Intent To Prepare a Draft Environmental Impact Statement for Hurricane and Storm Damage Reduction for South Ponte Vedra Beach, Vilano Beach, and Summer Haven Beach Reaches, St. Johns County, FL, 17132-17133 [2010-7598]
Download as PDF
17132
Federal Register / Vol. 75, No. 64 / Monday, April 5, 2010 / Notices
by the IPHC between the commercial
and charter vessel fisheries. If approved
by the Secretary of Commerce, this new
allocation program would not be
effective before 2012.
Authority: 16 U.S.C. 773 et seq.
Dated: March 30, 2010.
Emily H. Menashes,
Acting Director, Office of Sustainable
Fisheries, National Marine Fisheries Service.
[FR Doc. 2010–7626 Filed 4–2–10; 8:45 am]
BILLING CODE 3510–22–S
DEPARTMENT OF COMMERCE
Economic Development Administration
Notice of Petitions by Firms for
Determination of Eligibility To Apply
for Trade Adjustment Assistance
AGENCY: Economic Development
Administration, Department of
Commerce.
ACTION: Notice and opportunity for
public comment.
Pursuant to Section 251 of the Trade
Act of 1974 (19 U.S.C. 2341 et seq.), the
Economic Development Administration
(EDA) has received petitions for
certification of eligibility to apply for
Trade Adjustment Assistance from the
firms listed below. EDA has initiated
separate investigations to determine
whether increased imports into the
United States of articles like or directly
competitive with those produced by
each firm contributed importantly to the
total or partial separation of the firm’s
workers, or threat thereof, and to a
decrease in sales or production of each
petitioning firm.
LIST OF PETITIONS RECEIVED BY EDA FOR CERTIFICATION OF ELIGIBILITY TO APPLY FOR TRADE ADJUSTMENT
[3/23/2010 through 3/30/2010]
Date accepted
for filing
Firm
Address
Mansfield Plumbing Products, LLC
150 E. 1st St., Perrysville, OH
44864.
1551 East Broadway, Princeton,
NJ 47670.
610
S
Jefferson
Avenue,
Cookeville, TN 38501.
1606 Sanders Ave, NE., Fort
Payne, AL 35967.
300 Old Baptist Road, North Kingston, RI 02852.
Hurst Manufacturing .......................
Adams USA, Inc .............................
Bailey Knit Corporation ..................
Development Associates, Inc .........
3/23/2010
Sinks and lavatories made of porcelain or china.
3/24/2010
Electric Motors, Brushless DC, AC Induction, Stepper and Synchronous.
The firm produces sporting goods equipment; primary materials include plastic and fabric.
The firm produces socks; primary materials include
cotton and synthetic fibers.
Development Associates manufactures polyurethane Resin, clear polyurethane resin—auto
grade, non-yellowing, uv stable, mercury free,
urethane Adhesive, epoxy primer, wire and cable
coating.
Hawaiian Sun produces tropical fruit juices, preserves, chocolate covered food products, macadamia nuts, and a variety of other food products.
Pierce Aluminum specializes in aluminum products
for use in the marine, transportation, defense, Architectural, and general manufacturing. They also
provide finished aluminum products for first line
production capabilities for the same industries.
Machined parts for the aircraft industry.
3/25/2010
3/25/2010
3/25/2010
259 Sand Island Access, Honolulu, HI 96819.
3/25/2010
Pierce Aluminum Company, Inc .....
34 Forge
02038.
MA
3/25/2010
Alpha Machining & Manufacturing,
Inc.
jlentini on DSKJ8SOYB1PROD with NOTICES
Hawaiian Sun Products, Inc ...........
1604 N. 161st East
Tulsa, OK 74116.
Avenue,
3/29/2010
Any party having a substantial
interest in these proceedings may
request a public hearing on the matter.
