---------------------------------------------------------------------------
Currently Identified Environmental Issues
We have already identified several issues that we think deserve
attention based on a preliminary review of the planned facilities and
the environmental information provided by Questar. This preliminary
list of issues may be changed based on your comments and our analysis.
Approach and crossing of the Green River;
Crossing the Uintah and Ouray Reservation; and
Crossing state and federal lands.
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the project. Your comments should focus on
the potential environmental effects, reasonable alternatives, and
measures to avoid or lessen environmental impacts. The more specific
your comments, the more useful they will be. To ensure that your
comments are timely and properly recorded, please send your comments so
that they will be received in Washington, DC on or before May 29, 2010.
For your convenience, there are three methods you can use to submit
your comments to the Commission. In all instances, please reference the
project docket number PF10-7-000 with your submission. The Commission
encourages electronic filing of comments and has expert eFiling staff
available to assist you at (202) 502-8258 or efiling@ferc.gov.
(1) You may file your comments electronically by using the Quick
Comment feature, which is located at https://www.ferc.gov under the link
called ``Documents and Filings''. A Quick Comment is an easy method for
interested persons to submit text-only comments on a project;
(2) You may file your comments electronically by using the
``eFiling'' feature that is listed under the ``Documents and Filings''
link. eFiling involves preparing your submission in the same manner as
you would if filing on paper, and then saving the file on your
computer's hard drive. You will attach that file to your submission.
New eFiling users must first create an account by clicking on the links
called ``Sign up'' or ``eRegister''. You will be asked to select the
type of filing you are making. A comment on a particular project is
considered a ``Comment on a Filing''; or
(3) You may file a paper copy of your comments at the following
address: Kimberly D. Bose, Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE., Room 1A, Washington, DC 20426.
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; and
local libraries and newspapers. This list includes all affected
landowners (as defined in the Commission's regulations) who are
potential right-of-way grantors, whose property may be used temporarily
for project purposes, or who own homes within certain distances of
aboveground facilities, and anyone who submits comments on the project.
We will update the environmental mailing list as the analysis proceeds
to ensure that we send the information related to this environmental
review to all individuals, organizations, and government entities
interested in and/or potentially affected by the planned project.
If the EA is published for distribution, copies will be sent to the
environmental mailing list for public review and comment. If you would
prefer to receive a paper copy of the document instead of the CD
version or would like to remove your name from the mailing list, please
return the attached Information Request (appendix 2).
Becoming an Intervenor
Once Questar files its application with the Commission, you may
want to become an ``intervenor'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
[[Page 24940]]
An intervenor formally participates in the proceeding by filing a
request to intervene. Instructions for becoming an intervenor are
included in the User's Guide under the ``e-filing'' link on the
Commission's Web site. Please note that the Commission will not accept
requests for intervenor status at this time. You must wait until a
formal application for the project is filed with the Commission.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site (https://www.ferc.gov) using the eLibrary link. Click on
the eLibrary link, click on ``General Search'' and enter the docket
number, excluding the last three digits in the Docket Number field
(i.e., PF10-7). Be sure you have selected an appropriate date range.
For assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to https://www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at https://www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010-10641 Filed 5-5-10; 8:45 am]
BILLING CODE 6717-01-P