FirstEnergy Nuclear Operating Company, Perry Nuclear Power Plant; Exemption, 16524-16525 [2010-7375]
Download as PDF
16524
Federal Register / Vol. 75, No. 62 / Thursday, April 1, 2010 / Notices
mstockstill on DSKH9S0YB1PROD with NOTICES
licensee has provided adequate
justification for its request for an
extension of the compliance date with
regard to the one specified requirement
of 10 CFR 73.55 to February 3, 2011.
Accordingly, the Commission has
determined that pursuant to10 CFR
73.5, ‘‘Specific exemptions,’’ an
exemption from the March 31, 2010,
compliance date is authorized by law
and will not endanger life or property or
the common defense and security, and
is otherwise in the public interest.
The NRC staff has determined that the
long-term benefits that will be realized
when the DBNPS equipment installation
is complete, justifies extending the full
compliance date with regard to the
specified requirement of 10 CFR 73.55.
The security measures DBNPS needs
additional time to implement are new
requirements imposed by March 27,
2009, amendments to 10 CFR 73.55, and
are in addition to those required by the
security orders issued in response to the
events of September 11, 2001.
Therefore, the NRC concluded that the
licensee’s actions are in the best interest
of protecting the public health and
safety through the security changes that
will result from granting this exemption.
As per the licensee’s request and the
NRC’s regulatory authority to grant an
exemption from the March 31, 2010,
deadline for the one item specified in
the enclosure of FENOC letter dated
November 30, 2009, the licensee is
required to be in full compliance by
February 3, 2011. In achieving
compliance, the licensee is reminded
that it is responsible for determining the
appropriate licensing mechanism (i.e.,
10 CFR 50.54(p) or 10 CFR 50.90) for
incorporation of all necessary changes
to its security plans.
Pursuant to 10 CFR 51.32, ‘‘Finding of
no significant impact,’’ the Commission
has previously determined that the
granting of this exemption will not have
a significant effect on the quality of the
human environment (75 FR 14635).
This exemption is effective upon
issuance.
Dated at Rockville, Maryland, this 26th day
of March 2010.
For the Nuclear Regulatory Commission.
Joseph G. Giitter,
Director, Division of Operating Reactor
Licensing, Office of Nuclear Reactor
Regulation.
[FR Doc. 2010–7378 Filed 3–31–10; 8:45 am]
BILLING CODE 7590–01–P
VerDate Nov<24>2008
16:51 Mar 31, 2010
Jkt 220001
NUCLEAR REGULATORY
COMMISSION
[Docket No. 50–440; NRC–2010–0124]
FirstEnergy Nuclear Operating
Company, Perry Nuclear Power Plant;
Exemption
1.0
Background
FirstEnergy Nuclear Operating
Company (FENOC, the licensee) is the
holder of Facility Operating License No.
NFP–58, which authorizes operation of
the Perry Nuclear Power Plant, Unit 1
(PNPP). The license provides, among
other things, that the facility is subject
to all rules, regulations, and orders of
the U.S. Nuclear Regulatory
Commission (NRC, the Commission)
now or hereafter in effect.
The facility consists of one boilingwater reactor located in Lake County,
Ohio.
2.0
Request/Action
Title 10 of the Code of Federal
Regulations (10 CFR) part 73, ‘‘Physical
protection of plants and materials,’’
section 73.55, ‘‘Requirements for
physical protection of licensed activities
in nuclear power reactors against
radiological sabotage,’’ published March
27, 2009, effective May 26, 2009, with
a full implementation date of March 31,
2010, requires licensees to protect, with
high assurance, against radiological
sabotage by designing and
implementing comprehensive site
security programs. The amendments to
10 CFR 73.55 published on March 27,
2009, establish and update generically
applicable security requirements similar
to those previously imposed by
Commission orders issued after the
terrorist attacks of September 11, 2001,
and implemented by licensees. In
addition, the amendments to 10 CFR
73.55 includes additional requirements
to further enhance site security based
upon insights gained from
implementation of the post-September
11, 2001, security orders. It is from one
of these new requirements that PNPP
now seeks an exemption from the March
31, 2010, implementation date. All other
physical security requirements
established by this recent rulemaking
have already been or will be
implemented by the licensee by March
31, 2010.
By letter dated November 30, 2009, as
supplemented by letter dated December
23, 2009, the licensee requested an
exemption in accordance with 10 CFR
73.5, ‘‘Specific exemptions.’’ The
licensee’s November 30, 2009, letter
contains proprietary and safeguards
information and, accordingly, is not
PO 00000
Frm 00103
Fmt 4703
Sfmt 4703
available to the public. The licensee has
requested an exemption from the March
31, 2010, compliance date stating that it
must complete a significant
modification to the current site security
configuration before all requirements
can be met. Specifically, the request is
for one specific requirement from the
current March 31, 2010, deadline, to
November 25, 2010. Being granted this
exemption for the one item would allow
the licensee to complete the
modification and incorporate state-ofthe-art technology to meet or exceed
regulatory requirements.
3.0 Discussion of Part 73 Schedule
Exemptions From the March 31, 2010,
Full Implementation Date
Pursuant to 10 CFR 73.55(a)(1), ‘‘By
March 31, 2010, each nuclear power
reactor licensee, licensed under 10 CFR
Part 50, shall implement the
requirements of this section through its
Commission-approved Physical Security
Plan, Training and Qualification Plan,
Safeguards Contingency Plan, and Cyber
Security Plan referred to collectively
hereafter as ‘security plans.’ ’’ Pursuant
to 10 CFR 73.5, the Commission may,
upon application by any interested
person or upon its own initiative, grant
exemptions from the requirements of 10
CFR part 73 when the exemptions are
authorized by law, and will not
endanger life or property or the common
defense and security, and are otherwise
in the public interest.
The approval of this exemption, as
noted above, would allow an extension
from March 31, 2010, until November
25, 2010, for one specified area of the
new rule. As stated above, 10 CFR 73.5
allows the NRC to grant exemptions
from the requirements of 10 CFR part
73. The NRC staff has determined that
granting of the licensee’s proposed
exemption would not result in a
violation of the Atomic Energy Act of
1954, as amended, or the Commission’s
regulations. Therefore, the exemption is
authorized by law.
In the draft final rule Power Reactor
Security provided to the Commission,
the NRC staff proposed that the
requirements of the new regulation be
met within 180 days. The Commission
directed a change from 180 days to
approximately 1 year for licensees to
fully implement the new requirements.
This change was incorporated into the
final rule. From this, it is clear that the
Commission wanted to provide a
reasonable timeframe for licensees to
achieve full compliance.
As noted in the final rule, the
Commission also anticipated that
licensees would have to conduct sitespecific analyses to determine what
E:\FR\FM\01APN1.SGM
01APN1
Federal Register / Vol. 75, No. 62 / Thursday, April 1, 2010 / Notices
changes were necessary to implement
the rule’s requirements, and that
changes could be accomplished through
a variety of licensing mechanisms,
including exemptions. Since issuance of
the final rule, the Commission has
rejected a generic industry request to
extend the rule’s compliance date for all
operating nuclear power plants, but
noted that the Commission’s regulations
provide mechanisms for individual
licensees, with good cause, to apply for
relief from the compliance date
(Reference: June 4, 2009, letter from R.
W. Borchardt, NRC, to M. S. Fertel,
Nuclear Energy Institute). The licensee’s
request for an exemption is therefore
consistent with the approach set forth
by the Commission and discussed in the
June 4, 2009, letter.
mstockstill on DSKH9S0YB1PROD with NOTICES
Perry Nuclear Power Plant Schedule
Exemption Request
The licensee provided detailed
information in the enclosure of its
November 30, 2009, letter, requesting an
exemption. Enclosure 1 contains
proprietary information regarding the
site security plan, details of specific
portions of the regulation for which the
site cannot be in compliance by the
March 31, 2010, deadline and why, the
required changes to the site’s security
configuration, and a timeline with
critical path activities that would enable
the licensee to achieve full compliance
by November 25, 2010. The timeline
provides dates indicating when (1)
Construction will begin on various
phases of the project, (2) outages are
scheduled for the unit, and (3) critical
equipment will be ordered, installed,
tested and become operational.
Notwithstanding the schedule
exemption for this specific requirement,
the licensee will continue to be in
compliance with all other applicable
physical security requirements as
described in 10 CFR 73.55 and reflected
in its current NRC-approved physical
security program. By November 25,
2010, PNPP will be in full compliance
with all the regulatory requirements of
10 CFR 73.55, as issued on March 27,
2009.
