Powertech (USA) Inc.; Dewey-Burdock Project; New Source Material License Application; Notice of Intent To Prepare a Supplemental Environmental Impact Statement, 3261-3262 [2010-955]

Download as PDF pwalker on DSK8KYBLC1PROD with NOTICES Federal Register / Vol. 75, No. 12 / Wednesday, January 20, 2010 / Notices Mine: E4–1 Mine, MSHA I.D. No. 15– 18565, located in Perry County, Kentucky. Regulation Affected: 30 CFR 75.503 (Permissible electric face equipment; maintenance). Modification Request: The petitioner requests a modification of the existing standard to permit the E4–1 Mine to increase the maximum length of trailing cables supplying power to permissible pumps in the mines. The petitioner states that: (1) This petition will apply only to trailing cables supplying threephase, 480-volt power for permissible pumps; (2) the maximum length of the 480-volt power for permissible pump will be 4,000 feet; (3) all circuit breakers used to protect trailing cables exceeding the pump approval length or Table 9 of Part 18 will have an instantaneous trip unit calibrated to trip at 75 percent of phase to phase short-circuit current. The trip setting of these circuit breakers will be sealed or locked, and these circuit breakers will have permanent legible labels. Each label will identify the circuit breaker as being suitable for protecting the trailing cables, and the labels will be maintained legible. In instances where a 75 percent instantaneous set point will not allow a pump to start due to motor inrush, a thermal magnetic breaker will be furnished. The thermal rating of the circuit breaker will be no greater than 75 percent of the available short-circuit current and the instantaneous setting will be adjusted one setting above the motor inrush trip point. This setting will also be sealed or locked; (4) replacement instantaneous trip units used to protect pump trailing cables exceeding the length of Table 9 of Part 18 will be calibrated to trip at 75 percent of the available phase to phase short circuit current and this setting will be sealed or locked; (5) permanent warning labels will be installed and maintained on the cover(s) of the power center to identify the location of each sealed or locked short-circuit protection device. These labels will warn miners not to change or alter the short circuit settings; (6) the pump circuits attached to this petition have greater lengths than approved or in Table 9. All future pump installation with excessive cable lengths will have a short-circuit survey conducted and items 1–5 will be implemented. A copy of each pump’s short-circuit survey will be available at the mine site for inspection; and (7) the petitioner’s alternative method will not be implemented until designated miners have been trained to examine the integrity of the seals or locks, verify the short-circuit settings, and perform proper procedures for examining VerDate Nov<24>2008 16:06 Jan 19, 2010 Jkt 220001 trailing cables for defects and damage. The petitioner further states that within 60 days after the Proposed Decision and Order becomes final, proposed revisions for approved 30 CFR Part 48 training plan at any of the listed mines will be submitted to the Coal Mine Safety and Health District Manager. The training plan will include: (a) Training in the mining methods and operating procedures for protecting the trailing cables against damage; (b) training in proper procedures for examining the trailing cables to ensure they are in safe operating condition; (c) training in hazards of setting the instantaneous circuit breakers too high to adequately protect the trailing cables; and (d) training in how to verify that the circuit interrupting device(s) protecting the trailing cable(s) are properly set and maintained; and (e) the procedures of 30 CFR 48.3 for approval of proposed revisions to already approved training plans will apply. The petitioner asserts that the proposed alternative method will at all times guarantee no less than the same measure of protection to all miners at Perry County Coal Corporation than is provided the existing standard. Dated: January 14, 2010. Patricia W. Silvey, Director, Office of Standards, Regulations and Variances. [FR Doc. 2010–935 Filed 1–19–10; 8:45 am] BILLING CODE 4510–43–P NUCLEAR REGULATORY COMMISSION [Docket No. 40–9075; NRC–2009–0575] Powertech (USA) Inc.; Dewey-Burdock Project; New Source Material License Application; Notice of Intent To Prepare a Supplemental Environmental Impact Statement AGENCY: U.S. Nuclear Regulatory Commission. ACTION: Notice of Intent (NOI). SUMMARY: By letter dated August 10, 2009, Powertech (USA) (Powertech) submitted to the U.S. Nuclear Regulatory Commission (NRC) an application for a new source material license. The requested