FFP Qualified Hydro 18 LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications, 352 [E9-31317]
Download as PDF
352
Federal Register / Vol. 75, No. 2 / Tuesday, January 5, 2010 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13582–000]
FFP Qualified Hydro 18 LLC; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
srobinson on DSKHWCL6B1PROD with PROPOSALS
December 29, 2009.
On September 8, 2009, FFP Qualified
Hydro 18 LLC filed an application for a
preliminary permit, pursuant to section
4(f) of the Federal Power Act, proposing
to study the feasibility of the John
Rankin Lock and Dam Hydroelectric
Project, located on the TennesseeTombigbee Waterway, in Itawamba
County, Mississippi. The sole purpose
of a preliminary permit, if issued, is to
grant the permit holder priority to file
a license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
any land disturbing activities or
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
The proposed project would consist of
the following:
(1) A 30-ft by 250-ft long power canal;
(2) a 40-ft by 40-ft powerhouse; (3) a
new 3 MVA substation; (4) a 200-ft long
transmission line; (5) 100 feet of new
access roads; and (6) appurtenant
facilities. The proposed John Rankin
Lock and Dam Hydroelectric Project
would have an average annual
generation of 9.5 gigawatt-hours.
Applicant Contact: Ramya
Swaminathan, Free Flow Power
Corporation, 33 Commercial Street,
Gloucester, MA 01930.
FERC Contact: Allyson Conner, 202–
502–6082.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Comments, motions to intervene,
notices of intent, and competing
applications may be filed electronically
via the Internet. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site (https://
www.ferc.gov/docs-filing/ferconline.asp)
under the ‘‘eFiling’’ link. For a simpler
method of submitting text only
comments, click on ‘‘Quick Comment.’’
For assistance, please contact FERC
Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
VerDate Nov<24>2008
16:41 Jan 04, 2010
Jkt 220001
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and eight copies to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–13582) in the docket number field to
access the document. For assistance,
contact FERC Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–31317 Filed 1–4–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12569–001]
Enloe Hydroelectric Project; Notice of
Application Ready for Environmental
Analysis and Soliciting Comments,
Recommendations, Terms and
Conditions, and Prescriptions
December 28, 2009.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Major License.
b. Project No.: 12569–001.
c. Date filed: August 22, 2008.
d. Applicant: Public Utility District
No. 1 of Okanogan County.
e. Name of Project: Enloe
Hydroelectric Project.
f. Location: On the Similkameen
River, in the Town of Oroville,
Okanogan County, Washington. The
project would occupy about 35.47 acres
of federal land administered by the U.S.
Bureau of Land Management.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: John R.
Grubich, General Manager, Public
Utility District No. 1 of Okanogan
County, P.O. Box 912, Okanogan, WA
98840, (509) 422–8485.
i. FERC Contact: Kim A. Nguyen, 888
First Street, NE., Room 61–01,
Washington, DC 20426, (202) 502–6105.
j. Deadline for filing comments,
recommendations, terms and
conditions, and prescriptions is 60 days
from the issuance of this notice; reply
comments are due 105 days from the
issuance date of this notice.
All documents may be filed
electronically via the Internet. See 18
PO 00000
Frm 00017
Fmt 4703
Sfmt 4703
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site (https://www.ferc.gov/docs-filing/
ferconline.asp) under the ‘‘eFiling’’ link.
For a simpler method of submitting text
only comments click on ‘‘Quick
Comment.’’ For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and eight copies to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted
and is now ready for environmental
analysis.
l. The Enloe Project would consist of:
(1) An existing 315-foot-long and 54foot-high concrete gravity arch dam
with an integrated 276-foot-long central
overflow spillway with 5-foot-high
flashboards; (2) an existing 76.6-acre
reservoir (narrow channel of the
Similkameen River) with a storage
capacity of 775 acre-feet at 1,049.3 feet
mean sea level; (3) a 190-foot-long
intake canal on the east abutment of the
dam diverting flows into the penstock
intake structure; (4) a 35-foot-long by
30-foot-wide penstock intake structure;
(5) two aboveground 8.5-foot-diameter
steel penstocks carrying flows from the
intake to the powerhouse; (6) a
powerhouse containing two vertical
Kaplan turbine/generator units with a
total installed capacity of 9.0 megawatts;
(7) a 180-foot-long tailrace channel that
would convey flows from the
powerhouse to the Similkameen River,
downstream of the Similkameen Falls;
(8) a new substation adjacent to the
powerhouse; (9) a new 100-foot-long,
13.2-kilovolt primary transmission line
from the substation connecting to an
existing distribution line; (10) new and
upgraded access roads, and (11)
appurtenant facilities. The project is
estimated to generate an average of 54
gigawatt-hours annually.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
E:\FR\FM\05JAN1.SGM
05JAN1
Agencies
[Federal Register Volume 75, Number 2 (Tuesday, January 5, 2010)]
[Notices]
[Page 352]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-31317]
[[Page 352]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 13582-000]
FFP Qualified Hydro 18 LLC; Notice of Preliminary Permit
Application Accepted for Filing and Soliciting Comments, Motions To
Intervene, and Competing Applications
December 29, 2009.
On September 8, 2009, FFP Qualified Hydro 18 LLC filed an
application for a preliminary permit, pursuant to section 4(f) of the
Federal Power Act, proposing to study the feasibility of the John
Rankin Lock and Dam Hydroelectric Project, located on the Tennessee-
Tombigbee Waterway, in Itawamba County, Mississippi. The sole purpose
of a preliminary permit, if issued, is to grant the permit holder
priority to file a license application during the permit term. A
preliminary permit does not authorize the permit holder to perform any
land disturbing activities or otherwise enter upon lands or waters
owned by others without the owners' express permission.
The proposed project would consist of the following:
(1) A 30-ft by 250-ft long power canal; (2) a 40-ft by 40-ft
powerhouse; (3) a new 3 MVA substation; (4) a 200-ft long transmission
line; (5) 100 feet of new access roads; and (6) appurtenant facilities.
The proposed John Rankin Lock and Dam Hydroelectric Project would have
an average annual generation of 9.5 gigawatt-hours.
Applicant Contact: Ramya Swaminathan, Free Flow Power Corporation,
33 Commercial Street, Gloucester, MA 01930.
FERC Contact: Allyson Conner, 202-502-6082.
Deadline for filing comments, motions to intervene, competing
applications (without notices of intent), or notices of intent to file
competing applications: 60 days from the issuance of this notice.
Comments, motions to intervene, notices of intent, and competing
applications may be filed electronically via the Internet. See 18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's Web site
(https://www.ferc.gov/docs-filing/ferconline.asp) under the ``eFiling''
link. For a simpler method of submitting text only comments, click on
``Quick Comment.'' For assistance, please contact FERC Online Support
at FERCOnlineSupport@ferc.gov; call toll-free at (866) 208-3676; or,
for TTY, contact (202) 502-8659. Although the Commission strongly
encourages electronic filing, documents may also be paper-filed. To
paper-file, mail an original and eight copies to: Kimberly D. Bose,
Secretary, Federal Energy Regulatory Commission, 888 First Street, NE.,
Washington, DC 20426.
More information about this project, including a copy of the
application, can be viewed or printed on the ``eLibrary'' link of
Commission's Web site at https://www.ferc.gov/docs-filing/elibrary.asp.
Enter the docket number (P-13582) in the docket number field to access
the document. For assistance, contact FERC Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. E9-31317 Filed 1-4-10; 8:45 am]
BILLING CODE 6717-01-P