East Tennessee Natural Gas, LLC; Notice of Application, 15426-15427 [2010-6826]
Download as PDF
15426
Federal Register / Vol. 75, No. 59 / Monday, March 29, 2010 / Notices
and (7) transmitting, or otherwise
disclosing the information.
The estimate of cost for respondents
is based upon salaries for professional
and clerical support, as well as direct
and indirect overhead costs. Direct costs
include all costs directly attributable to
providing this information, such as
administrative costs and the cost for
information technology. Indirect or
overhead costs are costs incurred by an
organization in support of its mission.
These costs apply to activities which
benefit the whole organization rather
than any one particular function or
activity.
Comments are invited on: (1) Whether
the proposed collections of information
are necessary for the proper
performance of the functions of the
Commission, including whether the
information will have practical utility;
(2) the accuracy of the agency’s
estimates of the burden of the proposed
collections of information, including the
validity of the methodology and
assumptions used; (3) ways to enhance
the quality, utility and clarity of the
information to be collected; and (4)
ways to minimize the burden of the
collections of information on those who
are to respond, including the use of
appropriate automated, electronic,
mechanical, or other technological
collection techniques or other forms of
information technology, e.g. permitting
electronic submission of responses.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–6823 Filed 3–26–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. CP10–89–000; PF09–13–000]
East Tennessee Natural Gas, LLC;
Notice of Application
cprice-sewell on DSK89S0YB1PROD with NOTICES
March 22, 2010.
Take notice that on March 8, 2010,
East Tennessee Natural Gas, LLC (East
Tennessee), 5400 Westheimer Court,
Houston, Texas 77056–5310, filed in the
above referenced docket an application
pursuant to sections 7(b) and 7(c) of the
Natural Gas Act (NGA) for authorization
to: (i) Install an approximately 8.4-mile,
24-inch diameter mainline extension
and to construct of a new meter station
and installation of a launcher/receiver at
the terminus of the extension; (ii) install
8.0 miles of 24-inch diameter pipeline
looping, including a launcher/receiver,
mainline valve, and regulator; (iii)
VerDate Nov<24>2008
09:18 Apr 05, 2010
Jkt 220001
abandon and replace approximately 2.3
miles of 12-inch diameter pipeline with
24-inch diameter pipeline, including
new piping connections at the Fordtown
Compressor Station; (iv) abandon and
replace 9.2 miles of 8-inch diameter
pipeline with 24-inch diameter
pipeline, including new piping
connections at the Bristol Compressor
Station; and (v) modify and install of
regulation and piping at the existing
Flatwoods and Glade Spring
Compressor Stations (the NET Project).
The NET Project is located in Greene,
Hawkins, Sullivan, and Washington
Counties, Tennessee and Washington
County, Virginia. East Tennessee states
that the NET Project will allow it to
provide 150,000 dekatherms (Dth) per
day of firm transportation to a proposed
natural gas-fired power generation
facility of Tennessee Valley Authority
(TVA), all as more fully set forth in the
application which is on file with the
Commission and open to public
inspection. The filing is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site Web at
https://www.ferc.gov using the ‘‘eLibrary’’
link. Enter the docket number excluding
the last three digits in the docket
number field to access the document.
For assistance, contact FERC at
FERCOnlineSupport@ferc.gov or call
toll-free, (886) 208–3676 or TTY, (202)
502–8659.
Any questions concerning this
application may be directed to Lisa A.
Moore, General Manager, Rates and
Certificates, East Tennessee Natural Gas,
LLC, 5400 Westheimer Court, PO Box
1642, Houston, Texas 77251–1642, at
(713) 627–4102, or
lamoore@spectraenergy.com.
On August 10, 2009, Commission staff
granted East Tennessee’s request to
utilize the Pre-Filing Process and
assigned Docket No. PF09–13–000 to
staff activities involved the NET Project.
