Entergy Operations, Inc., Grand Gulf Nuclear Station, Unit 1; Exemption, 15749-15750 [2010-7022]
Download as PDF
Federal Register / Vol. 75, No. 60 / Tuesday, March 30, 2010 / Notices
jlentini on DSKJ8SOYB1PROD with NOTICES
timeline for achieving full compliance
with the new regulation. Enclosures 1
and 2 contain proprietary information
regarding the site security plan, details
of the specific requirements of the
regulation for which the site cannot be
in compliance by the March 31, 2010,
deadline and why, the required changes
to the site’s security configuration, and
a timeline with ‘‘critical path’’ activities
that will enable the licensee to achieve
full compliance by May 31, 2011. The
timeline provides dates indicating when
(1) construction will begin on various
phases of the project (i.e., new buildings
and fences), and (2) critical equipment
will be installed, tested and become
operational.
Notwithstanding the schedule
exemptions of these limited
requirements, the licensee indicated
that it will continue to be in compliance
with all other applicable physical
security requirements as described in 10
CFR 73.55 and reflected in its current
NRC-approved physical security
program. By May 31, 2011, the licensee
also stated that Fermi 2 will be in full
compliance with the regulatory
requirements of 10 CFR 73.55, as issued
on March 27, 2009.
4.0 Conclusion for Part 73 Schedule
Exemption Request
The NRC staff has reviewed the
licensee’s submittals and concludes that
the licensee has provided adequate
justification for its request for an
extension of the compliance date to May
31, 2011, with regard to five specified
requirements of 10 CFR 73.55.
Accordingly, the Commission has
determined that pursuant to 10 CFR
73.5, ‘‘Specific exemptions,’’ an
exemption from the March 31, 2010,
compliance date is authorized by law
and will not endanger life or property or
the common defense and security, and
is otherwise in the public interest.
Therefore, the Commission hereby
grants the requested exemption. The
NRC staff has determined that the longterm benefits that will be realized when
the Fermi 2 modifications are completed
justifies exceeding the full compliance
date in the case of this particular
licensee. The security measures Fermi 2
needs additional time to implement are
new requirements imposed by March
27, 2009, amendments to 10 CFR 73.55,
and are in addition to those currently
required by the security orders issued in
response to the events of September 11,
2001. Therefore, the NRC concludes that
the licensee’s actions are in the best
interest of protecting the public health
and safety through the security changes
that will result from granting this
exemption.
VerDate Nov<24>2008
16:22 Mar 29, 2010
Jkt 220001
As per the licensee’s request and the
NRC’s regulatory authority to grant an
exemption from the March 31, 2010,
deadline for the five requirements
specified in Enclosure 1 of the Detroit
Edison letter dated December 23, 2009,
the licensee is required to be in full
compliance by May 31, 2011. In
achieving compliance, the licensee is
reminded that it is responsible for
determining the appropriate licensing
mechanism (i.e., 10 CFR 50.54(p) or 10
CFR 50.90) for incorporation of all
necessary changes to its security plans.
Pursuant to 10 CFR 51.32, ‘‘Finding of
no significant impact,’’ the Commission
has previously determined that the
granting of this exemption will not have
a significant effect on the quality of the
human environment [75 FR 11946;
dated March 12, 2010].
This exemption is effective upon
issuance.
15749
1.0 Background
Entergy Operations, Inc. (Entergy or
the licensee), is the holder of Facility
Operating License No. NPF–29 which
authorizes operation of the Grand Gulf
Nuclear Station, Unit 1 (GGNS). The
license provides, among other things,
that the facility is subject to the rules,
regulations, and orders of the Nuclear
Regulatory Commission (NRC, the
Commission) now or hereafter in effect.
The facility consists of a boiling-water
reactor located in Claiborne County,
Mississippi.
assurance, against radiological sabotage
by designing and implementing
comprehensive site security programs.
The amendments to 10 CFR 73.55
published on March 27, 2009 (74 FR
13926), establish and update generically
applicable security requirements similar
to those previously imposed by
Commission orders issued after the
terrorist attacks of September 11, 2001,
and implemented by licensees. In
addition, the amendments to 10 CFR
73.55 include additional requirements
to further enhance site security based
upon insights gained from
implementation of the post-September
11, 2001, security orders. It is from two
of these additional requirements that
Entergy now seeks an exemption from
the March 31, 2010, implementation
date. All other physical security
requirements established by this recent
rulemaking have already been or will be
implemented by the licensee by March
31, 2010.
