Notice of Acceptance for Docketing of the Application, Notice of Opportunity for Hearing for Facility Operating License Nos. DPR-80 and DPR-82 for an Additional 20-Year Period; Pacific Gas & Electric Company, Diablo Canyon Nuclear Power Plant, Units 1 and 2; and Order Imposing Procedures for Access to Sensitive Unclassified Non-Safeguards Information (SUNSI) for Contention Preparation, 3493-3497 [2010-1080]

Download as PDF Federal Register / Vol. 75, No. 13 / Thursday, January 21, 2010 / Notices NATIONAL SCIENCE FOUNDATION NUCLEAR REGULATORY COMMISSION Proposal Review Panel for Physics; Notice of Meeting [Docket Nos. 50–275 and 50–323; NRC– 2009–0552] In accordance with the Federal Advisory Committee Act (Pub. L. 92– 463, as amended), the National Science Foundation announces the following meeting. Name: University of Nebraska Site Visit in Physics (1208). Date and Time: Monday, February 1, 2010; 8 a.m.–6 p.m.; Tuesday, February 2, 2010: 8 a.m.–3 p.m. Place: University of Nebraska, Lincoln, Nebraska. Type of Meeting: Partially Closed. Contact Person: Dr. James Reidy, Program Director for Elementary Particle Physics, National Science Foundation, 4201 Wilson Blvd., Arlington, VA 22230. Telephone: (703) 292–7392. Purpose of Meeting: To provide an evaluation concerning the proposal submitted to the National Science Foundation. Agenda Monday. February 1, 2010 Closed 8–9 Executive Session. Open 9–3 Open Discussions and/or presentations. Closed 3–3:30 Executive Session. Open 3:30–6 Open Discussions and/or presentations. Tuesday, February 2, 2010 Closed 8–9 Executive Session. Open 9–11:30 Open Discussions and/or presentations. Closed 11:30–3:30 Executive Session & Close out with Lab Leaders. Reason For Closing: The proposal contains proprietary or confidential material including technical information; financial data, such as salaries; and personal information concerning individuals associated with the proposals. These matters are exempt under 5 U.S.C. 552b (c) and (6) of the Government in the Sunshine Act. Dated: January 14, 2010. Susanne Bolton, Committee Management Officer. [FR Doc. 2010–967 Filed 1–20–10; 8:45 am] jlentini on DSKJ8SOYB1PROD with NOTICES BILLING CODE 7555–01–P VerDate Nov<24>2008 16:17 Jan 20, 2010 Jkt 220001 Notice of Acceptance for Docketing of the Application, Notice of Opportunity for Hearing for Facility Operating License Nos. DPR–80 and DPR–82 for an Additional 20-Year Period; Pacific Gas & Electric Company, Diablo Canyon Nuclear Power Plant, Units 1 and 2; and Order Imposing Procedures for Access to Sensitive Unclassified Non-Safeguards Information (SUNSI) for Contention Preparation The U.S. Nuclear Regulatory Commission (NRC) is considering an application for the renewal of operating licenses DPR–80 and DPR–82, which authorize Pacific Gas & Electric Company (PG&E) to operate the Diablo Canyon Nuclear Power Plant (DCPP), Units 1 and 2, at 3411 megawatts thermal, each. The renewed licenses would authorize the applicant to operate DCPP, Units 1 and 2, for an additional 20 years beyond the period specified in the current licenses. DCPP, Units 1 and 2, are located near San Luis Obispo, California. The current operating licenses expire on November 2, 2024, and August 26, 2025, respectively. PG&E submitted the application dated November 23, 2009, pursuant to Title 10 of the Code of Federal Regulations, Part 54 (10 CFR part 54) to renew operating licenses DPR–80 and DPR–82. A notice of receipt and availability of the license renewal application (LRA) was published in the Federal Register on December 11, 2009 (74 FR 65811). The Commission has determined that PG&E has submitted sufficient information in accordance with 10 CFR Sections 2.101, 54.19, 54.21, 54.22, 54.23, 51.45, and 51.53(c), to enable the staff to undertake a review of the application, and the application is therefore acceptable for docketing. The Commission will retain the current Docket Nos. 50–275 and 50–323 for operating license Nos. DPR–80 and DPR–82. The determination to accept the LRA for docketing does not constitute a determination that the renewed licenses should be issued, and does not preclude the NRC staff from requesting additional information as the review proceeds. Before issuance of the requested renewed licenses, the NRC will have made the findings required by the Atomic Energy Act of 1954, as amended (the Act), and the Commission’s rules and regulations. In accordance with 10 CFR 54.29, the NRC may issue a PO 00000 Frm 00052 Fmt 4703 Sfmt 4703 3493 renewed license on the basis of its review if it finds that actions have been identified and have been or will be taken with respect to: (1) Managing the effects of aging during the period of extended operation on the functionality of structures and components that have been identified as requiring aging management review, and (2) timelimited aging analyses that have been identified as requiring review, such that there is reasonable assurance that the activities authorized by the renewed license will continue to be conducted in accordance with the current licensing basis (CLB) and that any changes made to the plant’s CLB will comply with the Act and the Commission’s regulations. Additionally, in accordance with 10 CFR 51.95(c), the NRC will prepare an environmental impact statement that is a supplement to the Commission’s NUREG–1437, ‘‘Generic Environmental Impact Statement for License Renewal of Nuclear Power Plants,’’ dated May 1996. In considering the LRA, the Commission must find that the applicable requirements of subpart A of 10 CFR part 51 have been satisfied, and that matters raised under 10 CFR 2.335 have been addressed. Pursuant to 10 CFR 51.26, and as part of the environmental scoping process, the staff intends to hold public scoping meetings. Detailed information regarding the environmental scoping meetings will be the subject of a separate Federal Register notice. Within 60 days after the date of publication of this Federal Register notice, any person whose interest may be affected by this proceeding and who wishes to participate as a party in the proceeding must file a written request for a hearing and a petition for leave to intervene with respect to the renewal of the licenses. Requests for a hearing or petitions for leave to intervene must be filed in accordance with the Commission’s ‘‘Rules of Practice for Domestic Licensing Proceedings and Issuance of Orders’’ in 10 CFR part 2. Interested persons should consult a current copy of 10 CFR 2.309, which is available at the Commission’s Public Document Room (PDR), located at One White Flint North, 11555 Rockville Pike (first floor), Rockville, Maryland 20852 and is accessible from the NRC’s Agencywide Documents Access and Management System (ADAMS) Public Electronic Reading Room on the Internet at https://www.nrc.gov/reading-rm/ adams.html. Persons who do not have access to the Internet or who encounter problems in accessing the documents located in ADAMS should contact the NRC’s PDR reference staff by telephone at 1–800–397–4209, or 301–415–4737, E:\FR\FM\21JAN1.SGM 21JAN1 jlentini on DSKJ8SOYB1PROD with NOTICES 3494 Federal Register / Vol. 75, No. 13 / Thursday, January 21, 2010 / Notices or by e-mail at PDR.Resource@nrc.gov. If a request for a hearing/petition for leave to intervene is filed within the 60-day period, the Commission or a presiding officer designated by the Commission or by the Chief Administrative Judge of the Atomic Safety and Licensing Board Panel will rule on the request and/or petition; and the Secretary or the Chief Administrative Judge of the Atomic Safety and Licensing Board Panel will issue a notice of a hearing or an appropriate order. In the event that no request for a hearing or petition for leave to intervene is filed within the 60day period, the NRC may, upon completion of its evaluations and upon making the findings required under 10 CFR parts 51 and 54, renew the licenses without further notice. As required by 10 CFR 2.309, a petition for leave to intervene shall set forth with particularity the interest of the petitioner in the proceeding, and how that interest may be affected by the results of the proceeding, taking into consideration the limited scope of matters that may be considered pursuant to 10 CFR parts 51 and 54. The petition must specifically explain the reasons why intervention should be permitted with particular reference to the following factors: (1) The nature of the requestor’s/petitioner’s right under the Act to be made a party to the proceeding; (2) the nature and extent of the requestor’s/petitioner’s property, financial, or other interest in the proceeding; and (3) the possible effect of any decision or order which may be entered in the proceeding on the requestor’s/petitioner’s interest. The petition must also set forth the specific contentions which the requestor/ petitioner seeks to have litigated at the proceeding. Each contention must consist of a specific statement of the issue of law or fact to be raised or controverted. In addition, the requestor/petitioner shall provide a brief explanation of the bases of each contention and a concise statement of the alleged facts or the expert opinion that supports the contention on which the requestor/ petitioner intends to rely in proving the contention at the hearing. The requestor/petitioner must also provide references to those specific sources and documents of which the requestor/ petitioner is aware and on which the requestor/petitioner intends to rely to establish those facts or expert opinion. The requestor/petitioner must provide sufficient information to show that a genuine dispute exists with the applicant on a material issue of law or fact. Contentions shall be limited to matters within the scope of the action VerDate Nov<24>2008 16:17 Jan 20, 2010 Jkt 220001 under consideration. The contention must be one that, if proven, would entitle the requestor/petitioner to relief. A requestor/petitioner who fails to satisfy these requirements with respect to at least one contention will not be permitted to participate as a party. The Commission requests that each contention be given a separate numeric or alpha designation within one of the following groups: (1) Technical (primarily related to safety concerns); (2) environmental; or (3) miscellaneous. As specified in 10 CFR 2.309, if two or more requestors/petitioners seek to co-sponsor a contention or propose substantially the same contention, the requestors/petitioners must jointly designate a representative who shall have the authority to act for the requestors/petitioners with respect to that contention. All documents filed in NRC adjudicatory proceedings, including a request for hearing, a petition for leave to intervene, any motion or other document filed in the proceeding prior to the submission of a request for hearing or petition to intervene, and documents filed by interested governmental entities participating under 10 CFR 2.315(c), must be filed in accordance with the NRC E-Filing rule (72 FR 49139, August 28, 2007). The EFiling process requires participants to submit and serve all adjudicatory documents over the internet, or in some cases to mail copies on electronic storage media. Participants may not submit paper copies of their filings unless they seek an exemption in accordance with the procedures described below. To comply with the procedural requirements of E-Filing, at least ten (10) days prior to the filing deadline, the participant should contact the Office of the Secretary by e-mail at hearing.docket@nrc.gov, or by telephone at (301) 415–1677, to request (1) a digital ID certificate, which allows the participant (or its counsel or representative) to digitally sign documents and access the E-Submittal server for any proceeding in which it is participating; and (2) advise the Secretary that the participant will be submitting a request or petition for hearing (even in instances in which the participant, or its counsel or representative, already holds an NRCissued digital ID certificate). Based upon this information, the Secretary will establish an electronic docket for the hearing in this proceeding if the Secretary has not already established an electronic docket. Information about applying for a digital ID certificate is available on PO 00000 Frm 00053 Fmt 4703 Sfmt 4703 NRC’s public Web site at https:// www.nrc.gov/site-help/e-submittals/ apply-certificates.html. System requirements for accessing the ESubmittal server are detailed in NRC’s ‘‘Guidance for Electronic Submission,’’ which is available on the agency’s public Web site at https://www.nrc.gov/ site-help/e-submittals.html. Participants may attempt to use other software not listed on the Web site, but should note that the NRC’s E-Filing system does not support unlisted software, and the NRC Meta System Help Desk will not be able to offer assistance in using unlisted software. If a participant is electronically submitting a document to the NRC in accordance with the E-Filing rule, the participant must file the document using the NRC’s online, Web-based submission form. In order to serve documents through EIE, users will be required to install a Web browser plugin from the NRC Web site. Further information on the Web-based submission form, including the installation of the Web browser plug-in, is available on the NRC’s public Web site at https://www.nrc.gov/site-help/esubmittals.html. Once a participant has obtained a digital ID certificate and a docket has been created, the participant can then submit a request for hearing or petition for leave to intervene. Submissions should be in Portable Document Format (PDF) in accordance with NRC guidance available on the NRC public Web site at https://www.nrc.gov/site-help/esubmittals.html. A filing is considered complete at the time the documents are submitted through the NRC’s E-Filing system. To be timely, an electronic filing must be submitted to the E-Filing system no later than 11:59 p.m. Eastern Time on the due date. Upon receipt of a transmission, the E-Filing system time-stamps the document and sends the submitter an e-mail notice confirming receipt of the document. The E-Filing system also distributes an email notice that provides access to the document to the NRC Office of the General Counsel and any others who have advised the Office of the Secretary that they wish to participate in the proceeding, so that the filer need not serve the documents on those participants separately. Therefore, applicants and other participants (or their counsel or representative) must apply for and receive a digital ID certificate before a hearing request/ petition to intervene is filed so that they can obtain access to the document via the E-Filing system. A person filing electronically using the agency’s adjudicatory E-Filing E:\FR\FM\21JAN1.SGM 21JAN1 jlentini on DSKJ8SOYB1PROD with NOTICES Federal Register / Vol. 75, No. 13 / Thursday, January 21, 2010 / Notices system may seek assistance by contacting the NRC Meta System Help Desk through the ‘‘Contact Us’’ link located on the NRC Web site at https:// www.nrc.gov/site-help/esubmittals.html, by e-mail at MSHD.Resource@nrc.gov, or by a tollfree call at (866) 672–7640. The NRC Meta System Help Desk is available between 8 a.m. and 8 p.m., Eastern Time, Monday through Friday, excluding government holidays. Participants who believe that they have a good cause for not submitting documents electronically must file an exemption request, in accordance with 10 CFR 2.302(g), with their initial paper filing requesting authorization to continue to submit documents in paper format. Such filings must be submitted by: (1) First class mail addressed to the Office of the Secretary of the Commission, U.S. Nuclear Regulatory Commission, Washington, DC 20555– 0001, Attention: Rulemaking and Adjudications Staff; or (2) courier, express mail, or expedited delivery service to the Office of the Secretary, Sixteenth Floor, One White Flint North, 11555 Rockville Pike, Rockville, Maryland, 20852, Attention: Rulemaking and Adjudications Staff. Participants filing a document in this manner are responsible for serving the document on all other participants. Filing is considered complete by firstclass mail as of the time of deposit in the mail, or by courier, express mail, or expedited delivery service upon depositing the document with the provider of the service. A presiding officer, having granted an exemption request from using E-Filing, may require a participant or party to use E-Filing if the presiding officer subsequently determines that the reason for granting the exemption from use of E-Filing no longer exists. Documents submitted in adjudicatory proceedings will appear in NRC’s electronic hearing docket which is available to the public at https:// ehd.nrc.gov/EHD_Proceeding/home.asp, unless excluded pursuant to an order of the Commission, or the presiding officer. Participants are requested not to include personal privacy information, such as social security numbers, home addresses, or home phone numbers in their filings, unless an NRC regulation or other law requires submission of such information. With respect to copyrighted works, except for limited excerpts that serve the purpose of the adjudicatory filings and would constitute a Fair Use application, participants are requested not to include copyrighted materials in their submission. VerDate Nov<24>2008 16:17 Jan 20, 2010 Jkt 220001 Petitions for leave to intervene must be filed no later than 60 days from the date of publication of this Federal Register notice. Non-timely filings will not be entertained absent a determination by the presiding officer that the petition or request should be granted or the contentions should be admitted, based on a balancing of the factors specified in 10 CFR 2.309(c)(1)(i)–(viii). Detailed information about the license renewal process can be found under the Nuclear Reactors icon at https:// www.nrc.gov/reactors/operating/ licensing/renewal.html on the NRC’s Web site. Copies of the application to renew the operating licenses for DCPP are available for public inspection at the Commission’s PDR, located at One White Flint