Southern Nuclear Operating Company; Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing, 11202-11205 [2010-5092]

Download as PDF erowe on DSK5CLS3C1PROD with NOTICES 11202 Federal Register / Vol. 75, No. 46 / Wednesday, March 10, 2010 / Notices Congress and oversight agencies, and annual cost accounting reports. 22. Department of Transportation, National Highway Traffic Safety Administration (N1–416–10–1, 1 item, 1 temporary item). Master files of an electronic information system used to allow public access to agency publications through its traffic safety materials catalog. 23. Department of the Treasury, Departmental Offices (N1–56–09–20, 5 items, 3 temporary items). Master files, inputs, and outputs associated with an electronic correspondence management system used to track incoming documentation related to case files, litigation, and other legal matters. Records relating to White House and congressional correspondence are proposed for permanent retention. 24. Department of the Treasury, Alcohol and Tobacco Tax and Trade Bureau (N1–564–09–10, 2 items, 2 temporary items). Inputs and master files of an electronic information system that contains data on industry tax liabilities on regulated products. 25. Department of the Treasury, Internal Revenue Service (N1–58–09– 59, 4 items, 4 temporary items). Master files, outputs, and system documentation associated with an electronic information system used to streamline customer service by providing a common user interface. 26. Department of the Treasury, Internal Revenue Service (N1–58–09– 85, 2 items, 2 temporary items). Applications for grants used to fund programs which offer tax counseling and assistance to low income and elderly taxpayers. 27. Department of the Treasury, Internal Revenue Service (N1–58–09– 87, 2 items, 2 temporary items). Master files and system documentation associated with an electronic information system used to verify the employment status of agency staff. 28. Department of the Treasury, Internal Revenue Service (N1–58–09– 89, 3 items, 3 temporary items). Master files and system documentation associated with an electronic information system used to scan and route paper correspondence received from taxpayers. Dated: March 4, 2010. Michael J. Kurtz, Assistant Archivist for Records Services— Washington, DC. [FR Doc. 2010–5197 Filed 3–9–10; 8:45 am] BILLING CODE 7515–01–P VerDate Nov<24>2008 15:07 Mar 09, 2010 Jkt 220001 NUCLEAR REGULATORY COMMISSION [Docket No. 50–364; NRC–2010–0092] Southern Nuclear Operating Company; Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing The U.S. Nuclear Regulatory Commission (NRC, the Commission) is considering issuance of an amendment to Facility Operating License No. NPF– 8, issued to Southern Nuclear Operating Company, Inc. (SNC, the licensee), for operation of the Joseph M. Farley Nuclear Plant, Unit 2 (FNP, Unit 2), located in Houston County, Alabama. The proposed amendment would delay implementation of a modification to eliminate the reactor coolant pump breaker position reactor trip function for FNP Unit 2. Elimination of this trip function was approved by license amendment issued on September 18, 2009, which approved the licensee making the modification prior to the end of the 20th refueling outage (U2R20) for Unit 2. The licensee requested approval to delay implementation of the modification until prior to the end of Unit 2’s refueling outage 21 (U2R21). Before issuance of the proposed license amendment, the Commission will have made findings required by the Atomic Energy Act of 1954, as amended (the Act), and the Commission’s regulations. The Commission has made a proposed determination that the amendment request involves no significant hazards consideration. Under the Commission’s regulations in Title 10 of the Code of Federal Regulations (10 CFR), section 50.92, this means that operation of the facility in accordance with the proposed amendment would not (1) Involve a significant increase in the probability or consequences of an accident previously evaluated; or (2) create the possibility of a new or different kind of accident from any accident previously evaluated; or (3) involve a significant reduction in a margin of safety. As required by 10 CFR 50.91(a), the licensee has provided its analysis of the issue of no significant hazards consideration, which is presented below: 1. Does the proposed change involve a significant increase in the probability or consequences of an accident previously evaluated? Response: No. The proposed Unit 2 amendment implementation schedule extension is administrative in nature and does not require PO 00000 Frm 00099 Fmt 4703 Sfmt 4703 any physical plant modifications, physically affect any plant systems or components, or entail changes in plant operation. The amendment implementation schedule extension does not significantly increase the probability or consequences of an accident previously evaluated in the Final Safety Analysis Report (FSAR). All of the safety analyses have been evaluated for impact. The change in the implementation schedule of the reactor coolant pump breaker position reactor trip and technical specification change will not initiate any accident; therefore, the probability of an accident has not been increased. An evaluation of dose consequences, with respect to the proposed changes, indicates there is no impact due to the proposed changes and all acceptance criteria continue to be met. Operation for an additional cycle with the RCP breaker position trip enabled will have negligible safety consequences given that the configuration of plant equipment currently in place to minimize the likelihood of an unwarranted trip will remain. There is no change to the current licensing basis. Therefore, this change does not involve a significant increase in the probability or consequences of an accident previously evaluated. 2. Does the proposed change create the possibility of a new or different kind of accident from any previously evaluated? Response: No. The proposed Unit 2 amendment implementation schedule extension is administrative in nature and does not require any physical plant modifications, physically affect any plant systems or components, or entail changes in plant operation. The proposed amendment implementation schedule extension does not create the possibility of a new or different kind of accident than any accident already evaluated in the FSAR. No new accident scenarios, failure mechanisms or limiting single failures are introduced as result of the proposed change. The proposed amendment implementation schedule extension has no adverse effects on any safety-related system. Operation for an additional cycle with the RCP breaker position trip enabled will have negligible safety consequences given that the configuration of plant equipment currently in place to minimize the likelihood of an unwarranted trip will remain. There is no change to the current licensing basis. Therefore, all accident analyses criteria continue to be met and this change does not create the possibility of a new or different kind of accident from any accident previously evaluated. 