license, or the proposed action, would authorize the construction, operation, and decommissioning of Powertech’s proposed in-situ uranium recovery (ISR, also known as in-situ leach) facilities, and would require restoration of the aquifer from which the uranium would be extracted. A notice of receipt and availability of the license application, PO 00000 Frm 00069 Fmt 4703 Sfmt 4703 3261 including the Environmental Report (ER), and opportunity to request a hearing was published in the Federal Register on January 05, 2010 (75 FR 467–471). The purpose of this notice of intent is to inform the public that the NRC will be preparing a site-specific Supplemental Environmental Impact Statement (SEIS) regarding the proposed action. The SEIS will tier off of the Generic Environmental Impact Statement for In-Situ Leach Uranium Milling Facilities (ISR GEIS) that was published in 2009. As outlined in 36 CFR 800.8, ‘‘Coordination with the National Environmental Policy Act,’’ the NRC plans to use the environmental review process set forth in its 10 CFR Part 51 regulations to coordinate compliance with Section 106 of the National Historic Preservation Act. FOR FURTHER INFORMATION CONTACT: For general information on the NRC National Environmental Policy Act (NEPA) process or the environmental review process related to the DeweyBurdock Uranium Project application, please contact the NRC Environmental Project Manager, Haimanot Yilma, at (301) 415–8029 or haimanot.yilma@nrc.gov. Information and documents associated with the Dewey-Burdock Uranium Project, including the license application, are available for public review through our electronic reading room: https://www.nrc.gov/reading-rm/ adams.html and on the NRC’s DeweyBurdock Uranium Project web page: https://www.nrc.gov/info-finder/ materials/uranium/apps-in-review/ dewey-burdock-new-app-review.html. Documents may also be obtained from NRC’s Public Document Room at the U.S. Nuclear Regulatory Commission Headquarters, 11555 Rockville Pike (first floor), Rockville, Maryland. SUPPLEMENTARY INFORMATION: 1.0 Background Powertech submitted its application for a 10 CFR Part 40 license by letter dated August 10, 2009. A notice of receipt and availability of the license application, including the ER, and opportunity to request a hearing was published in the Federal Register on January 5, 2010 (75 FR 467471). The NRC is required by 10 CFR 51.20(b)(8) to prepare an environmental impact statement (EIS) or supplement to an EIS for the issuance of a license to possess and use source material for uranium milling. The ISR GEIS and the site-specific SEIS will meet this regulatory requirement. The purpose of this NOI is to inform the public that the E:\FR\FM\20JAN1.SGM 20JAN1 3262 Federal Register / Vol. 75, No. 12 / Wednesday, January 20, 2010 / Notices NRC staff, as part of its review of Powertech’s application, is preparing a draft SEIS for public comment that will tier off of the ISR GEIS (NUREG–1910). While NRC’s Part 51 regulations do not require scoping for SEISs, the NRC staff is planning to place ads in newspapers serving communities near the proposed site, requesting information and comments from the public regarding the proposed action. NRC staff may also use relevant information gathered during scoping for the GEIS to define the scope of the SEIS. In preparing the SEIS, the NRC staff is consulting with Bureau of Land Management; Region 8 Environmental Protection Agency; U.S. Fish & Wildlife Service; U.S. Army Corps of Engineers; South Dakota Department of Environment and Natural Resources; South Dakota State Historic Preservation Office; potentially interested Tribes and public interest groups; South Dakota Game and Fish Department; and the Forest Service. The NRC has begun evaluating the potential environmental impacts associated with the proposed ISR facility in parallel with the ongoing safety review of the license application. The environmental evaluation will be documented in draft and final SEISs in accordance with NEPA and NRC’s implementing regulations contained in 10 CFR Part 51. pwalker on DSK8KYBLC1PROD with NOTICES 2.0 Dewey-Burdock ISR Facilities The facilities, if licensed, would include a central processing plant, satellite facility, accompanying wellfields (including injection and production wells), and ion exchange columns. The ISR process involves the dissolution of the water-soluble uranium from the mineralized host sandstone rock by pumping oxidants (oxygen or hydrogen peroxide) and chemical compounds (sodium bicarbonate) through a series of injection wells. The uranium-rich solution is transferred from production wells to either the central processing plant or satellite facility for uranium concentration using ion exchange columns. Final processing is conducted in the central processing plant to produce yellowcake, which would be sold to offsite facilities for further processing and eventual use as commercial fuel in nuclear power reactors. 