4.0 Conclusion for Part 73 Schedule
Exemption Request
The staff has reviewed the licensee’s
submittals and concludes that the
licensee has provided adequate
justification for its request for an
extension of the compliance date with
regard to the one specified requirement
of 10 CFR 73.55 to November 25, 2010.
Accordingly, the Commission has
determined that pursuant to 10 CFR
73.5, ‘‘Specific exemptions,’’ an
exemption from the March 31, 2010,
VerDate Nov<24>2008
16:51 Mar 31, 2010
Jkt 220001
compliance date is authorized by law
and will not endanger life or property or
the common defense and security, and
is otherwise in the public interest.
The NRC staff has determined that the
long-term benefits that will be realized
when the PNPP equipment installation
is complete, justifies extending the full
compliance date with regard to the
specified requirement of 10 CFR 73.55.
The security measures PNPP needs
additional time to implement are new
requirements imposed by March 27,
2009, amendments to 10 CFR 73.55, and
are in addition to those required by the
security orders issued in response to the
events of September 11, 2001.
Therefore, the NRC concluded that the
licensee’s actions are in the best interest
of protecting the public health and
safety through the security changes that
will result from granting this exemption.
As per the licensee’s request and the
NRC’s regulatory authority to grant an
exemption from the March 31, 2010,
deadline for the one item specified in
the enclosure of FENOC letter dated
November 30, 2009, the licensee is
required to be in full compliance by
November 25, 2010. In achieving
compliance, the licensee is reminded
that it is responsible for determining the
appropriate licensing mechanism (i.e.,
10 CFR 50.54(p) or 10 CFR 50.90) for
incorporation of all necessary changes
to its security plans.
Pursuant to 10 CFR 51.32, ‘‘Finding of
no significant impact,’’ the Commission
has previously determined that the
granting of this exemption will not have
a significant effect on the quality of the
human environment (75 FR 14638).
This exemption is effective upon
issuance.
Dated at Rockville, Maryland, this 26th day
of March 2010.
For the Nuclear Regulatory Commission.
Joseph G. Giitter,
Director, Division of Operating Reactor
Licensing, Office of Nuclear Reactor
Regulation.
[FR Doc. 2010–7375 Filed 3–31–10; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[NRC–2009–0413]
Notice of Issuance of Regulatory Guide
AGENCY: Nuclear Regulatory
Commission.
ACTION: Notice of Issuance and
Availability of Regulatory Guide 1.11,
Revision 1, ‘‘Instrument Lines
Penetrating the Primary Reactor
Containment.’’
PO 00000
Frm 00104
Fmt 4703
Sfmt 4703
16525
FOR FURTHER INFORMATION CONTACT:
Mekonen M. Bayssie, Regulatory Guide
Development Branch, Division of
Engineering, Office of Nuclear
Regulatory Research, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555–0001, telephone (301) 251–
7489 or e-mail
Mekonen.Bayssie@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Introduction
The U.S. Nuclear Regulatory
Commission (NRC) is issuing a revision
to an existing guide in the agency’s
‘‘Regulatory Guide’’ series. This series
was developed to describe and make
available to the public information such
as methods that are acceptable to the
NRC staff for implementing specific
parts of the agency’s regulations,
techniques that the staff uses in
evaluating specific problems or
postulated accidents, and data that the
staff needs in its review of applications
for permits and licenses.
Revision 1 of Regulatory Guide 1.11,
Instrument Lines Penetrating the
Primary Reactor Containment,’’ was
issued with a temporary identification
as Draft Regulatory Guide, DG–1225.
This guide defines a basis that the staff
of the NRC considers acceptable to
implement the intent of General Design
Criterion 55 and 56 with regard to
instrument lines. This guide applies to
light-water-cooled reactors with a
primary containment.
II. Further Information
In September 2009, DG–1225 was
published with a public comment
period of 60 days from the issuance of
the guide. A Summary of the Public
Comment Resolution is available
through the NRC’s Agencywide
Documents Access and Management
System (ADAMS) Accession No.
ML100250972. Electronic copies of
Regulatory Guide 1.11, Revision 1 are
available through the NRC’s public Web
site under ‘‘Regulatory Guides’’ at
https://www.nrc.gov/reading-rm/doccollections/.
