p. Pre-filing process schedule. The
pre-filing process will be conducted
pursuant to the following tentative
schedule. Snohomish PUD plans to
complete studies in 2010 to provide
further support for the environmental
analysis. Revisions to the schedule
below may be made based on staff’s
review of the draft application and any
comments received.
Milestone
Date
Comments on pre-filing materials due.
Issuance of meeting
notice (if needed).
Public meeting/technical conference (if
needed).
Issuance of notice
concluding pre-filing process and
ILP waiver request
determination.
February 26, 2010.
March 15, 2010.
April 14, 2010.
March 28, 2010 (if
no meeting is
needed). April 29,
2010 (if meeting
is needed).
q. Register online at https://ferc.gov/
esubscribenow.htm to be notified via email of new filing and issuances related
to this or other pending projects. For
assistance, contact FERC Online
Support.
Kimberly D. Bose,
Secretary.
[FR Doc. 2010–64 Filed 1–7–10; 8:45 am]
BILLING CODE 6717–01–P
Alabama Power Company has requested
that Project Nos. 2146, 82, and 618 be
consolidated into one project. We are
processing these three projects under
Project No. 2146–111. This final
environmental assessment (EA) is a
cooperative undertaking between the
U.S. Army Corps of Engineers and the
Commission.
The Coosa River Project is located on
the Coosa River, in the States of
Alabama and Georgia. The Logan Martin
development affects less than 1 acre of
Federal lands, the Lay development
affects 133.5 acres of Federal lands, the
Mitchell Project affects 127.3 acres of
Federal lands, and the Jordan Project
affects 10.1 acres of Federal lands. Staff
has prepared a final EA for the project.
The final EA contains staff’s analysis
of the potential environmental effects of
the project and concludes that licensing
the project, with appropriate
environmental protective measures,
would not constitute a major Federal
action that would significantly affect the
quality of the human environment.
A copy of the final EA is available for
review at the Commission in the Public
Reference Room or may be viewed on
the Commission’s Web site at https://
www.ferc.gov using the ‘‘eLibrary’’ link.
Enter the docket number excluding the
last three digits in the docket number
field to access the document. For
assistance, contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,
(202) 502–8659.
For further information, please
contact Janet Hutzel at (202) 502–8675
or at janet.hutzel@ferc.gov.
DEPARTMENT OF ENERGY
Kimberly D. Bose,
Secretary.
Federal Energy Regulatory
Commission
[FR Doc. 2010–65 Filed 1–7–10; 8:45 am]
BILLING CODE 6717–01–P
[Project No. 2146–111]
DEPARTMENT OF ENERGY
Alabama Power Company; Notice of
Availability of Final Environmental
Assessment
pwalker on DSK8KYBLC1PROD with NOTICES
In accordance with the National
Environmental Policy Act of 1969 and
the Federal Energy Regulatory
Commission’s (Commission)
regulations, 18 CFR part 380 (Order No.
486, 52 FR 47897), the Office of Energy
Projects has reviewed the application
for a new major license for the Coosa
River Hydroelectric Project (Coosa River
Project), which includes the Weiss, H.
Neely Henry, Logan Martin, Lay, and
Bouldin developments; the Mitchell
Hydroelectric Project (P–82); and the
Jordan Hydroelectric Project (P–618).
VerDate Nov<24>2008
16:14 Jan 07, 2010
Jkt 220001
Kimberly D. Bose,
Secretary.
Federal Energy Regulatory
Commission
December 31, 2009.
Regulatory Commission by Delegation
Order No. 00–037.00, submitted Rate
Schedule L–F9 for confirmation and
approval on a final basis effective
January 1, 2010, and ending December
31, 2014.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. On or before the
comment date, it is not necessary to
serve motions to intervene or protests
on persons other than the Applicant.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 pm Eastern Time on
January 15, 2010.
[FR Doc. 2010–58 Filed 1–7–10; 8:45 am]
[Docket No. EF10–1–000]
BILLING CODE 6717–01–P
Western Area Power Administration;
Notice of Filing
DEPARTMENT OF ENERGY
December 30, 2009.
Take notice that on December 16,
2009, the Deputy Secretary of the
Department of Energy submitted Rate
Order No. WAPA–146, confirmed and
approved on an interim basis, effective
on January 1, 2010, Rate Schedule L–F9
for firm electric service from the
Loveland Area Projects, and under the
authority vested in the Federal Energy
PO 00000
Frm 00025
Fmt 4703
Sfmt 4703
Federal Energy Regulatory
Commission
[Docket No. EF10–2–000]
Western Area Power Administration;
Notice of Filing
December 30, 2009.
Take notice that on December 16,
2009, the Deputy Secretary of the
E:\FR\FM\08JAN1.SGM
08JAN1
Agencies
[Federal Register Volume 75, Number 5 (Friday, January 8, 2010)]
[Notices]
[Page 1050]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 2010-65]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2146-111]
Alabama Power Company; Notice of Availability of Final
Environmental Assessment
December 31, 2009.
In accordance with the National Environmental Policy Act of 1969
and the Federal Energy Regulatory Commission's (Commission)
regulations, 18 CFR part 380 (Order No. 486, 52 FR 47897), the Office
of Energy Projects has reviewed the application for a new major license
for the Coosa River Hydroelectric Project (Coosa River Project), which
includes the Weiss, H. Neely Henry, Logan Martin, Lay, and Bouldin
developments; the Mitchell Hydroelectric Project (P-82); and the Jordan
Hydroelectric Project (P-618). Alabama Power Company has requested that
Project Nos. 2146, 82, and 618 be consolidated into one project. We are
processing these three projects under Project No. 2146-111. This final
environmental assessment (EA) is a cooperative undertaking between the
U.S. Army Corps of Engineers and the Commission.
The Coosa River Project is located on the Coosa River, in the
States of Alabama and Georgia. The Logan Martin development affects
less than 1 acre of Federal lands, the Lay development affects 133.5
acres of Federal lands, the Mitchell Project affects 127.3 acres of
Federal lands, and the Jordan Project affects 10.1 acres of Federal
lands. Staff has prepared a final EA for the project.
The final EA contains staff's analysis of the potential
environmental effects of the project and concludes that licensing the
project, with appropriate environmental protective measures, would not
constitute a major Federal action that would significantly affect the
quality of the human environment.
A copy of the final EA is available for review at the Commission in
the Public Reference Room or may be viewed on the Commission's Web site
at https://www.ferc.gov using the ``eLibrary'' link. Enter the docket
number excluding the last three digits in the docket number field to
access the document. For assistance, contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll-free at 1-866-208-3676, or for TTY,
(202) 502-8659.
For further information, please contact Janet Hutzel at (202) 502-
8675 or at janet.hutzel@ferc.gov.