3.0 Alternatives To Be Evaluated No-Action—The no-action alternative would be to deny the license application. Under this alternative, the NRC would not issue the license. This serves as a baseline for comparison. VerDate Nov<24>2008 16:06 Jan 19, 2010 Jkt 220001 Proposed action—The proposed federal action is to issue a license authorizing the possession and use of source material at the proposed ISR facilities. The license review process analyzes the safety and environmental issues related to the construction, operation, and decommissioning of the ISR facilities, and the restoration of the aquifer from which the uranium would be extracted. The ISR facilities would be located near Edgemont, South Dakota in Custer and Fall River Counties. The applicant would be issued an NRC license under the provisions of 10 CFR Part 40. Other alternatives not listed here may be identified through the environmental review process. 4.0 Environmental Impact Areas To Be Analyzed The following areas have been tentatively identified for analysis in the SEIS: • Land Use: Plans, policies, and controls; • Transportation: Transportation modes, routes, quantities, and risk estimates; • Geology and Soils: Physical geography, topography, geology, and soil characteristics; • Water Resources: Surface and groundwater hydrology, water use and quality, and the potential for degradation; • Ecology: Wetlands, aquatic, terrestrial, economically and recreationally; important species, and threatened and endangered species; • Air Quality: Meteorological conditions, ambient background, pollutant sources, and the potential for degradation; • Noise: Ambient, sources, and sensitive receptors; • Historical and Cultural Resources: Historical, archaeological, and traditional cultural resources; • Visual and Scenic Resources: Landscape characteristics, manmade features and viewshed; • Socioeconomics: Demography, economic base, labor pool, housing, transportation, utilities, public services/ facilities, and education; • Environmental Justice: Potential disproportionately high and adverse impacts to minority and low-income populations; • Public and Occupational Health: Potential public and occupational consequences from construction, routine operation, transportation, and credible accident scenarios (including natural events); • Waste Management: Types of wastes expected to be generated, handled, and stored; and PO 00000 Frm 00070 Fmt 4703 Sfmt 4703 • Cumulative Effects: Impacts from past, present, and reasonably foreseeable actions at and near the site(s). This list is not intended to be all inclusive, nor is it a predetermination of potential environmental impacts. 5.0 The NEPA Process The SEIS for the Dewey-Burdock Uranium Project will be prepared pursuant to the NRC’s NEPA regulations at 10 CFR Part 51. The NRC will conduct its environmental review of the application and as soon as practicable, the NRC and its contractor will prepare and publish a draft SEIS. The NRC currently plans to have a 45-day public comment period for the draft SEIS. Availability of the draft SEIS and the dates of the public comment period will be announced in the Federal Register and the NRC Web site: https:// www.nrc.gov. The final SEIS will include responses to public comments received on the draft SEIS. Dated at Rockville, Maryland, this 12th day of January, 2010. For the Nuclear Regulatory Commission. Patrice M. Bubar, Deputy Director, Environmental Protection and Performance Assessment Directorate, Division of Waste Management and Environmental Protection, Office of Federal and State Materials and Environmental Management Programs. [FR Doc. 2010–955 Filed 1–19–10; 8:45 am] BILLING CODE 7590–01–P NUCLEAR REGULATORY COMMISSION Advisory Committee on Reactor Safeguards; Meeting of the ACRS Subcommittee on AP1000; Revision to February 2–3, 2010 ACRS Meeting Federal Register Notice The Federal Register Notice for the ACRS Subcommittee Meeting on AP1000 scheduled to be held on February 2–3, 2010, is being revised to notify the following: The meeting will be open to public attendance with exception of portions that may be closed to protect unclassified safeguards information or information that is proprietary to Westinghouse Electric Company and its contractors, pursuant to 5 U.S.C. 552b(c)(3) and (4). The notice of this meeting was previously published in the Federal Register on Wednesday, January 13, 2010 [75 FR 1831]. All other items remain the same as previously published. Further information regarding this meeting can be obtained by contacting E:\FR\FM\20JAN1.SGM 20JAN1

