Enloe Hydroelectric Project; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions, 352-353 [E9-31210]
Download as PDF
352
Federal Register / Vol. 75, No. 2 / Tuesday, January 5, 2010 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13582–000]
FFP Qualified Hydro 18 LLC; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
srobinson on DSKHWCL6B1PROD with PROPOSALS
December 29, 2009.
On September 8, 2009, FFP Qualified
Hydro 18 LLC filed an application for a
preliminary permit, pursuant to section
4(f) of the Federal Power Act, proposing
to study the feasibility of the John
Rankin Lock and Dam Hydroelectric
Project, located on the TennesseeTombigbee Waterway, in Itawamba
County, Mississippi. The sole purpose
of a preliminary permit, if issued, is to
grant the permit holder priority to file
a license application during the permit
term. A preliminary permit does not
authorize the permit holder to perform
any land disturbing activities or
otherwise enter upon lands or waters
owned by others without the owners’
express permission.
The proposed project would consist of
the following:
(1) A 30-ft by 250-ft long power canal;
(2) a 40-ft by 40-ft powerhouse; (3) a
new 3 MVA substation; (4) a 200-ft long
transmission line; (5) 100 feet of new
access roads; and (6) appurtenant
facilities. The proposed John Rankin
Lock and Dam Hydroelectric Project
would have an average annual
generation of 9.5 gigawatt-hours.
Applicant Contact: Ramya
Swaminathan, Free Flow Power
Corporation, 33 Commercial Street,
Gloucester, MA 01930.
FERC Contact: Allyson Conner, 202–
502–6082.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Comments, motions to intervene,
notices of intent, and competing
applications may be filed electronically
via the Internet. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site (https://
www.ferc.gov/docs-filing/ferconline.asp)
under the ‘‘eFiling’’ link. For a simpler
method of submitting text only
comments, click on ‘‘Quick Comment.’’
For assistance, please contact FERC
Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
VerDate Nov<24>2008
16:41 Jan 04, 2010
Jkt 220001
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and eight copies to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–13582) in the docket number field to
access the document. For assistance,
contact FERC Online Support.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–31317 Filed 1–4–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 12569–001]
Enloe Hydroelectric Project; Notice of
Application Ready for Environmental
Analysis and Soliciting Comments,
Recommendations, Terms and
Conditions, and Prescriptions
December 28, 2009.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Major License.
b. Project No.: 12569–001.
c. Date filed: August 22, 2008.
d. Applicant: Public Utility District
No. 1 of Okanogan County.
e. Name of Project: Enloe
Hydroelectric Project.
f. Location: On the Similkameen
River, in the Town of Oroville,
Okanogan County, Washington. The
project would occupy about 35.47 acres
of federal land administered by the U.S.
Bureau of Land Management.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: John R.
Grubich, General Manager, Public
Utility District No. 1 of Okanogan
County, P.O. Box 912, Okanogan, WA
98840, (509) 422–8485.
i. FERC Contact: Kim A. Nguyen, 888
First Street, NE., Room 61–01,
Washington, DC 20426, (202) 502–6105.
j. Deadline for filing comments,
recommendations, terms and
conditions, and prescriptions is 60 days
from the issuance of this notice; reply
comments are due 105 days from the
issuance date of this notice.
All documents may be filed
electronically via the Internet. See 18
PO 00000
Frm 00017
Fmt 4703
Sfmt 4703
CFR 385.2001(a)(1)(iii) and the
instructions on the Commission’s Web
site (https://www.ferc.gov/docs-filing/
ferconline.asp) under the ‘‘eFiling’’ link.
For a simpler method of submitting text
only comments click on ‘‘Quick
Comment.’’ For assistance, please
contact FERC Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and eight copies to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
k. This application has been accepted
and is now ready for environmental
analysis.
l. The Enloe Project would consist of:
(1) An existing 315-foot-long and 54foot-high concrete gravity arch dam
with an integrated 276-foot-long central
overflow spillway with 5-foot-high
flashboards; (2) an existing 76.6-acre
reservoir (narrow channel of the
Similkameen River) with a storage
capacity of 775 acre-feet at 1,049.3 feet
mean sea level; (3) a 190-foot-long
intake canal on the east abutment of the
dam diverting flows into the penstock
intake structure; (4) a 35-foot-long by
30-foot-wide penstock intake structure;
(5) two aboveground 8.5-foot-diameter
steel penstocks carrying flows from the
intake to the powerhouse; (6) a
powerhouse containing two vertical
Kaplan turbine/generator units with a
total installed capacity of 9.0 megawatts;
(7) a 180-foot-long tailrace channel that
would convey flows from the
powerhouse to the Similkameen River,
downstream of the Similkameen Falls;
(8) a new substation adjacent to the
powerhouse; (9) a new 100-foot-long,
13.2-kilovolt primary transmission line
from the substation connecting to an
existing distribution line; (10) new and
upgraded access roads, and (11)
appurtenant facilities. The project is
estimated to generate an average of 54
gigawatt-hours annually.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
E:\FR\FM\05JAN1.SGM
05JAN1
srobinson on DSKHWCL6B1PROD with PROPOSALS
Federal Register / Vol. 75, No. 2 / