Combined Notice of Filings, 23756-23757 [2010-10352]
Download as PDF
mstockstill on DSKH9S0YB1PROD with NOTICES
23756
Federal Register / Vol. 75, No. 85 / Tuesday, May 4, 2010 / Notices
CIP–005–2, Cyber Security, Electronic
Security Perimeter(s), Section 4.2.2 and
Requirement R1.3.
Filed Date: 04/21/2010.
Accession Number: 20100421–5078.
Comment Date: 5 p.m. Eastern Time
on Wednesday, May 12, 2010.
Take notice that the Commission
received the following electric
reliability filings:
Docket Numbers: RR10–1–001.
Applicants: North American Electric
Reliability Corporation.
Description: Compliance Filing of the
North American Electric Reliability
Corp in Response to January 21, 2010
Commission Order Concerning
Appendix 4D to the NERC Rules of
Procedure- Procedure for Requesting
and Receiving Technical Feasibility
Exceptions.
Filed Date: 04/21/2010.
Accession Number: 20100421–5166.
Comment Date: 5 p.m. Eastern Time
on Wednesday, May 12, 2010.
Any person desiring to intervene or to
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s Rules of
Practice and Procedure (18 CFR 385.211
and 385.214) on or before 5 p.m. Eastern
time on the specified comment date. It
is not necessary to separately intervene
again in a subdocket related to a
compliance filing if you have previously
intervened in the same docket. Protests
will be considered by the Commission
in determining the appropriate action to
be taken, but will not serve to make
protestants parties to the proceeding.
Anyone filing a motion to intervene or
protest must serve a copy of that
document on the Applicant. In reference
to filings initiating a new proceeding,
interventions or protests submitted on
or before the comment deadline need
not be served on persons other than the
Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 14 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First St. NE., Washington, DC
20426.
The filings in the above proceedings
are accessible in the Commission’s
VerDate Mar<15>2010
18:58 May 03, 2010
Jkt 220001
eLibrary system by clicking on the
appropriate link in the above list. They
are also available for review in the
Commission’s Public Reference Room in
Washington, DC. There is an
eSubscription link on the Web site that
enables subscribers to receive e-mail
notification when a document is added
to a subscribed dockets(s). For
assistance with any FERC Online
service, please e-mail
FERCOnlineSupport@ferc.gov. or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2010–10353 Filed 5–3–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Combined Notice of Filings
April 26, 2010.
Take notice that the Commission has
received the following Natural Gas
Pipeline Rate and Refund Report filings:
Docket Numbers: RP10–623–000.
Applicants: Texas Eastern
Transmission, L.P.
Description: Texas Eastern
Transmission, LP submits First Revised
Eighth Revised Sheet No 529 et al. to
FERC Gas Tariff, Seventh Revised
Volume No 1, to be effective 11/16/09.
Filed Date: 04/21/2010.
Accession Number: 20100426–0201.
Comment Date: 5 p.m. Eastern Time
on Monday, May 3, 2010.
Docket Numbers: RP10–627–000.
Applicants: Saltville Gas Storage
Company L.L.C.
Description: Saltville Gas Storage
Company, LLC submits First Revised
Sheet 1 et al. to FERC Gas Tariff,
Original Volume 1, to be effective 5/24/
10.
Filed Date: 04/22/2010.
Accession Number: 20100423–0204.
Comment Date: 5 p.m. Eastern Time
on Tuesday, May 4, 2010.
Docket Numbers: RP10–628–000.
Applicants: Egan Hub Storage, LLC.
Description: Egan Hub Storage, LLC
submits Third Revised Sheet 2 et al. to
FERC Gas Tariff, First Revised Volume
1, to be effective 5/24/10.
Filed Date: 04/22/2010.
Accession Number: 20100423–0203.
Comment Date: 5 p.m. Eastern Time
on Tuesday, May 4, 2010.
Docket Numbers: RP10–629–000.
Applicants: Gulf South Pipeline
Company, LP.
PO 00000
Frm 00093
Fmt 4703
Sfmt 4703
Description: Gulf South Pipeline
Company, LP submits a capacity release
agreement containing negotiated rate
provisions with Texla Energy
Management, Inc.
Filed Date: 04/22/2010.
Accession Number: 20100423–0201.
Comment Date: 5 p.m. Eastern Time
on Tuesday, May 4, 2010.
Docket Numbers: RP10–630–000.
