STP Nuclear Operating Company, 8150-8151 [2010-3498]
Download as PDF
8150
Federal Register / Vol. 75, No. 35 / Tuesday, February 23, 2010 / Notices
for calculating KIM stress intensity
values.
The proposed action would exempt
the licensee from certain requirements
of Appendix G to 10 CFR Part 50 to
allow the application of the
methodology in CE NPSD–683–A,
Revision 6, for the calculation of flaw
stress intensity factors due to internal
pressure loadings (KIM).
mstockstill on DSKH9S0YB1PROD with NOTICES
The Need for the Proposed Action
The exemption is needed to allow the
licensee to use an alternate methodology
to meet the fracture toughness
requirements for the reactor coolant
pressure boundary. In the considering
the exemption request, the staff has
determined that, pursuant to 10 CFR
50.12(a)(2)(ii), the application of the
regulation in the particular
circumstances is not necessary to
achieve the underlying purpose of the
rule, based on the alternate
methodology proposed by the licensee.
The proposed action would revise the
currently-approved methodology for P–
T limit calculations to incorporate the
methodology approved for use in CE
NPSD–683–A, Revision 6. The topical
report allows the use of an alternate
methodology to calculate the flaw stress
intensity factors due to internal pressure
loadings (KIM). Specifically, the
exemption is needed because the
methodology in CE NPSD–683–A,
Revision 6, could not be shown to be
conservative with respect to the
methodology for the determination of
KIM provided in Editions and Addenda
of the American Society of Mechanical
Engineers Boiler and Pressure Vessel
Code (ASME Code), Section XI,
Appendix G, through the 1995 Edition
and 1996 Addenda (the latest Edition
and Addenda of the ASME Code which
had been incorporated into 10 CFR
50.55a at the time of the staff’s review
of CE NPSD–683–A, Revision 6).
Therefore, the licensee submitted an
exemption request, consistent with the
requirements of 10 CFR 50.60, to apply
the KIM calculational methodology of CE
NPSD–683–A, Revision 6, as part of the
PVNGS, Units 1, 2, and 3, PTLR
methodology.
Environmental Impacts of the Proposed
Action
The NRC has completed its evaluation
of the proposed action and concludes
that the use of the alternate
methodology described above would
provide an adequate margin of safety
against brittle failure of the reactor
pressure vessels at PVNGS, Units 1, 2
and 3. The proposed change does not
involve any replacement or
modification of plant components and
VerDate Nov<24>2008
16:25 Feb 22, 2010
Jkt 220001
no changes are proposed in the
operation of PVNGS. Therefore the staff
concludes that the use of an alternate
methodology as described in the
licensee’s request would not
significantly affect plant safety and
would not have a significant adverse
affect on the probability of an accident
occurring.
The proposed action will not result in
any non-radiological impacts or
radiological impacts. The proposed
action does not result in changes to the
operation of the plant and supporting
facilities, land use, or water use, nor
does it result in changes to the quality
or quantity of non-radiological and
radiological effluents. No impacts are
expected to the air or ambient air
quality. No impacts are expected to
aquatic or terrestrial habitats or species,
or to threatened, endangered, or
protected species. No impacts are
expected to historic and cultural
resources, or to socioeconomic
resources. Accordingly, the NRC
concludes that there are no significant
environmental impacts associated with
the proposed action.
The details of the staff’s safety
evaluation will be provided in the
exemption to 10 CFR 50, Appendix G,
which will allow the use of the
methodology in Topical Report CE
NPSD–683–A, Revision 6, to calculate
the flaw stress intensity factors due to
internal pressure loadings (KIM). The
exemption will be issued in a future
letter to the licensee.
Environmental Impacts of the
Alternatives to the Proposed Action
As an alternative to the proposed
action, the staff considered denial of the
proposed action (i.e., the ‘‘no-action’’
alternative). Denial of the application
would result in no change in current
environmental impacts. The
environmental impacts of the proposed
action and the alternative action are
similar.