3. Does the proposed change involve a significant reduction in a margin of safety? Response: No. The proposed Unit 2 amendment implementation schedule extension is administrative in nature and does not require any physical plant modifications, physically affect any plant systems or components, or entail changes in plant operation. The proposed amendment implementation schedule extension does not involve a significant reduction in a margin of safety. All analyses that credit the Reactor Coolant System Low Flow reactor trip function have E:\FR\FM\10MRN1.SGM 10MRN1 Federal Register / Vol. 75, No. 46 / Wednesday, March 10, 2010 / Notices erowe on DSK5CLS3C1PROD with NOTICES been reviewed and no changes to any inputs are required. The evaluation demonstrated that all applicable acceptance criteria are met. Operation for an additional cycle with the RCP breaker position trip enabled will have negligible safety consequences given that the configuration of plant equipment currently in place to minimize the likelihood of an unwarranted trip will remain. There is no change to the current licensing basis. Therefore, the proposed amendment implementation schedule extension does not involve a significant reduction in the margin of safety. The NRC staff has reviewed the licensee’s analysis and, based on this review, it appears that the three standards of 10 CFR 50.92(c) are satisfied. Therefore, the NRC staff proposes to determine that the amendment request involves no significant hazards consideration. The Commission is seeking public comments on this proposed determination. Any comments received within 30 days after the date of publication of this notice will be considered in making any final determination. Normally, the Commission will not issue the amendment until the expiration of 60 days after the date of publication of this notice. The Commission may issue the license amendment before expiration of the 60day period provided that its final determination is that the amendment involves no significant hazards consideration. In addition, the Commission may issue the amendment prior to the expiration of the 30-day comment period should circumstances change during the 30-day comment period such that failure to act in a timely way would result, for example, in derating or shutdown of the facility. Should the Commission take action prior to the expiration of either the comment period or the notice period, it will publish in the Federal Register a notice of issuance. Should the Commission make a final No Significant Hazards Consideration Determination, any hearing will take place after issuance. The Commission expects that the need to take this action will occur very infrequently. Written comments may be submitted by mail to the Chief, Rulemaking and Directives Branch (RDB), TWB–05– B01M, Division of Administrative Services, Office of Administration, U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001, and should cite the publication date and page number of this Federal Register notice. Written comments may also be faxed to the RDB at 301–492–3446. Documents may be examined, and/or copied for a fee, at the NRC’s Public VerDate Nov<24>2008 15:07 Mar 09, 2010 Jkt 220001 Document Room (PDR), located at One White Flint North, Room O1 F21, 11555 Rockville Pike (first floor), Rockville, Maryland. Within 60 days after the date of publication of this notice, any person(s) whose interest may be affected by this action may file a request for a hearing and a petition to intervene with respect to issuance of the amendment to the subject facility operating license. Requests for a hearing and a petition for leave to intervene shall be filed in accordance with the Commission’s ‘‘Rules of Practice for Domestic Licensing Proceedings’’ in 10 CFR Part 2. Interested person(s) should consult a current copy of 10 CFR 2.309, which is available at the Commission’s PDR, located at One White Flint North, Room O1F21, 11555 Rockville Pike (first floor), Rockville, Maryland. Publicly available records will be accessible from the Agencywide Documents Access and Management System’s (ADAMS) Public Electronic Reading Room on the Internet at the NRC Web site, https:// www.nrc.gov/reading-rm/doccollections/cfr/. If a request for a hearing or petition for leave to intervene is filed by the above date, the Commission or a presiding officer designated by the Commission or by the Chief Administrative Judge of the Atomic Safety and Licensing Board Panel, will rule on the request and/or petition; and the Secretary or the Chief Administrative Judge of the Atomic Safety and Licensing Board will issue a notice of a hearing or an appropriate order. As required by 10 CFR 2.309, a petition for leave to intervene shall set forth with particularity the interest of the petitioner in the proceeding, and how that interest may be affected by the results of the proceeding. The petition should specifically explain the reasons why intervention should be permitted with particular reference to the following general requirements: (1) The name, address and telephone number of the requestor or petitioner; (2) the nature of the requestor’s/petitioner’s right under the Act to be made a party to the proceeding; (3) the nature and extent of the requestor’s/petitioner’s property, financial, or other interest in the proceeding; and (4) the possible effect of any decision or order which may be entered in the proceeding on the requestor’s/petitioner’s interest. The petition must also identify the specific contentions which the requestor/ petitioner seeks to have litigated at the proceeding. Each contention must consist of a specific statement of the issue of law or fact to be raised or controverted. In PO 00000 Frm 00100 Fmt 4703 Sfmt 4703 11203 addition, the requestor/petitioner shall provide a brief explanation of the bases for the contention and a concise statement of the alleged facts or expert opinion which support the contention and on which the petitioner intends to rely in proving the contention at the hearing. The requestor/petitioner must also provide references to those specific sources and documents of which the petitioner is aware and on which the petitioner intends to rely to establish those facts or expert opinion. The petition must include sufficient information to show that a genuine dispute exists with the applicant on a material issue of law or fact. Contentions shall be limited to matters within the scope of the amendment under consideration. The contention must be one which, if proven, would entitle the petitioner to relief. A requestor/petitioner who fails to satisfy these requirements with respect to at least one contention will not be permitted to participate as a party. Those permitted to intervene become parties to the proceeding, subject to any limitations in the order granting leave to intervene, and have the opportunity to participate fully in the conduct of the hearing. If a hearing is requested, the Commission will make a final determination on the issue of no significant hazards consideration. The final determination will serve to decide when the hearing is held. If the final determination is that the amendment request involves no significant hazards consideration, the Commission may issue the amendment and make it immediately effective, notwithstanding the request for a hearing. Any hearing held would take place after issuance of the amendment. If the final determination is that the amendment request involves a significant hazards consideration, any hearing held would take place before the issuance of any amendment. All documents filed in NRC adjudicatory proceedings, including a request for hearing, a petition for leave to intervene, any motion or other document filed in the proceeding prior to the submission of a