In addition, regulatory guides are
available for inspection at the NRC’s
Public Document Room (PDR) located at
Room O–1F21, One White Flint North,
11555 Rockville Pike, Rockville,
Maryland 20852–2738. The PDR’s
mailing address is USNRC PDR,
Washington, DC 20555–0001. The PDR
can also be reached by telephone at
(301) 415–4737 or (800) 397–4209, by
fax at (301) 415–3548, and by e-mail to
pdr@nrc.gov.
Regulatory guides are not
copyrighted, and NRC approval is not
required to reproduce them.
E:\FR\FM\01APN1.SGM
01APN1
Agencies
[Federal Register Volume 75, Number 62 (Thursday, April 1, 2010)]
[Notices]
[Pages 16524-16525]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-7375]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-440; NRC-2010-0124]
FirstEnergy Nuclear Operating Company, Perry Nuclear Power Plant;
Exemption
1.0 Background
FirstEnergy Nuclear Operating Company (FENOC, the licensee) is the
holder of Facility Operating License No. NFP-58, which authorizes
operation of the Perry Nuclear Power Plant, Unit 1 (PNPP). The license
provides, among other things, that the facility is subject to all
rules, regulations, and orders of the U.S. Nuclear Regulatory
Commission (NRC, the Commission) now or hereafter in effect.
The facility consists of one boiling-water reactor located in Lake
County, Ohio.
2.0 Request/Action
Title 10 of the Code of Federal Regulations (10 CFR) part 73,
``Physical protection of plants and materials,'' section 73.55,
``Requirements for physical protection of licensed activities in
nuclear power reactors against radiological sabotage,'' published March
27, 2009, effective May 26, 2009, with a full implementation date of
March 31, 2010, requires licensees to protect, with high assurance,
against radiological sabotage by designing and implementing
comprehensive site security programs. The amendments to 10 CFR 73.55
published on March 27, 2009, establish and update generically
applicable security requirements similar to those previously imposed by
Commission orders issued after the terrorist attacks of September 11,
2001, and implemented by licensees. In addition, the amendments to 10
CFR 73.55 includes additional requirements to further enhance site
security based upon insights gained from implementation of the post-
September 11, 2001, security orders. It is from one of these new
requirements that PNPP now seeks an exemption from the March 31, 2010,
implementation date. All other physical security requirements
established by this recent rulemaking have already been or will be
implemented by the licensee by March 31, 2010.
By letter dated November 30, 2009, as supplemented by letter dated
December 23, 2009, the licensee requested an exemption in accordance
with 10 CFR 73.5, ``Specific exemptions.'' The licensee's November 30,
2009, letter contains proprietary and safeguards information and,
accordingly, is not available to the public. The licensee has requested
an exemption from the March 31, 2010, compliance date stating that it
must complete a significant modification to the current site security
configuration before all requirements can be met. Specifically, the
request is for one specific requirement from the current March 31,
2010, deadline, to November 25, 2010. Being granted this exemption for
the one item would allow the licensee to complete the modification and
incorporate state-of-the-art technology to meet or exceed regulatory
requirements.
3.0 Discussion of Part 73 Schedule Exemptions From the March 31, 2010,
Full Implementation Date
Pursuant to 10 CFR 73.55(a)(1), ``By March 31, 2010, each nuclear
power reactor licensee, licensed under 10 CFR Part 50, shall implement
the requirements of this section through its Commission-approved
Physical Security Plan, Training and Qualification Plan, Safeguards
Contingency Plan, and Cyber Security Plan referred to collectively
hereafter as `security plans.' '' Pursuant to 10 CFR 73.5, the
Commission may, upon application by any interested person or upon its
own initiative, grant exemptions from the requirements of 10 CFR part
73 when the exemptions are authorized by law, and will not endanger
life or property or the common defense and security, and are otherwise
in the public interest.
The approval of this exemption, as noted above, would allow an
extension from March 31, 2010, until November 25, 2010, for one
specified area of the new rule. As stated above, 10 CFR 73.5 allows the
NRC to grant exemptions from the requirements of 10 CFR part 73. The
NRC staff has determined that granting of the licensee's proposed
exemption would not result in a violation of the Atomic Energy Act of
1954, as amended, or the Commission's regulations. Therefore, the
exemption is authorized by law.
