Hayden Power Station permit does not
comply with 40 CFR part 70 in that: (I)
the title V permit fails to require
compliance with particulate matter
limits; and (II) the title V permit fails to
ensure compliance with Prevention of
Significant Deterioration (PSD)
requirements in regard to carbon
dioxide emissions.
On March 24, 2010, the Administrator
issued an order partially granting and
partially denying the petition. The order
explains the reasons behind EPA’s
conclusions.
Dated: April 7, 2010.
Carol L. Campbell,
Acting Regional Administrator, Region 8.
[FR Doc. 2010–8773 Filed 4–15–10; 8:45 am]
BILLING CODE 6560–50–P
ENVIRONMENTAL PROTECTION
AGENCY
[ER–FRL–8989–8]
Environmental Impacts Statements;
Notice of Availability
WReier-Aviles on DSKGBLS3C1PROD with NOTICES
Responsible Agency: Office of Federal
Activities, General Information (202)
564–1399 or https://www.epa.gov/
compliance/nepa/.
Weekly receipt of Environmental
Impact Statements Filed 04/05/2010
Through 04/09/2010 Pursuant to 40 CFR
1506.9.
Notice
In accordance with Section 309(a) of
the Clean Air Act, EPA is required to
make its comments on EISs issued by
other Federal agencies public.
Historically, EPA has met this mandate
by publishing weekly notices of
availability of EPA comments, which
includes a brief summary of EPA’s
comment letters, in the Federal
Register. Since February 2008, EPA has
been including its comment letters on
EISs on its Web site at: https://
www.epa.gov/compliance/nepa/
eisdata.html. Including the entire EIS
comment letters on the Web site
satisfies the Section 309(a) requirement
to make EPA’s comments on EISs
available to the public. Accordingly,
after March 31, 2010, EPA will
discontinue the publication of this
notice of availability of EPA comments
in the Federal Register.
EIS No. 20100121, Draft EIS, DOI, CA,
Stanford University Habitat
Conservation Plan, Authorization for
Incidental Take and Implementation,
San Mateo and Santa Clara Counties,
CA, Comment Period Ends: 07/15/
2010, Contact: Gary Stern, 707–575–
6060.
VerDate Nov<24>2008
15:07 Apr 15, 2010
Jkt 220001
EIS No. 20100122, Final EIS, USFS, 00,
Black Hills National Forest Travel
Management Plan, Proposes to
Designate Certain Roads and Trails
Open to Motorized Travel, Custer,
Fall River, Lawrence, Meade,
Pennington Counties, SD and Crook
and Weston Counties, WY, Wait
Period Ends: 05/17/2010, Contact:
Thomas Willems, 605–673–9217.
EIS No. 20100123, Final EIS, FHWA,
TX, US 290 Corridor, Propose to
Construct Roadway Improvements
from Farm-to-Market (FM) 2920 to
Interstate Highway (IH) 610, Funding
and Right-of-Way Grant, Harris
County, TX, Wait Period Ends: 05/17/
2010, Contact: Daniel Mott, 512–536–
5964.
EIS No. 20100124, Final EIS, NPS, CA,
Prisoners Harbor Coastal Wetland
Restoration Project, Proposes to
Restore a Functional, Self-Sustaining
Ecosystem at a Coastal Wetland Site,
Channel Islands National Park, Santa
Cruz Island, Santa Barbara County,
CA, Wait Period Ends: 05/17/2010,
Contact: Paula Power, 805–658–5784.
EIS No. 20100125, Final EIS, BLM, 00,
UNEV Pipeline Project, Construction
of a 399-mile Long Main Petroleum
Products Pipeline, Salt Lake, Tooele,
Juab, Millard, Iron, and Washington
Counties, UT and Lincoln and Clark
Counties, NV, Wait Period Ends: 05/
17/2010, Contact: Joe Incardine, 801–
524–3833.
EIS No. 20100126, Draft EIS, DOS, 00,
Keystone XL Oil Pipeline Project,
Presidential Permit for the Proposed
Construction, Connection, Operation,
and Maintenance of a Pipeline and
Associated Facilities at United State
border for Importation of Crude Oil
from Canada, Comment Period Ends:
06/01/2010, Contact: Elizabeth
Orlando, 202–647–4284.
EIS No. 20100127, Final EIS, BIA, MT,
Kerr Hydroelectric Project, Proposed
Drought Management Plan,
Implementation, Flathead Lake, MT,
Wait Period Ends: 05/17/2010,
Contact: Bob Dach, 503–231–6711.
