Inglis Hydropower, LLC; Notice of Application Accepted for Filing and Soliciting Motions To Intervene and Protests, 10230-10231 [2010-4621]
Download as PDF
10230
Federal Register / Vol. 75, No. 43 / Friday, March 5, 2010 / Notices
proceeding or to be heard by filing
comments on, or protests to, this
application should file a petition to
intervene, comment, or protest at the
address provided above in accordance
with §§ 385.211 or 385.214 of FERC’s
Rules of Practice and Procedures (18
CFR 385.211, 385.214). Fifteen copies of
each petition and protest should be filed
with DOE on or before the date listed
above.
Additional copies of such petitions to
intervene, comments, or protests should
also be filed directly with Mr. Donald
Jessome, President, Transmission
Developers Inc., Pieter Schuyler
Building, 600 Broadway, Albany, New
York 12207–2283.
Before a Presidential permit may be
issued or amended, DOE must
determine that the proposed action is in
the public interest. In making that
determination, DOE considers the
environmental impacts of the proposed
project pursuant to the National
Environmental Policy Act of 1969,
determines the project’s impact on
electric reliability by ascertaining
whether the proposed project would
adversely affect the operation of the U.S.
electric power supply system under
normal and contingency conditions, and
any other factors that DOE may also
consider relevant to the public interest.
Also, DOE must obtain the concurrences
of the Secretary of State and the
Secretary of Defense before taking final
action on a Presidential permit
application.
Copies of this application will be
made available, upon request, for public
inspection and copying at the address
provided above, by accessing the
program Web site at https://
www.oe.energy.gov/
permits_pending.htm, or by emailing
Odessa Hopkins at
Odessa.hopkins@hq.doe.gov.
Issued in Washington, DC, on February 23,
2010.
Anthony J. Como,
Director, Permitting and Siting, Office of
Electricity Delivery and Energy Reliability.
[FR Doc. 2010–4677 Filed 3–4–10; 8:45 am]
BILLING CODE 6450–01–P
DEPARTMENT OF ENERGY
erowe on DSK5CLS3C1PROD with NOTICES
Federal Energy Regulatory
Commission
[Docket No. CP10–65–000]
Mississippi Hub, LLC; Notice of
Amendment Application
February 25, 2010.
On February 8, 2010, Mississippi
Hub, LLC (MS Hub), pursuant to section
VerDate Nov<24>2008
14:45 Mar 04, 2010
Jkt 220001
7(c) of the Natural Gas Act, as amended,
and parts 157 and 284 of the Federal
Energy Regulatory Commission’s
(Commission) regulations, filed to
amend its certificate. The amendment
would expand the gas storage project
certificated in CP09–19–000 on
September 17, 2009, by adding 37,305
horsepower of additional compression
and adding working gas capacity
totaling 15 billion cubic feet (Bcf) in two
new salt dome storage caverns. The
amendment would expand total storage
project working gas capacity to 30 Bcf
and project delivery and injection
capabilities, respectively to 2.8 and 1.5
Bcf per day. MS Hub also requests that
the Commission reaffirm its marketbased rates authority and issue all
required authorizations by June 1, 2010.
Questions regarding this application
should be directed to William Rapp,
Mississippi Hub, LLC, 101 Ash Street,
San Diego, CA 92101, (619) 699–5050.
There are two ways to become
involved in the Commission’s review of
this project. First, any person wishing to
obtain legal status by becoming a party
to the proceedings for this project
should, on or before the comment date
stated below, file with the Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426,
a motion to intervene in accordance
with the requirements of the
Commission’s Rules of Practice and
Procedure (18 CFR 385.214 or 385.211)
and the Regulations under the NGA (18
CFR 157.10). A person obtaining party
status will be placed on the service list
maintained by the Secretary of the
Commission and will receive copies of
all documents filed by the applicant and
by all other parties. A party must submit
14 copies of filings made with the
Commission and must mail a copy to
the applicant and to every other party in
the proceeding. Only parties to the
proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to
intervene in order to have comments
considered. The second way to
participate is by filing with the
Secretary of the Commission, as soon as
possible, an original and two copies of
comments in support of or in opposition
to this project. The Commission will
consider these comments in
determining the appropriate action to be
taken, but the filing of a comment alone
will not serve to make the filer a party
to the proceeding. The Commission’s
rules require that persons filing
comments in opposition to the project
provide copies of their protests only to
the party or parties directly involved in
the protest.
