Notice; Applications and Amendments to Facility Operating Licenses Involving Proposed No Significant Hazards Considerations and Containing Sensitive Unclassified Non-Safeguards Information and Order Imposing Procedures for Access to Sensitive Unclassified Non-Safeguards Information, 9445-9449 [2010-3988]
Download as PDF
Federal Register / Vol. 75, No. 40 / Tuesday, March 2, 2010 / Notices
NUCLEAR REGULATORY
COMMISSION
[NRC–2010–0054]
Notice; Applications and Amendments
to Facility Operating Licenses
Involving Proposed No Significant
Hazards Considerations and
Containing Sensitive Unclassified NonSafeguards Information and Order
Imposing Procedures for Access to
Sensitive Unclassified Non-Safeguards
Information
I. Background
Pursuant to section 189a.(2) of the
Atomic Energy Act of 1954, as amended
(the Act), the U.S. Nuclear Regulatory
Commission (the Commission or NRC
staff) is publishing this notice. The Act
requires the Commission publish notice
of any amendments issued, or proposed
to be issued and grants the Commission
the authority to issue and make
immediately effective any amendment
to an operating license upon a
determination by the Commission that
such amendment involves no significant
hazards consideration, notwithstanding
the pendency before the Commission of
a request for a hearing from any person.
This notice includes notices of
amendments containing sensitive
unclassified non-safeguards information
(SUNSI).
WReier-Aviles on DSKGBLS3C1PROD with NOTICES
Notice of Consideration of Issuance of
Amendments to Facility Operating
Licenses, Proposed No Significant
Hazards Consideration Determination,
and Opportunity for a Hearing
The Commission has made a
proposed determination that the
following amendment requests involve
no significant hazards consideration.
Under the Commission’s regulations in
Title 10 of the Code of Federal
Regulations (10 CFR), Section 50.92,
this means that operation of the facility
in accordance with the proposed
amendment would not (1) involve a
significant increase in the probability or
consequences of an accident previously
evaluated; or (2) create the possibility of
a new or different kind of accident from
any accident previously evaluated; or
(3) involve a significant reduction in a
margin of safety. The basis for this
proposed determination for each
amendment request is shown below.
The Commission is seeking public
comments on this proposed
determination. Any comments received
within 30 days after the date of
publication of this notice will be
considered in making any final
determination.
VerDate Nov<24>2008
15:07 Mar 01, 2010
Jkt 220001
Normally, the Commission will not
issue the amendment until the
expiration of 60 days after the date of
publication of this notice. The
Commission may issue the license
amendment before expiration of the 60day period provided that its final
determination is that the amendment
involves no significant hazards
consideration. In addition, the
Commission may issue the amendment
prior to the expiration of the 30-day
comment period should circumstances
change during the 30-day comment
period such that failure to act in a
timely way would result, for example in
derating or shutdown of the facility.
Should the Commission take action
prior to the expiration of either the
comment period or the notice period, it
will publish in the Federal Register a
notice of issuance. Should the
Commission make a final No Significant
Hazards Consideration Determination,
any hearing will take place after
issuance. The Commission expects that
the need to take this action will occur
very infrequently.
Written comments may be submitted
by mail to the Chief, Rulemaking and
Directives Branch (RDB), TWB–05–
B01M, Division of Administrative
Services, Office of Administration, U.S.
Nuclear Regulatory Commission,
Washington, DC 20555–0001, and
should cite the publication date and
page number of this Federal Register
notice. Written comments may also be
faxed to the RDB at 301–492–3446.
Documents may be examined, and/or
copied for a fee, at the NRC’s Public
Document Room (PDR), located at One
White Flint North, Public File Area O1
F21, 11555 Rockville Pike (first floor),
Rockville, Maryland.
Within 60 days after the date of
publication of this notice, any person(s)
whose interest may be affected by this
action may file a request for a hearing
and a petition to intervene with respect
to issuance of the amendment to the
subject facility operating license.
Requests for a hearing and a petition for
leave to intervene shall be filed in
accordance with the Commission’s
‘‘Rules of Practice for Domestic
Licensing Proceedings’’ in 10 CFR Part
2. Interested person(s) should consult a
current copy of 10 CFR 2.309, which is
available at the Commission’s PDR,
located at One White Flint North, Public
File Area O1F21, 11555 Rockville Pike
(first floor), Rockville, Maryland, or at
https://www.nrc.gov/reading-rm/doccollections/cfr/part002/part0020309.html. Publicly available records
will be accessible from the Agencywide
Documents Access and Management
System’s (ADAMS) Public Electronic
PO 00000
Frm 00066
Fmt 4703
Sfmt 4703
9445
Reading Room on the Internet at the
NRC Web site, https://www.nrc.gov/
reading-rm.html. If a request for a
hearing or petition for leave to intervene
is filed within 60 days, the Commission
or a presiding officer designated by the
Commission or by the Chief
Administrative Judge of the Atomic
Safety and Licensing Board Panel, will
rule on the request and/or petition; and
the Secretary or the Chief
Administrative Judge of the Atomic
Safety and Licensing Board will issue a
notice of a hearing or an appropriate
order.
As required by 10 CFR 2.309, a
petition for leave to intervene shall set
forth with particularity the interest of
the petitioner in the proceeding, and
how that interest may be affected by the
results of the proceeding. The petition
should specifically explain the reasons
why intervention should be permitted
with particular reference to the
following general requirements: (1) The
name, address, and telephone number of
the requestor or petitioner; (2) the
nature of the requestor’s/petitioner’s
right under the Act to be made a party
to the proceeding; (3) the nature and
extent of the requestor’s/petitioner’s
property, financial, or other interest in
the proceeding; and (4) the possible
effect of any decision or order which
may be entered in the proceeding on the
requestor’s/petitioner’s interest. The
petition must also set forth the specific
contentions which the requestor/
petitioner seeks to have litigated at the
proceeding.
Each contention must consist of a
specific statement of the issue of law or
fact to be raised or controverted. In
addition, the requestor/petitioner shall
provide a brief explanation of the bases
for the contention and a concise
statement of the alleged facts or expert
opinion which support the contention
and on which the requestor/petitioner
intends to rely in proving the contention
at the hearing. The requestor/petitioner
must also provide references to those
specific sources and documents of
which the petitioner is aware and on
which the requestor/petitioner intends
to rely to establish those facts or expert
opinion. The petition must include
sufficient information to show that a
genuine dispute exists with the
applicant on a material issue of law or
fact. Contentions shall be limited to
matters within the scope of the
amendment under consideration. The
contention must be one which, if
proven, would entitle the requestor/
petitioner to relief. A requestor/
petitioner who fails to satisfy these
requirements with respect to at least one
E:\FR\FM\02MRN1.SGM
02MRN1
WReier-Aviles on DSKGBLS3C1PROD with NOTICES
9446
Federal Register / Vol. 75, No. 40 / Tuesday, March 2, 2010 / Notices
contention will not be permitted to
participate as a party.
Those permitted to intervene become
parties to the proceeding, subject to any
limitations in the order granting leave to
intervene, and have the opportunity to
participate fully in the conduct of the
hearing.
If a hearing is requested, and the
Commission has not made a final
determination on the issue of no
significant hazards consideration, the
Commission will make a final
determination on the issue of no
significant hazards consideration. The
final determination will serve to decide
when the hearing is held. If the final
determination is that the amendment
request involves no significant hazards
consideration, the Commission may
issue the amendment and make it
immediately effective, notwithstanding
the request for a hearing. Any hearing
held would take place after issuance of
the amendment. If the final
determination is that the amendment
request involves a significant hazards
consideration, any hearing held would
take place before the issuance of any
amendment.
All documents filed in NRC
adjudicatory proceedings, including a
request for hearing, a petition for leave
to intervene, any motion or other
document filed in the proceeding prior
to the submission of a request for
hearing or petition to intervene, and
documents filed by interested
governmental entities participating
under 10 CFR 2.315(c), must be filed in
accordance with the NRC E-Filing rule
(72 FR 49139, August 28, 2007). The
E-Filing process requires participants to
submit and serve all adjudicatory
documents over the internet, or in some
cases to mail copies on electronic
storage media. Participants may not
submit paper copies of their filings
unless they seek an exemption in
accordance with the procedures
described below.