North, 11555 Rockville Pike (first floor), Rockville, Maryland 20852– 2738, and at https://www.nrc.gov/ reactors/operating/licensing/renewal/ applications.html, the NRC’s Web site while the application is under review. The application may be accessed in ADAMS through the NRC’s Public Electronic Reading Room on the Internet at https://www.nrc.gov/reading-rm/ adams.html under ADAMS Accession Number ML093340125. As stated above, persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS may contact the NRC PDR reference staff by telephone at 1–800– 397–4209 or 301–415–4737, or by e-mail to PDR.Resource@nrc.gov. The NRC staff has verified that a copy of the license renewal application is also available to local residents near the site at the San Luis Obispo Public Library, 995 Palm Street, San Luis Obispo, California 93401, and at the Paso Robles Public Library, 1000 Spring Street, Paso Robles, California 93446. Order Imposing Procedures for Access to Sensitive Unclassified NonSafeguards Information for Contention Preparation A. This Order contains instructions regarding how potential parties to this proceeding may request access to documents containing Sensitive Unclassified Non-Safeguards Information (SUNSI). B. Within 10 days after publication of this notice of hearing and opportunity to petition for leave to intervene, any potential party who believes access to SUNSI is necessary to respond to this notice may request such access. A ‘‘potential party’’ is any person who intends to participate as a party by demonstrating standing and filing an admissible contention under 10 CFR 2.309. Requests for access to SUNSI PO 00000 Frm 00054 Fmt 4703 Sfmt 4703 3495 submitted later than 10 days after publication will not be considered absent a showing of good cause for the late filing, addressing why the request could not have been filed earlier. C. The requestor shall submit a letter requesting permission to access SUNSI to the Office of the Secretary, U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001, Attention: Rulemakings and Adjudications Staff, and provide a copy to the Associate General Counsel for Hearings, Enforcement and Administration, Office of the General Counsel, Washington, DC 20555–0001. The expedited delivery or courier mail address for both offices is: U.S. Nuclear Regulatory Commission, 11555 Rockville Pike, Rockville, Maryland 20852. The e-mail address for the Office of the Secretary and the Office of the General Counsel are Hearing.Docket@nrc.gov and OGCmailcenter@nrc.gov, respectively.1 The request must include the following information: (1) A description of the licensing action with a citation to this Federal Register notice; (2) The name and address of the potential party and a description of the potential party’s particularized interest that could be harmed by the action identified in C.(1); (3) The identity of the individual or entity requesting access to SUNSI and the requestor’s basis for the need for the information in order to meaningfully participate in this adjudicatory proceeding. In particular, the request must explain why publicly-available versions of the information requested would not be sufficient to provide the basis and specificity for a proffered contention; D. Based on an evaluation of the information submitted under paragraph C.(3) the NRC staff will determine within 10 days of receipt of the request whether: (1) There is a reasonable basis to believe the petitioner is likely to establish standing to participate in this NRC proceeding; and (2) The requestor has established a legitimate need for access to SUNSI. E. If the NRC staff determines that the requestor satisfies both D.(1) and D.(2) above, the NRC staff will notify the requestor in writing that access to SUNSI has been granted. The written notification will contain instructions on how the requestor may obtain copies of 1 While a request for hearing or petition to intervene in this proceeding must comply with the filing requirements of the NRC’s ‘‘E-Filing Rule,’’ the initial request to access SUNSI under these procedures should be submitted as described in this paragraph. E:\FR\FM\21JAN1.SGM 21JAN1 3496 Federal Register / Vol. 75, No. 13 / Thursday, January 21, 2010 / Notices the requested documents, and any other conditions that may apply to access to those documents. These conditions may include, but are not limited to, the signing of a Non-Disclosure Agreement or Affidavit, or Protective Order 2 setting forth terms and conditions to prevent the unauthorized or inadvertent disclosure of SUNSI by each individual who will be granted access to SUNSI. F. Filing of Contentions. Any contentions in these proceedings that are based upon the information received as a result of the request made for SUNSI must be filed by the requestor no later than 25 days after the requestor is granted access to that information. However, if more than 25 days remain between the date the petitioner is granted access to the information and the deadline for filing all other contentions (as established in the notice of hearing or opportunity for hearing), the petitioner may file its SUNSI contentions by that later deadline. G. Review of Denials of Access. (1) If the request for access to SUNSI is denied by the NRC staff either after a determination on standing and need for access, or after a determination on trustworthiness and reliability, the NRC staff shall immediately notify the requestor in writing, briefly stating the reason or reasons for the denial. (2) The requestor may challenge the NRC staff’s adverse determination by filing a challenge within 5 days of receipt of that determination with: (a) The presiding officer designated in this proceeding; (b) if no presiding officer has been appointed, the Chief Administrative Judge, or if he or she is unavailable, another administrative judge, or an administrative law judge with jurisdiction pursuant to 10 CFR 2.318(a); or (c) if another officer has been designated to rule on information access issues, with that officer. H. Review of Grants of Access. A party other than the requestor may challenge an NRC staff determination granting access to SUNSI whose release would harm that party’s interest independent of the proceeding. Such a challenge must be filed with the Chief Administrative Judge within 5 days of the notification by the NRC staff of its grant of access. If challenges to the NRC staff determinations are filed, these procedures give way to the normal process for litigating disputes concerning access to information. The availability of interlocutory review by the Commission of orders ruling on such NRC staff determinations (whether granting or denying access) is governed by 10 CFR 2.311.3 I. The Commission expects that the NRC staff and presiding officers (and any other reviewing officers) will consider and resolve requests for access to SUNSI, and motions for protective orders, in a timely fashion in order to minimize any unnecessary delays in identifying those petitioners who have standing and who have propounded contentions meeting the specificity and basis requirements in 10 CFR part 2. Attachment 1 to this Order summarizes the general target schedule for processing and resolving requests under these procedures. It is so ordered. Dated at Rockville, Maryland, this 14th day of January 2010. For the Commission. Annette L. Vietti-Cook, Secretary of the Commission. ATTACHMENT 1—GENERAL TARGET SCHEDULE FOR PROCESSING AND RESOLVING REQUESTS FOR ACCESS TO SENSITIVE UNCLASSIFIED NON-SAFEGUARDS INFORMATION IN THIS PROCEEDING Day Event/activity 0 ............... Publication of FEDERAL REGISTER notice of hearing and opportunity to petition for leave to intervene, including order with instructions for access requests. Deadline for submitting requests for access to Sensitive Unclassified Non-Safeguards Information (SUNSI) with information: supporting the standing of a potential party identified by name and address; describing the need for the information in order for the potential party to participate meaningfully in an adjudicatory proceeding. Deadline for submitting petition for intervention containing: (i) Demonstration of standing; (ii) all contentions whose formulation does not require access to SUNSI (+25 Answers to petition for intervention; +7 petitioner/requestor reply). Nuclear Regulatory Commission (NRC) staff informs the requestor of the staff’s determination whether the request for access provides a reasonable basis to believe standing can be established and shows need for SUNSI. (NRC staff also informs any party to the proceeding whose interest independent of the proceeding would be harmed by the release of the information.) If NRC staff makes the finding of need for SUNSI and likelihood of standing, NRC staff begins document processing (preparation of redactions or review of redacted documents). If NRC staff finds no ‘‘need’’ or no likelihood of standing, the deadline for petitioner/requestor to file a motion seeking a ruling to reverse the NRC staff’s denial of access; NRC staff files copy of access determination