In the draft final rule Power Reactor Security provided to the
Commission, the NRC staff proposed that the requirements of the new
regulation be met within 180 days. The Commission directed a change
from 180 days to approximately 1 year for licensees to fully implement
the new requirements. This change was incorporated into the final rule.
From this, it is clear that the Commission wanted to provide a
reasonable timeframe for licensees to achieve full compliance.
As noted in the final rule, the Commission also anticipated that
licensees would have to conduct site-specific analyses to determine
what
[[Page 16525]]
changes were necessary to implement the rule's requirements, and that
changes could be accomplished through a variety of licensing
mechanisms, including exemptions. Since issuance of the final rule, the
Commission has rejected a generic industry request to extend the rule's
compliance date for all operating nuclear power plants, but noted that
the Commission's regulations provide mechanisms for individual
licensees, with good cause, to apply for relief from the compliance
date (Reference: June 4, 2009, letter from R. W. Borchardt, NRC, to M.
S. Fertel, Nuclear Energy Institute). The licensee's request for an
exemption is therefore consistent with the approach set forth by the
Commission and discussed in the June 4, 2009, letter.
Perry Nuclear Power Plant Schedule Exemption Request
The licensee provided detailed information in the enclosure of its
November 30, 2009, letter, requesting an exemption. Enclosure 1
contains proprietary information regarding the site security plan,
details of specific portions of the regulation for which the site
cannot be in compliance by the March 31, 2010, deadline and why, the
required changes to the site's security configuration, and a timeline
with critical path activities that would enable the licensee to achieve
full compliance by November 25, 2010. The timeline provides dates
indicating when (1) Construction will begin on various phases of the
project, (2) outages are scheduled for the unit, and (3) critical
equipment will be ordered, installed, tested and become operational.
Notwithstanding the schedule exemption for this specific
requirement, the licensee will continue to be in compliance with all
other applicable physical security requirements as described in 10 CFR
73.55 and reflected in its current NRC-approved physical security
program. By November 25, 2010, PNPP will be in full compliance with all
the regulatory requirements of 10 CFR 73.55, as issued on March 27,
2009.
4.0 Conclusion for Part 73 Schedule Exemption Request
The staff has reviewed the licensee's submittals and concludes that
the licensee has provided adequate justification for its request for an
extension of the compliance date with regard to the one specified
requirement of 10 CFR 73.55 to November 25, 2010.
Accordingly, the Commission has determined that pursuant to 10 CFR
73.5, ``Specific exemptions,'' an exemption from the March 31, 2010,
compliance date is authorized by law and will not endanger life or
property or the common defense and security, and is otherwise in the
public interest.
The NRC staff has determined that the long-term benefits that will
be realized when the PNPP equipment installation is complete, justifies
extending the full compliance date with regard to the specified
requirement of 10 CFR 73.55. The security measures PNPP needs
additional time to implement are new requirements imposed by March 27,
2009, amendments to 10 CFR 73.55, and are in addition to those required
by the security orders issued in response to the events of September
11, 2001. Therefore, the NRC concluded that the licensee's actions are
in the best interest of protecting the public health and safety through
the security changes that will result from granting this exemption.
As per the licensee's request and the NRC's regulatory authority to
grant an exemption from the March 31, 2010, deadline for the one item
specified in the enclosure of FENOC letter dated November 30, 2009, the
licensee is required to be in full compliance by November 25, 2010. In
achieving compliance, the licensee is reminded that it is responsible
for determining the appropriate licensing mechanism (i.e., 10 CFR
50.54(p) or 10 CFR 50.90) for incorporation of all necessary changes to
its security plans.
Pursuant to 10 CFR 51.32, ``Finding of no significant impact,'' the
Commission has previously determined that the granting of this
exemption will not have a significant effect on the quality of the
human environment (75 FR 14638).
This exemption is effective upon issuance.
Dated at Rockville, Maryland, this 26th day of March 2010.
For the Nuclear Regulatory Commission.
Joseph G. Giitter,
Director, Division of Operating Reactor Licensing, Office of Nuclear
Reactor Regulation.
[FR Doc. 2010-7375 Filed 3-31-10; 8:45 am]
BILLING CODE 7590-01-P