Applicants: Gulf Stream Natural Gas
System, LLC.
Description: Gulfstream Natural Gas
System, LLC submits Second Revised
Sheet 121 et al. FERC Gas tariff, Original
Volume 1, to be effective 5/24/2010.
Filed Date: 04/23/2010.
Accession Number: 20100423–0216.
Comment Date: 5 p.m. Eastern Time
on Wednesday, May 5, 2010.
Docket Numbers: RP10–631–000.
Applicants: Horizon Pipeline
Company, L.L.C.
Description: Horizon Pipeline
Company, LLC submits a report of the
refund of penalty revenues.
Filed Date: 04/23/2010.
Accession Number: 20100423–0217.
Comment Date: 5 p.m. Eastern Time
on Wednesday, May 5, 2010.
Docket Numbers: RP10–632–000.
Applicants: Gulf South Pipeline
Company, LP.
Description: Gulf South Pipeline
Company, LP submits a capacity release
agreement containing negotiated rate
provisions.
Filed Date: 04/23/2010.
Accession Number: 20100423–0218.
Comment Date: 5 p.m. Eastern Time
on Wednesday, May 5, 2010.
Docket Numbers: RP10–633–000.
Applicants: Gulf Crossing Pipeline
Company LLC.
Description: Gulf Crossing Pipeline
Company submits First Revised Sheet 1
of its FERC Gas Tariff, Original Volume
1, to be effective 6/1/10.
Filed Date: 04/23/2010.
Accession Number: 20100423–0219.
Comment Date: 5 p.m. Eastern Time
on Wednesday, May 5, 2010.
Any person desiring to intervene or to
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s Rules of
Practice and Procedure (18 CFR 385.211
and 385.214) on or before 5 p.m. Eastern
time on the specified comment date. It
is not necessary to separately intervene
again in a subdocket related to a
compliance filing if you have previously
intervened in the same docket. Protests
will be considered by the Commission
in determining the appropriate action to
be taken, but will not serve to make
protestants parties to the proceeding.
Anyone filing a motion to intervene or
E:\FR\FM\04MYN1.SGM
04MYN1
Federal Register / Vol. 75, No. 85 / Tuesday, May 4, 2010 / Notices
Federal Energy Regulatory
Commission
Project involving construction and
operation of facilities by Eastern Shore
Natural Gas Company (ESNG) in
Lancaster and Chester Counties,
Pennsylvania. This EA will be used by
the Commission in its decision-making
process to determine whether the
project is in the public convenience and
necessity.
This notice announces the opening of
the scoping process the Commission
will use to gather input from the public
and interested agencies on the project.
Your input will help the Commission
staff determine what issues need to be
evaluated in the EA. Please note that the
scoping period will close on May 28,
2010.
This notice is being sent to the
Commission’s current environmental
mailing list for this project. State and
local government representatives are
asked to notify their constituents of this
planned project and encourage them to
comment on their areas of concern.
If you are a landowner receiving this
notice, you may be contacted by a
pipeline company representative about
the acquisition of an easement to
construct, operate, and maintain the
proposed facilities. The company would
seek to negotiate a mutually acceptable
agreement. However, if the project is
approved by the Commission, that
approval conveys with it the right of
eminent domain. Therefore, if easement
negotiations fail to produce an
agreement, the pipeline company could
initiate condemnation proceedings in
accordance with State law.
A fact sheet prepared by the FERC
entitled ‘‘An Interstate Natural Gas
Facility On My Land? What Do I Need
To Know?’’ was attached to the project
notice ESNG provided to landowners.
This fact sheet addresses a number of
typically-asked questions, including the
use of eminent domain and how to
participate in the Commission’s
proceedings. It is also available for
viewing on the FERC Web site (https://
www.ferc.gov).
[Docket No. CP10–76–000]
Summary of the Proposed Project
Eastern Shore Natural Gas Company;
Notice of Intent To Prepare an
Environmental Assessment for the
Proposed Mainline Extension
Interconnect Project and Request for
Comments on Environmental Issues
ESNG proposes to construct and
operate approximately 8.3 miles of 16inch-diameter natural gas pipeline and
other associated facilities in Lancaster
and Chester Counties, Pennsylvania.
