Download as PDF Federal Register / Vol. 75, No. 87 / Thursday, May 6, 2010 / Notices document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: May 19, 2010. Kimberly D. Bose, Secretary. [FR Doc. 2010–10640 Filed 5–5–10; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 12717–002] Northern Illinois Hydropower, LLC; Notice of Application Accepted for Filing and Soliciting Motions To Intervene and Protests mstockstill on DSKH9S0YB1PROD with NOTICES April 29, 2010. Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection. a. Type of Application: Original Major License. b. Project No.: 12717–002. c. Date filed: May 27, 2009. d. Applicant: Northern Illinois Hydropower, LLC. e. Name of Project: Brandon Road Hydroelectric Project. f. Location: U.S. Army Corps of Engineers Brandon Road Dam on the Des Plaines River, in the City of Joliet, Will County, Illinois. g. Filed Pursuant to: Federal Power Act, 16 U.S.C 791 (a)–825(r). h. Applicant Contact: Damon Zdunich, Northern Illinois Hydropower, LLC, 801 Oakland Avenue, Joliet, IL 60435, (312) 320–1610. i. FERC Contact: Dr. Nicholas Palso, (202) 502–8854 or nicholas.palso@ferc.gov. j. Deadline for filing motions to intervene and protests: 60 days from the issuance date of this notice. All documents may be filed electronically via the Internet. See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s Web site (https://www.ferc.gov/docs-filing/ ferconline.asp) under the ‘‘eFiling’’ link. For a simpler method of submitting text only comments, click on ‘‘Quick Comment.’’ For assistance, please contact FERC Online Support at FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY, contact (202) 502–8659. Although the Commission strongly encourages electronic filing, documents may also be VerDate Mar<15>2010 16:53 May 05, 2010 Jkt 220001 paper-filed. To paper-file, mail an original and eight copies to: Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. The Commission’s Rules of Practice and Procedures require all intervenors filing documents with the Commission to serve a copy of that document on each person on the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. k. This application has been accepted for filing, but is not ready for environmental analysis at this time. l. Project Description: The Brandon Road Hydroelectric Project would utilize the Corps of Engineer’s existing Brandon Road Dam and reservoir and would consist of: (1) A new 90-foot-by 118-foot concrete powerhouse between headgate sections 1 through 4 immediately below the existing dam containing two S-type turbine generator units with a combined installed capacity of 10.2 MW; (2) one 50-foot by 50-foot switchyard adjacent to the west side of the proposed powerhouse; (3) a new one-mile-long, 34.5-kilovolt transmission line; and (4) appurtenant facilities. The project would have an average annual generation of about 59,100 megawatt-hours. m. A copy of the application is available for review at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https://www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support. A copy is also available for inspection and reproduction at the address in item h above. You may also register online at https://www.ferc.gov/docs-filing/ esubscription.asp to be notified via e-mail of new filings and issuances related to this or other pending projects. For assistance, contact FERC Online Support. n. Any qualified applicant desiring to file a competing application must submit to the Commission, on or before the specified intervention deadline date, a competing development application, or a notice of intent to file such an application. Submission of a timely notice of intent allows an interested person to file the competing development application no later than 120 days after the specified intervention deadline date. Applications for PO 00000 Frm 00073 Fmt 4703 Sfmt 9990 24937 preliminary permits will not be accepted in response to this notice. A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit a development application. A notice of intent must be served on the applicant(s) named in this public notice. Anyone may submit a protest or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, 385.211, and 385.214. In determining the appropriate action to take, the Commission will consider all protests filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any protests or motions to intervene must be received on or before the specified deadline date for the particular application. When the application is ready for environmental analysis, the Commission will issue a public notice requesting comments, recommendations, terms and conditions, and prescriptions. All filings must (1) bear in all capital letters the title ‘‘PROTEST’’ or ‘‘MOTION TO INTERVENE,’’ ‘‘NOTICE OF INTENT TO FILE COMPETING APPLICATION,’’ or ‘‘COMPETING APPLICATION;’’ (2) set forth in the heading the name of the applicant and the project number of the application to which the filing responds; (3) furnish the name, address, and telephone number of the person protesting or intervening; and (4) otherwise comply with the requirements of 18 CFR 385.2001 through 385.2005. Agencies may obtain copies of the application directly from the applicant. A copy of any protest or motion to intervene must be served upon each representative of the applicant specified in the particular application. Kimberly D. Bose, Secretary. [FR Doc. 2010–10638 Filed 5–5–10; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\06MYN1.SGM 06MYN1

Agencies

[Federal Register Volume 75, Number 87 (Thursday, May 6, 2010)]
[Notices]
[Page 24937]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-10638]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 12717-002]