Agencies

[Federal Register Volume 75, Number 12 (Wednesday, January 20, 2010)]
[Notices]
[Pages 3261-3262]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-955]


=======================================================================
-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 40-9075; NRC-2009-0575]


Powertech (USA) Inc.; Dewey-Burdock Project; New Source Material 
License Application; Notice of Intent To Prepare a Supplemental 
Environmental Impact Statement

AGENCY: U.S. Nuclear Regulatory Commission.

ACTION: Notice of Intent (NOI).

-----------------------------------------------------------------------

SUMMARY: By letter dated August 10, 2009, Powertech (USA) (Powertech) 
submitted to the U.S. Nuclear Regulatory Commission (NRC) an 
application for a new source material license. The requested license, 
or the proposed action, would authorize the construction, operation, 
and decommissioning of Powertech's proposed in-situ uranium recovery 
(ISR, also known as in-situ leach) facilities, and would require 
restoration of the aquifer from which the uranium would be extracted. A 
notice of receipt and availability of the license application, 
including the Environmental Report (ER), and opportunity to request a 
hearing was published in the Federal Register on January 05, 2010 (75 
FR 467-471).
    The purpose of this notice of intent is to inform the public that 
the NRC will be preparing a site-specific Supplemental Environmental 
Impact Statement (SEIS) regarding the proposed action. The SEIS will 
tier off of the Generic Environmental Impact Statement for In-Situ 
Leach Uranium Milling Facilities (ISR GEIS) that was published in 2009. 
As outlined in 36 CFR 800.8, ``Coordination with the National 
Environmental Policy Act,'' the NRC plans to use the environmental 
review process set forth in its 10 CFR Part 51 regulations to 
coordinate compliance with Section 106 of the National Historic 
Preservation Act.

FOR FURTHER INFORMATION CONTACT: For general information on the NRC 
National Environmental Policy Act (NEPA) process or the environmental 
review process related to the Dewey- Burdock Uranium Project 
application, please contact the NRC Environmental Project Manager, 
Haimanot Yilma, at (301) 415-8029 or haimanot.yilma@nrc.gov.
    Information and documents associated with the Dewey-Burdock Uranium 
Project, including the license application, are available for public 
review through our electronic reading room: https://www.nrc.gov/reading-rm/adams.html and on the NRC's Dewey-Burdock Uranium Project web page: 
https://www.nrc.gov/info-finder/materials/uranium/apps-in-review/dewey-burdock-new-app-review.html. Documents may also be obtained from NRC's 
Public Document Room at the U.S. Nuclear Regulatory Commission 
Headquarters, 11555 Rockville Pike (first floor), Rockville, Maryland.

SUPPLEMENTARY INFORMATION:

1.0 Background

    Powertech submitted its application for a 10 CFR Part 40 license by 
letter dated August 10, 2009. A notice of receipt and availability of 
the license application, including the ER, and opportunity to request a 
hearing was published in the Federal Register on January 5, 2010 (75 FR 
467471).
    The NRC is required by 10 CFR 51.20(b)(8) to prepare an 
environmental impact statement (EIS) or supplement to an EIS for the 
issuance of a license to possess and use source material for uranium 
milling. The ISR GEIS and the site-specific SEIS will meet this 
regulatory requirement. The purpose of this NOI is to inform the public 
that the

[[Page 3262]]

NRC staff, as part of its review of Powertech's application, is 
preparing a draft SEIS for public comment that will tier off of the ISR 
GEIS (NUREG-1910). While NRC's Part 51 regulations do not require 
scoping for SEISs, the NRC staff is planning to place ads in newspapers 
serving communities near the proposed site, requesting information and 
comments from the public regarding the proposed action. NRC staff may 
also use relevant information gathered during scoping for the GEIS to 
define the scope of the SEIS. In preparing the SEIS, the NRC staff is 
consulting with Bureau of Land Management; Region 8 Environmental 
Protection Agency; U.S. Fish & Wildlife Service; U.S. Army Corps of 
Engineers; South Dakota Department of Environment and Natural 
Resources; South Dakota State Historic Preservation Office; potentially 
interested Tribes and public interest groups; South Dakota Game and 
Fish Department; and the Forest Service.
    The NRC has begun evaluating the potential environmental impacts 
associated with the proposed ISR facility in parallel with the ongoing 
safety review of the license application. The environmental evaluation 
will be documented in draft and final SEISs in accordance with NEPA and 
NRC's implementing regulations contained in 10 CFR Part 51.