A written request for a hearing must
be submitted to the Trade Adjustment
Assistance for Firms Division, Room
7106, Economic Development
Administration, U.S. Department of
Commerce, Washington, DC 20230, no
later than ten (10) calendar days
following publication of this notice.
Please follow the procedures set forth
in section 315.9 of EDA’s final rule (71
FR 56704) for procedures for requesting
a public hearing. The Catalog of Federal
Domestic Assistance official program
number and title of the program under
which these petitions are submitted is
11.313, Trade Adjustment Assistance.
VerDate Nov<24>2008
16:35 Apr 02, 2010
Jkt 220001
Park,
Franklin,
Products
Dated: March 30, 2010.
Bryan Borlik,
Program Director.
[FR Doc. 2010–7587 Filed 4–2–10; 8:45 am]
BILLING CODE 3510–24–P
DEPARTMENT OF DEFENSE
Department of the Army; Corps of
Engineers
Intent To Prepare a Draft
Environmental Impact Statement for
Hurricane and Storm Damage
Reduction for South Ponte Vedra
Beach, Vilano Beach, and Summer
Haven Beach Reaches, St. Johns
County, FL
Department of the Army, U.S.
Army Corps of Engineers, DoD.
ACTION: Notice of intent.
AGENCY:
PO 00000
Frm 00013
Fmt 4703
Sfmt 4703
SUMMARY: The U.S. Army Corps of
Engineers, Jacksonville District, intends
to prepare a Draft Environmental Impact
Statement (DEIS) for evaluation of the
feasibility of providing hurricane and
storm damage reduction (HSDR), and
related purposes to the shores of St.
Johns County, Florida. In cooperation
with St. Johns County, the study will
evaluate alternatives that will maximize
HSDR while minimizing environmental
impacts within three reaches designated
critically eroded by Florida Department
of Environmental Protection (FDEP): (1)
South Ponte Vedra Beach (R84–R110/5
miles), (2) Vilano Beach (R110–R122/2.5
miles) and (3) Summer Haven Beach
(R197–R209/2.3 miles).
ADDRESSES: U.S. Army Corps of
Engineers, Planning Division,
Environmental Branch, P.O. Box 4970,
Jacksonville, FL 32232–0019.
E:\FR\FM\05APN1.SGM
05APN1
jlentini on DSKJ8SOYB1PROD with NOTICES
Federal Register / Vol. 75, No. 64 / Monday, April 5, 2010 / Notices
FOR FURTHER INFORMATION CONTACT: Mr.
Paul M. DeMarco, by e-mail
Paul.M.DeMarco@usace.army.mil or by
telephone at 904–232–1897.
SUPPLEMENTARY INFORMATION:
a. Proposed Action. The Rivers and
Harbors Act of 1962 gave the Secretary
of the Army broad authorization to
survey coastal areas of the United States
and its possessions in the interest of
beach erosion control, hurricane
protection and related purposes,
provided that surveys of particular areas
would be authorized by appropriate
resolutions (Pub. L. 87–874, Section
110). As a result, portions of the St.
Johns County shoreline experiencing
severe erosion were studied extensively.
The St. Johns County, Florida General
Reevaluation Report (GRR) (USACE
1998), recommended beach
nourishment along St. Augustine Beach.
Initial fill was completed in January
2003.
Authority for the proposed study is
House Resolution 2646 adopted June 21,
2000. A Reconnaissance Report
completed in March 2004, by the Corps,
concluded based on preliminary
findings, there was a federal interest in
pursuing HSDR for the Vilano Beach
and Summer Haven Beach reaches.