EIS No. 20100128, Final EIS, USFS, SD,
Norbeck Wildlife Project, Proposing to
Manage Vegetation to Benefit Game
Animals and Birds, Black Hills
National Forest, Custer and
Pennington Counties, SD, Wait Period
Ends: 05/17/2010, Contact: Kelly
Honors, 605–673–4853.
EIS No. 20100129, Draft EIS, BLM, NV,
Silver State Solar Energy Project,
Construct and Operate a 400megawatt Photovoltaic Solar Plant
and Associated Facilities on Public
Lands, Application Right-of-Way
PO 00000
Frm 00034
Fmt 4703
Sfmt 4703
19969
Grant, Primm, Clark County, NV,
Comment Period Ends: 06/01/2010,
Contact: Gregory Helseth, 702–515–
5173.
EIS No. 20100130, Final EIS, DOT, CA,
Silicon Valley Rapid Transit Corridor
Project, Proposes to Construct an
Extension of the Bay Area Rapid
Transit (BART) Rail System from
Warm Spring Station in Fremont to
Santa Clara County, CA, Wait Period
Ends: 05/17/2010, Contact: Eric
Eidlin, 415–744–2502.
EIS No. 20100131, Final EIS, EPA, GU,
Apra Harbor, Guam, Proposed Site
Designation of an Ocean Dredged
Material Disposal Site Offshore of
Guam, Wait Period Ends: 05/17/2010,
Contact: Allan Ota, 415–972–3476.
EIS No. 20100132, Draft Supplement,
BLM, CA, Ivanpah Solar Electric
Generating System (07–AFC–5)
Project, Proposal to Construct a 400Megawatts Concentrated Solar Power
Tower, Thermal-Electric Power Plant,
San Bernardino County, CA,
Comment Period Ends: 06/01/2010,
Contact: Tom Hurshman, 970–240–
5345.
Dated: April 13, 2010.
Robert W. Hargrove,
Director, NEPA Compliance Division, Office
of Federal Activities.
[FR Doc. 2010–8762 Filed 4–15–10; 8:45 am]
BILLING CODE 6560–50–P
ENVIRONMENTAL PROTECTION
AGENCY
[FRL–9138–2]
Science Advisory Board Staff Office;
Notification of a Public Meeting of the
Advisory Council on Clean Air
Compliance Analysis (Council)
AGENCY: Environmental Protection
Agency (EPA).
ACTION: Notice.
SUMMARY: The EPA Science Advisory
Board (SAB) Staff Office announces a
public meeting of the Advisory Council
on Clean Air Compliance Analysis
(Council). The Council will conduct
quality reviews of three subcommittee
reports and review draft chapters of the
EPA Office of Air and Radiation’s
Second Section 812 Prospective
Analysis of the benefits and costs of the
Clean Air Act.
DATES: The meeting will be held on
Tuesday, May 4, 2010 and Wednesday,
May 5, 2010, beginning at 8:30 a.m. and
ending no later than 5 p.m. (Eastern
Time), each day.
ADDRESSES: The public meeting will be
held in the Science Advisory Board
E:\FR\FM\16APN1.SGM
16APN1
Agencies
[Federal Register Volume 75, Number 73 (Friday, April 16, 2010)]
[Notices]
[Page 19969]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-8762]
-----------------------------------------------------------------------
ENVIRONMENTAL PROTECTION AGENCY
[ER-FRL-8989-8]
Environmental Impacts Statements; Notice of Availability
Responsible Agency: Office of Federal Activities, General
Information (202) 564-1399 or https://www.epa.gov/compliance/nepa/.
Weekly receipt of Environmental Impact Statements Filed 04/05/2010
Through 04/09/2010 Pursuant to 40 CFR 1506.9.
Notice
In accordance with Section 309(a) of the Clean Air Act, EPA is
required to make its comments on EISs issued by other Federal agencies
public. Historically, EPA has met this mandate by publishing weekly
notices of availability of EPA comments, which includes a brief summary
of EPA's comment letters, in the Federal Register. Since February 2008,
EPA has been including its comment letters on EISs on its Web site at:
https://www.epa.gov/compliance/nepa/eisdata.html. Including the entire
EIS comment letters on the Web site satisfies the Section 309(a)
requirement to make EPA's comments on EISs available to the public.
Accordingly, after March 31, 2010, EPA will discontinue the publication
of this notice of availability of EPA comments in the Federal Register.