To comply with the procedural
requirements of E-Filing, at least ten
(10) days prior to the filing deadline, the
participant should contact the Office of
the Secretary by e-mail at
hearing.docket@nrc.gov, or by telephone
at (301) 415–1677, to request (1) a
digital ID certificate, which allows the
participant (or its counsel or
representative) to digitally sign
documents and access the E-Submittal
server for any proceeding in which it is
participating; and (2) advise the
Secretary that the participant will be
submitting a request or petition for
hearing (even in instances in which the
participant, or its counsel or
representative, already holds an NRC-
VerDate Nov<24>2008
15:07 Mar 01, 2010
Jkt 220001
issued digital ID certificate). Based upon
this information, the Secretary will
establish an electronic docket for the
hearing in this proceeding if the
Secretary has not already established an
electronic docket.
Information about applying for a
digital ID certificate is available on
NRC’s public Web site at https://
www.nrc.gov/site-help/e-submittals/
apply-certificates.html. System
requirements for accessing the ESubmittal server are detailed in NRC’s
‘‘Guidance for Electronic Submission,’’
which is available on the agency’s
public Web site at https://www.nrc.gov/
site-help/e-submittals.html. Participants
may attempt to use other software not
listed on the Web site, but should note
that the NRC’s E-Filing system does not
support unlisted software, and the NRC
Meta System Help Desk will not be able
to offer assistance in using unlisted
software.
If a participant is electronically
submitting a document to the NRC in
accordance with the E-Filing rule, the
participant must file the document
using the NRC’s online, Web-based
submission form. In order to serve
documents through EIE, users will be
required to install a Web browser plugin from the NRC Web site. Further
information on the Web-based
submission form, including the
installation of the Web browser plug-in,
is available on the NRC’s public Web
site at https://www.nrc.gov/site-help/esubmittals.html.
Once a participant has obtained a
digital ID certificate and a docket has
been created, the participant can then
submit a request for hearing or petition
for leave to intervene. Submissions
should be in Portable Document Format
(PDF) in accordance with NRC guidance
available on the NRC public Web site at
https://www.nrc.gov/site-help/esubmittals.html. A filing is considered
complete at the time the documents are
submitted through the NRC’s E-Filing
system. To be timely, an electronic
filing must be submitted to the E-Filing
system no later than 11:59 p.m. Eastern
Time on the due date. Upon receipt of
a transmission, the E-Filing system
time-stamps the document and sends
the submitter an e-mail notice
confirming receipt of the document. The
E-Filing system also distributes an email notice that provides access to the
document to the NRC Office of the
General Counsel and any others who
have advised the Office of the Secretary
that they wish to participate in the
proceeding, so that the filer need not
serve the documents on those
participants separately. Therefore,
applicants and other participants (or
PO 00000
Frm 00067
Fmt 4703
Sfmt 4703
their counsel or representative) must
apply for and receive a digital ID
certificate before a hearing request/
petition to intervene is filed so that they
can obtain access to the document via
the E-Filing system.
A person filing electronically using
the agency’s adjudicatory E-Filing
system may seek assistance by
contacting the NRC Meta System Help
Desk through the ‘‘Contact Us’’ link
located on the NRC Web site at https://
www.nrc.gov/site-help/esubmittals.html, by e-mail at
MSHD.Resource@nrc.gov, or by a tollfree call at (866) 672–7640. The NRC
Meta System Help Desk is available
between 8 a.m. and 8 p.m., Eastern
Time, Monday through Friday,
excluding government holidays.
Participants who believe that they
have a good cause for not submitting
documents electronically must file an
exemption request, in accordance with
10 CFR 2.302(g), with their initial paper
filing requesting authorization to
continue to submit documents in paper
format. Such filings must be submitted
by: (1) First class mail addressed to the
Office of the Secretary of the
Commission, U.S. Nuclear Regulatory
Commission, Washington, DC 20555–
0001, Attention: Rulemaking and
Adjudications Staff; or (2) courier,
express mail, or expedited delivery
service to the Office of the Secretary,
Sixteenth Floor, One White Flint North,
11555 Rockville Pike, Rockville,
Maryland, 20852, Attention:
Rulemaking and Adjudications Staff.
Participants filing a document in this
manner are responsible for serving the
document on all other participants.
Filing is considered complete by firstclass mail as of the time of deposit in
the mail, or by courier, express mail, or
expedited delivery service upon
depositing the document with the
provider of the service. A presiding
officer, having granted an exemption
request from using E-Filing, may require
a participant or party to use E-Filing if
the presiding officer subsequently
determines that the reason for granting
the exemption from use of E-Filing no
longer exists.
Documents submitted in adjudicatory
proceedings will appear in NRC’s
electronic hearing docket which is
available to the public at https://
ehd.nrc.gov/EHD_Proceeding/home.asp,
unless excluded pursuant to an order of
the Commission, or the presiding
officer. Participants are requested not to
include personal privacy information,
such as social security numbers, home
addresses, or home phone numbers in
their filings, unless an NRC regulation
or other law requires submission of such
E:\FR\FM\02MRN1.SGM
02MRN1
Federal Register / Vol. 75, No. 40 / Tuesday, March 2, 2010 / Notices
WReier-Aviles on DSKGBLS3C1PROD with NOTICES
information. With respect to
copyrighted works, except for limited
excerpts that serve the purpose of the
adjudicatory filings and would
constitute a Fair Use application,
participants are requested not to include
copyrighted materials in their
submission.
Petitions for leave to intervene must
be filed no later than 60 days from the
date of publication of this notice. Nontimely filings will not be entertained
absent a determination by the presiding
officer that the petition or request
should be granted or the contentions
should be admitted, based on a
balancing of the factors specified in 10
CFR 2.309(c)(1)(i)–(viii).
For further details with respect to this
amendment action, see the application
for amendment which is available for
public inspection at the Commission’s
PDR, located at One White Flint North,
Public File Area 01F21, 11555 Rockville
Pike (first floor), Rockville, Maryland.
Publicly available records will be
accessible electronically from the
ADAMS Public Electronic Reading
Room on the Internet at the NRC Web
site, https://www.nrc.gov/reading-rm/
adams.html. If you do not have access
to ADAMS or if there are problems in
accessing the documents located in
ADAMS, contact the PDR Reference
staff at 1–800–397–4209, 301–415–4737,
or by e-mail to pdr.resource@nrc.gov.
PSEG Nuclear LLC, Docket No. 50–354,
Hope Creek Generating Station, Salem
County, New Jersey
Date of amendment request:
December 21, 2009.
Description of amendment request:
This amendment request contains
sensitive unclassified non-safeguards
information (SUNSI). The proposed
amendment would allow the production
of Cobalt-60 (Co-60) by irradiating
Cobalt-59 targets located in modified
fuel assemblies called Isotope Test
Assemblies (ITAs). The amendment
would allow the licensee to load up to
12 ITAs into the Hope Creek Generating
Station (HCGS) reactor core beginning
with the fall 2010 refueling outage. The
modified fuel assemblies, also referred
to as GE14i ITAs, are planned to be in
operation as part of a joint pilot program
with Global Nuclear Fuel—Americas,
LLC and GE—Hitachi Nuclear Energy
Americas, LLC (GEH). The purpose of
the pilot program is to obtain data to
verify that the modified fuel assemblies
perform satisfactorily in service prior to
use on a production basis. The Co-60 is
ultimately intended for use in the
medical industry for use in cancer
treatments, and blood and instrument
sterilization; in the radiography and
VerDate Nov<24>2008
15:07 Mar 01, 2010
Jkt 220001
security industries for imaging; and in
the food industry for cold pasteurization
and irradiation sterilization.