By application dated January 14,
2010, as supplemented by letters dated
January 18 and February 4, 2010, the
licensee requested an exemption in
accordance with 10 CFR 73.5, ‘‘Specific
exemptions.’’ The licensee’s letters
dated January 14 and February 4, 2010,
contain security-related information
and, accordingly, are being withheld
from public disclosure. The licensee’s
letter dated January 18, 2010, is publicly
available in Agencywide Documents
Access and Management System
(ADAMS) Accession No. ML100190852.
The licensee has requested an
exemption from the March 31, 2010,
implementation date, stating that it
must complete a number of
modifications to the current site security
configuration before all requirements
can be met. Specifically, the request is
to extend the implementation date from
the current March 31, 2010, deadline to
July 30, 2010, for one requirement and
to March 31, 2011, for a second
requirement. Granting this exemption
for the two requirements would allow
the licensee to complete the
modifications designed to provide
significant upgrades to meet the noted
regulatory requirements.
2.0 Request/Action
Title 10 of the Code of Federal
Regulations (10 CFR), Part 73, ‘‘Physical
protection of plants and materials,’’
Section 73.55, ‘‘Requirements for
physical protection of licensed activities
in nuclear power reactors against
radiological sabotage,’’ published in the
Federal Register on March 27, 2009,
effective May 26, 2009, with a full
implementation date of March 31, 2010,
requires licensees to protect, with high
3.0 Discussion of Part 73 Schedule
Exemptions From the March 31, 2010,
Full Implementation Date
Pursuant to 10 CFR 73.55(a)(1), ‘‘By
March 31, 2010, each nuclear power
reactor licensee, licensed under 10 CFR
Part 50, shall implement the
requirements of this section through its
Commission-approved Physical Security
Plan, Training and Qualification Plan,
Safeguards Contingency Plan, and Cyber
Security Plan referred to collectively
Dated at Rockville, Maryland, this 19th day
of March 2010.
For the Nuclear Regulatory Commission.
Allen G. Howe,
Acting Director, Division of Operating Reactor
Licensing, Office of Nuclear Reactor
Regulation.
[FR Doc. 2010–7030 Filed 3–29–10; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket No. 50–416; NRC–2010–0082]
Entergy Operations, Inc., Grand Gulf
Nuclear Station, Unit 1; Exemption
PO 00000
Frm 00082
Fmt 4703
Sfmt 4703
E:\FR\FM\30MRN1.SGM
30MRN1
jlentini on DSKJ8SOYB1PROD with NOTICES
15750
Federal Register / Vol. 75, No. 60 / Tuesday, March 30, 2010 / Notices
hereafter as ‘security plans.’ ’’ Pursuant
to 10 CFR 73.5, the Commission may,
upon application by any interested
person or upon its own initiative, grant
exemptions from the requirements of 10
CFR Part 73 when the exemptions are
authorized by law, and will not
endanger life or property or the common
defense and security, and are otherwise
in the public interest.
NRC approval of this exemption, as
noted above, would allow an extension
from March 31, 2010, to July 30, 2010,
for the implementation date of one
specific requirement and to March 31,
2011, for the implementation date of
another specific requirement of the new
rule. As stated above, 10 CFR 73.5
allows the NRC to grant exemptions
from the requirements of 10 CFR Part
73. The NRC staff has determined that
granting of the licensee’s proposed
exemption would not result in a
violation of the Atomic Energy Act of
1954, as amended, or the Commission’s
regulations. Therefore, NRC approval of
the licensee’s exemption request is
authorized by law.
In the draft final rule provided to the
Commission, the NRC staff proposed
that the requirements of the new
regulation be met within 180 days. The
Commission directed a change from 180
days to approximately 1 year for
licensees to fully implement the new
requirements. This change was
incorporated into the final rule. From
this, it is clear that the Commission
wanted to provide a reasonable
timeframe for licensees to achieve full
compliance.
As noted in the final rule, the
Commission also anticipated that
licensees would have to conduct sitespecific analyses to determine what
changes were necessary to implement
the rule’s requirements, and that any
such changes could be accomplished
through a variety of licensing
mechanisms, including exemptions.
Since issuance of the final rule, the
Commission has rejected a generic
industry request to extend the rule’s
compliance date for all operating
nuclear power plants, but noted that the
Commission’s regulations provide
mechanisms for individual licensees,
with good cause, to apply for relief from
the compliance date, as documented in
the letter from R. W. Borchardt (NRC) to
M. S. Fertel (Nuclear Energy Institute)
dated June 4, 2009. The licensee’s
request for an exemption is therefore
consistent with the approach set forth
by the Commission and discussed in the
June 4, 2009, letter.