with the presiding officer (or Chief Administrative Judge or other designated officer, as appropriate). If NRC staff finds ‘‘need’’ for SUNSI, the deadline for any party to the proceeding whose interest independent of the proceeding would be harmed by the release of the information to file a motion seeking a ruling to reverse the NRC staff’s grant of access. Deadline for NRC staff reply to motions to reverse NRC staff determination(s). (Receipt +30) If NRC staff finds standing and need for SUNSI, deadline for NRC staff to complete information processing and file motion for Protective Order and draft Non-Disclosure Affidavit. Deadline for applicant/licensee to file Non-Disclosure Agreement for SUNSI. If access granted: Issuance of presiding officer or other designated officer decision on motion for protective order for access to sensitive information (including schedule for providing access and submission of contentions) or decision reversing a final adverse determination by the NRC staff. Deadline for filing executed Non-Disclosure Affidavits. Access provided to SUNSI consistent with decision issuing the protective order. Deadline for submission of contentions whose development depends upon access to SUNSI. However, if more than 25 days remain between the petitioner’s receipt of (or access to) the information and the deadline for filing all other contentions (as established in the notice of hearing or opportunity for hearing), the petitioner may file its SUNSI contentions by that later deadline. (Contention receipt +25) Answers to contentions whose development depends upon access to SUNSI. 10 ............. 60 ............. 20 ............. 25 ............. 30 ............. 40 ............. A .............. A + 3 ........ jlentini on DSKJ8SOYB1PROD with NOTICES A + 28 ...... A + 53 ...... 2 Any motion for Protective Order or draft NonDisclosure Affidavit or Agreement for SUNSI must be filed with the presiding officer or the Chief Administrative Judge if the presiding officer has not VerDate Nov<24>2008 16:17 Jan 20, 2010 Jkt 220001 yet been designated, within 30 days of the deadline for the receipt of the written access request. 3 Requesters should note that the filing requirements of the NRC’s E-Filing Rule (72 FR 49139; August 28, 2007) apply to appeals of NRC PO 00000 Frm 00055 Fmt 4703 Sfmt 4703 staff determinations (because they must be served on a presiding officer or the Commission, as applicable), but not to the initial SUNSI request submitted to the NRC staff under these procedures. E:\FR\FM\21JAN1.SGM 21JAN1 Federal Register / Vol. 75, No. 13 / Thursday, January 21, 2010 / Notices 3497 ATTACHMENT 1—GENERAL TARGET SCHEDULE FOR PROCESSING AND RESOLVING REQUESTS FOR ACCESS TO SENSITIVE UNCLASSIFIED NON-SAFEGUARDS INFORMATION IN THIS PROCEEDING—Continued Day A + 60 ...... >A + 60 .... Event/activity (Answer receipt +7) Petitioner/Intervenor reply to answers. Decision on contention admission. [FR Doc. 2010–1080 Filed 1–20–10; 8:45 am] BILLING CODE 7590–01–P NUCLEAR REGULATORY COMMISSION [Docket Nos. 50–247 and 50–286; NRC– 2010–0006] Entergy Nuclear Operations, Inc., Entergy Nuclear Indian Point 2, LLC, Entergy Nuclear Indian Point 3, LLC,: Indian Point Nuclear Generating Unit Nos. 2 and 3; Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity To Request a Hearing, and Order Imposing Procedures for Access to Sensitive Unclassified Non-Safeguards Information AGENCY: Nuclear Regulatory Commission. ACTION: Notice of amendment and opportunity to request a hearing and to petition for leave to intervene. jlentini on DSKJ8SOYB1PROD with NOTICES DATES: Request for a hearing and/or petition for leave to intervene must be filed within 60 days after the date of publication of this notice in the Federal Register. Any potential party as defined in 10 CFR 2.4 who believes access to Sensitive Unclassified Non-Safeguards Information and/or Safeguards Information is necessary to respond to this notice must request document access within 10 days after the date of publication of this notice in the Federal Register. I. Introduction The U.S. Nuclear Regulatory Commission (NRC or the Commission) is considering an application for amendment to Facility Operating License Nos. DPR–26 and DPR–64, issued to Entergy Nuclear Operations, Inc. (Entergy) and Entergy Nuclear Indian Point 2, LLC, for operation of the Indian Point Nuclear Generating Unit No. 2 (IP2) and to Entergy and Entergy Nuclear Indian Point 3, LLC, for operation of the Indian Point Nuclear Generating Unit No. 3 (IP3), both located in Westchester County, New York. The proposed amendment would revise the IP2 and IP3 operating licenses to permit the transfer of spent fuel from VerDate Nov<24>2008 16:17 Jan 20, 2010 Jkt 220001 IP3 to IP2, using a newly-designed transfer cask, with plans for further transfer to the onsite independent spent fuel storage installation, on an asneeded basis as determined by Entergy’s fuel management needs. The July 8, 2009, application (Agencywide Documents Access and Management System (ADAMS) Accession No. ML091940177 and ML091940178), as supplemented by letters dated September 28 and October 26, 2009 (ADAMS Accession Nos. ML092950437 and ML093020080) contains proprietary information, which the Commission classifies as sensitive unclassified nonsafeguards information (SUNSI). Before issuance of the proposed license amendment, the Commission will have made findings required by the Atomic Energy Act of 1954, as amended (the Act), and the Commission’s regulations. These findings will be documented in a Safety Evaluation Report and an Environmental Assessment and/or an Environmental Impact Statement. II. Opportunity To Request a Hearing Within 60 days after the date of publication of this notice in the Federal Register, any person(s) whose interest may be affected by this action and who desires to participate as a party to this action, may file a request for a hearing and a petition to intervene with respect to whether the amendment to the subject facility operating licenses should be issued. Requests for a hearing and petitions for leave to intervene shall be filed in accordance with the Commission’s ‘‘Rules of Practice for Domestic Licensing Proceedings’’ in 10 CFR Part 2. Interested person(s) should consult a current copy of 10 CFR 2.309, ‘‘Hearing Requests, Petitions to Intervene, Requirements for Standing, and Contentions,’’ which is available at the Commission’s Public Document Room (PDR), located at One White Flint North, Room O1–F21, 11555 Rockville Pike (first floor), Rockville, Maryland. Publicly available records will be accessible from the Agencywide Documents Access and Management System’s (ADAMS) Public Electronic Reading Room on the Internet at the NRC Web site, https://www.nrc.gov/ reading-rm/doc-collections/cfr/. If a request for a hearing or petition for PO 00000 Frm 00056 Fmt 4703 Sfmt 4703 leave to intervene is filed by the above date, the Commission or a presiding officer designated by the Commission or by the Chief Administrative Judge of the Atomic Safety and Licensing Board Panel, will rule on the request and/or petition; and the Secretary or the Chief Administrative Judge of the Atomic Safety and Licensing Board will issue a notice of a hearing or an appropriate order. III. Petitions for Leave To Intervene As required by 10 CFR 2.309, a petition for leave to intervene or request for hearing shall set forth with particularity the interest of the petitioner/requester in the proceeding, and how that interest may be affected by the results of the proceeding. The petition should specifically explain the reasons why intervention should be permitted with particular reference to the following general requirements: (1) The name, address and telephone number of the requester or petitioner; (2) the nature of the requester’s/ petitioner’s right under the Act to be made a party to the proceeding; (3) the nature and extent of the requester’s/ petitioner’s property, financial, or other interest in the proceeding; and (4) the possible effect of any decision or order which may be entered in the proceeding on the requester’s/petitioner’s interest. The petition must also identify the specific contentions which the petitioner/requester seeks to have litigated in the proceeding. Each contention must consist of a specific statement of the issue of law or fact to be raised or controverted, as well as a brief explanation of the basis for the contention. The petitioner must demonstrate that the issue raised by each contention is within the scope of the proceeding and is material to the findings that the NRC must make to support the granting of the license amendment in response to the application. The petition must also include a concise statement of the alleged facts or expert opinion which support the contention and on which the petitioner intends to rely in proving the contention at the hearing. The petitioner must also provide references to those specific sources and documents of which the petitioner is aware and on which the petitioner intends to rely. E:\FR\FM\21JAN1.SGM 21JAN1