Basis for proposed no significant
hazards consideration determination:
As required by 10 CFR 50.91(a), the
licensee has provided its analysis of the
issue of no significant hazards
consideration, which is presented
below:
1. Does the proposed amendment involve
a significant increase in the probability or
consequences of an accident previously
evaluated?
Response: No.
The proposed changes to the license
conditions provide clarification and do not
impact plant operation in any manner. The
handling of byproduct material (i.e., Co-60)
will continue to be done in accordance with
the requirements of 10 CFR 30 and the
requirements of the HCGS Facility Operating
License. The proposed change to [Technical
Specification (TS)] 5.3.1 provides
clarification and additional description of the
proposed ITAs to be used in the HCGS core.
These changes do not involve an increase in
the probability or consequences of an
accident previously evaluated.
The use of the GE14i ITAs, has been
evaluated for impact on the previously
evaluated transients and design basis
accidents for HCGS. GEH Safety Analysis
Report—NEDC–33529P, ‘‘Safety Analysis
Report to Support Introduction of GE14i
Isotope Test Assemblies (ITAs) in Hope
Creek Generating Station,’’ dated December
2009, documents the results of the analyses
completed to demonstrate the impact on
operation following introduction of the ITAs
in the HCGS core. The use of these ITAs does
not adversely affect accident initiators or
precursors, design assumptions, or the
manner in which the plant is operated and
maintained. The Cycle 17 (i.e., the first cycle
of operation with the GE14i assembly) core
will be designed so that the ITAs will be
placed in non-limiting locations with respect
to thermal limit margins or shutdown
margins. The ITAs do not adversely affect the
ability of any structures, systems or
components (SSCs) to perform their intended
safety function to mitigate the consequences
of an initiating event within the assumed
acceptance limits.
PSEG has also evaluated the effects of these
ITAs on post-irradiation conditions. The
additional heat from the Co-60 decay is
insignificant when compared to the total heat
from a normal refueling discharge. The small
amount of extra heat added by the cobalt
isotope rods poses no additional risk of spent
fuel pool (SFP) local boiling over that
previously analyzed. The maximum incident
radiation due to an irradiated GE14i bundle
placed one foot from the spent fuel pool
walls is in excess of the radiation that would
result in significant gamma heating of the
concrete. However, analysis has
demonstrated that at four feet, the energy
deposition rate is well below that required to
cause significant concrete heating. HCGS
procedures exist to guide placement of
irradiated fuel bundles in the SFP to avoid
gamma heating of the wall concrete. These
PO 00000
Frm 00068
Fmt 4703
Sfmt 4703
9447
procedures will be modified to specify that
irradiated GE14i bundles must be stored at
least four feet from the SFP walls. With the
four foot distance requirement in effect, there
is no limitation on the amount of time an
irradiated GE14i bundle can be stored in the
SFP.
Handling of the licensed transfer casks will
be in accordance with the guidance in
NUREG 0612, ‘‘Control of Heavy Loads at
Nuclear Power Plants,’’ using the Reactor
Building crane. These precautions will
support safe movement of the casks within
the Reactor Building.
The consequences of a previously analyzed
event are dependent on the initial conditions
assumed in the analysis, the availability and
successful functioning of equipment assumed
to operate in response to the analyzed event,
and the setpoints at which these actions are
initiated. The consequences of a previously
evaluated accident are not significantly
increased by the proposed change. As
documented in NEDC–33529P, the proposed
change does not affect the performance of
any equipment credited to mitigate the
radiological consequences of an accident.
Evaluation of operation with the GE14i
assemblies in the HCGS core demonstrated
that the licensing basis radiological analyses
are not adversely impacted by the
introduction of twelve GE14i assemblies at
HCGS. This includes the analyses done for
the transients and design basis accident
events.
Therefore, the proposed change does not
involve a significant increase in the
probability or consequences of an accident
previously evaluated.
2. Does the proposed amendment create
the possibility of a new or different kind of
accident from any accident previously
evaluated?
Response: No.
The proposed revision to the HCGS license
conditions and TS 5.3.1 will not introduce
any new or modified equipment since these
changes are intended to provide clarification
only. These clarifications will not result in
operation of the facility in a different way
than currently operated.
While the proposed ITA pilot program
does result in the introduction of several
modified fuel bundles (the GE14i assemblies)
these assemblies are essentially the same as
the GE14 assemblies currently in use in the
HCGS core. The only difference is the use of
a number of cobalt isotope rods in place of
fuel rods. The GE14i assembly was designed
for mechanical, nuclear, and thermalhydraulic compatibility with the GE14 fuel
design. The details of the design differences
between GE14 and GE14i are documented in
NEDC–33529P. Use of the proposed ITAs
does not involve the addition or modification
of any plant equipment other than the
bundles modified to include the cobalt
isotope rods. Also, use of the proposed ITAs
will not alter the design configuration or
method of operation of plant equipment
beyond its normal functional capabilities.
The ITA pilot program does not create any
new credible failure mechanisms,
malfunctions or accident initiators.
Therefore, the proposed change does not
create the possibility of a new or different
E:\FR\FM\02MRN1.SGM
02MRN1
9448
Federal Register / Vol. 75, No. 40 / Tuesday, March 2, 2010 / Notices
kind of accident from any previously
evaluated.
3. Does the proposed amendment involve
a significant reduction in a margin of safety?
Response: No.
The proposed changes to the HCGS
operating license conditions are intended to
provide clarification as to how the generation
of byproduct material in the HCGS reactor
core meets the requirements of 10 CFR Part
30. The proposed change to TS 5.3.1 also
provides clarification and additional
description of the proposed ITAs to be used
in the HCGS core. These proposed changes
will not affect the design or operation of any
equipment important to safety. In addition,
the proposed changes to the license
conditions and TS do not affect the results
of any safety calculations.
Cycle independent analyses documented
in NEDC–33529P show that the acceptance
criteria for the safety analyses are not affected
and are met. Cycle specific analyses for the
ITAs will be performed as described in
NEDC–33529P to establish fuel operating
requirements that assure compliance with
regulatory limits.
The proposed ITA pilot program has no
impact on equipment design or fundamental
operation, other than the modifications made
to the fuel assembly as part of the program.
The GE14i ITAs meet the same fuel design
and licensing criteria as GE14 bundles. There
are no changes being made to safety limits or
safety system allowable values that would
adversely affect plant safety as a result of the
proposed ITAs. The performance of the
systems important to safety is not affected by
the use of the proposed ITAs. The proposed
change does not adversely affect safety
analysis assumptions, initial conditions, or
acceptance criteria and therefore, the margin
of safety in the original safety analyses is
maintained.
Therefore, the proposed change does not
involve a significant reduction in a margin of
safety.
WReier-Aviles on DSKGBLS3C1PROD with NOTICES
The NRC staff has reviewed the
licensee’s analysis and, based on this
review, it appears that the three
standards of 10 CFR 50.92(c) are
satisfied. Therefore, the NRC staff
proposes to determine that the
amendment request involves no
significant hazards consideration.
Attorney for licensee: Vincent
Zabielski, PSEG Nuclear LLC—N21,
P.O. Box 236, Hancocks Bridge, NJ
08038.
NRC Branch Chief: Harold K.
Chernoff.
Order Imposing Procedures for Access
to Sensitive Unclassified NonSafeguards Information for Contention
Preparation
PSEG Nuclear LLC, Docket No. 50–354,
Hope Creek Generating Station, Salem
County, New Jersey
A. This Order contains instructions
regarding how potential parties to this
proceeding may request access to
documents containing Sensitive
VerDate Nov<24>2008
15:07 Mar 01, 2010
Jkt 220001
Unclassified Non-Safeguards
Information (SUNSI).
B. Within 10 days after publication of
this notice of hearing and opportunity to
petition for leave to intervene, any
potential party who believes access to
SUNSI is necessary to respond to this
notice may request such access. A
‘‘potential party’’ is any person who
intends to participate as a party by
demonstrating standing and filing an
admissible contention under 10 CFR
2.309. Requests for access to SUNSI
submitted later than 10 days after
publication will not be considered
absent a showing of good cause for the
late filing, addressing why the request
could not have been filed earlier.