Subsequent to the completion of that
report, South Ponte Vedra Beach
experienced severe erosion, was
designated as a critically eroded beach
by FDEP, and therefore added to the
scope of the Federal study.
b. Alternatives. Project’s alternatives
include no action and various levels of
protection along approximately 9.8
miles of coastal shoreline along three
reaches designated as critically eroded
areas. In addition to various levels of
beach nourishment and periodic
renourishment, the Corps will consider
other management measures such as
nearshore placement of sand,
breakwaters, submerged artificial reef,
groins, revetments, seawalls, dunes/
vegetation, change to the Coastal
Construction Control Line, relocation of
structures, moratorium on construction,
establish a no-growth program,
relocation of structures, flood proofing
of structures, and condemnation of
structures with land acquisition.
c. Scoping Process. The scoping
process as outlined by the Council on
Environmental Quality has been and
will continue to be utilized to involve
Federal, State, and local agencies,
affected Indian tribes, and other
interested persons and organizations.
Scoping letters were sent to the
appropriate parties requesting their
comments and concerns on August 17,
2005, for the Summer Haven and Vilano
VerDate Nov<24>2008
16:35 Apr 02, 2010
Jkt 220001
Beach reaches of the study area. After
that time, FDEP designated the South
Ponte Vedra Reach as critically eroding.
A second scoping letter was sent out on
September 16, 2008, to include the
South Ponte Vedra Reach in the study
area. Initial comments and concerns
have been received. Any additional
persons and organizations wishing to
participate in the scoping process
should contact the U.S. Army Corps of
Engineers at the above address.
Significant issues to be analyzed in
the DEIS would include effects on
Federally listed threatened and
endangered species, and Essential Fish
Habitat. Other issues would be health
and safety, water quality, aesthetics and
recreation, fish and wildlife resources,
cultural resources, and socio-economic
resources. Issues identified through
scoping and public involvement thus far
include loss of land and property due to
erosion, lack of protection from
hurricanes, loss of recreational beach,
concern over impacts to sea turtles and
shore birds from renourishment,
concern over impacts to benthic
organisms from mining and fill, concern
over protecting surfing spots and the
revenue they generate, concern over
wasting Federal tax dollars, too much
time since the first studies without
positive results, and concern that
revetments and seawalls harm sea turtle
nesting.
Any proposed action would be
coordinated with the U.S. Fish and
Wildlife Service and the National
Marine Fisheries Service (NMFS)
pursuant to Section 7 of the Endangered
Species Act, and with the State Historic
Preservation Officer. The NMFS Habitat
Conservation Division (HCD) has
accepted cooperating agency status on
the study.
Any proposed action would also
involve evaluation for compliance with
guidelines pursuant to section 404(b) of
the Clean Water Act; application (to the
State of Florida) for Water Quality
Certification pursuant to section 401 of
the Clean Water Act; certification of
state lands, easements, and rights of
way; and determination of Coastal Zone
Management Act consistency. The FDEP
Bureau of Beaches and Coastal Systems
(BBCS) has also accepted cooperating
agency status on the study.
The U.S. Army Corps of Engineers
and the non-Federal sponsor, St. Johns
County, would provide extensive
information and assistance on the
resources to be impacted and
alternatives.
d. Scoping Meetings. Public scoping
meetings could be held. Exact dates,
times, and locations would be published
in local papers.
PO 00000
Frm 00014
Fmt 4703
Sfmt 4703
17133
e. Agency Role. As the cooperating
agency, NMFS HCD and FDEP BBCS
will provide information and assistance
on the resources to be impacted,
mitigation measures and alternatives.
Other agencies having either regulatory
authority or special expertise may also
be invited to become a cooperating
agency in preparation of the EIS.
Specifically, as a Federal agency with
jurisdiction to manage resources
available on the Outer Continental Shelf
(OCS), the U.S. Minerals Management
Service would be invited should
potential borrow areas be identified
within Federal waters (outside the 3mile State statutory limit).
f. Draft Environmental Impact
Statement Availability. The study
schedule is dependent upon
Congressional funding and the current
estimate is for the Draft Environmental
Impact Statement to be available on or
after 2012.
Dated: March 25, 2010.
Eric P. Summa,
Chief, Environmental Branch.