Agencies

[Federal Register Volume 75, Number 13 (Thursday, January 21, 2010)]
[Notices]
[Pages 3493-3497]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-1080]


=======================================================================
-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket Nos. 50-275 and 50-323; NRC-2009-0552]


Notice of Acceptance for Docketing of the Application, Notice of 
Opportunity for Hearing for Facility Operating License Nos. DPR-80 and 
DPR-82 for an Additional 20-Year Period; Pacific Gas & Electric 
Company, Diablo Canyon Nuclear Power Plant, Units 1 and 2; and Order 
Imposing Procedures for Access to Sensitive Unclassified Non-Safeguards 
Information (SUNSI) for Contention Preparation

    The U.S. Nuclear Regulatory Commission (NRC) is considering an 
application for the renewal of operating licenses DPR-80 and DPR-82, 
which authorize Pacific Gas & Electric Company (PG&E) to operate the 
Diablo Canyon Nuclear Power Plant (DCPP), Units 1 and 2, at 3411 
megawatts thermal, each. The renewed licenses would authorize the 
applicant to operate DCPP, Units 1 and 2, for an additional 20 years 
beyond the period specified in the current licenses. DCPP, Units 1 and 
2, are located near San Luis Obispo, California. The current operating 
licenses expire on November 2, 2024, and August 26, 2025, respectively.
    PG&E submitted the application dated November 23, 2009, pursuant to 
Title 10 of the Code of Federal Regulations, Part 54 (10 CFR part 54) 
to renew operating licenses DPR-80 and DPR-82. A notice of receipt and 
availability of the license renewal application (LRA) was published in 
the Federal Register on December 11, 2009 (74 FR 65811).
    The Commission has determined that PG&E has submitted sufficient 
information in accordance with 10 CFR Sections 2.101, 54.19, 54.21, 
54.22, 54.23, 51.45, and 51.53(c), to enable the staff to undertake a 
review of the application, and the application is therefore acceptable 
for docketing. The Commission will retain the current Docket Nos. 50-
275 and 50-323 for operating license Nos. DPR-80 and DPR-82. The 
determination to accept the LRA for docketing does not constitute a 
determination that the renewed licenses should be issued, and does not 
preclude the NRC staff from requesting additional information as the 
review proceeds.
    Before issuance of the requested renewed licenses, the NRC will 
have made the findings required by the Atomic Energy Act of 1954, as 
amended (the Act), and the Commission's rules and regulations. In 
accordance with 10 CFR 54.29, the NRC may issue a renewed license on 
the basis of its review if it finds that actions have been identified 
and have been or will be taken with respect to: (1) Managing the 
effects of aging during the period of extended operation on the 
functionality of structures and components that have been identified as 
requiring aging management review, and (2) time-limited aging analyses 
that have been identified as requiring review, such that there is 
reasonable assurance that the activities authorized by the renewed 
license will continue to be conducted in accordance with the current 
licensing basis (CLB) and that any changes made to the plant's CLB will 
comply with the Act and the Commission's regulations.
    Additionally, in accordance with 10 CFR 51.95(c), the NRC will 
prepare an environmental impact statement that is a supplement to the 
Commission's NUREG-1437, ``Generic Environmental Impact Statement for 
License Renewal of Nuclear Power Plants,'' dated May 1996. In 
considering the LRA, the Commission must find that the applicable 
requirements of subpart A of 10 CFR part 51 have been satisfied, and 
that matters raised under 10 CFR 2.335 have been addressed. Pursuant to 
10 CFR 51.26, and as part of the environmental scoping process, the 
staff intends to hold public scoping meetings. Detailed information 
regarding the environmental scoping meetings will be the subject of a 
separate Federal Register notice.
    Within 60 days after the date of publication of this Federal 
Register notice, any person whose interest may be affected by this 
proceeding and who wishes to participate as a party in the proceeding 
must file a written request for a hearing and a petition for leave to 
intervene with respect to the renewal of the licenses. Requests for a 
hearing or petitions for leave to intervene must be filed in accordance 
with the Commission's ``Rules of Practice for Domestic Licensing 
Proceedings and Issuance of Orders'' in 10 CFR part 2. Interested 
persons should consult a current copy of 10 CFR 2.309, which is 
available at the Commission's Public Document Room (PDR), located at 
One White Flint North, 11555 Rockville Pike (first floor), Rockville, 
Maryland 20852 and is accessible from the NRC's Agencywide Documents 
Access and Management System (ADAMS) Public Electronic Reading Room on 
the Internet at https://www.nrc.gov/reading-rm/adams.html. Persons who 
do not have access to the Internet or who encounter problems in 
accessing the documents located in ADAMS should contact the NRC's PDR 
reference staff by telephone at 1-800-397-4209, or 301-415-4737,