C. The requestor shall submit a letter
requesting permission to access SUNSI
to the Office of the Secretary, U.S.
Nuclear Regulatory Commission,
Washington, DC 20555–0001, Attention:
Rulemakings and Adjudications Staff,
and provide a copy to the Associate
General Counsel for Hearings,
Enforcement and Administration, Office
of the General Counsel, Washington, DC
20555–0001. The expedited delivery or
courier mail address for both offices is:
U.S. Nuclear Regulatory Commission,
11555 Rockville Pike, Rockville,
Maryland 20852. The e-mail address for
the Office of the Secretary and the
Office of the General Counsel are
Hearing.Docket@nrc.gov and
OGCmailcenter@nrc.gov, respectively.1
The request must include the following
information:
(1) A description of the licensing
action with a citation to this Federal
Register notice;
(2) The name and address of the
potential party and a description of the
potential party’s particularized interest
that could be harmed by the action
identified in C.(1);
(3) The identity of the individual or
entity requesting access to SUNSI and
the requestor’s basis for the need for the
information in order to meaningfully
participate in this adjudicatory
proceeding. In particular, the request
must explain why publicly-available
versions of the information requested
would not be sufficient to provide the
basis and specificity for a proffered
contention;
D. Based on an evaluation of the
information submitted under paragraph
C.(3) the NRC staff will determine
within 10 days of receipt of the request
whether:
(1) There is a reasonable basis to
believe the petitioner is likely to
establish standing to participate in this
NRC proceeding; and
(2) The requestor has established a
legitimate need for access to SUNSI.
E. If the NRC staff determines that the
requestor satisfies both D.(1) and D.(2)
above, the NRC staff will notify the
requestor in writing that access to
SUNSI has been granted. The written
notification will contain instructions on
how the requestor may obtain copies of
the requested documents, and any other
conditions that may apply to access to
those documents. These conditions may
include, but are not limited to, the
signing of a Non-Disclosure Agreement
or Affidavit, or Protective Order 2 setting
forth terms and conditions to prevent
the unauthorized or inadvertent
disclosure of SUNSI by each individual
who will be granted access to SUNSI.
F. Filing of Contentions. Any
contentions in these proceedings that
are based upon the information received
as a result of the request made for
SUNSI must be filed by the requestor no
later than 25 days after the requestor is
granted access to that information.
However, if more than 25 days remain
between the date the petitioner is
granted access to the information and
the deadline for filing all other
contentions (as established in the notice
of hearing or opportunity for hearing),
the petitioner may file its SUNSI
contentions by that later deadline.
G. Review of Denials of Access.
(1) If the request for access to SUNSI
is denied by the NRC staff either after
a determination on standing and need
for access, or after a determination on
trustworthiness and reliability, the NRC
staff shall immediately notify the
requestor in writing, briefly stating the
reason or reasons for the denial.
(2) The requestor may challenge the
NRC staff’s adverse determination by
filing a challenge within 5 days of
receipt of that determination with: (a)
The presiding officer designated in this
proceeding; (b) if no presiding officer
has been appointed, the Chief
Administrative Judge, or if he or she is
unavailable, another administrative
judge, or an administrative law judge
with jurisdiction pursuant to 10 CFR
2.318(a); or (c) if another officer has
been designated to rule on information
access issues, with that officer.
H. Review of Grants of Access. A
party other than the requestor may
1 While a request for hearing or petition to
intervene in this proceeding must comply with the
filing requirements of the NRC’s ‘‘E-Filing Rule,’’ the
initial request to access SUNSI under these
procedures should be submitted as described in this
paragraph.
2 Any motion for Protective Order or draft NonDisclosure Affidavit or Agreement for SUNSI must
be filed with the presiding officer or the Chief
Administrative Judge if the presiding officer has not
yet been designated, within 30 days of the deadline
for the receipt of the written access request.
PO 00000
Frm 00069
Fmt 4703
Sfmt 4703
E:\FR\FM\02MRN1.SGM
02MRN1
Federal Register / Vol. 75, No. 40 / Tuesday, March 2, 2010 / Notices
challenge an NRC staff determination
granting access to SUNSI whose release
would harm that party’s interest
independent of the proceeding. Such a
challenge must be filed with the Chief
Administrative Judge within 5 days of
the notification by the NRC staff of its
grant of access.
If challenges to the NRC staff
determinations are filed, these
procedures give way to the normal
process for litigating disputes
concerning access to information. The
availability of interlocutory review by
the Commission of orders ruling on
such NRC staff determinations (whether
granting or denying access) is governed
by 10 CFR 2.311.3
I. The Commission expects that the
NRC staff and presiding officers (and
any other reviewing officers) will
consider and resolve requests for access
to SUNSI, and motions for protective
orders, in a timely fashion in order to
minimize any unnecessary delays in
identifying those petitioners who have
standing and who have propounded
contentions meeting the specificity and
basis requirements in 10 CFR Part 2.
Attachment 1 to this Order summarizes
9449
the general target schedule for
processing and resolving requests under
these procedures.
It is so ordered.
Dated at Rockville, Maryland, this 22nd
day of February 2010.
For the Commission.
Annette L. Vietti-Cook,
Secretary of the Commission.
ATTACHMENT 1—General Target
Schedule for Processing and Resolving
Requests for Access to Sensitive
Unclassified Non-Safeguards
Information in This Proceeding
Day
Event/activity
0 ........................
Publication of Federal Register notice of hearing and opportunity to petition for leave to intervene, including order with instructions for access requests.
Deadline for submitting requests for access to Sensitive Unclassified Non-Safeguards Information (SUNSI) with information:
supporting the standing of a potential party identified by name and address; describing the need for the information in order
for the potential party to participate meaningfully in an adjudicatory proceeding.
Deadline for submitting petition for intervention containing: (i) Demonstration of standing; (ii) all contentions whose formulation
does not require access to SUNSI (+25 Answers to petition for intervention; +7 requestor/petitioner reply).
Nuclear Regulatory Commission (NRC) staff informs the requestor of the staff’s determination whether the request for access
provides a reasonable basis to believe standing can be established and shows need for SUNSI. (NRC staff also informs
any party to the proceeding whose interest independent of the proceeding would be harmed by the release of the information.) If NRC staff makes the finding of need for SUNSI and likelihood of standing, NRC staff begins document processing
(preparation of redactions or review of redacted documents).
If NRC staff finds no ‘‘need’’ or no likelihood of standing, the deadline for requestor/petitioner to file a motion seeking a ruling
to reverse the NRC staff’s denial of access; NRC staff files copy of access determination with the presiding officer (or Chief
Administrative Judge or other designated officer, as appropriate). If NRC staff finds ‘‘need’’ for SUNSI, the deadline for any
party to the proceeding whose interest independent of the proceeding would be harmed by the release of the information to
file a motion seeking a ruling to reverse the NRC staff’s grant of access.
Deadline for NRC staff reply to motions to reverse NRC staff determination(s).
(Receipt +30) If NRC staff finds standing and need for SUNSI, deadline for NRC staff to complete information processing and
file motion for Protective Order and draft Non-Disclosure Affidavit. Deadline for applicant/licensee to file Non-Disclosure
Agreement for SUNSI.
If access granted: Issuance of presiding officer or other designated officer decision on motion for protective order for access
to sensitive information (including schedule for providing access and submission of contentions) or decision reversing a
final adverse determination by the NRC staff.
Deadline for filing executed Non-Disclosure Affidavits. Access provided to SUNSI consistent with decision issuing the protective order.
Deadline for submission of contentions whose development depends upon access to SUNSI. However, if more than 25 days
remain between the petitioner’s receipt of (or access to) the information and the deadline for filing all other contentions (as
established in the notice of hearing or opportunity for hearing), the petitioner may file its SUNSI contentions by that later
deadline.
(Contention receipt +25) Answers to contentions whose development depends upon access to SUNSI.
(Answer receipt +7) Petitioner/Intervenor reply to answers.