The action does not involve the use of
any different resources than those
previously considered in the Final
Environmental Statement for the Palo
Verde Nuclear Generating Station, Units
1, 2, and 3, NUREG–0841, dated
February 1982.
Agencies and Persons Consulted
In accordance with its stated policy,
on February 12, 2010, the staff
consulted with the Arizona State
official, Mr. Aubrey Godwin of the
Arizona Radiation Regulatory Agency,
regarding the environmental impact of
Frm 00120
Fmt 4703
Sfmt 4703
Finding of No Significant Impact
On the basis of the environmental
assessment, the NRC concludes that the
proposed action will not have a
significant effect on the quality of the
human environment. Accordingly, the
NRC has determined not to prepare an
environmental impact statement for the
proposed action.
For further details with respect to the
proposed action, see the licensee’s
letters dated February 19 and December
22, 2009 (Agencywide Documents
Access and Management System
(ADAMS) Accession Nos. ML090641014
and ML10040069, respectively).
Documents may be examined, and/or
copied for a fee, at the NRC’s Public
Document Room (PDR), located at One
White Flint North, Public File Area O1
F21, 11555 Rockville Pike (first floor),
Rockville, Maryland. Publicly available
records will be accessible electronically
from the ADAMS Public Electronic
Reading Room on the Internet at the
NRC Web site, https://www.nrc.gov/
reading-rm/adams.html. Persons who
do not have access to ADAMS or who
encounter problems in accessing the
documents located in ADAMS should
contact the NRC PDR Reference staff by
telephone at 1–800–397–4209 or 301–
415–4737, or send an e-mail to
pdr.resource@nrc.gov.
Dated at Rockville, Maryland, this 16th day
of February 2010.
For the Nuclear Regulatory Commission.
James R. Hall,
Senior Project Manager, Plant Licensing
Branch IV, Division of Operating Reactor
Licensing, Office of Nuclear Reactor
Regulation.
[FR Doc. 2010–3496 Filed 2–22–10; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
[Docket Nos. 50–498 and 50–499; NRC–
2010–060]
Alternative Use of Resources
PO 00000
the proposed action. The State official
had no comments.
STP Nuclear Operating Company
South Texas Project, Units 1 and 2
Environmental Assessment and Finding
of No Significant Impact
The U.S. Nuclear Regulatory
Commission (NRC) is considering
issuance of an exemption, pursuant to
Title 10 of the Code of Federal
Regulations (10 CFR) Section 73.5,
‘‘Specific exemptions,’’ from the
implementation date for certain new
requirements of 10 CFR Part 73,
‘‘Physical protection of plants and
materials,’’ for Facility Operating
E:\FR\FM\23FEN1.SGM
23FEN1
Federal Register / Vol. 75, No. 35 / Tuesday, February 23, 2010 / Notices
Licenses numbered NPF–76 and NPF–
80, issued to STP Nuclear Operating
Company (the licensee), for operation of
South Texas Project (STP), Units 1 and
2, located in Matagorda County, Texas.
In accordance with 10 CFR 51.21, the
NRC prepared an environmental
assessment documenting its finding.
The NRC concluded that the proposed
actions will have no significant
environmental impact.
Environmental Assessment
Identification of the Proposed Action
The proposed action would exempt
STP, Units 1 and 2, from the required
implementation date of March 31, 2010,
for certain new requirements of 10 CFR
Part 73. Specifically, STP, Units 1 and
2, would be granted an exemption from
being in full compliance with certain
new requirements contained in 10 CFR
73.55 by the March 31, 2010, deadline.
The licensee for STP, Units 1 and 2, has
proposed an alternate full compliance
implementation date of June 30, 2010, 3
months beyond the date required by 10
CFR Part 73. The proposed action, an
extension of the schedule for
completion of certain actions required
by the revised 10 FR Part 73, does not
involve any physical changes to the
reactor, fuel, plant structures, support
structures, water, or land at the STP,
Units 1 and 2, site.
The proposed action is in accordance
with the licensee’s application dated
November 18, 2009.