[[Page 3494]]

or by e-mail at PDR.Resource@nrc.gov. If a request for a hearing/
petition for leave to intervene is filed within the 60-day period, the 
Commission or a presiding officer designated by the Commission or by 
the Chief Administrative Judge of the Atomic Safety and Licensing Board 
Panel will rule on the request and/or petition; and the Secretary or 
the Chief Administrative Judge of the Atomic Safety and Licensing Board 
Panel will issue a notice of a hearing or an appropriate order. In the 
event that no request for a hearing or petition for leave to intervene 
is filed within the 60-day period, the NRC may, upon completion of its 
evaluations and upon making the findings required under 10 CFR parts 51 
and 54, renew the licenses without further notice.
    As required by 10 CFR 2.309, a petition for leave to intervene 
shall set forth with particularity the interest of the petitioner in 
the proceeding, and how that interest may be affected by the results of 
the proceeding, taking into consideration the limited scope of matters 
that may be considered pursuant to 10 CFR parts 51 and 54. The petition 
must specifically explain the reasons why intervention should be 
permitted with particular reference to the following factors: (1) The 
nature of the requestor's/petitioner's right under the Act to be made a 
party to the proceeding; (2) the nature and extent of the requestor's/
petitioner's property, financial, or other interest in the proceeding; 
and (3) the possible effect of any decision or order which may be 
entered in the proceeding on the requestor's/petitioner's interest. The 
petition must also set forth the specific contentions which the 
requestor/petitioner seeks to have litigated at the proceeding.
    Each contention must consist of a specific statement of the issue 
of law or fact to be raised or controverted. In addition, the 
requestor/petitioner shall provide a brief explanation of the bases of 
each contention and a concise statement of the alleged facts or the 
expert opinion that supports the contention on which the requestor/
petitioner intends to rely in proving the contention at the hearing. 
The requestor/petitioner must also provide references to those specific 
sources and documents of which the requestor/petitioner is aware and on 
which the requestor/petitioner intends to rely to establish those facts 
or expert opinion. The requestor/petitioner must provide sufficient 
information to show that a genuine dispute exists with the applicant on 
a material issue of law or fact. Contentions shall be limited to 
matters within the scope of the action under consideration. The 
contention must be one that, if proven, would entitle the requestor/
petitioner to relief. A requestor/petitioner who fails to satisfy these 
requirements with respect to at least one contention will not be 
permitted to participate as a party.
    The Commission requests that each contention be given a separate 
numeric or alpha designation within one of the following groups: (1) 
Technical (primarily related to safety concerns); (2) environmental; or 
(3) miscellaneous.
    As specified in 10 CFR 2.309, if two or more requestors/petitioners 
seek to co-sponsor a contention or propose substantially the same 
contention, the requestors/petitioners must jointly designate a 
representative who shall have the authority to act for the requestors/
petitioners with respect to that contention.
    All documents filed in NRC adjudicatory proceedings, including a 
request for hearing, a petition for leave to intervene, any motion or 
other document filed in the proceeding prior to the submission of a 
request for hearing or petition to intervene, and documents filed by 
interested governmental entities participating under 10 CFR 2.315(c), 
must be filed in accordance with the NRC E-Filing rule (72 FR 49139, 
August 28, 2007). The E-Filing process requires participants to submit 
and serve all adjudicatory documents over the internet, or in some 
cases to mail copies on electronic storage media. Participants may not 
submit paper copies of their filings unless they seek an exemption in 
accordance with the procedures described below.
    To comply with the procedural requirements of E-Filing, at least 
ten (10) days prior to the filing deadline, the participant should 
contact the Office of the Secretary by e-mail at 
hearing.docket@nrc.gov, or by telephone at (301) 415-1677, to request 
(1) a digital ID certificate, which allows the participant (or its 
counsel or representative) to digitally sign documents and access the 
E-Submittal server for any proceeding in which it is participating; and 
(2) advise the Secretary that the participant will be submitting a 
request or petition for hearing (even in instances in which the 
participant, or its counsel or representative, already holds an NRC-
issued digital ID certificate). Based upon this information, the 
Secretary will establish an electronic docket for the hearing in this 
proceeding if the Secretary has not already established an electronic 
docket.
    Information about applying for a digital ID certificate is 
available on NRC's public Web site at https://www.nrc.gov/site-help/e-submittals/apply-certificates.html. System requirements for accessing 
the E-Submittal server are detailed in NRC's ``Guidance for Electronic 
Submission,'' which is available on the agency's public Web site at 
https://www.nrc.gov/site-help/e-submittals.html. Participants may 
attempt to use other software not listed on the Web site, but should 
note that the NRC's E-Filing system does not support unlisted software, 
and the NRC Meta System Help Desk will not be able to offer assistance 
in using unlisted software.
    If a participant is electronically submitting a document to the NRC 
in accordance with the E-Filing rule, the participant must file the 
document using the NRC's online, Web-based submission form. In order to 
serve documents through EIE, users will be required to install a Web 
browser plug-in from the NRC Web site. Further information on the Web-
based submission form, including the installation of the Web browser 
plug-in, is available on the NRC's public Web site at https://www.nrc.gov/site-help/e-submittals.html.
    Once a participant has obtained a digital ID certificate and a 
docket has been created, the participant can then submit a request for 
hearing or petition for leave to intervene. Submissions should be in 
Portable Document Format (PDF) in accordance with NRC guidance 
available on the NRC public Web site at https://www.nrc.gov/site-help/e-submittals.html. A filing is considered complete at the time the 
documents are submitted through the NRC's E-Filing system. To be 
timely, an electronic filing must be submitted to the E-Filing system 
no later than 11:59 p.m. Eastern Time on the due date. Upon receipt of 
a transmission, the E-Filing system time-stamps the document and sends 
the submitter an e-mail notice confirming receipt of the document. The 
E-Filing system also distributes an e-mail notice that provides access 
to the document to the NRC Office of the General Counsel and any others 
who have advised the Office of the Secretary that they wish to 
participate in the proceeding, so that the filer need not serve the 
documents on those participants separately. Therefore, applicants and 
other participants (or their counsel or representative) must apply for 
and receive a digital ID certificate before a hearing request/petition 
to intervene is filed so that they can obtain access to the document 
via the E-Filing system.
    A person filing electronically using the agency's adjudicatory E-
Filing