The Mainline Extension Interconnect
Project would provide its shippers the
opportunity to receive natural gas
supplies, with a capacity of 40,000
dekatherms per day, from the
Appalachian region and other areas
through an interconnection with Texas
Eastern Transmission, LP’s pipeline
system.
protest must serve a copy of that
document on the Applicant. In reference
to filings initiating a new proceeding,
interventions or protests submitted on
or before the comment deadline need
not be served on persons other than the
Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper, using the
FERC Online links at https://
www.ferc.gov. To facilitate electronic
service, persons with Internet access
who will eFile a document and/or be
listed as a contact for an intervenor
must create and validate an
eRegistration account using the
eRegistration link. Select the eFiling
link to log on and submit the
intervention or protests.
Persons unable to file electronically
should submit an original and 14 copies
of the intervention or protest to the
Federal Energy Regulatory Commission,
888 First St., NE., Washington, DC
20426.
The filings in the above proceedings
are accessible in the Commission’s
eLibrary system by clicking on the
appropriate link in the above list. They
are also available for review in the
Commission’s Public Reference Room in
Washington, DC. There is an
eSubscription link on the Web site that
enables subscribers to receive e-mail
notification when a document is added
to a subscribed dockets(s). For
assistance with any FERC Online
service, please e-mail
FERCOnlineSupport@ferc.gov. or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2010–10352 Filed 5–3–10; 8:45 am]
BILLING CODE 6717–01–P
mstockstill on DSKH9S0YB1PROD with NOTICES
DEPARTMENT OF ENERGY
April 27, 2010.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Mainline Extension Interconnect
VerDate Mar<15>2010
18:58 May 03, 2010
Jkt 220001
PO 00000
Frm 00094
Fmt 4703
Sfmt 4703
23757
The Mainline Extension Interconnect
Project would consist of the following
facilities:
• 8.3 miles of 16-inch-diameter
natural gas pipeline;
• One meter station/pig 1 launcher at
the interconnect with Texas Eastern
Transmission, LP, near Honey Brook,
Pennsylvania;
• One mainline valve; and
• One interconnect/pig receiver at the
existing ESNG meter station near
Parkesburg, Pennsylvania.
The general location of the project
facilities is shown in Appendix 1.2
Land Requirements for Construction
Construction of the proposed facilities
would disturb about 76.4 acres of land
for the aboveground facilities and the
pipeline. Following construction, about
51.1 acres would be maintained for
permanent operation of the project’s
facilities; the remaining acreage would
be restored and allowed to revert to
former uses.
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us 3 to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping’’. The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
notice, the Commission requests public
comments on the scope of the issues to
address in the EA. All comments
received will be considered during the
preparation of the EA.
In the EA we will discuss impacts that
could occur as a result of the
construction and operation of the
proposed project under these general
headings:
• Geology and soils;
• Land use;
• Water resources, fisheries, and
wetlands;
• Cultural resources;
1 A ‘‘pig’’ is a tool that is inserted into and moves
through the pipeline, and is used for cleaning the
pipeline, internal inspections, or other purposes.
2 The appendices referenced in this notice are not
being printed in the Federal Register. Copies of
appendices were sent to all those receiving this
notice in the mail and are available at https://
www.ferc.gov using the link called ‘‘eLibrary’’ or
from the Commission’s Public Reference Room, 888
First Street, NE., Washington, DC 20426, or call
(202) 502–8371. For instructions on connecting to
eLibrary, refer to the last page of this notice.
3 ‘‘We’’, ‘‘us’’, and ‘‘our’’ refer to the environmental
staff of the Commission’s Office of Energy Projects.
E:\FR\FM\04MYN1.SGM
04MYN1
Agencies
[Federal Register Volume 75, Number 85 (Tuesday, May 4, 2010)]
[Notices]
[Pages 23756-23757]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-10352]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Combined Notice of Filings
April 26, 2010.
Take notice that the Commission has received the following Natural
Gas Pipeline Rate and Refund Report filings:
Docket Numbers: RP10-623-000.
Applicants: Texas Eastern Transmission, L.P.
Description: Texas Eastern Transmission, LP submits First Revised
Eighth Revised Sheet No 529 et al. to FERC Gas Tariff, Seventh Revised
Volume No 1, to be effective 11/16/09.
Filed Date: 04/21/2010.
Accession Number: 20100426-0201.
Comment Date: 5 p.m. Eastern Time on Monday, May 3, 2010.
Docket Numbers: RP10-627-000.
Applicants: Saltville Gas Storage Company L.L.C.