[FR Doc. 2010–7598 Filed 4–2–10; 8:45 am]
BILLING CODE 3720–58–P
DEPARTMENT OF DEFENSE
Department of the Army
Draft Environmental Impact Statement
(DEIS) for Training Range and Garrison
Support Facilities Construction and
Operation at Fort Stewart, GA
Department of the Army, DoD.
Notice of Availability (NOA).
AGENCY:
ACTION:
SUMMARY: The Department of the Army
has prepared a DEIS to analyze the
environmental and socioeconomic
impacts resulting from the proposed
construction of 12 range projects and 2
garrison support facilities at Fort
Stewart, Georgia. Completion of these
projects will better allow the Army to
support Soldier training requirements
and will support Fort Stewart’s existing
and future units. Construction of these
projects will help to ensure Fort Stewart
can meet unit training requirements if
and when the pace of operational
deployments slows.
DATES: The public comment period will
end 45 days after the publication of an
NOA in the Federal Register by the U.S.
Environmental Protection Agency.
ADDRESSES: For further information
regarding the EIS, please contact Mr.
Charles Walden, Project Manager,
Directorate of Public Works, Prevention
and Compliance Branch, Environmental
Division, 1550 Frank Cochran Drive,
Building 1137–A, Fort Stewart, Georgia
E:\FR\FM\05APN1.SGM
05APN1
Agencies
[Federal Register Volume 75, Number 64 (Monday, April 5, 2010)]
[Notices]
[Pages 17132-17133]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-7598]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF DEFENSE
Department of the Army; Corps of Engineers
Intent To Prepare a Draft Environmental Impact Statement for
Hurricane and Storm Damage Reduction for South Ponte Vedra Beach,
Vilano Beach, and Summer Haven Beach Reaches, St. Johns County, FL
AGENCY: Department of the Army, U.S. Army Corps of Engineers, DoD.
ACTION: Notice of intent.
-----------------------------------------------------------------------
SUMMARY: The U.S. Army Corps of Engineers, Jacksonville District,
intends to prepare a Draft Environmental Impact Statement (DEIS) for
evaluation of the feasibility of providing hurricane and storm damage
reduction (HSDR), and related purposes to the shores of St. Johns
County, Florida. In cooperation with St. Johns County, the study will
evaluate alternatives that will maximize HSDR while minimizing
environmental impacts within three reaches designated critically eroded
by Florida Department of Environmental Protection (FDEP): (1) South
Ponte Vedra Beach (R84-R110/5 miles), (2) Vilano Beach (R110-R122/2.5
miles) and (3) Summer Haven Beach (R197-R209/2.3 miles).
ADDRESSES: U.S. Army Corps of Engineers, Planning Division,
Environmental Branch, P.O. Box 4970, Jacksonville, FL 32232-0019.
[[Page 17133]]
FOR FURTHER INFORMATION CONTACT: Mr. Paul M. DeMarco, by e-mail
Paul.M.DeMarco@usace.army.mil or by telephone at 904-232-1897.
SUPPLEMENTARY INFORMATION:
a. Proposed Action. The Rivers and Harbors Act of 1962 gave the
Secretary of the Army broad authorization to survey coastal areas of
the United States and its possessions in the interest of beach erosion
control, hurricane protection and related purposes, provided that
surveys of particular areas would be authorized by appropriate
resolutions (Pub. L. 87-874, Section 110). As a result, portions of the
St. Johns County shoreline experiencing severe erosion were studied
extensively. The St. Johns County, Florida General Reevaluation Report
(GRR) (USACE 1998), recommended beach nourishment along St. Augustine
Beach. Initial fill was completed in January 2003.