[[Page 3495]]

system may seek assistance by contacting the NRC Meta System Help Desk 
through the ``Contact Us'' link located on the NRC Web site at https://www.nrc.gov/site-help/e-submittals.html, by e-mail at 
MSHD.Resource@nrc.gov, or by a toll-free call at (866) 672-7640. The 
NRC Meta System Help Desk is available between 8 a.m. and 8 p.m., 
Eastern Time, Monday through Friday, excluding government holidays.
    Participants who believe that they have a good cause for not 
submitting documents electronically must file an exemption request, in 
accordance with 10 CFR 2.302(g), with their initial paper filing 
requesting authorization to continue to submit documents in paper 
format. Such filings must be submitted by: (1) First class mail 
addressed to the Office of the Secretary of the Commission, U.S. 
Nuclear Regulatory Commission, Washington, DC 20555-0001, Attention: 
Rulemaking and Adjudications Staff; or (2) courier, express mail, or 
expedited delivery service to the Office of the Secretary, Sixteenth 
Floor, One White Flint North, 11555 Rockville Pike, Rockville, 
Maryland, 20852, Attention: Rulemaking and Adjudications Staff. 
Participants filing a document in this manner are responsible for 
serving the document on all other participants. Filing is considered 
complete by first-class mail as of the time of deposit in the mail, or 
by courier, express mail, or expedited delivery service upon depositing 
the document with the provider of the service. A presiding officer, 
having granted an exemption request from using E-Filing, may require a 
participant or party to use E-Filing if the presiding officer 
subsequently determines that the reason for granting the exemption from 
use of E-Filing no longer exists.
    Documents submitted in adjudicatory proceedings will appear in 
NRC's electronic hearing docket which is available to the public at 
https://ehd.nrc.gov/EHD_Proceeding/home.asp, unless excluded pursuant 
to an order of the Commission, or the presiding officer. Participants 
are requested not to include personal privacy information, such as 
social security numbers, home addresses, or home phone numbers in their 
filings, unless an NRC regulation or other law requires submission of 
such information. With respect to copyrighted works, except for limited 
excerpts that serve the purpose of the adjudicatory filings and would 
constitute a Fair Use application, participants are requested not to 
include copyrighted materials in their submission.
    Petitions for leave to intervene must be filed no later than 60 
days from the date of publication of this Federal Register notice. Non-
timely filings will not be entertained absent a determination by the 
presiding officer that the petition or request should be granted or the 
contentions should be admitted, based on a balancing of the factors 
specified in 10 CFR 2.309(c)(1)(i)-(viii).
    Detailed information about the license renewal process can be found 
under the Nuclear Reactors icon at https://www.nrc.gov/reactors/operating/licensing/renewal.html on the NRC's Web site. Copies of the 
application to renew the operating licenses for DCPP are available for 
public inspection at the Commission's PDR, located at One White Flint 
North, 11555 Rockville Pike (first floor), Rockville, Maryland 20852-
2738, and at https://www.nrc.gov/reactors/operating/licensing/renewal/applications.html, the NRC's Web site while the application is under 
review. The application may be accessed in ADAMS through the NRC's 
Public Electronic Reading Room on the Internet at https://www.nrc.gov/reading-rm/adams.html under ADAMS Accession Number ML093340125. As 
stated above, persons who do not have access to ADAMS or who encounter 
problems in accessing the documents located in ADAMS may contact the 
NRC PDR reference staff by telephone at 1-800-397-4209 or 301-415-4737, 
or by e-mail to PDR.Resource@nrc.gov.
    The NRC staff has verified that a copy of the license renewal 
application is also available to local residents near the site at the 
San Luis Obispo Public Library, 995 Palm Street, San Luis Obispo, 
California 93401, and at the Paso Robles Public Library, 1000 Spring 
Street, Paso Robles, California 93446.

Order Imposing Procedures for Access to Sensitive Unclassified Non-
Safeguards Information for Contention Preparation

    A. This Order contains instructions regarding how potential parties 
to this proceeding may request access to documents containing Sensitive 
Unclassified Non-Safeguards Information (SUNSI).
    B. Within 10 days after publication of this notice of hearing and 
opportunity to petition for leave to intervene, any potential party who 
believes access to SUNSI is necessary to respond to this notice may 
request such access. A ``potential party'' is any person who intends to 
participate as a party by demonstrating standing and filing an 
admissible contention under 10 CFR 2.309. Requests for access to SUNSI 
submitted later than 10 days after publication will not be considered 
absent a showing of good cause for the late filing, addressing why the 
request could not have been filed earlier.
    C. The requestor shall submit a letter requesting permission to 
access SUNSI to the Office of the Secretary, U.S. Nuclear Regulatory 
Commission, Washington, DC 20555-0001, Attention: Rulemakings and 
Adjudications Staff, and provide a copy to the Associate General 
Counsel for Hearings, Enforcement and Administration, Office of the 
General Counsel, Washington, DC 20555-0001. The expedited delivery or 
courier mail address for both offices is: U.S. Nuclear Regulatory 
Commission, 11555 Rockville Pike, Rockville, Maryland 20852. The e-mail 
address for the Office of the Secretary and the Office of the General 
Counsel are Hearing.Docket@nrc.gov and OGCmailcenter@nrc.gov, 
respectively.\1\ The request must include the following information:
---------------------------------------------------------------------------

    \1\ While a request for hearing or petition to intervene in this 
proceeding must comply with the filing requirements of the NRC's 
``E-Filing Rule,'' the initial request to access SUNSI under these 
procedures should be submitted as described in this paragraph.
---------------------------------------------------------------------------

    (1) A description of the licensing action with a citation to this 
Federal Register notice;
    (2) The name and address of the potential party and a description 
of the potential party's particularized interest that could be harmed 
by the action identified in C.(1);
    (3) The identity of the individual or entity requesting access to 
SUNSI and the requestor's basis for the need for the information in 
order to meaningfully participate in this adjudicatory proceeding. In 
particular, the request must explain why publicly-available versions of 
the information requested would not be sufficient to provide the basis 
and specificity for a proffered contention;
    D. Based on an evaluation of the information submitted under 
paragraph C.(3) the NRC staff will determine within 10 days of receipt 
of the request whether:
    (1) There is a reasonable basis to believe the petitioner is likely 
to establish standing to participate in this NRC proceeding; and
    (2) The requestor has established a legitimate need for access to 
SUNSI.
    E. If the NRC staff determines that the requestor satisfies both 
D.(1) and D.(2) above, the NRC staff will notify the requestor in 
writing that access to SUNSI has been granted. The written notification 
will contain instructions on how the requestor may obtain copies of