VerDate Nov<24>2008
16:22 Mar 29, 2010
Jkt 220001
GGNS Schedule Exemption Request
The licensee provided detailed
information in the Attachments to its
letters dated January 14 and February 4,
2010, requesting an exemption. The
licensee is requesting additional time to
implement certain new requirements
due to the long equipment lead time
from the vendor, the time required for
installation and testing of the new
security equipment, and the impact to
available resources from a scheduled
spring 2010 refueling outage. The
licensee describes a comprehensive plan
to expand the protected area with
upgrades to the security capabilities of
its GGNS site and provides a timeline
for achieving full compliance with the
new regulation. The Attachments to the
licensee’s letters contain securityrelated information regarding the site
security plan, details of the specific
requirements of the regulation for which
the site cannot be in compliance by the
March 31, 2010, deadline, justification
for the exemption request, a description
of the required changes to the site’s
security configuration, and a timeline
with ‘‘critical path’’ activities that would
enable the licensee to achieve full
compliance by March 31, 2011. The
timeline provides dates indicating when
(1) construction will begin on various
phases of the project (e.g., new
buildings and fences), and (2) critical
equipment will be ordered, installed,
tested and become operational. A
redacted version of the licensee’s
exemption request, including
attachment, is publicly available at
Agencywide Documents Management
and Access System (ADAMS) Accession
No. ML100190852.
Notwithstanding the schedule
exemptions for these limited
requirements, the licensee indicated
that it will continue to be in compliance
with all other applicable physical
security requirements as described in 10
CFR 73.55 and reflected in its current
NRC-approved physical security
program. By March 31, 2011, GGNS also
stated that it will be in full compliance
with the regulatory requirements of 10
CFR 73.55, as issued on March 27, 2009.
4.0 Conclusion for Part 73 Schedule
Exemption Request
The staff has reviewed the licensee’s
submittal and concludes that the
licensee has provided adequate
justification for its request for an
extension of the compliance date with
regard to one specified requirement of
10 CFR 73.55 until March 31, 2011, and
another specified requirement of 10 CFR
73.55 until July 30, 2010.
PO 00000
Frm 00083
Fmt 4703
Sfmt 9990
Accordingly, the Commission has
determined that pursuant to 10 CFR
73.5, ‘‘Specific exemptions,’’ an
exemption from the March 31, 2010,
compliance date is authorized by law
and will not endanger life or property or
the common defense and security, and
is otherwise in the public interest.
Therefore, the Commission hereby
grants the requested exemption.
The NRC staff has determined that the
long-term benefits that will be realized
when the GGNS modifications are
complete justifies extending the full
compliance date in the case of this
particular licensee. The security
measures GGNS needs additional time
to complete are new requirements
imposed by the March 27, 2009,
amendments to 10 CFR 73.55, and are
in addition to those currently required
by the security orders issued in
response to the events of September 11,
2001. Therefore, the NRC staff
concludes that the licensee’s actions are
in the best interest of protecting the
public health and safety through the
security changes that will result from
granting this exemption.
As per the licensee’s request and the
NRC’s regulatory authority to grant an
exemption from the March 31, 2010,
deadline for the two items specified in
the Attachments to Entergy’s letters
dated January 14, January 18, and
February 4, 2010, the licensee is
required to be in full compliance with
10 CFR 73.55 by March 31, 2011. In
achieving compliance, the licensee is
reminded that it is responsible for
determining the appropriate licensing
mechanism (i.e., 10 CFR 50.54(p) or 10
CFR 50.90) for incorporation of all
necessary changes to its security plans.
Pursuant to 10 CFR 51.32, ‘‘Finding of
no significant impact,’’ the Commission
has previously determined that the
granting of this exemption will not have
a significant effect on the quality of the
human environment (75 FR 9955; March
4, 2010).
This exemption is effective upon
issuance.
Dated at Rockville, Maryland, this 23rd day
of March 2010.
For the Nuclear Regulatory Commission.
Joseph G. Giitter,
Director, Division of Operating Reactor
Licensing, Office of Nuclear Reactor
Regulation.