Authority for the proposed study is House Resolution 2646 adopted
June 21, 2000. A Reconnaissance Report completed in March 2004, by the
Corps, concluded based on preliminary findings, there was a federal
interest in pursuing HSDR for the Vilano Beach and Summer Haven Beach
reaches. Subsequent to the completion of that report, South Ponte Vedra
Beach experienced severe erosion, was designated as a critically eroded
beach by FDEP, and therefore added to the scope of the Federal study.
b. Alternatives. Project's alternatives include no action and
various levels of protection along approximately 9.8 miles of coastal
shoreline along three reaches designated as critically eroded areas. In
addition to various levels of beach nourishment and periodic
renourishment, the Corps will consider other management measures such
as nearshore placement of sand, breakwaters, submerged artificial reef,
groins, revetments, seawalls, dunes/vegetation, change to the Coastal
Construction Control Line, relocation of structures, moratorium on
construction, establish a no-growth program, relocation of structures,
flood proofing of structures, and condemnation of structures with land
acquisition.
c. Scoping Process. The scoping process as outlined by the Council
on Environmental Quality has been and will continue to be utilized to
involve Federal, State, and local agencies, affected Indian tribes, and
other interested persons and organizations. Scoping letters were sent
to the appropriate parties requesting their comments and concerns on
August 17, 2005, for the Summer Haven and Vilano Beach reaches of the
study area. After that time, FDEP designated the South Ponte Vedra
Reach as critically eroding. A second scoping letter was sent out on
September 16, 2008, to include the South Ponte Vedra Reach in the study
area. Initial comments and concerns have been received. Any additional
persons and organizations wishing to participate in the scoping process
should contact the U.S. Army Corps of Engineers at the above address.
Significant issues to be analyzed in the DEIS would include effects
on Federally listed threatened and endangered species, and Essential
Fish Habitat. Other issues would be health and safety, water quality,
aesthetics and recreation, fish and wildlife resources, cultural
resources, and socio-economic resources. Issues identified through
scoping and public involvement thus far include loss of land and
property due to erosion, lack of protection from hurricanes, loss of
recreational beach, concern over impacts to sea turtles and shore birds
from renourishment, concern over impacts to benthic organisms from
mining and fill, concern over protecting surfing spots and the revenue
they generate, concern over wasting Federal tax dollars, too much time
since the first studies without positive results, and concern that
revetments and seawalls harm sea turtle nesting.
Any proposed action would be coordinated with the U.S. Fish and
Wildlife Service and the National Marine Fisheries Service (NMFS)
pursuant to Section 7 of the Endangered Species Act, and with the State
Historic Preservation Officer. The NMFS Habitat Conservation Division
(HCD) has accepted cooperating agency status on the study.
Any proposed action would also involve evaluation for compliance
with guidelines pursuant to section 404(b) of the Clean Water Act;
application (to the State of Florida) for Water Quality Certification
pursuant to section 401 of the Clean Water Act; certification of state
lands, easements, and rights of way; and determination of Coastal Zone
Management Act consistency. The FDEP Bureau of Beaches and Coastal
Systems (BBCS) has also accepted cooperating agency status on the
study.
The U.S. Army Corps of Engineers and the non-Federal sponsor, St.
Johns County, would provide extensive information and assistance on the
resources to be impacted and alternatives.
d. Scoping Meetings. Public scoping meetings could be held. Exact
dates, times, and locations would be published in local papers.
e. Agency Role. As the cooperating agency, NMFS HCD and FDEP BBCS
will provide information and assistance on the resources to be
impacted, mitigation measures and alternatives. Other agencies having
either regulatory authority or special expertise may also be invited to
become a cooperating agency in preparation of the EIS. Specifically, as
a Federal agency with jurisdiction to manage resources available on the
Outer Continental Shelf (OCS), the U.S. Minerals Management Service
would be invited should potential borrow areas be identified within
Federal waters (outside the 3-mile State statutory limit).
f. Draft Environmental Impact Statement Availability. The study
schedule is dependent upon Congressional funding and the current
estimate is for the Draft Environmental Impact Statement to be
available on or after 2012.
Dated: March 25, 2010.
Eric P. Summa,
Chief, Environmental Branch.
[FR Doc. 2010-7598 Filed 4-2-10; 8:45 am]
BILLING CODE 3720-58-P