request for hearing or petition to intervene, and documents filed by interested governmental entities participating under 10 CFR 2.315(c), must be filed in accordance with the NRC E–Filing rule (72 FR 49139, August 28, 2007). The E– Filing process requires participants to submit and serve all adjudicatory documents over the Internet, or in some cases to mail copies on electronic storage media. Participants may not submit paper copies of their filings E:\FR\FM\10MRN1.SGM 10MRN1 erowe on DSK5CLS3C1PROD with NOTICES 11204 Federal Register / Vol. 75, No. 46 / Wednesday, March 10, 2010 / Notices unless they seek an exemption in accordance with the procedures described below. To comply with the procedural requirements of E–Filing, at least ten (10) days prior to the filing deadline, the participant should contact the Office of the Secretary by e-mail at hearing.docket@nrc.gov, or by telephone at (301) 415–1677, to request (1) a digital ID certificate, which allows the participant (or its counsel or representative) to digitally sign documents and access the E–Submittal server for any proceeding in which it is participating; and (2) advise the Secretary that the participant will be submitting a request or petition for hearing (even in instances in which the participant, or its counsel or representative, already holds an NRCissued digital ID certificate). Based upon this information, the Secretary will establish an electronic docket for the hearing in this proceeding if the Secretary has not already established an electronic docket. Information about applying for a digital ID certificate is available on NRC’s public Web site at https:// www.nrc.gov/site-help/e-submittals/ apply-certificates.html. System requirements for accessing the E– Submittal server are detailed in NRC’s ‘‘Guidance for Electronic Submission,’’ which is available on the agency’s public Web site at https://www.nrc.gov/ site-help/e-submittals.html. Participants may attempt to use other software not listed on the Web site, but should note that the NRC’s E–Filing system does not support unlisted software, and the NRC Meta System Help Desk will not be able to offer assistance in using unlisted software. If a participant is electronically submitting a document to the NRC in accordance with the E–Filing rule, the participant must file the document using the NRC’s online, Web-based submission form. In order to serve documents through EIE, users will be required to install a Web browser plugin from the NRC Web site. Further information on the Web-based submission form, including the installation of the Web browser plug-in, is available on the NRC’s public Web site at https://www.nrc.gov/site-help/esubmittals.html. Once a participant has obtained a digital ID certificate and a docket has been created, the participant can then submit a request for hearing or petition for leave to intervene. Submissions should be in Portable Document Format (PDF) in accordance with NRC guidance available on the NRC public Web site at https://www.nrc.gov/site-help/e- VerDate Nov<24>2008 15:07 Mar 09, 2010 Jkt 220001 submittals.html. A filing is considered complete at the time the documents are submitted through the NRC’s E–Filing system. To be timely, an electronic filing must be submitted to the E–Filing system no later than 11:59 p.m. Eastern Time on the due date. Upon receipt of a transmission, the E–Filing system time-stamps the document and sends the submitter an e-mail notice confirming receipt of the document. The E–Filing system also distributes an email notice that provides access to the document to the NRC Office of the General Counsel and any others who have advised the Office of the Secretary that they wish to participate in the proceeding, so that the filer need not serve the documents on those participants separately. Therefore, applicants and other participants (or their counsel or representative) must apply for and receive a digital ID certificate before a hearing request/ petition to intervene is filed so that they can obtain access to the document via the E–Filing system. A person filing electronically using the agency’s adjudicatory E–Filing system may seek assistance by contacting the NRC Meta System Help Desk through the ‘‘Contact Us’’ link located on the NRC Web site at https:// www.nrc.gov/site-help/esubmittals.html, by e-mail at MSHD.Resource@nrc.gov, or by a tollfree call at (866) 672–7640. The NRC Meta System Help Desk is available between 8 a.m. and 8 p.m., Eastern Time, Monday through Friday, excluding government holidays. Participants who believe that they have a good cause for not submitting documents electronically must file an exemption request, in accordance with 10 CFR 2.302(g), with their initial paper filing requesting authorization to continue to submit documents in paper format. Such filings must be submitted by: (1) First class mail addressed to the Office of the Secretary of the Commission, U.S. Nuclear Regulatory Commission, Washington, DC 20555– 0001, Attention: Rulemaking and Adjudications Staff; or (2) courier, express mail, or expedited delivery service to the Office of the Secretary, Sixteenth Floor, One White Flint North, 11555 Rockville Pike, Rockville, Maryland, 20852, Attention: Rulemaking and Adjudications Staff. Participants filing a document in this manner are responsible for serving the document on all other participants. Filing is considered complete by firstclass mail as of the time of deposit in the mail, or by courier, express mail, or expedited delivery service upon depositing the document with the PO 00000 Frm 00101 Fmt 4703 Sfmt 4703 provider of the service. A presiding officer, having granted an exemption request from using E–Filing, may require a participant or party to use E– Filing if the presiding officer subsequently determines that the reason for granting the exemption from use of E–Filing no longer exists. Documents submitted in adjudicatory proceedings will appear in NRC’s electronic hearing docket which is available to the public at https:// ehd.nrc.gov/EHD_Proceeding/home.asp, unless excluded pursuant to an order of the Commission, or the presiding officer. Participants are requested not to include personal privacy information, such as social security numbers, home addresses, or home phone numbers in their filings, unless an NRC regulation or other law requires submission of such information. With respect to copyrighted works, except for limited excerpts that serve the purpose of the adjudicatory filings and would constitute a Fair Use application, participants are requested not to include copyrighted materials in their submission. Petitions for leave to intervene must be filed no later than 60 days from the date of publication of this notice. Nontimely filings will not be entertained absent a determination by the presiding officer that the petition or request should be granted or the contentions should be admitted, based on a balancing of the factors specified in 10 CFR 2.309(c)(1)(i)–(viii). For further details with respect to this license amendment application, see the application for amendment dated February 26, 2010, which is available for public inspection at the Commission’s PDR, located at One White Flint North, File Public Area O1 F21, 11555 Rockville Pike (first floor), Rockville, Maryland. Publicly available records will be accessible electronically from the Agencywide Documents Access and Management System’s (ADAMS) Public Electronic Reading Room on the Internet at the NRC Web site, https://www.nrc.gov/reading-rm/ adams.html. Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS, should contact the NRC PDR Reference staff by telephone at 1–800–397–4209, 301–415–4737, or by e-mail to pdr.resource@nrc.gov. Attorney for licensee: M. Stanford Blanton, Esq., Balch and Bingham, Post Office Box 306, 1710 Sixth Avenue North, Birmingham, Alabama 35201. Dated at Rockville, Maryland, this 2nd day of March 2010. E:\FR\FM\10MRN1.SGM 10MRN1 Federal Register / Vol. 75, No. 46 / Wednesday, March 10, 2010 / Notices For the Nuclear Regulatory Commission. Robert E. Martin, Senior Project Manager, Plant Licensing Branch 2–1, Division of Operating Reactor Licensing, Office of Nuclear Reactor Regulation. February 2, 2010 (ADAMS Accession No. ML100351182). The Need for the Proposed Action The proposed action is needed to provide the licensee with additional time to perform the required upgrades to the Pilgrim security system due to resource and logistical impacts. The request for an exemption from the March 31, 2010, implementation date to September 15, 2010, is based on the delivery dates for the new equipment and the time needed to install this new equipment to meet the revised requirements. [FR Doc. 2010–5092 Filed 3–9–10; 8:45 am] BILLING CODE 7590–01–P NUCLEAR REGULATORY COMMISSION [ Docket No. 50–293; NRC–2010–0094] Entergy Nuclear Operations, Inc; Pilgrim Nuclear Power Station Environmental Assessment and Finding of No Significant Impact The U.S. Nuclear Regulatory Commission (NRC) is considering issuance of an exemption, pursuant to Title 10 of the Code of Federal Regulations (10 CFR) section 73.5, ‘‘Specific exemptions,’’ from the implementation date for certain new requirements of 10 CFR Part 73, ‘‘Physical protection of plants and materials,’’ for Facility Operating License No. DPR–35, issued to Entergy Nuclear Operations, Inc. (Entergy or the licensee), for operation of Pilgrim Nuclear Power Station (Pilgrim), located in Plymouth County, MA. In accordance with 10 CFR 51.21, the NRC prepared an environmental assessment documenting its finding. The NRC concluded that the proposed action will have no significant impact. Environmental Assessment erowe on DSK5CLS3C1PROD with NOTICES Identification of the Proposed Action The proposed action would exempt Pilgrim from the required implementation date of March 31, 2010, for several new requirements of 10 CFR part 73. Specifically, Pilgrim would be granted an exemption from being in full compliance with certain new requirements contained in 10 CFR 73.55 by the March 31, 2010, deadline. Entergy has proposed an alternate full compliance implementation date of September 15, 2010, approximately 61⁄2 months beyond the date required by 10 CFR Part 73. The proposed action, an extension of the schedule for completion of certain actions required by the revised 10 CFR part 73, does not involve any physical changes to the reactor, fuel, plant structures, water, or land at the Pilgrim site. The proposed action is in accordance with the licensee=s application dated January 22, 2010 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML100260716), as supplemented on VerDate Nov<24>2008 15:07 Mar 09, 2010 Jkt 220001 Environmental Impacts of the Proposed Action The NRC has completed its environmental assessment of the proposed exemption. The staff has concluded that the proposed action to extend the implementation deadline would not significantly affect plant safety and would not have a significant adverse effect on the probability of an accident occurring. The proposed action would not result in an increased radiological hazard beyond those previously analyzed in the environmental assessment and finding of no significant impact made by the Commission in promulgating its revisions to 10 CFR Part 73, as discussed in a Federal Register notice dated March 27, 2009 (74 FR 13967). There will be no change to radioactive effluents that affect radiation exposures to plant workers and members of the public. Therefore, no changes or different types of radiological impacts are expected as a result of the proposed exemption. The proposed action does not result in changes to land use or water use, or result in changes to the quality or quantity of non-radiological effluents. No changes to the National Pollution Discharge Elimination System permit are needed. No effects on the aquatic or terrestrial habitat in the vicinity of the plant, or to threatened, endangered, or protected species under the Endangered Species Act, or impacts to essential fish habitat covered by the MagnusonSteven’s Act are expected. There are no impacts to the air or ambient air quality. There are no impacts to historical and cultural resources. There would be no impact to socioeconomic resources. Therefore, no changes to or different types of non-radiological environmental impacts are expected as a result of the proposed exemption. Accordingly, the NRC concludes that there are no significant environmental impacts associated with the proposed action. In addition, in promulgating its PO 00000 Frm 00102 Fmt 4703 Sfmt 4703 11205 revisions to 10 CFR part 73, the Commission prepared an environmental assessment and published a finding of no significant impact [Part 73, Power Reactor Security Requirements, 74 FR 13926, 13967 (March 27, 2009)]. The NRC staff’s safety evaluation will be provided in the exemption that will be issued as part of the letter to the licensee approving the exemption to the regulation, if granted. Environmental Impacts of the Alternatives to the Proposed Action As an alternative to the proposed action, the NRC staff considered denial of the proposed action (i.e., the ‘‘noaction’’ alternative). Denial of the application would result in no change in current environmental impacts. If the proposed action was denied, the licensee would have to comply with the March 31, 2010, implementation deadline. The environmental impacts of the proposed action and the ‘‘no action’’ alternative action are similar. Alternative Use of Resources The action does not involve the use of any different resources than those previously considered in the Final Environmental Statement for Pilgrim, dated January 1972, and the ‘‘Generic Environmental Impact Statement for License Renewal of Nuclear Plants: Regarding Pilgrim Nuclear Power Station,’’ NUREG–1437, Supplement 29, published in July 2007 (ADAMS Accession No. ML071990027). Agencies and Persons Consulted In accordance with its stated policy, on February 5, 2010, the NRC staff consulted with the Massachusetts State official of the Massachusetts Emergency Management Agency regarding the environmental impact of the proposed action. The State official had no comments. Finding of No Significant Impact On the basis of the environmental assessment, the NRC concludes that the proposed action will not have a significant effect on the quality of the human environment. Accordingly, the NRC has determined not to prepare an environmental impact statement for the proposed action. For further details with respect to the proposed action, see the licensee’s letter dated January 22, 2010, as supplemented by letter dated February 2, 2010. Portions of the submittal dated January 22, 2010, as supplemented by letter dated February 2, 2010, contain security-related information and, accordingly, are not available to the public. Publicly-available versions of E:\FR\FM\10MRN1.SGM 10MRN1