[FR Doc. 2010–7022 Filed 3–29–10; 8:45 am]
BILLING CODE 7590–01–P
E:\FR\FM\30MRN1.SGM
30MRN1
Agencies
[Federal Register Volume 75, Number 60 (Tuesday, March 30, 2010)]
[Notices]
[Pages 15749-15750]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-7022]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-416; NRC-2010-0082]
Entergy Operations, Inc., Grand Gulf Nuclear Station, Unit 1;
Exemption
1.0 Background
Entergy Operations, Inc. (Entergy or the licensee), is the holder
of Facility Operating License No. NPF-29 which authorizes operation of
the Grand Gulf Nuclear Station, Unit 1 (GGNS). The license provides,
among other things, that the facility is subject to the rules,
regulations, and orders of the Nuclear Regulatory Commission (NRC, the
Commission) now or hereafter in effect.
The facility consists of a boiling-water reactor located in
Claiborne County, Mississippi.
2.0 Request/Action
Title 10 of the Code of Federal Regulations (10 CFR), Part 73,
``Physical protection of plants and materials,'' Section 73.55,
``Requirements for physical protection of licensed activities in
nuclear power reactors against radiological sabotage,'' published in
the Federal Register on March 27, 2009, effective May 26, 2009, with a
full implementation date of March 31, 2010, requires licensees to
protect, with high assurance, against radiological sabotage by
designing and implementing comprehensive site security programs. The
amendments to 10 CFR 73.55 published on March 27, 2009 (74 FR 13926),
establish and update generically applicable security requirements
similar to those previously imposed by Commission orders issued after
the terrorist attacks of September 11, 2001, and implemented by
licensees. In addition, the amendments to 10 CFR 73.55 include
additional requirements to further enhance site security based upon
insights gained from implementation of the post-September 11, 2001,
security orders. It is from two of these additional requirements that
Entergy now seeks an exemption from the March 31, 2010, implementation
date. All other physical security requirements established by this
recent rulemaking have already been or will be implemented by the
licensee by March 31, 2010.
By application dated January 14, 2010, as supplemented by letters
dated January 18 and February 4, 2010, the licensee requested an
exemption in accordance with 10 CFR 73.5, ``Specific exemptions.'' The
licensee's letters dated January 14 and February 4, 2010, contain
security-related information and, accordingly, are being withheld from
public disclosure. The licensee's letter dated January 18, 2010, is
publicly available in Agencywide Documents Access and Management System
(ADAMS) Accession No. ML100190852. The licensee has requested an
exemption from the March 31, 2010, implementation date, stating that it
must complete a number of modifications to the current site security
configuration before all requirements can be met. Specifically, the
request is to extend the implementation date from the current March 31,
2010, deadline to July 30, 2010, for one requirement and to March 31,
2011, for a second requirement. Granting this exemption for the two
requirements would allow the licensee to complete the modifications
designed to provide significant upgrades to meet the noted regulatory
requirements.
3.0 Discussion of Part 73 Schedule Exemptions From the March 31, 2010,
Full Implementation Date
Pursuant to 10 CFR 73.55(a)(1), ``By March 31, 2010, each nuclear
power reactor licensee, licensed under 10 CFR Part 50, shall implement
the requirements of this section through its Commission-approved
Physical Security Plan, Training and Qualification Plan, Safeguards
Contingency Plan, and Cyber Security Plan referred to collectively
[[Page 15750]]
hereafter as `security plans.' '' Pursuant to 10 CFR 73.5, the
Commission may, upon application by any interested person or upon its
own initiative, grant exemptions from the requirements of 10 CFR Part
73 when the exemptions are authorized by law, and will not endanger
life or property or the common defense and security, and are otherwise
in the public interest.
NRC approval of this exemption, as noted above, would allow an
extension from March 31, 2010, to July 30, 2010, for the implementation
date of one specific requirement and to March 31, 2011, for the
implementation date of another specific requirement of the new rule. As
stated above, 10 CFR 73.5 allows the NRC to grant exemptions from the
requirements of 10 CFR Part 73. The NRC staff has determined that
granting of the licensee's proposed exemption would not result in a
violation of the Atomic Energy Act of 1954, as amended, or the
Commission's regulations. Therefore, NRC approval of the licensee's
exemption request is authorized by law.
In the draft final rule provided to the Commission, the NRC staff
proposed that the requirements of the new regulation be met within 180
days. The Commission directed a change from 180 days to approximately 1
year for licensees to fully implement the new requirements. This change
was incorporated into the final rule. From this, it is clear that the
Commission wanted to provide a reasonable timeframe for licensees to
achieve full compliance.
