Virginia Electric and Power Company; Surry Power Station, Unit Nos. 1 and 2 (Surry 1 and 2); Correction to Environmental Assessment and Finding of No Significant Impact, 13318 [2010-6054]
Download as PDF
13318
Federal Register / Vol. 75, No. 53 / Friday, March 19, 2010 / Notices
Day
Event/Activity
25 ..................................
If NRC staff finds no ‘‘need’’ or no likelihood of standing, the deadline for requestor/petitioner to file a motion seeking
a ruling to reverse the NRC staff’s denial of access; NRC staff files copy of access determination with the presiding
officer (or Chief Administrative Judge or other designated officer, as appropriate). If NRC staff finds ‘‘need’’ for
SUNSI, the deadline for any party to the proceeding whose interest independent of the proceeding would be
harmed by the release of the information to file a motion seeking a ruling to reverse the NRC staff’s grant of access.
Deadline for NRC staff reply to motions to reverse NRC staff determination(s).
(Receipt +30) If NRC staff finds standing and need for SUNSI, deadline for NRC staff to complete information processing and file motion for Protective Order and draft Non-Disclosure Affidavit. Deadline for applicant/licensee to file
Non-Disclosure Agreement for SUNSI.
If access granted: Issuance of presiding officer or other designated officer decision on motion for protective order for
access to sensitive information (including schedule for providing access and submission of contentions) or decision
reversing a final adverse determination by the NRC staff.
Deadline for filing executed Non-Disclosure Affidavits. Access provided to SUNSI consistent with decision issuing the
protective order.
Deadline for submission of contentions whose development depends upon access to SUNSI. However, if more than
25 days remain between the petitioner’s receipt of (or access to) the information and the deadline for filing all other
contentions (as established in the notice of hearing or opportunity for hearing), the petitioner may file its SUNSI
contentions by that later deadline.
(Contention receipt +25) Answers to contentions whose development depends upon access to SUNSI.
(Answer receipt +7) Petitioner/Intervenor reply to answers.
Decision on contention admission.
30 ..................................
40 ..................................
A ....................................
A + 3 .............................
A + 28 ...........................
A + 53 ...........................
A + 60 ...........................
>A + 60 .........................
1 and 2, respectively, approximately 5
months for Unit 1 and 17 months for
Unit 2 beyond the date required by 10
CFR part 73.’’
[FR Doc. 2010–6071 Filed 3–18–10; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket Nos. 50–280 and 50–281; NRC–
2010–0079]
Virginia Electric and Power Company;
Surry Power Station, Unit Nos. 1 and
2 (Surry 1 and 2); Correction to
Environmental Assessment and
Finding of No Significant Impact
erowe on DSK5CLS3C1PROD with NOTICES
AGENCY: Nuclear Regulatory
Commission.
ACTION: Correction notice.
14:14 Mar 18, 2010
[FR Doc. 2010–6054 Filed 3–18–10; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
SUMMARY: This document corrects a
notice appearing in the Federal Register
on March 3, 2010 (75 FR 9618), that
cited the implementation date for
compliance with Title 10 of the Code of
Federal Regulations (10 CFR), part 73 as
‘‘August 31, 2010,’’ rather than ‘‘August
31, 2010, and August 31, 2011, for Surry
1 and 2, respectively.’’ This action is
necessary to add an implementation
date for Surry Unit 2.
FOR FURTHER INFORMATION CONTACT:
Karen Cotton, Office of Nuclear Reactor
Regulation, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001; telephone, (301) 415–1438; e-mail,
Karen.Cotton@nrc.gov.
SUPPLEMENTARY INFORMATION: On page
9619, in the first column, second line,
it reads ‘‘implementation dated of
August 31, 2010, approximately 5
months beyond the date required by 10
CFR Part 73,’’ and it is corrected to read
‘‘* * * implementation date of August
31, 2010 and August 31, 2011, for Surry
VerDate Nov<24>2008
Dated in Rockville, Maryland, this 12th
day of March 2010.
For the Nuclear Regulatory Commission.
Karen Cotton,
Project Manager, Plant Licensing Branch II–
1, Division of Operating Licensing, Office of
Nuclear Reactor Regulation.