Now, as of the filing the March 8, 2010
application, the Pre-Filing Process for
this project has ended. From this time
forward, this proceeding will be
conducted in Docket No. CP10–89–000,
as noted in the caption of this Notice.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
PO 00000
Frm 00026
Fmt 4703
Sfmt 4703
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
14 copies of filings made in the
proceeding with the Commission and
must mail a copy to the applicant and
to every other party. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
Persons who wish to comment only
on the environmental review of this
project should submit an original and
two copies of their comments to the
Secretary of the Commission.
Environmental commentors will be
placed on the Commission’s
environmental mailing list, will receive
copies of the environmental documents,
and will be notified of meetings
associated with the Commission’s
environmental review process.
Environmental commentors will not be
required to serve copies of filed
documents on all other parties.
However, the non-party commentors
will not receive copies of all documents
filed by other parties or issued by the
Commission (except for the mailing of
environmental documents issued by the
Commission) and will not have the right
to seek court review of the
Commission’s final order.
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible online at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
E:\FR\FM\29MRN1.SGM
29MRN1
Federal Register / Vol. 75, No. 59 / Monday, March 29, 2010 / Notices
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: April 12, 2010.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–6826 Filed 3–26–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Western Area Power Administration
DEPARTMENT OF THE INTERIOR
Bureau of Land Management
Notice of Intent To Prepare an
Environmental Impact Statement/Staff
Assessment for the Proposed
Construction and Operation of the Rice
Solar Energy Project, Riverside
County, CA (DOE/EIS–0439) and
Possible Land Use Plan Amendments
Western Area Power
Administration, DOE; Bureau of Land
Management, DOI.
ACTION: Notice of Intent to Prepare an
Environmental Impact Statement/Staff
Assessment, Possible Land Use Plan
Amendments and to Conduct Scoping
Meetings; Notice of Floodplain and
Wetlands Involvement.
cprice-sewell on DSK89S0YB1PROD with NOTICES
AGENCY:
SUMMARY: In compliance with the
National Environmental Policy Act of
1969 (NEPA), as amended, the Federal
Land Policy and Management Act of
1976 (FLPMA), as amended, and the
California Environmental Quality Act
(CEQA), the Western Area Power
Administration (Western), an agency of
the DOE, and the Bureau of Land
Management (BLM) Palm Springs—
South Coast Field Office, together with
the California Energy Commission
(CEC), intend to prepare a joint
Environmental Impact Statement (EIS)/
Staff Assessment (SA), which may
include an amendment to the California
Desert Conservation Area (CDCA) Plan
(1980, as amended) and by this notice
are announcing the beginning of the
scoping process to inform the public
and interested parties and to solicit
public comments and identify issues
concerning the scope, proposed actions,
and alternatives to be addressed in the
EIS and SA for the proposed Rice Solar
Energy Project (Project) in Riverside
County, California. Rice Solar Energy,
VerDate Nov<24>2008
09:18 Apr 05, 2010
Jkt 220001
LLC (RSE) has applied to Western to
interconnect the proposed Project to
Western’s electrical transmission
system. This EIS/SA will address
Western’s proposed Federal action of
interconnecting the proposed Project to
Western’s transmission system and
making any necessary modifications to
Western facilities to accommodate the
interconnection and will also address
BLM’s proposed action of authorizing
rights of way (ROW) for a 230-kilovolt
(kV) transmission line, access road, and
fiber optic line and possibly amending
the CDCA. The EIS/SA will also review
the potential environmental impacts of
constructing, operating, and
maintaining RSE’s 150-megawatt (MW)
solar-powered generating facility,
consisting of a solar field of heliostat
mirrors, power block, thermal energy
storage system, substation site,
transmission line, temporary laydown
areas, and other ancillary facilities.
The public scoping period begins
with the publication of this notice and
will end on April 28, 2010. Western and
BLM will host public scoping meetings
to provide information on the proposed
Project and gather comments on the
proposal. The public scoping meetings
will be on March 31, 2010 at Big River
Community Services District, 150351
Del Rey Street, Big River, California, and
on April 1, 2010 at University of
California Riverside-Palm Desert
Campus, 75080 Frank Sinatra Drive,
Palm Desert, California 92211. Scoping
meetings will be from 4 p.m. to 7 p.m.