As noted in the final rule, the Commission also anticipated that
licensees would have to conduct site-specific analyses to determine
what changes were necessary to implement the rule's requirements, and
that any such changes could be accomplished through a variety of
licensing mechanisms, including exemptions. Since issuance of the final
rule, the Commission has rejected a generic industry request to extend
the rule's compliance date for all operating nuclear power plants, but
noted that the Commission's regulations provide mechanisms for
individual licensees, with good cause, to apply for relief from the
compliance date, as documented in the letter from R. W. Borchardt (NRC)
to M. S. Fertel (Nuclear Energy Institute) dated June 4, 2009. The
licensee's request for an exemption is therefore consistent with the
approach set forth by the Commission and discussed in the June 4, 2009,
letter.
GGNS Schedule Exemption Request
The licensee provided detailed information in the Attachments to
its letters dated January 14 and February 4, 2010, requesting an
exemption. The licensee is requesting additional time to implement
certain new requirements due to the long equipment lead time from the
vendor, the time required for installation and testing of the new
security equipment, and the impact to available resources from a
scheduled spring 2010 refueling outage. The licensee describes a
comprehensive plan to expand the protected area with upgrades to the
security capabilities of its GGNS site and provides a timeline for
achieving full compliance with the new regulation. The Attachments to
the licensee's letters contain security-related information regarding
the site security plan, details of the specific requirements of the
regulation for which the site cannot be in compliance by the March 31,
2010, deadline, justification for the exemption request, a description
of the required changes to the site's security configuration, and a
timeline with ``critical path'' activities that would enable the
licensee to achieve full compliance by March 31, 2011. The timeline
provides dates indicating when (1) construction will begin on various
phases of the project (e.g., new buildings and fences), and (2)
critical equipment will be ordered, installed, tested and become
operational. A redacted version of the licensee's exemption request,
including attachment, is publicly available at Agencywide Documents
Management and Access System (ADAMS) Accession No. ML100190852.
Notwithstanding the schedule exemptions for these limited
requirements, the licensee indicated that it will continue to be in
compliance with all other applicable physical security requirements as
described in 10 CFR 73.55 and reflected in its current NRC-approved
physical security program. By March 31, 2011, GGNS also stated that it
will be in full compliance with the regulatory requirements of 10 CFR
73.55, as issued on March 27, 2009.
4.0 Conclusion for Part 73 Schedule Exemption Request
The staff has reviewed the licensee's submittal and concludes that
the licensee has provided adequate justification for its request for an
extension of the compliance date with regard to one specified
requirement of 10 CFR 73.55 until March 31, 2011, and another specified
requirement of 10 CFR 73.55 until July 30, 2010.
Accordingly, the Commission has determined that pursuant to 10 CFR
73.5, ``Specific exemptions,'' an exemption from the March 31, 2010,
compliance date is authorized by law and will not endanger life or
property or the common defense and security, and is otherwise in the
public interest. Therefore, the Commission hereby grants the requested
exemption.
The NRC staff has determined that the long-term benefits that will
be realized when the GGNS modifications are complete justifies
extending the full compliance date in the case of this particular
licensee. The security measures GGNS needs additional time to complete
are new requirements imposed by the March 27, 2009, amendments to 10
CFR 73.55, and are in addition to those currently required by the
security orders issued in response to the events of September 11, 2001.
Therefore, the NRC staff concludes that the licensee's actions are in
the best interest of protecting the public health and safety through
the security changes that will result from granting this exemption.
As per the licensee's request and the NRC's regulatory authority to
grant an exemption from the March 31, 2010, deadline for the two items
specified in the Attachments to Entergy's letters dated January 14,
January 18, and February 4, 2010, the licensee is required to be in
full compliance with 10 CFR 73.55 by March 31, 2011. In achieving
compliance, the licensee is reminded that it is responsible for
determining the appropriate licensing mechanism (i.e., 10 CFR 50.54(p)
or 10 CFR 50.90) for incorporation of all necessary changes to its
security plans.
Pursuant to 10 CFR 51.32, ``Finding of no significant impact,'' the
Commission has previously determined that the granting of this
exemption will not have a significant effect on the quality of the
human environment (75 FR 9955; March 4, 2010).
This exemption is effective upon issuance.
Dated at Rockville, Maryland, this 23rd day of March 2010.
For the Nuclear Regulatory Commission.
Joseph G. Giitter,
Director, Division of Operating Reactor Licensing, Office of Nuclear
Reactor Regulation.
[FR Doc. 2010-7022 Filed 3-29-10; 8:45 am]
BILLING CODE 7590-01-P