The Need for the Proposed Action
The proposed action is needed to
provide the licensee with additional
time required to perform the required
upgrades to the STP, Units 1 and 2
security systems.
mstockstill on DSKH9S0YB1PROD with NOTICES
Environmental Impacts of the Proposed
Action
The NRC staff has completed its
environmental assessment of the
proposed exemption. The NRC staff has
concluded that the proposed action to
extend the compliance implementation
deadline would not significantly affect
plant safety and would not have a
significant adverse effect on the
probability or consequences of an
accident.
The proposed action would not result
in any increased radiological hazards
beyond those previously analyzed in the
environmental assessment and finding
of no significant impact made by the
Commission in promulgating its
revisions to 10 CFR Part 73 as discussed
in a Federal Register notice dated
March 27, 2009 (74 FR 13926). There
will be no change to radioactive
VerDate Nov<24>2008
16:25 Feb 22, 2010
Jkt 220001
effluents that affect radiation exposures
to plant workers and members of the
public. Therefore, no changes or
different types of radiological impacts
are expected as a result of the proposed
exemption.
The proposed action does not result
in changes to land use or water use, or
result in changes to the quality or
quantity of non-radiological effluents.
No changes to the National Pollution
Discharge Elimination System permit
are needed. No effects on the aquatic or
terrestrial habitat in the vicinity of the
plant, or to threatened, endangered, or
protected species under the Endangered
Species Act, or impacts to essential fish
habitat covered by the MagnusonStevens Act are expected. There are no
impacts to the air or ambient air quality.
There are no impacts to historical and
cultural resources. There would be no
impact to socioeconomic resources.
Therefore, no changes to or different
types of non-radiological environmental
impacts are expected as a result of the
proposed exemption.
Accordingly, the NRC staff concludes
that there are no significant
environmental impacts associated with
the proposed action. In addition, in
promulgating its revisions to 10 CFR
Part 73, the Commission prepared an
environmental assessment and
published a finding of no significant
impact (Part 73, Power Reactor Security
Requirements, 74 FR 13926 (March 27,
2009)).
With its request to extend the
compliance implementation deadline,
the licensee has proposed compensatory
measures to be taken in lieu of full
compliance with the new requirements
specified in 10 CFR Part 73. The
licensee currently maintains a security
system acceptable to the NRC. The
proposed compensatory measures will
continue to provide acceptable physical
protection of the STP, Units 1 and 2, in
lieu of the new requirements in 10 CFR
Part 73. Therefore, the extension of the
implementation date of the new
requirements of 10 CFR Part 73 to June
30, 2010, would not have any significant
environmental impacts.
The NRC staff’s safety evaluation will
be provided as part of a letter to the
licensee approving the exemption to the
regulation, if granted.
Environmental Impacts of the
Alternatives to the Proposed Action
As an alternative to the proposed
action, the NRC staff considered denial
of the proposed actions (i.e., the ‘‘noaction’’ alternative). Denial of the
exemption request would result in no
change in current environmental
impacts. If the proposed action was
PO 00000
Frm 00121
Fmt 4703
Sfmt 9990
8151
denied, the licensee would have to
comply with the March 31, 2010,
compliance implementation deadline.
The environmental impacts of the
proposed exemption and the ‘‘no-action’’
alternative are similar.
Alternative Use of Resources
The action does not involve the use of
any different resources than those
considered in the Final Environmental
Statement for the STP, Units 1 and 2,
NUREG–1172, dated August 1986.
Agencies and Persons Consulted
In accordance with its stated policy,
on February 1, 2010, the NRC staff
consulted with the Texas State official,
Ms. Alice Rogers of the Texas State
Department of Health, regarding the
environmental impact of the proposed
action. The Texas State official had no
comments.
Finding of No Significant Impact
On the basis of the environmental
assessment, the NRC concludes that the
proposed action will not have a
significant effect on the quality of the
human environment. Accordingly, the
NRC has determined not to prepare an
environmental impact statement for the
proposed action.