Decision on contention admission.
10 ......................
60 ......................
20 ......................
25 ......................
30 ......................
40 ......................
A .......................
A + 3 .................
A + 28 ...............
A + 53 ...............
A + 60 ...............
>A + 60 .............
[FR Doc. 2010–3988 Filed 3–1–10; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket Nos. 50–338 and 50–339; NRC–
2010–0026
WReier-Aviles on DSKGBLS3C1PROD with NOTICES
Virginia Electric and Power Company;
North Anna Power Station, Unit Nos. 1
and 2
1.0
Background
The Virginia Electric and Power
Company, (the licensee) is the holder of
Facility Operating License Nos. NPF–4
and NPF–7, which authorize operation
3 Requestors should note that the filing
requirements of the NRC’s E–Filing Rule (72 FR
49139; August 28, 2007) apply to appeals of NRC
VerDate Nov<24>2008
15:07 Mar 01, 2010
Jkt 220001
staff determinations (because they must be served
on a presiding officer or the Commission, as
PO 00000
Frm 00070
Fmt 4703
Sfmt 4703
of the North Anna Power Station, Unit
Nos. 1 and 2 (NAPS). The licenses
provide, among other things, that the
facility is subject to all rules,
regulations, and orders of the U.S.
Nuclear Regulatory Commission (NRC,
the Commission) now or hereafter in
effect.
The facility consists of two
pressurized water reactors located in
Louisa County, Virginia.
2.0
Request/Action
Title 10 of the Code of Federal
Regulations (10 CFR) Part 73, ‘‘Physical
applicable), but not to the initial SUNSI request
submitted to the NRC staff under these procedures.
E:\FR\FM\02MRN1.SGM
02MRN1
Agencies
[Federal Register Volume 75, Number 40 (Tuesday, March 2, 2010)]
[Notices]
[Pages 9445-9449]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-3988]
[[Page 9445]]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[NRC-2010-0054]
Notice; Applications and Amendments to Facility Operating
Licenses Involving Proposed No Significant Hazards Considerations and
Containing Sensitive Unclassified Non-Safeguards Information and Order
Imposing Procedures for Access to Sensitive Unclassified Non-Safeguards
Information
I. Background
Pursuant to section 189a.(2) of the Atomic Energy Act of 1954, as
amended (the Act), the U.S. Nuclear Regulatory Commission (the
Commission or NRC staff) is publishing this notice. The Act requires
the Commission publish notice of any amendments issued, or proposed to
be issued and grants the Commission the authority to issue and make
immediately effective any amendment to an operating license upon a
determination by the Commission that such amendment involves no
significant hazards consideration, notwithstanding the pendency before
the Commission of a request for a hearing from any person.
This notice includes notices of amendments containing sensitive
unclassified non-safeguards information (SUNSI).
Notice of Consideration of Issuance of Amendments to Facility Operating
Licenses, Proposed No Significant Hazards Consideration Determination,
and Opportunity for a Hearing
The Commission has made a proposed determination that the following
amendment requests involve no significant hazards consideration. Under
the Commission's regulations in Title 10 of the Code of Federal
Regulations (10 CFR), Section 50.92, this means that operation of the
facility in accordance with the proposed amendment would not (1)
involve a significant increase in the probability or consequences of an
accident previously evaluated; or (2) create the possibility of a new
or different kind of accident from any accident previously evaluated;
or (3) involve a significant reduction in a margin of safety. The basis
for this proposed determination for each amendment request is shown
below.
The Commission is seeking public comments on this proposed
determination. Any comments received within 30 days after the date of
publication of this notice will be considered in making any final
determination.
Normally, the Commission will not issue the amendment until the
expiration of 60 days after the date of publication of this notice. The
Commission may issue the license amendment before expiration of the 60-
day period provided that its final determination is that the amendment
involves no significant hazards consideration. In addition, the
Commission may issue the amendment prior to the expiration of the 30-
day comment period should circumstances change during the 30-day
comment period such that failure to act in a timely way would result,
for example in derating or shutdown of the facility. Should the
Commission take action prior to the expiration of either the comment
period or the notice period, it will publish in the Federal Register a
notice of issuance. Should the Commission make a final No Significant
Hazards Consideration Determination, any hearing will take place after
issuance. The Commission expects that the need to take this action will
occur very infrequently.
Written comments may be submitted by mail to the Chief, Rulemaking
and Directives Branch (RDB), TWB-05-B01M, Division of Administrative
Services, Office of Administration, U.S. Nuclear Regulatory Commission,
Washington, DC 20555-0001, and should cite the publication date and
page number of this Federal Register notice. Written comments may also
be faxed to the RDB at 301-492-3446. Documents may be examined, and/or
copied for a fee, at the NRC's Public Document Room (PDR), located at
One White Flint North, Public File Area O1 F21, 11555 Rockville Pike
(first floor), Rockville, Maryland.
Within 60 days after the date of publication of this notice, any
person(s) whose interest may be affected by this action may file a
request for a hearing and a petition to intervene with respect to
issuance of the amendment to the subject facility operating license.
Requests for a hearing and a petition for leave to intervene shall be
filed in accordance with the Commission's ``Rules of Practice for
Domestic Licensing Proceedings'' in 10 CFR Part 2. Interested person(s)
should consult a current copy of 10 CFR 2.309, which is available at
the Commission's PDR, located at One White Flint North, Public File
Area O1F21, 11555 Rockville Pike (first floor), Rockville, Maryland, or
at https://www.nrc.gov/reading-rm/doc-collections/cfr/part002/part002-0309.html. Publicly available records will be accessible from the
Agencywide Documents Access and Management System's (ADAMS) Public
Electronic Reading Room on the Internet at the NRC Web site, https://www.nrc.gov/reading-rm.html. If a request for a hearing or petition for
leave to intervene is filed within 60 days, the Commission or a
presiding officer designated by the Commission or by the Chief
Administrative Judge of the Atomic Safety and Licensing Board Panel,
will rule on the request and/or petition; and the Secretary or the
Chief Administrative Judge of the Atomic Safety and Licensing Board
will issue a notice of a hearing or an appropriate order.
As required by 10 CFR 2.309, a petition for leave to intervene
shall set forth with particularity the interest of the petitioner in
the proceeding, and how that interest may be affected by the results of
the proceeding. The petition should specifically explain the reasons
why intervention should be permitted with particular reference to the
following general requirements: (1) The name, address, and telephone
number of the requestor or petitioner; (2) the nature of the
requestor's/petitioner's right under the Act to be made a party to the
proceeding; (3) the nature and extent of the requestor's/petitioner's
property, financial, or other interest in the proceeding; and (4) the
possible effect of any decision or order which may be entered in the
proceeding on the requestor's/petitioner's interest. The petition must
also set forth the specific contentions which the requestor/petitioner
seeks to have litigated at the proceeding.
Each contention must consist of a specific statement of the issue
of law or fact to be raised or controverted. In addition, the
requestor/petitioner shall provide a brief explanation of the bases for
the contention and a concise statement of the alleged facts or expert
opinion which support the contention and on which the requestor/
petitioner intends to rely in proving the contention at the hearing.
The requestor/petitioner must also provide references to those specific
sources and documents of which the petitioner is aware and on which the
requestor/petitioner intends to rely to establish those facts or expert
opinion. The petition must include sufficient information to show that
a genuine dispute exists with the applicant on a material issue of law
or fact. Contentions shall be limited to matters within the scope of
the amendment under consideration. The contention must be one which, if
proven, would entitle the requestor/petitioner to relief. A requestor/
petitioner who fails to satisfy these requirements with respect to at
least one
[[Page 9446]]
contention will not be permitted to participate as a party.
Those permitted to intervene become parties to the proceeding,
subject to any limitations in the order granting leave to intervene,
and have the opportunity to participate fully in the conduct of the
hearing.