EIS No. 20100121, Draft EIS, DOI, CA, Stanford University Habitat
Conservation Plan, Authorization for Incidental Take and
Implementation, San Mateo and Santa Clara Counties, CA, Comment Period
Ends: 07/15/2010, Contact: Gary Stern, 707-575-6060.
EIS No. 20100122, Final EIS, USFS, 00, Black Hills National Forest
Travel Management Plan, Proposes to Designate Certain Roads and Trails
Open to Motorized Travel, Custer, Fall River, Lawrence, Meade,
Pennington Counties, SD and Crook and Weston Counties, WY, Wait Period
Ends: 05/17/2010, Contact: Thomas Willems, 605-673-9217.
EIS No. 20100123, Final EIS, FHWA, TX, US 290 Corridor, Propose to
Construct Roadway Improvements from Farm-to-Market (FM) 2920 to
Interstate Highway (IH) 610, Funding and Right-of-Way Grant, Harris
County, TX, Wait Period Ends: 05/17/2010, Contact: Daniel Mott, 512-
536-5964.
EIS No. 20100124, Final EIS, NPS, CA, Prisoners Harbor Coastal Wetland
Restoration Project, Proposes to Restore a Functional, Self-Sustaining
Ecosystem at a Coastal Wetland Site, Channel Islands National Park,
Santa Cruz Island, Santa Barbara County, CA, Wait Period Ends: 05/17/
2010, Contact: Paula Power, 805-658-5784.
EIS No. 20100125, Final EIS, BLM, 00, UNEV Pipeline Project,
Construction of a 399-mile Long Main Petroleum Products Pipeline, Salt
Lake, Tooele, Juab, Millard, Iron, and Washington Counties, UT and
Lincoln and Clark Counties, NV, Wait Period Ends: 05/17/2010, Contact:
Joe Incardine, 801-524-3833.
EIS No. 20100126, Draft EIS, DOS, 00, Keystone XL Oil Pipeline Project,
Presidential Permit for the Proposed Construction, Connection,
Operation, and Maintenance of a Pipeline and Associated Facilities at
United State border for Importation of Crude Oil from Canada, Comment
Period Ends: 06/01/2010, Contact: Elizabeth Orlando, 202-647-4284.
EIS No. 20100127, Final EIS, BIA, MT, Kerr Hydroelectric Project,
Proposed Drought Management Plan, Implementation, Flathead Lake, MT,
Wait Period Ends: 05/17/2010, Contact: Bob Dach, 503-231-6711.
EIS No. 20100128, Final EIS, USFS, SD, Norbeck Wildlife Project,
Proposing to Manage Vegetation to Benefit Game Animals and Birds, Black
Hills National Forest, Custer and Pennington Counties, SD, Wait Period
Ends: 05/17/2010, Contact: Kelly Honors, 605-673-4853.
EIS No. 20100129, Draft EIS, BLM, NV, Silver State Solar Energy
Project, Construct and Operate a 400-megawatt Photovoltaic Solar Plant
and Associated Facilities on Public Lands, Application Right-of-Way
Grant, Primm, Clark County, NV, Comment Period Ends: 06/01/2010,
Contact: Gregory Helseth, 702-515-5173.
EIS No. 20100130, Final EIS, DOT, CA, Silicon Valley Rapid Transit
Corridor Project, Proposes to Construct an Extension of the Bay Area
Rapid Transit (BART) Rail System from Warm Spring Station in Fremont to
Santa Clara County, CA, Wait Period Ends: 05/17/2010, Contact: Eric
Eidlin, 415-744-2502.
EIS No. 20100131, Final EIS, EPA, GU, Apra Harbor, Guam, Proposed Site
Designation of an Ocean Dredged Material Disposal Site Offshore of
Guam, Wait Period Ends: 05/17/2010, Contact: Allan Ota, 415-972-3476.
EIS No. 20100132, Draft Supplement, BLM, CA, Ivanpah Solar Electric
Generating System (07-AFC-5) Project, Proposal to Construct a 400-
Megawatts Concentrated Solar Power Tower, Thermal-Electric Power Plant,
San Bernardino County, CA, Comment Period Ends: 06/01/2010, Contact:
Tom Hurshman, 970-240-5345.
Dated: April 13, 2010.
Robert W. Hargrove,
Director, NEPA Compliance Division, Office of Federal Activities.
[FR Doc. 2010-8762 Filed 4-15-10; 8:45 am]