For further details with respect to the
proposed action, see the licensee’s letter
dated November 18, 2009. Portions of
November 18, 2009, submittal contains
security related information and,
accordingly, are not available to the
public. Other parts of the documents
may be examined, and/or copied for a
fee, at the NRC’s Public Document
Room (PDR), located at One White Flint
North, Public File Area O–1F21, 11555
Rockville Pike (first floor), Rockville,
Maryland 20852. Publicly available
records will be accessible electronically
from the Agencywide Documents
Access and Management System
(ADAMS) Public Electronic Reading
Room on the Internet at the NRC Web
site: https://www.nrc.gov/reading-rm/
adams.html. Persons who do not have
access to ADAMS or who encounter
problems in accessing the documents
located in ADAMS should contact the
NRC PDR Reference staff by telephone
at 1–800–397–4209 or 301–415–4737, or
send an e-mail to pdr.resource@nrc.gov.
Dated at Rockville, Maryland, this 16th day
of February 2010.
For the Nuclear Regulatory Commission.
Mohan C. Thadani,
Senior Project Manager, Plant Licensing
Branch LPLIV, Division of Operating Reactor
Licensing, Office of Nuclear Reactor
Regulation.
[FR Doc. 2010–3498 Filed 2–22–10; 8:45 am]
BILLING CODE 7590–01–P
E:\FR\FM\23FEN1.SGM
23FEN1
Agencies
[Federal Register Volume 75, Number 35 (Tuesday, February 23, 2010)]
[Notices]
[Pages 8150-8151]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-3498]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-498 and 50-499; NRC-2010-060]
STP Nuclear Operating Company
South Texas Project, Units 1 and 2 Environmental Assessment and
Finding of No Significant Impact
The U.S. Nuclear Regulatory Commission (NRC) is considering
issuance of an exemption, pursuant to Title 10 of the Code of Federal
Regulations (10 CFR) Section 73.5, ``Specific exemptions,'' from the
implementation date for certain new requirements of 10 CFR Part 73,
``Physical protection of plants and materials,'' for Facility Operating
[[Page 8151]]
Licenses numbered NPF-76 and NPF-80, issued to STP Nuclear Operating
Company (the licensee), for operation of South Texas Project (STP),
Units 1 and 2, located in Matagorda County, Texas. In accordance with
10 CFR 51.21, the NRC prepared an environmental assessment documenting
its finding. The NRC concluded that the proposed actions will have no
significant environmental impact.
Environmental Assessment
Identification of the Proposed Action
The proposed action would exempt STP, Units 1 and 2, from the
required implementation date of March 31, 2010, for certain new
requirements of 10 CFR Part 73. Specifically, STP, Units 1 and 2, would
be granted an exemption from being in full compliance with certain new
requirements contained in 10 CFR 73.55 by the March 31, 2010, deadline.
The licensee for STP, Units 1 and 2, has proposed an alternate full
compliance implementation date of June 30, 2010, 3 months beyond the
date required by 10 CFR Part 73. The proposed action, an extension of
the schedule for completion of certain actions required by the revised
10 FR Part 73, does not involve any physical changes to the reactor,
fuel, plant structures, support structures, water, or land at the STP,
Units 1 and 2, site.
The proposed action is in accordance with the licensee's
application dated November 18, 2009.
The Need for the Proposed Action
The proposed action is needed to provide the licensee with
additional time required to perform the required upgrades to the STP,
Units 1 and 2 security systems.
Environmental Impacts of the Proposed Action
The NRC staff has completed its environmental assessment of the
proposed exemption. The NRC staff has concluded that the proposed
action to extend the compliance implementation deadline would not
significantly affect plant safety and would not have a significant
adverse effect on the probability or consequences of an accident.
The proposed action would not result in any increased radiological
hazards beyond those previously analyzed in the environmental
assessment and finding of no significant impact made by the Commission
in promulgating its revisions to 10 CFR Part 73 as discussed in a
Federal Register notice dated March 27, 2009 (74 FR 13926). There will
be no change to radioactive effluents that affect radiation exposures
to plant workers and members of the public. Therefore, no changes or
different types of radiological impacts are expected as a result of the
proposed exemption.