If a hearing is requested, and the Commission has not made a final
determination on the issue of no significant hazards consideration, the
Commission will make a final determination on the issue of no
significant hazards consideration. The final determination will serve
to decide when the hearing is held. If the final determination is that
the amendment request involves no significant hazards consideration,
the Commission may issue the amendment and make it immediately
effective, notwithstanding the request for a hearing. Any hearing held
would take place after issuance of the amendment. If the final
determination is that the amendment request involves a significant
hazards consideration, any hearing held would take place before the
issuance of any amendment.
All documents filed in NRC adjudicatory proceedings, including a
request for hearing, a petition for leave to intervene, any motion or
other document filed in the proceeding prior to the submission of a
request for hearing or petition to intervene, and documents filed by
interested governmental entities participating under 10 CFR 2.315(c),
must be filed in accordance with the NRC E-Filing rule (72 FR 49139,
August 28, 2007). The E-Filing process requires participants to submit
and serve all adjudicatory documents over the internet, or in some
cases to mail copies on electronic storage media. Participants may not
submit paper copies of their filings unless they seek an exemption in
accordance with the procedures described below.
To comply with the procedural requirements of E-Filing, at least
ten (10) days prior to the filing deadline, the participant should
contact the Office of the Secretary by e-mail at
hearing.docket@nrc.gov, or by telephone at (301) 415-1677, to request
(1) a digital ID certificate, which allows the participant (or its
counsel or representative) to digitally sign documents and access the
E-Submittal server for any proceeding in which it is participating; and
(2) advise the Secretary that the participant will be submitting a
request or petition for hearing (even in instances in which the
participant, or its counsel or representative, already holds an NRC-
issued digital ID certificate). Based upon this information, the
Secretary will establish an electronic docket for the hearing in this
proceeding if the Secretary has not already established an electronic
docket.
Information about applying for a digital ID certificate is
available on NRC's public Web site at https://www.nrc.gov/site-help/e-submittals/apply-certificates.html. System requirements for accessing
the E-Submittal server are detailed in NRC's ``Guidance for Electronic
Submission,'' which is available on the agency's public Web site at
https://www.nrc.gov/site-help/e-submittals.html. Participants may
attempt to use other software not listed on the Web site, but should
note that the NRC's E-Filing system does not support unlisted software,
and the NRC Meta System Help Desk will not be able to offer assistance
in using unlisted software.
If a participant is electronically submitting a document to the NRC
in accordance with the E-Filing rule, the participant must file the
document using the NRC's online, Web-based submission form. In order to
serve documents through EIE, users will be required to install a Web
browser plug-in from the NRC Web site. Further information on the Web-
based submission form, including the installation of the Web browser
plug-in, is available on the NRC's public Web site at https://www.nrc.gov/site-help/e-submittals.html.
Once a participant has obtained a digital ID certificate and a
docket has been created, the participant can then submit a request for
hearing or petition for leave to intervene. Submissions should be in
Portable Document Format (PDF) in accordance with NRC guidance
available on the NRC public Web site at https://www.nrc.gov/site-help/e-submittals.html. A filing is considered complete at the time the
documents are submitted through the NRC's E-Filing system. To be
timely, an electronic filing must be submitted to the E-Filing system
no later than 11:59 p.m. Eastern Time on the due date. Upon receipt of
a transmission, the E-Filing system time-stamps the document and sends
the submitter an e-mail notice confirming receipt of the document. The
E-Filing system also distributes an e-mail notice that provides access
to the document to the NRC Office of the General Counsel and any others
who have advised the Office of the Secretary that they wish to
participate in the proceeding, so that the filer need not serve the
documents on those participants separately. Therefore, applicants and
other participants (or their counsel or representative) must apply for
and receive a digital ID certificate before a hearing request/petition
to intervene is filed so that they can obtain access to the document
via the E-Filing system.
A person filing electronically using the agency's adjudicatory E-
Filing system may seek assistance by contacting the NRC Meta System
Help Desk through the ``Contact Us'' link located on the NRC Web site
at https://www.nrc.gov/site-help/e-submittals.html, by e-mail at
MSHD.Resource@nrc.gov, or by a toll-free call at (866) 672-7640. The
NRC Meta System Help Desk is available between 8 a.m. and 8 p.m.,
Eastern Time, Monday through Friday, excluding government holidays.
Participants who believe that they have a good cause for not
submitting documents electronically must file an exemption request, in
accordance with 10 CFR 2.302(g), with their initial paper filing
requesting authorization to continue to submit documents in paper
format. Such filings must be submitted by: (1) First class mail
addressed to the Office of the Secretary of the Commission, U.S.
Nuclear Regulatory Commission, Washington, DC 20555-0001, Attention:
Rulemaking and Adjudications Staff; or (2) courier, express mail, or
expedited delivery service to the Office of the Secretary, Sixteenth
Floor, One White Flint North, 11555 Rockville Pike, Rockville,
Maryland, 20852, Attention: Rulemaking and Adjudications Staff.
Participants filing a document in this manner are responsible for
serving the document on all other participants. Filing is considered
complete by first-class mail as of the time of deposit in the mail, or
by courier, express mail, or expedited delivery service upon depositing
the document with the provider of the service. A presiding officer,
having granted an exemption request from using E-Filing, may require a
participant or party to use E-Filing if the presiding officer
subsequently determines that the reason for granting the exemption from
use of E-Filing no longer exists.
Documents submitted in adjudicatory proceedings will appear in
NRC's electronic hearing docket which is available to the public at
https://ehd.nrc.gov/EHD_Proceeding/home.asp, unless excluded pursuant
to an order of the Commission, or the presiding officer. Participants
are requested not to include personal privacy information, such as
social security numbers, home addresses, or home phone numbers in their
filings, unless an NRC regulation or other law requires submission of
such
[[Page 9447]]
information. With respect to copyrighted works, except for limited
excerpts that serve the purpose of the adjudicatory filings and would
constitute a Fair Use application, participants are requested not to
include copyrighted materials in their submission.
Petitions for leave to intervene must be filed no later than 60
days from the date of publication of this notice. Non-timely filings
will not be entertained absent a determination by the presiding officer
that the petition or request should be granted or the contentions
should be admitted, based on a balancing of the factors specified in 10
CFR 2.309(c)(1)(i)-(viii).
For further details with respect to this amendment action, see the
application for amendment which is available for public inspection at
the Commission's PDR, located at One White Flint North, Public File
Area 01F21, 11555 Rockville Pike (first floor), Rockville, Maryland.
Publicly available records will be accessible electronically from the
ADAMS Public Electronic Reading Room on the Internet at the NRC Web
site, https://www.nrc.gov/reading-rm/adams.html. If you do not have
access to ADAMS or if there are problems in accessing the documents
located in ADAMS, contact the PDR Reference staff at 1-800-397-4209,
301-415-4737, or by e-mail to pdr.resource@nrc.gov.
PSEG Nuclear LLC, Docket No. 50-354, Hope Creek Generating Station,
Salem County, New Jersey
Date of amendment request: December 21, 2009.
Description of amendment request: This amendment request contains
sensitive unclassified non-safeguards information (SUNSI). The proposed
amendment would allow the production of Cobalt-60 (Co-60) by
irradiating Cobalt-59 targets located in modified fuel assemblies
called Isotope Test Assemblies (ITAs). The amendment would allow the
licensee to load up to 12 ITAs into the Hope Creek Generating Station
(HCGS) reactor core beginning with the fall 2010 refueling outage. The
modified fuel assemblies, also referred to as GE14i ITAs, are planned
to be in operation as part of a joint pilot program with Global Nuclear
Fuel--Americas, LLC and GE--Hitachi Nuclear Energy Americas, LLC (GEH).
The purpose of the pilot program is to obtain data to verify that the
modified fuel assemblies perform satisfactorily in service prior to use
on a production basis. The Co-60 is ultimately intended for use in the
medical industry for use in cancer treatments, and blood and instrument
sterilization; in the radiography and security industries for imaging;
and in the food industry for cold pasteurization and irradiation
sterilization.