PO 00000
Frm 00027
Fmt 4703
Sfmt 4703
The Commission strongly encourages
electronic filings of comments, protests
and interventions in lieu of paper using
the ‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the intervention or protest to the
Federal Energy regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on March 18, 2010.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–4606 Filed 3–4–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12783–003]
Inglis Hydropower, LLC; Notice of
Application Accepted for Filing and
Soliciting Motions To Intervene and
Protests
February 26, 2010.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Original Major
License.
b. Project No.: P–12783–003.
c. Date filed: July 22, 2009.
d. Applicant: Inglis Hydropower, LLC.
e. Name of Project: Inglis Hydropower
Project.
f. Location: The proposed project
would be located at the existing Inglis
Bypass Channel and Spillway on the
Withlacoochee River, west of Lake
Rousseau and Inglis dam, within the
town of Inglis, in Levy, Citrus, and
Marion counties, Florida. No federal
lands would be occupied by the
proposed project.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791 (a)–825(r).
h. Applicant Contacts: Mr. Dean
Edwards, P.O. Box 1565, Dover, FL
E:\FR\FM\05MRN1.SGM
05MRN1
erowe on DSK5CLS3C1PROD with NOTICES
Federal Register / Vol. 75, No. 43 / Friday, March 5, 2010 / Notices
33527; Mr. Kevin Edwards, P.O. Box
143, Mayodan, NC 27027.
i. FERC Contact: Jennifer Adams at
(202) 502–8087, or
jennifer.adams@ferc.gov.
j. Deadline for filing motions to
intervene and protests: 60 days from the
issuance date of this notice, or April 27,
2010.
All documents may be filed
electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site (https://www.ferc.gov/docs-filing/
ferconline.asp) under the ‘‘eFiling’’ link.
For a simpler method of submitting text
only comments, click on ‘‘Quick
Comment.’’ For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and eight copies to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
and Procedure require all interveners
filing documents with the Commission
to serve a copy of that document on
each person on the official service list
for the project. Further, if an intervener
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
k. This application has been accepted
for filing, but is not ready for
environmental analysis at this time.
l. The proposed 2.0-megawatt Inglis
Hydropower Project would operate in a
run-of-river mode by using flows
released to maintain the surface
elevation of Lake Rousseau at 27.5 feet
mean sea level. Flow releases would be
determined by the Southwest Florida
Water Management District. The
proposed powerhouse would be 60 feet
long by 80 feet wide by 30 feet high, and
contain three vertical shaft turbines. The
penstock would be 130 feet in length.
The project would generate about
12,300,000 kilowatt hours annually,
which would be fed into the
interconnected transmission system via
an existing 3.4-mile-long, 12,470kilovolt transmission line.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room, or may be
viewed on the Commission’s Web site at
https://www.ferc.gov, using the
‘‘eLibrary’’ link. Enter the docket
number, excluding the last three digits
VerDate Nov<24>2008
14:45 Mar 04, 2010
Jkt 220001
in the docket number field, to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Any qualified applicant desiring to
file a competing application must
submit to the Commission, on or before
the specified intervention deadline date,
a competing development application
no later than 120 days after the specified
intervention deadline date. Applications
for preliminary permits will not be
accepted in response to this notice.
A notice of intent must specify the
exact name, business address, and
telephone number of the prospective
applicant, and must include an
unequivocal statement of intent to
submit a development application. A
notice of intent must be served on the
applicant(s) names in this public notice.
Anyone may submit a protest or a
motion to intervene in accordance with
the requirements of Rules of Practice
and Procedure, 18 CFR 385.210,
385.211, and 385.214. In determining
the appropriate action to take, the
Commission will consider all protests
filed, but only those who file a motion
to intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any protests or
motions to intervene must be received
on, or before, the specified deadline
date for the particular application.
When the application is ready for
environmental analysis, the
Commission will issue a public notice
requesting comments,
recommendations, terms and
conditions, or prescriptions.
All filings must: (1) Bear in all capital
letters the title ‘‘PROTEST’’ or ‘‘MOTION
TO INTERVENE;’’ (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person protesting or
intervening; and (4) otherwise comply
with the requirements of 18 CFR
385.2001 through 385.2005. Agencies
may obtain copies of the application
directly from the applicant. A copy of
any protest or motion to intervene must
be served upon each representative of
PO 00000
Frm 00028
Fmt 4703
Sfmt 4703
10231
the applicant specified in the particular
application.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–4621 Filed 3–4–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13658–000]
City of Pittsfield, MA; Notice of
Application Accepted for Filing and
Soliciting Comments, Motions To
Intervene, Protests,
Recommendations, and Terms and
Conditions
February 26, 2010.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Conduit
Exemption.
b. Project No.: 13658–000.
c. Date filed: January 27, 2010.
d. Applicant: City of Pittsfield,
Massachusetts.
e. Name of Project: Coltsville Flow
Control Station Project.
f. Location: The proposed Coltsville
Flow Control Station Project would be
located on a flow control pipeline in the
City of Pittsfield’s water distribution
system located in Berkshire County,
Massachusetts. The land on which all
the project structures are located is
owned by the applicant.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791a–825r.
h. Applicant Contact: Mr. Bruce
Collingwood, P.E., Commissioner,
Department of Public Works & Utilities,
70 Allen Street, Room 200, Pittsfield,
Massachusetts 01201; telephone (413)
499–9330.
i. FERC Contact: Linda Stewart,
telephone (202) 502–6680, and e-mail
address linda.stewart@ferc.gov.