Description: Saltville Gas Storage Company, LLC submits First
Revised Sheet 1 et al. to FERC Gas Tariff, Original Volume 1, to be
effective 5/24/10.
Filed Date: 04/22/2010.
Accession Number: 20100423-0204.
Comment Date: 5 p.m. Eastern Time on Tuesday, May 4, 2010.
Docket Numbers: RP10-628-000.
Applicants: Egan Hub Storage, LLC.
Description: Egan Hub Storage, LLC submits Third Revised Sheet 2 et
al. to FERC Gas Tariff, First Revised Volume 1, to be effective 5/24/
10.
Filed Date: 04/22/2010.
Accession Number: 20100423-0203.
Comment Date: 5 p.m. Eastern Time on Tuesday, May 4, 2010.
Docket Numbers: RP10-629-000.
Applicants: Gulf South Pipeline Company, LP.
Description: Gulf South Pipeline Company, LP submits a capacity
release agreement containing negotiated rate provisions with Texla
Energy Management, Inc.
Filed Date: 04/22/2010.
Accession Number: 20100423-0201.
Comment Date: 5 p.m. Eastern Time on Tuesday, May 4, 2010.
Docket Numbers: RP10-630-000.
Applicants: Gulf Stream Natural Gas System, LLC.
Description: Gulfstream Natural Gas System, LLC submits Second
Revised Sheet 121 et al. FERC Gas tariff, Original Volume 1, to be
effective 5/24/2010.
Filed Date: 04/23/2010.
Accession Number: 20100423-0216.
Comment Date: 5 p.m. Eastern Time on Wednesday, May 5, 2010.
Docket Numbers: RP10-631-000.
Applicants: Horizon Pipeline Company, L.L.C.
Description: Horizon Pipeline Company, LLC submits a report of the
refund of penalty revenues.
Filed Date: 04/23/2010.
Accession Number: 20100423-0217.
Comment Date: 5 p.m. Eastern Time on Wednesday, May 5, 2010.
Docket Numbers: RP10-632-000.
Applicants: Gulf South Pipeline Company, LP.
Description: Gulf South Pipeline Company, LP submits a capacity
release agreement containing negotiated rate provisions.
Filed Date: 04/23/2010.
Accession Number: 20100423-0218.
Comment Date: 5 p.m. Eastern Time on Wednesday, May 5, 2010.
Docket Numbers: RP10-633-000.
Applicants: Gulf Crossing Pipeline Company LLC.
Description: Gulf Crossing Pipeline Company submits First Revised
Sheet 1 of its FERC Gas Tariff, Original Volume 1, to be effective 6/1/
10.
Filed Date: 04/23/2010.
Accession Number: 20100423-0219.
Comment Date: 5 p.m. Eastern Time on Wednesday, May 5, 2010.
Any person desiring to intervene or to protest in any of the above
proceedings must file in accordance with Rules 211 and 214 of the
Commission's Rules of Practice and Procedure (18 CFR 385.211 and
385.214) on or before 5 p.m. Eastern time on the specified comment
date. It is not necessary to separately intervene again in a subdocket
related to a compliance filing if you have previously intervened in the
same docket. Protests will be considered by the Commission in
determining the appropriate action to be taken, but will not serve to
make protestants parties to the proceeding. Anyone filing a motion to
intervene or
[[Page 23757]]
protest must serve a copy of that document on the Applicant. In
reference to filings initiating a new proceeding, interventions or
protests submitted on or before the comment deadline need not be served
on persons other than the Applicant.
The Commission encourages electronic submission of protests and
interventions in lieu of paper, using the FERC Online links at https://www.ferc.gov. To facilitate electronic service, persons with Internet
access who will eFile a document and/or be listed as a contact for an
intervenor must create and validate an eRegistration account using the
eRegistration link. Select the eFiling link to log on and submit the
intervention or protests.
Persons unable to file electronically should submit an original and
14 copies of the intervention or protest to the Federal Energy
Regulatory Commission, 888 First St., NE., Washington, DC 20426.
The filings in the above proceedings are accessible in the
Commission's eLibrary system by clicking on the appropriate link in the
above list. They are also available for review in the Commission's
Public Reference Room in Washington, DC. There is an eSubscription link
on the Web site that enables subscribers to receive e-mail notification
when a document is added to a subscribed dockets(s). For assistance
with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov.
or call (866) 208-3676 (toll free). For TTY, call (202) 502-8659.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2010-10352 Filed 5-3-10; 8:45 am]