Basis for proposed no significant hazards consideration
determination: As required by 10 CFR 50.91(a), the licensee has
provided its analysis of the issue of no significant hazards
consideration, which is presented below:
1. Does the proposed amendment involve a significant increase in
the probability or consequences of an accident previously evaluated?
Response: No.
The proposed changes to the license conditions provide
clarification and do not impact plant operation in any manner. The
handling of byproduct material (i.e., Co-60) will continue to be
done in accordance with the requirements of 10 CFR 30 and the
requirements of the HCGS Facility Operating License. The proposed
change to [Technical Specification (TS)] 5.3.1 provides
clarification and additional description of the proposed ITAs to be
used in the HCGS core. These changes do not involve an increase in
the probability or consequences of an accident previously evaluated.
The use of the GE14i ITAs, has been evaluated for impact on the
previously evaluated transients and design basis accidents for HCGS.
GEH Safety Analysis Report--NEDC-33529P, ``Safety Analysis Report to
Support Introduction of GE14i Isotope Test Assemblies (ITAs) in Hope
Creek Generating Station,'' dated December 2009, documents the
results of the analyses completed to demonstrate the impact on
operation following introduction of the ITAs in the HCGS core. The
use of these ITAs does not adversely affect accident initiators or
precursors, design assumptions, or the manner in which the plant is
operated and maintained. The Cycle 17 (i.e., the first cycle of
operation with the GE14i assembly) core will be designed so that the
ITAs will be placed in non-limiting locations with respect to
thermal limit margins or shutdown margins. The ITAs do not adversely
affect the ability of any structures, systems or components (SSCs)
to perform their intended safety function to mitigate the
consequences of an initiating event within the assumed acceptance
limits.
PSEG has also evaluated the effects of these ITAs on post-
irradiation conditions. The additional heat from the Co-60 decay is
insignificant when compared to the total heat from a normal
refueling discharge. The small amount of extra heat added by the
cobalt isotope rods poses no additional risk of spent fuel pool
(SFP) local boiling over that previously analyzed. The maximum
incident radiation due to an irradiated GE14i bundle placed one foot
from the spent fuel pool walls is in excess of the radiation that
would result in significant gamma heating of the concrete. However,
analysis has demonstrated that at four feet, the energy deposition
rate is well below that required to cause significant concrete
heating. HCGS procedures exist to guide placement of irradiated fuel
bundles in the SFP to avoid gamma heating of the wall concrete.
These procedures will be modified to specify that irradiated GE14i
bundles must be stored at least four feet from the SFP walls. With
the four foot distance requirement in effect, there is no limitation
on the amount of time an irradiated GE14i bundle can be stored in
the SFP.
Handling of the licensed transfer casks will be in accordance
with the guidance in NUREG 0612, ``Control of Heavy Loads at Nuclear
Power Plants,'' using the Reactor Building crane. These precautions
will support safe movement of the casks within the Reactor Building.
The consequences of a previously analyzed event are dependent on
the initial conditions assumed in the analysis, the availability and
successful functioning of equipment assumed to operate in response
to the analyzed event, and the setpoints at which these actions are
initiated. The consequences of a previously evaluated accident are
not significantly increased by the proposed change. As documented in
NEDC-33529P, the proposed change does not affect the performance of
any equipment credited to mitigate the radiological consequences of
an accident. Evaluation of operation with the GE14i assemblies in
the HCGS core demonstrated that the licensing basis radiological
analyses are not adversely impacted by the introduction of twelve
GE14i assemblies at HCGS. This includes the analyses done for the
transients and design basis accident events.
Therefore, the proposed change does not involve a significant
increase in the probability or consequences of an accident
previously evaluated.
2. Does the proposed amendment create the possibility of a new
or different kind of accident from any accident previously
evaluated?
Response: No.
The proposed revision to the HCGS license conditions and TS
5.3.1 will not introduce any new or modified equipment since these
changes are intended to provide clarification only. These
clarifications will not result in operation of the facility in a
different way than currently operated.
While the proposed ITA pilot program does result in the
introduction of several modified fuel bundles (the GE14i assemblies)
these assemblies are essentially the same as the GE14 assemblies
currently in use in the HCGS core. The only difference is the use of
a number of cobalt isotope rods in place of fuel rods. The GE14i
assembly was designed for mechanical, nuclear, and thermal-hydraulic
compatibility with the GE14 fuel design. The details of the design
differences between GE14 and GE14i are documented in NEDC-33529P.
Use of the proposed ITAs does not involve the addition or
modification of any plant equipment other than the bundles modified
to include the cobalt isotope rods. Also, use of the proposed ITAs
will not alter the design configuration or method of operation of
plant equipment beyond its normal functional capabilities. The ITA
pilot program does not create any new credible failure mechanisms,
malfunctions or accident initiators.
Therefore, the proposed change does not create the possibility
of a new or different
[[Page 9448]]
kind of accident from any previously evaluated.
3. Does the proposed amendment involve a significant reduction
in a margin of safety?
Response: No.
The proposed changes to the HCGS operating license conditions
are intended to provide clarification as to how the generation of
byproduct material in the HCGS reactor core meets the requirements
of 10 CFR Part 30. The proposed change to TS 5.3.1 also provides
clarification and additional description of the proposed ITAs to be
used in the HCGS core. These proposed changes will not affect the
design or operation of any equipment important to safety. In
addition, the proposed changes to the license conditions and TS do
not affect the results of any safety calculations.
Cycle independent analyses documented in NEDC-33529P show that
the acceptance criteria for the safety analyses are not affected and
are met. Cycle specific analyses for the ITAs will be performed as
described in NEDC-33529P to establish fuel operating requirements
that assure compliance with regulatory limits.
The proposed ITA pilot program has no impact on equipment design
or fundamental operation, other than the modifications made to the
fuel assembly as part of the program. The GE14i ITAs meet the same
fuel design and licensing criteria as GE14 bundles. There are no
changes being made to safety limits or safety system allowable
values that would adversely affect plant safety as a result of the
proposed ITAs. The performance of the systems important to safety is
not affected by the use of the proposed ITAs. The proposed change
does not adversely affect safety analysis assumptions, initial
conditions, or acceptance criteria and therefore, the margin of
safety in the original safety analyses is maintained.
Therefore, the proposed change does not involve a significant
reduction in a margin of safety.
The NRC staff has reviewed the licensee's analysis and, based on
this review, it appears that the three standards of 10 CFR 50.92(c) are
satisfied. Therefore, the NRC staff proposes to determine that the
amendment request involves no significant hazards consideration.
Attorney for licensee: Vincent Zabielski, PSEG Nuclear LLC--N21,
P.O. Box 236, Hancocks Bridge, NJ 08038.
NRC Branch Chief: Harold K. Chernoff.
Order Imposing Procedures for Access to Sensitive Unclassified Non-
Safeguards Information for Contention Preparation
PSEG Nuclear LLC, Docket No. 50-354, Hope Creek Generating Station,
Salem County, New Jersey
A. This Order contains instructions regarding how potential parties
to this proceeding may request access to documents containing Sensitive
Unclassified Non-Safeguards Information (SUNSI).
B. Within 10 days after publication of this notice of hearing and
opportunity to petition for leave to intervene, any potential party who
believes access to SUNSI is necessary to respond to this notice may
request such access. A ``potential party'' is any person who intends to
participate as a party by demonstrating standing and filing an
admissible contention under 10 CFR 2.309. Requests for access to SUNSI
submitted later than 10 days after publication will not be considered
absent a showing of good cause for the late filing, addressing why the
request could not have been filed earlier.
C. The requestor shall submit a letter requesting permission to
access SUNSI to the Office of the Secretary, U.S. Nuclear Regulatory
Commission, Washington, DC 20555-0001, Attention: Rulemakings and
Adjudications Staff, and provide a copy to the Associate General
Counsel for Hearings, Enforcement and Administration, Office of the
General Counsel, Washington, DC 20555-0001. The expedited delivery or
courier mail address for both offices is: U.S. Nuclear Regulatory
Commission, 11555 Rockville Pike, Rockville, Maryland 20852. The e-mail
address for the Office of the Secretary and the Office of the General
Counsel are Hearing.Docket@nrc.gov and OGCmailcenter@nrc.gov,
respectively.\1\ The request must include the following information:
---------------------------------------------------------------------------
\1\ While a request for hearing or petition to intervene in this
proceeding must comply with the filing requirements of the NRC's
``E-Filing Rule,'' the initial request to access SUNSI under these
procedures should be submitted as described in this paragraph.