j. Status of Environmental Analysis:
This application is ready for
environmental analysis at this time, and
the Commission is requesting
comments, reply comments,
recommendations, terms and
conditions, and prescriptions.
k. Deadline for filing responsive
documents: Due to the small size and
location of the proposed project in a
closed system, as well as the resource
agency consultation letters filed with
the application, the 60-day timeframe
specified in 18 CFR 4.43(b) for filing all
comments, motions to intervene,
E:\FR\FM\05MRN1.SGM
05MRN1
Agencies
[Federal Register Volume 75, Number 43 (Friday, March 5, 2010)]
[Notices]
[Pages 10230-10231]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-4621]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 12783-003]
Inglis Hydropower, LLC; Notice of Application Accepted for Filing
and Soliciting Motions To Intervene and Protests
February 26, 2010.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Original Major License.
b. Project No.: P-12783-003.
c. Date filed: July 22, 2009.
d. Applicant: Inglis Hydropower, LLC.
e. Name of Project: Inglis Hydropower Project.
f. Location: The proposed project would be located at the existing
Inglis Bypass Channel and Spillway on the Withlacoochee River, west of
Lake Rousseau and Inglis dam, within the town of Inglis, in Levy,
Citrus, and Marion counties, Florida. No federal lands would be
occupied by the proposed project.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
h. Applicant Contacts: Mr. Dean Edwards, P.O. Box 1565, Dover, FL
[[Page 10231]]
33527; Mr. Kevin Edwards, P.O. Box 143, Mayodan, NC 27027.
i. FERC Contact: Jennifer Adams at (202) 502-8087, or
jennifer.adams@ferc.gov.
j. Deadline for filing motions to intervene and protests: 60 days
from the issuance date of this notice, or April 27, 2010.
All documents may be filed electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web
site (https://www.ferc.gov/docs-filing/ferconline.asp) under the
``eFiling'' link. For a simpler method of submitting text only
comments, click on ``Quick Comment.'' For assistance, please contact
FERC Online Support at FERCOnlineSupport@ferc.gov; call toll-free at
(866) 208-3676; or, for TTY, contact (202) 502-8659. Although the
Commission strongly encourages electronic filing, documents may also be
paper-filed. To paper-file, mail an original and eight copies to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
The Commission's Rules of Practice and Procedure require all
interveners filing documents with the Commission to serve a copy of
that document on each person on the official service list for the
project. Further, if an intervener files comments or documents with the
Commission relating to the merits of an issue that may affect the
responsibilities of a particular resource agency, they must also serve
a copy of the document on that resource agency.
k. This application has been accepted for filing, but is not ready
for environmental analysis at this time.
l. The proposed 2.0-megawatt Inglis Hydropower Project would
operate in a run-of-river mode by using flows released to maintain the
surface elevation of Lake Rousseau at 27.5 feet mean sea level. Flow
releases would be determined by the Southwest Florida Water Management
District. The proposed powerhouse would be 60 feet long by 80 feet wide
by 30 feet high, and contain three vertical shaft turbines. The
penstock would be 130 feet in length. The project would generate about
12,300,000 kilowatt hours annually, which would be fed into the
interconnected transmission system via an existing 3.4-mile-long,
12,470-kilovolt transmission line.
m. A copy of the application is available for review at the
Commission in the Public Reference Room, or may be viewed on the
Commission's Web site at https://www.ferc.gov, using the ``eLibrary''
link. Enter the docket number, excluding the last three digits in the
docket number field, to access the document. For assistance, contact
FERC Online Support. A copy is also available for inspection and
reproduction at the address in item h above.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via e-mail of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
n. Any qualified applicant desiring to file a competing application
must submit to the Commission, on or before the specified intervention
deadline date, a competing development application no later than 120
days after the specified intervention deadline date. Applications for
preliminary permits will not be accepted in response to this notice.
A notice of intent must specify the exact name, business address,
and telephone number of the prospective applicant, and must include an
unequivocal statement of intent to submit a development application. A
notice of intent must be served on the applicant(s) names in this
public notice.
Anyone may submit a protest or a motion to intervene in accordance
with the requirements of Rules of Practice and Procedure, 18 CFR
385.210, 385.211, and 385.214. In determining the appropriate action to
take, the Commission will consider all protests filed, but only those
who file a motion to intervene in accordance with the Commission's
Rules may become a party to the proceeding. Any protests or motions to
intervene must be received on, or before, the specified deadline date
for the particular application.
When the application is ready for environmental analysis, the
Commission will issue a public notice requesting comments,
recommendations, terms and conditions, or prescriptions.
All filings must: (1) Bear in all capital letters the title
``PROTEST'' or ``MOTION TO INTERVENE;'' (2) set forth in the heading
the name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person protesting or intervening; and (4) otherwise
comply with the requirements of 18 CFR 385.2001 through 385.2005.
Agencies may obtain copies of the application directly from the
applicant. A copy of any protest or motion to intervene must be served
upon each representative of the applicant specified in the particular
application.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010-4621 Filed 3-4-10; 8:45 am]
BILLING CODE 6717-01-P