Northern Illinois Hydropower, LLC; Notice of Application Accepted 
for Filing and Soliciting Motions To Intervene and Protests

April 29, 2010.
    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Original Major License.
    b. Project No.: 12717-002.
    c. Date filed: May 27, 2009.
    d. Applicant: Northern Illinois Hydropower, LLC.
    e. Name of Project: Brandon Road Hydroelectric Project.
    f. Location: U.S. Army Corps of Engineers Brandon Road Dam on the 
Des Plaines River, in the City of Joliet, Will County, Illinois.
    g. Filed Pursuant to: Federal Power Act, 16 U.S.C 791 (a)-825(r).
    h. Applicant Contact: Damon Zdunich, Northern Illinois Hydropower, 
LLC, 801 Oakland Avenue, Joliet, IL 60435, (312) 320-1610.
    i. FERC Contact: Dr. Nicholas Palso, (202) 502-8854 or 
nicholas.palso@ferc.gov.
    j. Deadline for filing motions to intervene and protests: 60 days 
from the issuance date of this notice.
    All documents may be filed electronically via the Internet. See 18 
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web 
site (https://www.ferc.gov/docs-filing/ferconline.asp) under the 
``eFiling'' link. For a simpler method of submitting text only 
comments, click on ``Quick Comment.'' For assistance, please contact 
FERC Online Support at FERCOnlineSupport@ferc.gov; call toll-free at 
(866) 208-3676; or, for TTY, contact (202) 502-8659. Although the 
Commission strongly encourages electronic filing, documents may also be 
paper-filed. To paper-file, mail an original and eight copies to: 
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888 
First Street, NE., Washington, DC 20426.
    The Commission's Rules of Practice and Procedures require all 
intervenors filing documents with the Commission to serve a copy of 
that document on each person on the official service list for the 
project. Further, if an intervenor files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency.
    k. This application has been accepted for filing, but is not ready 
for environmental analysis at this time.
    l. Project Description: The Brandon Road Hydroelectric Project 
would utilize the Corps of Engineer's existing Brandon Road Dam and 
reservoir and would consist of: (1) A new 90-foot-by 118-foot concrete 
powerhouse between headgate sections 1 through 4 immediately below the 
existing dam containing two S-type turbine generator units with a 
combined installed capacity of 10.2 MW; (2) one 50-foot by 50-foot 
switchyard adjacent to the west side of the proposed powerhouse; (3) a 
new one-mile-long, 34.5-kilovolt transmission line; and (4) appurtenant 
facilities. The project would have an average annual generation of 
about 59,100 megawatt-hours.
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at https://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via e-mail of new filings and 
issuances related to this or other pending projects. For assistance, 
contact FERC Online Support.
    n. Any qualified applicant desiring to file a competing application 
must submit to the Commission, on or before the specified intervention 
deadline date, a competing development application, or a notice of 
intent to file such an application. Submission of a timely notice of 
intent allows an interested person to file the competing development 
application no later than 120 days after the specified intervention 
deadline date. Applications for preliminary permits will not be 
accepted in response to this notice.
    A notice of intent must specify the exact name, business address, 
and telephone number of the prospective applicant, and must include an 
unequivocal statement of intent to submit a development application. A 
notice of intent must be served on the applicant(s) named in this 
public notice.
    Anyone may submit a protest or a motion to intervene in accordance 
with the requirements of Rules of Practice and Procedure, 18 CFR 
385.210, 385.211, and 385.214. In determining the appropriate action to 
take, the Commission will consider all protests filed, but only those 
who file a motion to intervene in accordance with the Commission's 
Rules may become a party to the proceeding. Any protests or motions to 
intervene must be received on or before the specified deadline date for 
the particular application.
    When the application is ready for environmental analysis, the 
Commission will issue a public notice requesting comments, 
recommendations, terms and conditions, and prescriptions.
    All filings must (1) bear in all capital letters the title 
``PROTEST'' or ``MOTION TO INTERVENE,'' ``NOTICE OF INTENT TO FILE 
COMPETING APPLICATION,'' or ``COMPETING APPLICATION;'' (2) set forth in 
the heading the name of the applicant and the project number of the 
application to which the filing responds; (3) furnish the name, 
address, and telephone number of the person protesting or intervening; 
and (4) otherwise comply with the requirements of 18 CFR 385.2001 
through 385.2005. Agencies may obtain copies of the application 
directly from the applicant. A copy of any protest or motion to 
intervene must be served upon each representative of the applicant 
specified in the particular application.

 Kimberly D. Bose,
Secretary.
[FR Doc. 2010-10638 Filed 5-5-10; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.