Agencies

[Federal Register Volume 75, Number 46 (Wednesday, March 10, 2010)]
[Notices]
[Pages 11202-11205]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-5092]


=======================================================================
-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 50-364; NRC-2010-0092]


Southern Nuclear Operating Company; Notice of Consideration of 
Issuance of Amendment to Facility Operating License, Proposed No 
Significant Hazards Consideration Determination, and Opportunity for a 
Hearing

    The U.S. Nuclear Regulatory Commission (NRC, the Commission) is 
considering issuance of an amendment to Facility Operating License No. 
NPF-8, issued to Southern Nuclear Operating Company, Inc. (SNC, the 
licensee), for operation of the Joseph M. Farley Nuclear Plant, Unit 2 
(FNP, Unit 2), located in Houston County, Alabama. The proposed 
amendment would delay implementation of a modification to eliminate the 
reactor coolant pump breaker position reactor trip function for FNP 
Unit 2. Elimination of this trip function was approved by license 
amendment issued on September 18, 2009, which approved the licensee 
making the modification prior to the end of the 20th refueling outage 
(U2R20) for Unit 2. The licensee requested approval to delay 
implementation of the modification until prior to the end of Unit 2's 
refueling outage 21 (U2R21).
    Before issuance of the proposed license amendment, the Commission 
will have made findings required by the Atomic Energy Act of 1954, as 
amended (the Act), and the Commission's regulations.
    The Commission has made a proposed determination that the amendment 
request involves no significant hazards consideration. Under the 
Commission's regulations in Title 10 of the Code of Federal Regulations 
(10 CFR), section 50.92, this means that operation of the facility in 
accordance with the proposed amendment would not (1) Involve a 
significant increase in the probability or consequences of an accident 
previously evaluated; or (2) create the possibility of a new or 
different kind of accident from any accident previously evaluated; or 
(3) involve a significant reduction in a margin of safety. As required 
by 10 CFR 50.91(a), the licensee has provided its analysis of the issue 
of no significant hazards consideration, which is presented below:

    1. Does the proposed change involve a significant increase in 
the probability or consequences of an accident previously evaluated?
    Response: No.
    The proposed Unit 2 amendment implementation schedule extension 
is administrative in nature and does not require any physical plant 
modifications, physically affect any plant systems or components, or 
entail changes in plant operation. The amendment implementation 
schedule extension does not significantly increase the probability 
or consequences of an accident previously evaluated in the Final 
Safety Analysis Report (FSAR). All of the safety analyses have been 
evaluated for impact. The change in the implementation schedule of 
the reactor coolant pump breaker position reactor trip and technical 
specification change will not initiate any accident; therefore, the 
probability of an accident has not been increased. An evaluation of 
dose consequences, with respect to the proposed changes, indicates 
there is no impact due to the proposed changes and all acceptance 
criteria continue to be met. Operation for an additional cycle with 
the RCP breaker position trip enabled will have negligible safety 
consequences given that the configuration of plant equipment 
currently in place to minimize the likelihood of an unwarranted trip 
will remain. There is no change to the current licensing basis. 
Therefore, this change does not involve a significant increase in 
the probability or consequences of an accident previously evaluated.
    2. Does the proposed change create the possibility of a new or 
different kind of accident from any previously evaluated?
    Response: No.
    The proposed Unit 2 amendment implementation schedule extension 
is administrative in nature and does not require any physical plant 
modifications, physically affect any plant systems or components, or 
entail changes in plant operation. The proposed amendment 
implementation schedule extension does not create the possibility of 
a new or different kind of accident than any accident already 
evaluated in the FSAR. No new accident scenarios, failure mechanisms 
or limiting single failures are introduced as result of the proposed 
change. The proposed amendment implementation schedule extension has 
no adverse effects on any safety-related system. Operation for an 
additional cycle with the RCP breaker position trip enabled will 
have negligible safety consequences given that the configuration of 
plant equipment currently in place to minimize the likelihood of an 
unwarranted trip will remain. There is no change to the current 
licensing basis. Therefore, all accident analyses criteria continue 
to be met and this change does not create the possibility of a new 
or different kind of accident from any accident previously 
evaluated.
    3. Does the proposed change involve a significant reduction in a 
margin of safety?
    Response: No.
    The proposed Unit 2 amendment implementation schedule extension 
is administrative in nature and does not require any physical plant 
modifications, physically affect any plant systems or components, or 
entail changes in plant operation. The proposed amendment 
implementation schedule extension does not involve a significant 
reduction in a margin of safety. All analyses that credit the 
Reactor Coolant System Low Flow reactor trip function have

[[Page 11203]]

been reviewed and no changes to any inputs are required. The 
evaluation demonstrated that all applicable acceptance criteria are 
met. Operation for an additional cycle with the RCP breaker position 
trip enabled will have negligible safety consequences given that the 
configuration of plant equipment currently in place to minimize the 
likelihood of an unwarranted trip will remain. There is no change to 
the current licensing basis. Therefore, the proposed amendment 
implementation schedule extension does not involve a significant 
reduction in the margin of safety.