The proposed action does not result in changes to land use or water
use, or result in changes to the quality or quantity of non-
radiological effluents. No changes to the National Pollution Discharge
Elimination System permit are needed. No effects on the aquatic or
terrestrial habitat in the vicinity of the plant, or to threatened,
endangered, or protected species under the Endangered Species Act, or
impacts to essential fish habitat covered by the Magnuson-Stevens Act
are expected. There are no impacts to the air or ambient air quality.
There are no impacts to historical and cultural resources. There
would be no impact to socioeconomic resources. Therefore, no changes to
or different types of non-radiological environmental impacts are
expected as a result of the proposed exemption.
Accordingly, the NRC staff concludes that there are no significant
environmental impacts associated with the proposed action. In addition,
in promulgating its revisions to 10 CFR Part 73, the Commission
prepared an environmental assessment and published a finding of no
significant impact (Part 73, Power Reactor Security Requirements, 74 FR
13926 (March 27, 2009)).
With its request to extend the compliance implementation deadline,
the licensee has proposed compensatory measures to be taken in lieu of
full compliance with the new requirements specified in 10 CFR Part 73.
The licensee currently maintains a security system acceptable to the
NRC. The proposed compensatory measures will continue to provide
acceptable physical protection of the STP, Units 1 and 2, in lieu of
the new requirements in 10 CFR Part 73. Therefore, the extension of the
implementation date of the new requirements of 10 CFR Part 73 to June
30, 2010, would not have any significant environmental impacts.
The NRC staff's safety evaluation will be provided as part of a
letter to the licensee approving the exemption to the regulation, if
granted.
Environmental Impacts of the Alternatives to the Proposed Action
As an alternative to the proposed action, the NRC staff considered
denial of the proposed actions (i.e., the ``no-action'' alternative).
Denial of the exemption request would result in no change in current
environmental impacts. If the proposed action was denied, the licensee
would have to comply with the March 31, 2010, compliance implementation
deadline. The environmental impacts of the proposed exemption and the
``no-action'' alternative are similar.
Alternative Use of Resources
The action does not involve the use of any different resources than
those considered in the Final Environmental Statement for the STP,
Units 1 and 2, NUREG-1172, dated August 1986.
Agencies and Persons Consulted
In accordance with its stated policy, on February 1, 2010, the NRC
staff consulted with the Texas State official, Ms. Alice Rogers of the
Texas State Department of Health, regarding the environmental impact of
the proposed action. The Texas State official had no comments.
Finding of No Significant Impact
On the basis of the environmental assessment, the NRC concludes
that the proposed action will not have a significant effect on the
quality of the human environment. Accordingly, the NRC has determined
not to prepare an environmental impact statement for the proposed
action.
For further details with respect to the proposed action, see the
licensee's letter dated November 18, 2009. Portions of November 18,
2009, submittal contains security related information and, accordingly,
are not available to the public. Other parts of the documents may be
examined, and/or copied for a fee, at the NRC's Public Document Room
(PDR), located at One White Flint North, Public File Area O-1F21, 11555
Rockville Pike (first floor), Rockville, Maryland 20852. Publicly
available records will be accessible electronically from the Agencywide
Documents Access and Management System (ADAMS) Public Electronic
Reading Room on the Internet at the NRC Web site: https://www.nrc.gov/reading-rm/adams.html. Persons who do not have access to ADAMS or who
encounter problems in accessing the documents located in ADAMS should
contact the NRC PDR Reference staff by telephone at 1-800-397-4209 or
301-415-4737, or send an e-mail to pdr.resource@nrc.gov.
Dated at Rockville, Maryland, this 16th day of February 2010.
For the Nuclear Regulatory Commission.
Mohan C. Thadani,
Senior Project Manager, Plant Licensing Branch LPLIV, Division of
Operating Reactor Licensing, Office of Nuclear Reactor Regulation.
[FR Doc. 2010-3498 Filed 2-22-10; 8:45 am]
BILLING CODE 7590-01-P