---------------------------------------------------------------------------
(1) A description of the licensing action with a citation to this
Federal Register notice;
(2) The name and address of the potential party and a description
of the potential party's particularized interest that could be harmed
by the action identified in C.(1);
(3) The identity of the individual or entity requesting access to
SUNSI and the requestor's basis for the need for the information in
order to meaningfully participate in this adjudicatory proceeding. In
particular, the request must explain why publicly-available versions of
the information requested would not be sufficient to provide the basis
and specificity for a proffered contention;
D. Based on an evaluation of the information submitted under
paragraph C.(3) the NRC staff will determine within 10 days of receipt
of the request whether:
(1) There is a reasonable basis to believe the petitioner is likely
to establish standing to participate in this NRC proceeding; and
(2) The requestor has established a legitimate need for access to
SUNSI.
E. If the NRC staff determines that the requestor satisfies both
D.(1) and D.(2) above, the NRC staff will notify the requestor in
writing that access to SUNSI has been granted. The written notification
will contain instructions on how the requestor may obtain copies of the
requested documents, and any other conditions that may apply to access
to those documents. These conditions may include, but are not limited
to, the signing of a Non-Disclosure Agreement or Affidavit, or
Protective Order \2\ setting forth terms and conditions to prevent the
unauthorized or inadvertent disclosure of SUNSI by each individual who
will be granted access to SUNSI.
---------------------------------------------------------------------------
\2\ Any motion for Protective Order or draft Non-Disclosure
Affidavit or Agreement for SUNSI must be filed with the presiding
officer or the Chief Administrative Judge if the presiding officer
has not yet been designated, within 30 days of the deadline for the
receipt of the written access request.
---------------------------------------------------------------------------
F. Filing of Contentions. Any contentions in these proceedings that
are based upon the information received as a result of the request made
for SUNSI must be filed by the requestor no later than 25 days after
the requestor is granted access to that information. However, if more
than 25 days remain between the date the petitioner is granted access
to the information and the deadline for filing all other contentions
(as established in the notice of hearing or opportunity for hearing),
the petitioner may file its SUNSI contentions by that later deadline.
G. Review of Denials of Access.
(1) If the request for access to SUNSI is denied by the NRC staff
either after a determination on standing and need for access, or after
a determination on trustworthiness and reliability, the NRC staff shall
immediately notify the requestor in writing, briefly stating the reason
or reasons for the denial.
(2) The requestor may challenge the NRC staff's adverse
determination by filing a challenge within 5 days of receipt of that
determination with: (a) The presiding officer designated in this
proceeding; (b) if no presiding officer has been appointed, the Chief
Administrative Judge, or if he or she is unavailable, another
administrative judge, or an administrative law judge with jurisdiction
pursuant to 10 CFR 2.318(a); or (c) if another officer has been
designated to rule on information access issues, with that officer.
H. Review of Grants of Access. A party other than the requestor may
[[Page 9449]]
challenge an NRC staff determination granting access to SUNSI whose
release would harm that party's interest independent of the proceeding.
Such a challenge must be filed with the Chief Administrative Judge
within 5 days of the notification by the NRC staff of its grant of
access.
If challenges to the NRC staff determinations are filed, these
procedures give way to the normal process for litigating disputes
concerning access to information. The availability of interlocutory
review by the Commission of orders ruling on such NRC staff
determinations (whether granting or denying access) is governed by 10
CFR 2.311.\3\
---------------------------------------------------------------------------
\3\ Requestors should note that the filing requirements of the
NRC's E-Filing Rule (72 FR 49139; August 28, 2007) apply to appeals
of NRC staff determinations (because they must be served on a
presiding officer or the Commission, as applicable), but not to the
initial SUNSI request submitted to the NRC staff under these
procedures.
---------------------------------------------------------------------------
I. The Commission expects that the NRC staff and presiding officers
(and any other reviewing officers) will consider and resolve requests
for access to SUNSI, and motions for protective orders, in a timely
fashion in order to minimize any unnecessary delays in identifying
those petitioners who have standing and who have propounded contentions
meeting the specificity and basis requirements in 10 CFR Part 2.
Attachment 1 to this Order summarizes the general target schedule for
processing and resolving requests under these procedures.
It is so ordered.
Dated at Rockville, Maryland, this 22nd day of February 2010.
For the Commission.
Annette L. Vietti-Cook,
Secretary of the Commission.
ATTACHMENT 1--General Target Schedule for Processing and Resolving
Requests for Access to Sensitive Unclassified Non-Safeguards
Information in This Proceeding
------------------------------------------------------------------------
Day Event/activity
------------------------------------------------------------------------
0........................ Publication of Federal Register notice of
hearing and opportunity to petition for
leave to intervene, including order with
instructions for access requests.
10....................... Deadline for submitting requests for access
to Sensitive Unclassified Non-Safeguards
Information (SUNSI) with information:
supporting the standing of a potential party
identified by name and address; describing
the need for the information in order for
the potential party to participate
meaningfully in an adjudicatory proceeding.
60....................... Deadline for submitting petition for
intervention containing: (i) Demonstration
of standing; (ii) all contentions whose
formulation does not require access to SUNSI
(+25 Answers to petition for intervention;
+7 requestor/petitioner reply).
20....................... Nuclear Regulatory Commission (NRC) staff
informs the requestor of the staff's
determination whether the request for access
provides a reasonable basis to believe
standing can be established and shows need
for SUNSI. (NRC staff also informs any party
to the proceeding whose interest independent
of the proceeding would be harmed by the
release of the information.) If NRC staff
makes the finding of need for SUNSI and
likelihood of standing, NRC staff begins
document processing (preparation of
redactions or review of redacted documents).
25....................... If NRC staff finds no ``need'' or no
likelihood of standing, the deadline for
requestor/petitioner to file a motion
seeking a ruling to reverse the NRC staff's
denial of access; NRC staff files copy of
access determination with the presiding
officer (or Chief Administrative Judge or
other designated officer, as appropriate).
If NRC staff finds ``need'' for SUNSI, the
deadline for any party to the proceeding
whose interest independent of the proceeding
would be harmed by the release of the
information to file a motion seeking a
ruling to reverse the NRC staff's grant of
access.
30....................... Deadline for NRC staff reply to motions to
reverse NRC staff determination(s).
40....................... (Receipt +30) If NRC staff finds standing and
need for SUNSI, deadline for NRC staff to
complete information processing and file
motion for Protective Order and draft Non-
Disclosure Affidavit. Deadline for applicant/
licensee to file Non-Disclosure Agreement
for SUNSI.
A........................ If access granted: Issuance of presiding
officer or other designated officer decision
on motion for protective order for access to
sensitive information (including schedule
for providing access and submission of
contentions) or decision reversing a final
adverse determination by the NRC staff.
A + 3.................... Deadline for filing executed Non-Disclosure
Affidavits. Access provided to SUNSI
consistent with decision issuing the
protective order.
A + 28................... Deadline for submission of contentions whose
development depends upon access to SUNSI.
However, if more than 25 days remain between
the petitioner's receipt of (or access to)
the information and the deadline for filing
all other contentions (as established in the
notice of hearing or opportunity for
hearing), the petitioner may file its SUNSI
contentions by that later deadline.
A + 53................... (Contention receipt +25) Answers to
contentions whose development depends upon
access to SUNSI.
A + 60................... (Answer receipt +7) Petitioner/Intervenor
reply to answers.
>A + 60.................. Decision on contention admission.
------------------------------------------------------------------------
[FR Doc. 2010-3988 Filed 3-1-10; 8:45 am]
BILLING CODE 7590-01-P