The meetings will be informal, and
attendees will be able to speak directly
with Western, BLM, and RSE
representatives about the proposed
Project. Oral or written comments may
be provided at the public scoping
meetings, mailed or e-mailed to Ms.
Liana Reilly at the address listed in the
addresses section.
DATES:
Written comments on the
scope of the EIS/SA and possible land
use plan amendment should be
addressed to:
Ms. Liana Reilly, NEPA Document
Manager, Western Area Power
Administration, P.O. Box 281213,
Lakewood, Colorado 80228–8213 or email at RiceSolar@wapa.gov.
Allison Shaffer, Project Manager,
Palm Springs-South Coast Field Office,
BLM 1201 Bird Center Drive, Palm
Springs, California 92262 or e-mail at
CAPSSolarRice@blm.gov.
John Kessler, Project Manager, Siting,
Transmission and Environmental
Protection Division, CEC 1516 Ninth
Street, Sacramento, California 95814 or
e-mail at Jkessler@energy.state.ca.us.
ADDRESSES:
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
15427
To help define the scope of the EIS,
written comments should be received
no later than April 28, 2010.
FOR FURTHER INFORMATION CONTACT: For
information on the proposed Project, the
EIS process or to receive a copy of the
Draft EIS (DEIS) when it is published,
contact Ms. Reilly at (720) 962–7253, or
(800) 336–7288, or the address provided
above.
For information relating to BLM’s
participation, contact Allison Shaffer at
(760) 833–7100 or the address provided
above.
For information relating to the CEC’s
participation, contact John Kessler at
(916) 654–4679 or the address above or
information can be obtained through the
CEC’s Public Adviser’s Office at (916)
654–8236 or toll free in California, (800)
822–6228, or by e-mail at
publicadviser@energy.state.ca.us.
For general information on DOE’s
NEPA review procedures or status of a
NEPA review, contact Ms. Carol M.
Borgstrom, Director of NEPA Policy and
Compliance, GC–54, U.S. Department of
Energy, 1000 Independence Avenue,
SW., Washington, DC 20585, telephone
(202) 586–4600 or (800) 472–2756.
SUPPLEMENTARY INFORMATION: Western,
an agency within DOE, markets Federal
hydroelectric power to preference
customers, as specified by law. These
customers include municipalities,
cooperatives, irrigation districts, Federal
and State agencies, and Native
American tribes. Western’s service
territory covers 15 western states,
including California. Western owns and
operates more than 17,000 miles of
high-voltage transmission lines. Under
Federal law, BLM is responsible for
responding to applications for ROW on
public lands. BLM has received an
application for a ROW authorization to
construct and operate a transmission
line that would interconnect the Rice
Solar Energy Project to Western’s
transmission system. A portion of the
transmission line would cross managed
lands in eastern Riverside County,
California. Pursuant to BLM’s CDCA
Plan, sites associated with power
generation or transmission not
identified in the CDCA Plan will be
considered through the plan
amendment process. By this notice, the
BLM is complying with the
requirements in 43 CFR 1610.2 (c) to
notify the public of potential
amendments to land use plans, subject
to the findings of the EIS.
Western and BLM intend to prepare
an EIS to analyze the impacts of their
respective proposed Federal action and
RSE’s proposed Project in accordance
with the NEPA, as amended, CEQ
E:\FR\FM\29MRN1.SGM
29MRN1
Agencies
[Federal Register Volume 75, Number 59 (Monday, March 29, 2010)]
[Notices]
[Pages 15426-15427]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-6826]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket Nos. CP10-89-000; PF09-13-000]
East Tennessee Natural Gas, LLC; Notice of Application
March 22, 2010.