    The NRC staff has reviewed the licensee's analysis and, based on 
this review, it appears that the three standards of 10 CFR 50.92(c) are 
satisfied. Therefore, the NRC staff proposes to determine that the 
amendment request involves no significant hazards consideration.
    The Commission is seeking public comments on this proposed 
determination. Any comments received within 30 days after the date of 
publication of this notice will be considered in making any final 
determination.
    Normally, the Commission will not issue the amendment until the 
expiration of 60 days after the date of publication of this notice. The 
Commission may issue the license amendment before expiration of the 60-
day period provided that its final determination is that the amendment 
involves no significant hazards consideration. In addition, the 
Commission may issue the amendment prior to the expiration of the 30-
day comment period should circumstances change during the 30-day 
comment period such that failure to act in a timely way would result, 
for example, in derating or shutdown of the facility. Should the 
Commission take action prior to the expiration of either the comment 
period or the notice period, it will publish in the Federal Register a 
notice of issuance. Should the Commission make a final No Significant 
Hazards Consideration Determination, any hearing will take place after 
issuance. The Commission expects that the need to take this action will 
occur very infrequently.
    Written comments may be submitted by mail to the Chief, Rulemaking 
and Directives Branch (RDB), TWB-05-B01M, Division of Administrative 
Services, Office of Administration, U.S. Nuclear Regulatory Commission, 
Washington, DC 20555-0001, and should cite the publication date and 
page number of this Federal Register notice. Written comments may also 
be faxed to the RDB at 301-492-3446. Documents may be examined, and/or 
copied for a fee, at the NRC's Public Document Room (PDR), located at 
One White Flint North, Room O1 F21, 11555 Rockville Pike (first floor), 
Rockville, Maryland.
    Within 60 days after the date of publication of this notice, any 
person(s) whose interest may be affected by this action may file a 
request for a hearing and a petition to intervene with respect to 
issuance of the amendment to the subject facility operating license. 
Requests for a hearing and a petition for leave to intervene shall be 
filed in accordance with the Commission's ``Rules of Practice for 
Domestic Licensing Proceedings'' in 10 CFR Part 2. Interested person(s) 
should consult a current copy of 10 CFR 2.309, which is available at 
the Commission's PDR, located at One White Flint North, Room O1F21, 
11555 Rockville Pike (first floor), Rockville, Maryland. Publicly 
available records will be accessible from the Agencywide Documents 
Access and Management System's (ADAMS) Public Electronic Reading Room 
on the Internet at the NRC Web site, https://www.nrc.gov/reading-rm/doc-collections/cfr/. If a request for a hearing or petition for leave to 
intervene is filed by the above date, the Commission or a presiding 
officer designated by the Commission or by the Chief Administrative 
Judge of the Atomic Safety and Licensing Board Panel, will rule on the 
request and/or petition; and the Secretary or the Chief Administrative 
Judge of the Atomic Safety and Licensing Board will issue a notice of a 
hearing or an appropriate order.
    As required by 10 CFR 2.309, a petition for leave to intervene 
shall set forth with particularity the interest of the petitioner in 
the proceeding, and how that interest may be affected by the results of 
the proceeding. The petition should specifically explain the reasons 
why intervention should be permitted with particular reference to the 
following general requirements: (1) The name, address and telephone 
number of the requestor or petitioner; (2) the nature of the 
requestor's/petitioner's right under the Act to be made a party to the 
proceeding; (3) the nature and extent of the requestor's/petitioner's 
property, financial, or other interest in the proceeding; and (4) the 
possible effect of any decision or order which may be entered in the 
proceeding on the requestor's/petitioner's interest. The petition must 
also identify the specific contentions which the requestor/petitioner 
seeks to have litigated at the proceeding.
    Each contention must consist of a specific statement of the issue 
of law or fact to be raised or controverted. In addition, the 
requestor/petitioner shall provide a brief explanation of the bases for 
the contention and a concise statement of the alleged facts or expert 
opinion which support the contention and on which the petitioner 
intends to rely in proving the contention at the hearing. The 
requestor/petitioner must also provide references to those specific 
sources and documents of which the petitioner is aware and on which the 
petitioner intends to rely to establish those facts or expert opinion. 
The petition must include sufficient information to show that a genuine 
dispute exists with the applicant on a material issue of law or fact. 
Contentions shall be limited to matters within the scope of the 
amendment under consideration. The contention must be one which, if 
proven, would entitle the petitioner to relief. A requestor/petitioner 
who fails to satisfy these requirements with respect to at least one 
contention will not be permitted to participate as a party.
    Those permitted to intervene become parties to the proceeding, 
subject to any limitations in the order granting leave to intervene, 
and have the opportunity to participate fully in the conduct of the 
hearing.
    If a hearing is requested, the Commission will make a final 
determination on the issue of no significant hazards consideration. The 
final determination will serve to decide when the hearing is held. If 
the final determination is that the amendment request involves no 
significant hazards consideration, the Commission may issue the 
amendment and make it immediately effective, notwithstanding the 
request for a hearing. Any hearing held would take place after issuance 
of the amendment. If the final determination is that the amendment 
request involves a significant hazards consideration, any hearing held 
would take place before the issuance of any amendment.
    All documents filed in NRC adjudicatory proceedings, including a 
request for hearing, a petition for leave to intervene, any motion or 
other document filed in the proceeding prior to the submission of a 
request for hearing or petition to intervene, and documents filed by 
interested governmental entities participating under 10 CFR 2.315(c), 
must be filed in accordance with the NRC E-Filing rule (72 FR 49139, 
August 28, 2007). The E-Filing process requires participants to submit 
and serve all adjudicatory documents over the Internet, or in some 
cases to mail copies on electronic storage media. Participants may not 
submit paper copies of their filings

[[Page 11204]]