[[Page 3496]]

the requested documents, and any other conditions that may apply to 
access to those documents. These conditions may include, but are not 
limited to, the signing of a Non-Disclosure Agreement or Affidavit, or 
Protective Order \2\ setting forth terms and conditions to prevent the 
unauthorized or inadvertent disclosure of SUNSI by each individual who 
will be granted access to SUNSI.
---------------------------------------------------------------------------

    \2\ Any motion for Protective Order or draft Non-Disclosure 
Affidavit or Agreement for SUNSI must be filed with the presiding 
officer or the Chief Administrative Judge if the presiding officer 
has not yet been designated, within 30 days of the deadline for the 
receipt of the written access request.
---------------------------------------------------------------------------

    F. Filing of Contentions. Any contentions in these proceedings that 
are based upon the information received as a result of the request made 
for SUNSI must be filed by the requestor no later than 25 days after 
the requestor is granted access to that information. However, if more 
than 25 days remain between the date the petitioner is granted access 
to the information and the deadline for filing all other contentions 
(as established in the notice of hearing or opportunity for hearing), 
the petitioner may file its SUNSI contentions by that later deadline.
    G. Review of Denials of Access.
    (1) If the request for access to SUNSI is denied by the NRC staff 
either after a determination on standing and need for access, or after 
a determination on trustworthiness and reliability, the NRC staff shall 
immediately notify the requestor in writing, briefly stating the reason 
or reasons for the denial.
    (2) The requestor may challenge the NRC staff's adverse 
determination by filing a challenge within 5 days of receipt of that 
determination with: (a) The presiding officer designated in this 
proceeding; (b) if no presiding officer has been appointed, the Chief 
Administrative Judge, or if he or she is unavailable, another 
administrative judge, or an administrative law judge with jurisdiction 
pursuant to 10 CFR 2.318(a); or (c) if another officer has been 
designated to rule on information access issues, with that officer.
    H. Review of Grants of Access. A party other than the requestor may 
challenge an NRC staff determination granting access to SUNSI whose 
release would harm that party's interest independent of the proceeding. 
Such a challenge must be filed with the Chief Administrative Judge 
within 5 days of the notification by the NRC staff of its grant of 
access.
    If challenges to the NRC staff determinations are filed, these 
procedures give way to the normal process for litigating disputes 
concerning access to information. The availability of interlocutory 
review by the Commission of orders ruling on such NRC staff 
determinations (whether granting or denying access) is governed by 10 
CFR 2.311.\3\
---------------------------------------------------------------------------

    \3\ Requesters should note that the filing requirements of the 
NRC's E-Filing Rule (72 FR 49139; August 28, 2007) apply to appeals 
of NRC staff determinations (because they must be served on a 
presiding officer or the Commission, as applicable), but not to the 
initial SUNSI request submitted to the NRC staff under these 
procedures.
---------------------------------------------------------------------------

    I. The Commission expects that the NRC staff and presiding officers 
(and any other reviewing officers) will consider and resolve requests 
for access to SUNSI, and motions for protective orders, in a timely 
fashion in order to minimize any unnecessary delays in identifying 
those petitioners who have standing and who have propounded contentions 
meeting the specificity and basis requirements in 10 CFR part 2. 
Attachment 1 to this Order summarizes the general target schedule for 
processing and resolving requests under these procedures.
    It is so ordered.

    Dated at Rockville, Maryland, this 14th day of January 2010.

    For the Commission.
Annette L. Vietti-Cook,
Secretary of the Commission.

   Attachment 1--General Target Schedule for Processing and Resolving
Requests for Access to Sensitive Unclassified Non-Safeguards Information
                           in This Proceeding
------------------------------------------------------------------------
          Day                            Event/activity
------------------------------------------------------------------------
0.....................  Publication of Federal Register notice of
                         hearing and opportunity to petition for leave
                         to intervene, including order with instructions
                         for access requests.
10....................  Deadline for submitting requests for access to
                         Sensitive Unclassified Non-Safeguards
                         Information (SUNSI) with information:
                         supporting the standing of a potential party
                         identified by name and address; describing the
                         need for the information in order for the
                         potential party to participate meaningfully in
                         an adjudicatory proceeding.
60....................  Deadline for submitting petition for
                         intervention containing: (i) Demonstration of
                         standing; (ii) all contentions whose
                         formulation does not require access to SUNSI
                         (+25 Answers to petition for intervention; +7
                         petitioner/requestor reply).
20....................  Nuclear Regulatory Commission (NRC) staff
                         informs the requestor of the staff's
                         determination whether the request for access
                         provides a reasonable basis to believe standing
                         can be established and shows need for SUNSI.
                         (NRC staff also informs any party to the
                         proceeding whose interest independent of the
                         proceeding would be harmed by the release of
                         the information.) If NRC staff makes the
                         finding of need for SUNSI and likelihood of
                         standing, NRC staff begins document processing
                         (preparation of redactions or review of
                         redacted documents).
25....................  If NRC staff finds no ``need'' or no likelihood
                         of standing, the deadline for petitioner/
                         requestor to file a motion seeking a ruling to
                         reverse the NRC staff's denial of access; NRC
                         staff files copy of access determination with
                         the presiding officer (or Chief Administrative
                         Judge or other designated officer, as
                         appropriate). If NRC staff finds ``need'' for
                         SUNSI, the deadline for any party to the
                         proceeding whose interest independent of the
                         proceeding would be harmed by the release of
                         the information to file a motion seeking a
                         ruling to reverse the NRC staff's grant of
                         access.
30....................  Deadline for NRC staff reply to motions to
                         reverse NRC staff determination(s).
40....................  (Receipt +30) If NRC staff finds standing and
                         need for SUNSI, deadline for NRC staff to
                         complete information processing and file motion
                         for Protective Order and draft Non-Disclosure
                         Affidavit. Deadline for applicant/licensee to
                         file Non-Disclosure Agreement for SUNSI.
A.....................  If access granted: Issuance of presiding officer
                         or other designated officer decision on motion
                         for protective order for access to sensitive
                         information (including schedule for providing
                         access and submission of contentions) or
                         decision reversing a final adverse
                         determination by the NRC staff.
A + 3.................  Deadline for filing executed Non-Disclosure
                         Affidavits. Access provided to SUNSI consistent
                         with decision issuing the protective order.
A + 28................  Deadline for submission of contentions whose
                         development depends upon access to SUNSI.
                         However, if more than 25 days remain between
                         the petitioner's receipt of (or access to) the
                         information and the deadline for filing all
                         other contentions (as established in the notice
                         of hearing or opportunity for hearing), the
                         petitioner may file its SUNSI contentions by
                         that later deadline.
A + 53................  (Contention receipt +25) Answers to contentions
                         whose development depends upon access to SUNSI.

[[Page 3497]]

 
A + 60................  (Answer receipt +7) Petitioner/Intervenor reply
                         to answers.
>A + 60...............  Decision on contention admission.
 
------------------------------------------------------------------------

[FR Doc. 2010-1080 Filed 1-20-10; 8:45 am]
BILLING CODE 7590-01-P