Take notice that on March 8, 2010, East Tennessee Natural Gas, LLC
(East Tennessee), 5400 Westheimer Court, Houston, Texas 77056-5310,
filed in the above referenced docket an application pursuant to
sections 7(b) and 7(c) of the Natural Gas Act (NGA) for authorization
to: (i) Install an approximately 8.4-mile, 24-inch diameter mainline
extension and to construct of a new meter station and installation of a
launcher/receiver at the terminus of the extension; (ii) install 8.0
miles of 24-inch diameter pipeline looping, including a launcher/
receiver, mainline valve, and regulator; (iii) abandon and replace
approximately 2.3 miles of 12-inch diameter pipeline with 24-inch
diameter pipeline, including new piping connections at the Fordtown
Compressor Station; (iv) abandon and replace 9.2 miles of 8-inch
diameter pipeline with 24-inch diameter pipeline, including new piping
connections at the Bristol Compressor Station; and (v) modify and
install of regulation and piping at the existing Flatwoods and Glade
Spring Compressor Stations (the NET Project). The NET Project is
located in Greene, Hawkins, Sullivan, and Washington Counties,
Tennessee and Washington County, Virginia. East Tennessee states that
the NET Project will allow it to provide 150,000 dekatherms (Dth) per
day of firm transportation to a proposed natural gas-fired power
generation facility of Tennessee Valley Authority (TVA), all as more
fully set forth in the application which is on file with the Commission
and open to public inspection. The filing is available for review at
the Commission in the Public Reference Room or may be viewed on the
Commission's Web site Web at https://www.ferc.gov using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For
assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-
free, (886) 208-3676 or TTY, (202) 502-8659.
Any questions concerning this application may be directed to Lisa
A. Moore, General Manager, Rates and Certificates, East Tennessee
Natural Gas, LLC, 5400 Westheimer Court, PO Box 1642, Houston, Texas
77251-1642, at (713) 627-4102, or lamoore@spectraenergy.com.
On August 10, 2009, Commission staff granted East Tennessee's
request to utilize the Pre-Filing Process and assigned Docket No. PF09-
13-000 to staff activities involved the NET Project. Now, as of the
filing the March 8, 2010 application, the Pre-Filing Process for this
project has ended. From this time forward, this proceeding will be
conducted in Docket No. CP10-89-000, as noted in the caption of this
Notice.
There are two ways to become involved in the Commission's review of
this project. First, any person wishing to obtain legal status by
becoming a party to the proceedings for this project should, on or
before the comment date stated below file with the Federal Energy
Regulatory Commission, 888 First Street, NE., Washington, DC 20426, a
motion to intervene in accordance with the requirements of the
Commission's Rules of Practice and Procedure (18 CFR 385.214 or
385.211) and the Regulations under the NGA (18 CFR 157.10). A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission and will receive copies of all
documents filed by the applicant and by all other parties. A party must
submit 14 copies of filings made in the proceeding with the Commission
and must mail a copy to the applicant and to every other party. Only
parties to the proceeding can ask for court review of Commission orders
in the proceeding.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commentors will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commentors will not be required to serve copies of filed
documents on all other parties. However, the non-party commentors will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right to seek court
review of the Commission's final order.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFiling'' link
at https://www.ferc.gov. Persons unable to file electronically should
submit an original and 14 copies of the protest or intervention to the
Federal Energy regulatory Commission, 888 First Street, NE.,
Washington, DC 20426.
This filing is accessible online at https://www.ferc.gov, using the
``eLibrary'' link and is available for review in the Commission's
Public Reference Room in Washington, DC.
[[Page 15427]]
There is an ``eSubscription'' link on the Web site that enables
subscribers to receive e-mail notification when a document is added to
a subscribed docket(s). For assistance with any FERC Online service,
please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll
free). For TTY, call (202) 502-8659.
Comment Date: April 12, 2010.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010-6826 Filed 3-26-10; 8:45 am]
BILLING CODE 6717-01-P