Jkt 220001
[Docket No. 50–331; NRC–2010–0107]
Nextera Energy Duane Arnold, LLC;
Duane Arnold Energy Center;
Environmental Assessment and
Finding of No Significant Impact
The U.S. Nuclear Regulatory
Commission (NRC) is considering
issuance of an exemption, pursuant to
10 CFR 50.12, from 10 CFR Part 50,
Appendix J, Option B and associated
changes to the Technical Specifications
(TSs) for main steamline isolation valve
local leakage rate testing for Facility
Operating License No. DPR–49, issued
to NextEra Energy Duane Arnold, LLC
(the licensee), for operation of the
Duane Arnold Energy Center, located in
Palo, Iowa. In accordance with 10 CFR
51.21, the NRC prepared an
environmental assessment documenting
its finding. The NRC concluded that the
proposed actions will have no
significant environmental impact.
PO 00000
Frm 00075
Fmt 4703
Sfmt 4703
Environmental Assessment
Identification of the Proposed Action
The proposed action would exempt
the licensee from certain portions of 10
CFR part 50, Appendix J, Option B.
Specifically, the licensee requests to be
exempted from the measured leakage
rate for the main steamline isolation
valves (MSIV), and associated inboard
drainline, from inclusion in both the
overall measured leakage rate for Type
A integrated tests and from the sum of
the local leakage rates for Type B and
Type C tests as required by Appendix J,
Option B, Paragraphs III.A and Ill.B,
respectively.
In conjunction with the exemption
request, the licensee also requests
approval, pursuant to the requirements
of 10 CFR 50.90, of associated changes
to the Duane Arnold Energy Center TS,
Section 5.5.12 (Primary Containment
Leakage Rate Testing Program) that
reflects the exemption to Appendix J
requested above. Also, there is an
additional proposed TS change to TS
Section 3.6.1.3 (Primary Containment
Isolation Valves) associated with MSIV
leakage testing requirements, which
does not require a corresponding
exemption from 10 CFR part 50,
Appendix J. The change to TS Section
3.6.1.3, is included in the amendment
request to remove the repair criterion for
MSIVs that fail their as-found leakage
rate acceptance criterion found in the
licensee’s Surveillance Requirement
3.6.1.3.9.
The Need for the Proposed Action
The proposed action is needed to
reconcile the requirements of 10 CFR
part 50, Appendix J, Option B and their
E:\FR\FM\19MRN1.SGM
19MRN1
Agencies
[Federal Register Volume 75, Number 53 (Friday, March 19, 2010)]
[Notices]
[Page 13318]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-6054]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-280 and 50-281; NRC-2010-0079]
Virginia Electric and Power Company; Surry Power Station, Unit
Nos. 1 and 2 (Surry 1 and 2); Correction to Environmental Assessment
and Finding of No Significant Impact
AGENCY: Nuclear Regulatory Commission.
ACTION: Correction notice.
-----------------------------------------------------------------------
SUMMARY: This document corrects a notice appearing in the Federal
Register on March 3, 2010 (75 FR 9618), that cited the implementation
date for compliance with Title 10 of the Code of Federal Regulations
(10 CFR), part 73 as ``August 31, 2010,'' rather than ``August 31,
2010, and August 31, 2011, for Surry 1 and 2, respectively.'' This
action is necessary to add an implementation date for Surry Unit 2.
FOR FURTHER INFORMATION CONTACT: Karen Cotton, Office of Nuclear
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC
20555-0001; telephone, (301) 415-1438; e-mail, Karen.Cotton@nrc.gov.
SUPPLEMENTARY INFORMATION: On page 9619, in the first column, second
line, it reads ``implementation dated of August 31, 2010, approximately
5 months beyond the date required by 10 CFR Part 73,'' and it is
corrected to read ``* * * implementation date of August 31, 2010 and
August 31, 2011, for Surry 1 and 2, respectively, approximately 5
months for Unit 1 and 17 months for Unit 2 beyond the date required by
10 CFR part 73.''
Dated in Rockville, Maryland, this 12th day of March 2010.
For the Nuclear Regulatory Commission.
Karen Cotton,
Project Manager, Plant Licensing Branch II-1, Division of Operating
Licensing, Office of Nuclear Reactor Regulation.