Onyx Specialty Papers, Inc.; Notice of Availability of Draft Environmental Assessment, 6377 [2010-2728]
Download as PDF
Federal Register / Vol. 75, No. 26 / Tuesday, February 9, 2010 / Notices
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. Eastern Time
on February 18, 2010.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–2722 Filed 2–8–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. PA10–1–000; ER09–555–000;
ER05–1065–000]
Entergy Services, Inc.; Notice of
Designation of Commission Staff as
Non-Decisional
Cprice-sewell on DSK2BSOYB1PROD with NOTICES
February 2, 2010.
With respect to the October 1, 2009
letter in Docket No. PA10–1–000
notifying Entergy Services, Inc. that the
Office of Enforcement and the Office of
Electric Reliability of the Federal Energy
Regulatory Commission are jointly
conducting an audit of Entergy Services,
Inc., the staff of the Office of
Enforcement is designated as nondecisional in deliberations by the
Commission in the above referenced
docket numbers, including all
subdockets thereto, for purposes of 18
CFR 385.2202 (2009). Mark Hegerle,
Olutayo Oyelade, Eric Vandenberg, Juan
Villar, and Kevin Wierzbicki of the
Office of Electric Reliability, Lawrence
Greenfield of the Office of the General
Counsel, Thomas Dautel of the Office of
Energy Policy and Innovation, and
Stephen Pointer of the Office of Energy
Market Regulation are also designated as
VerDate Nov<24>2008
14:39 Feb 08, 2010
Jkt 220001
non-decisional in these dockets and
subdockets.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–2729 Filed 2–8–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
6377
Comments may be filed electronically
via Internet in lieu of paper. The
Commission strongly encourages
electronic filings. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under the
‘‘eFiling’’ link. For further information,
contact Kristen Murphy at (202) 502–
6236.
Kimberly D. Bose,
Secretary.
Federal Energy Regulatory
Commission
[FR Doc. 2010–2728 Filed 2–8–10; 8:45 am]
[Project No. 2985–006]
BILLING CODE 6717–01–P
Onyx Specialty Papers, Inc.; Notice of
Availability of Draft Environmental
Assessment
DEPARTMENT OF ENERGY
February 2, 2010.
In accordance with the National
Environmental Policy Act of 1969 and
the Federal Energy Regulatory
Commission’s regulations, 18 CFR Part
380 (Order No. 486,52 FR 47897), the
Office of Energy Projects has reviewed
the application for a subsequent license
for the 100-kilowatt Willow Mill
Hydroelectric Project, located on the
Housatonic River, in the Town of Lee,
Berkshire County, Massachusetts, and
has prepared an Draft Environmental
Assessment (DEA). In the DEA,
Commission staff analyze the potential
environmental effects of relicensing the
project and conclude that issuing a
subsequent license for the project, with
appropriate environmental measures,
would not constitute a major federal
action significantly affecting the quality
of the human environment.
A copy of the DEA is on file with the
Commission and is available for public
inspection. The DEA may also be
viewed on the Commission’s Web site at
https://www.ferc.gov using the ‘‘eLibrary’’
link. Enter the docket number excluding
the last three digits in the docket
number field to access documents. For
assistance, contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
Comments on the DEA should be filed
within 30 days from the issuance date
of this notice, and should be addressed
to the Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Room 1–A, Washington, DC
20426. Please affix ‘‘Willow Mill Project
No. 2985–006’’ to all comments.
PO 00000
Frm 00037
Fmt 4703
Sfmt 4703
Federal Energy Regulatory
Commission
[ Docket No. ER10–505–000]
Dynegy Services Plum Point; Notice of
Filing
February 2, 2010.
Take notice that, on February 1, 2010,
Dynegy Services Plum Point filed to
supplement its filing in the above
captioned docket with information
required under the Commission’s
regulations. Such filing served to reset
the filing date in this proceeding.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. Anyone filing a motion
to intervene or protest must serve a copy
of that document on the Applicant and
all the parties in this proceeding.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
E:\FR\FM\09FEN1.SGM
09FEN1
Agencies
[Federal Register Volume 75, Number 26 (Tuesday, February 9, 2010)]
[Notices]
[Page 6377]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-2728]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2985-006]
Onyx Specialty Papers, Inc.; Notice of Availability of Draft
Environmental Assessment
February 2, 2010.
In accordance with the National Environmental Policy Act of 1969
and the Federal Energy Regulatory Commission's regulations, 18 CFR Part
380 (Order No. 486,52 FR 47897), the Office of Energy Projects has
reviewed the application for a subsequent license for the 100-kilowatt
Willow Mill Hydroelectric Project, located on the Housatonic River, in
the Town of Lee, Berkshire County, Massachusetts, and has prepared an
Draft Environmental Assessment (DEA). In the DEA, Commission staff
analyze the potential environmental effects of relicensing the project
and conclude that issuing a subsequent license for the project, with
appropriate environmental measures, would not constitute a major
federal action significantly affecting the quality of the human
environment.
A copy of the DEA is on file with the Commission and is available
for public inspection. The DEA may also be viewed on the Commission's
Web site at https://www.ferc.gov using the ``eLibrary'' link. Enter the
docket number excluding the last three digits in the docket number
field to access documents. For assistance, contact FERC Online Support
at FERCOnlineSupport@ferc.gov or toll-free at 1-866-208-3676, or for
TTY, (202) 502-8659.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via e-mail of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
Comments on the DEA should be filed within 30 days from the
issuance date of this notice, and should be addressed to the Secretary,
Federal Energy Regulatory Commission, 888 First Street, NE., Room 1-A,
Washington, DC 20426. Please affix ``Willow Mill Project No. 2985-006''
to all comments. Comments may be filed electronically via Internet in
lieu of paper. The Commission strongly encourages electronic filings.
See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's
Web site under the ``eFiling'' link. For further information, contact
Kristen Murphy at (202) 502-6236.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010-2728 Filed 2-8-10; 8:45 am]
BILLING CODE 6717-01-P