unless they seek an exemption in accordance with the procedures 
described below.
    To comply with the procedural requirements of E-Filing, at least 
ten (10) days prior to the filing deadline, the participant should 
contact the Office of the Secretary by e-mail at 
hearing.docket@nrc.gov, or by telephone at (301) 415-1677, to request 
(1) a digital ID certificate, which allows the participant (or its 
counsel or representative) to digitally sign documents and access the 
E-Submittal server for any proceeding in which it is participating; and 
(2) advise the Secretary that the participant will be submitting a 
request or petition for hearing (even in instances in which the 
participant, or its counsel or representative, already holds an NRC-
issued digital ID certificate). Based upon this information, the 
Secretary will establish an electronic docket for the hearing in this 
proceeding if the Secretary has not already established an electronic 
docket.
    Information about applying for a digital ID certificate is 
available on NRC's public Web site at https://www.nrc.gov/site-help/e-submittals/apply-certificates.html. System requirements for accessing 
the E-Submittal server are detailed in NRC's ``Guidance for Electronic 
Submission,'' which is available on the agency's public Web site at 
https://www.nrc.gov/site-help/e-submittals.html. Participants may 
attempt to use other software not listed on the Web site, but should 
note that the NRC's E-Filing system does not support unlisted software, 
and the NRC Meta System Help Desk will not be able to offer assistance 
in using unlisted software.
    If a participant is electronically submitting a document to the NRC 
in accordance with the E-Filing rule, the participant must file the 
document using the NRC's online, Web-based submission form. In order to 
serve documents through EIE, users will be required to install a Web 
browser plug-in from the NRC Web site. Further information on the Web-
based submission form, including the installation of the Web browser 
plug-in, is available on the NRC's public Web site at https://www.nrc.gov/site-help/e-submittals.html.
    Once a participant has obtained a digital ID certificate and a 
docket has been created, the participant can then submit a request for 
hearing or petition for leave to intervene. Submissions should be in 
Portable Document Format (PDF) in accordance with NRC guidance 
available on the NRC public Web site at https://www.nrc.gov/site-help/e-submittals.html. A filing is considered complete at the time the 
documents are submitted through the NRC's E-Filing system. To be 
timely, an electronic filing must be submitted to the E-Filing system 
no later than 11:59 p.m. Eastern Time on the due date. Upon receipt of 
a transmission, the E-Filing system time-stamps the document and sends 
the submitter an e-mail notice confirming receipt of the document. The 
E-Filing system also distributes an e-mail notice that provides access 
to the document to the NRC Office of the General Counsel and any others 
who have advised the Office of the Secretary that they wish to 
participate in the proceeding, so that the filer need not serve the 
documents on those participants separately. Therefore, applicants and 
other participants (or their counsel or representative) must apply for 
and receive a digital ID certificate before a hearing request/petition 
to intervene is filed so that they can obtain access to the document 
via the E-Filing system.
    A person filing electronically using the agency's adjudicatory E-
Filing system may seek assistance by contacting the NRC Meta System 
Help Desk through the ``Contact Us'' link located on the NRC Web site 
at https://www.nrc.gov/site-help/e-submittals.html, by e-mail at 
MSHD.Resource@nrc.gov, or by a toll-free call at (866) 672-7640. The 
NRC Meta System Help Desk is available between 8 a.m. and 8 p.m., 
Eastern Time, Monday through Friday, excluding government holidays.
    Participants who believe that they have a good cause for not 
submitting documents electronically must file an exemption request, in 
accordance with 10 CFR 2.302(g), with their initial paper filing 
requesting authorization to continue to submit documents in paper 
format. Such filings must be submitted by: (1) First class mail 
addressed to the Office of the Secretary of the Commission, U.S. 
Nuclear Regulatory Commission, Washington, DC 20555-0001, Attention: 
Rulemaking and Adjudications Staff; or (2) courier, express mail, or 
expedited delivery service to the Office of the Secretary, Sixteenth 
Floor, One White Flint North, 11555 Rockville Pike, Rockville, 
Maryland, 20852, Attention: Rulemaking and Adjudications Staff. 
Participants filing a document in this manner are responsible for 
serving the document on all other participants. Filing is considered 
complete by first-class mail as of the time of deposit in the mail, or 
by courier, express mail, or expedited delivery service upon depositing 
the document with the provider of the service. A presiding officer, 
having granted an exemption request from using E-Filing, may require a 
participant or party to use E-Filing if the presiding officer 
subsequently determines that the reason for granting the exemption from 
use of E-Filing no longer exists.
    Documents submitted in adjudicatory proceedings will appear in 
NRC's electronic hearing docket which is available to the public at 
https://ehd.nrc.gov/EHD_Proceeding/home.asp, unless excluded pursuant 
to an order of the Commission, or the presiding officer. Participants 
are requested not to include personal privacy information, such as 
social security numbers, home addresses, or home phone numbers in their 
filings, unless an NRC regulation or other law requires submission of 
such information. With respect to copyrighted works, except for limited 
excerpts that serve the purpose of the adjudicatory filings and would 
constitute a Fair Use application, participants are requested not to 
include copyrighted materials in their submission.
    Petitions for leave to intervene must be filed no later than 60 
days from the date of publication of this notice. Non-timely filings 
will not be entertained absent a determination by the presiding officer 
that the petition or request should be granted or the contentions 
should be admitted, based on a balancing of the factors specified in 10 
CFR 2.309(c)(1)(i)-(viii).
    For further details with respect to this license amendment 
application, see the application for amendment dated February 26, 2010, 
which is available for public inspection at the Commission's PDR, 
located at One White Flint North, File Public Area O1 F21, 11555 
Rockville Pike (first floor), Rockville, Maryland. Publicly available 
records will be accessible electronically from the Agencywide Documents 
Access and Management System's (ADAMS) Public Electronic Reading Room 
on the Internet at the NRC Web site, https://www.nrc.gov/reading-rm/adams.html. Persons who do not have access to ADAMS or who encounter 
problems in accessing the documents located in ADAMS, should contact 
the NRC PDR Reference staff by telephone at 1-800-397-4209, 301-415-
4737, or by e-mail to pdr.resource@nrc.gov.
    Attorney for licensee: M. Stanford Blanton, Esq., Balch and 
Bingham, Post Office Box 306, 1710 Sixth Avenue North, Birmingham, 
Alabama 35201.

    Dated at Rockville, Maryland, this 2nd day of March 2010.


[[Page 11205]]


    For the Nuclear Regulatory Commission.
Robert E. Martin,
Senior Project Manager, Plant Licensing Branch 2-1, Division of 
Operating Reactor Licensing, Office of Nuclear Reactor Regulation.
[FR Doc. 2010-5092 Filed 3-9-10; 8:45 am]
BILLING CODE 7590-01-P