2.0 Dewey-Burdock ISR Facilities

    The facilities, if licensed, would include a central processing 
plant, satellite facility, accompanying wellfields (including injection 
and production wells), and ion exchange columns. The ISR process 
involves the dissolution of the water-soluble uranium from the 
mineralized host sandstone rock by pumping oxidants (oxygen or hydrogen 
peroxide) and chemical compounds (sodium bicarbonate) through a series 
of injection wells. The uranium-rich solution is transferred from 
production wells to either the central processing plant or satellite 
facility for uranium concentration using ion exchange columns. Final 
processing is conducted in the central processing plant to produce 
yellowcake, which would be sold to offsite facilities for further 
processing and eventual use as commercial fuel in nuclear power 
reactors.

3.0 Alternatives To Be Evaluated

    No-Action--The no-action alternative would be to deny the license 
application. Under this alternative, the NRC would not issue the 
license. This serves as a baseline for comparison.
    Proposed action--The proposed federal action is to issue a license 
authorizing the possession and use of source material at the proposed 
ISR facilities. The license review process analyzes the safety and 
environmental issues related to the construction, operation, and 
decommissioning of the ISR facilities, and the restoration of the 
aquifer from which the uranium would be extracted. The ISR facilities 
would be located near Edgemont, South Dakota in Custer and Fall River 
Counties. The applicant would be issued an NRC license under the 
provisions of 10 CFR Part 40.
    Other alternatives not listed here may be identified through the 
environmental review process.

4.0 Environmental Impact Areas To Be Analyzed

    The following areas have been tentatively identified for analysis 
in the SEIS:
     Land Use: Plans, policies, and controls;
     Transportation: Transportation modes, routes, quantities, 
and risk estimates;
     Geology and Soils: Physical geography, topography, 
geology, and soil characteristics;
     Water Resources: Surface and groundwater hydrology, water 
use and quality, and the potential for degradation;
     Ecology: Wetlands, aquatic, terrestrial, economically and 
recreationally; important species, and threatened and endangered 
species;
     Air Quality: Meteorological conditions, ambient 
background, pollutant sources, and the potential for degradation;
     Noise: Ambient, sources, and sensitive receptors;
     Historical and Cultural Resources: Historical, 
archaeological, and traditional cultural resources;
     Visual and Scenic Resources: Landscape characteristics, 
manmade features and viewshed;
     Socioeconomics: Demography, economic base, labor pool, 
housing, transportation, utilities, public services/facilities, and 
education;
     Environmental Justice: Potential disproportionately high 
and adverse impacts to minority and low-income populations;
     Public and Occupational Health: Potential public and 
occupational consequences from construction, routine operation, 
transportation, and credible accident scenarios (including natural 
events);
     Waste Management: Types of wastes expected to be 
generated, handled, and stored; and
     Cumulative Effects: Impacts from past, present, and 
reasonably foreseeable actions at and near the site(s).
    This list is not intended to be all inclusive, nor is it a 
predetermination of potential environmental impacts.

5.0 The NEPA Process

    The SEIS for the Dewey-Burdock Uranium Project will be prepared 
pursuant to the NRC's NEPA regulations at 10 CFR Part 51. The NRC will 
conduct its environmental review of the application and as soon as 
practicable, the NRC and its contractor will prepare and publish a 
draft SEIS. The NRC currently plans to have a 45-day public comment 
period for the draft SEIS. Availability of the draft SEIS and the dates 
of the public comment period will be announced in the Federal Register 
and the NRC Web site: https://www.nrc.gov. The final SEIS will include 
responses to public comments received on the draft SEIS.

    Dated at Rockville, Maryland, this 12th day of January, 2010.
    For the Nuclear Regulatory Commission.

Patrice M. Bubar,
Deputy Director, Environmental Protection and Performance Assessment 
Directorate, Division of Waste Management and Environmental Protection, 
Office of Federal and State Materials and Environmental Management 
Programs.
[FR Doc. 2010-955 Filed 1-19-10; 8:45 am]
BILLING CODE 7590-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.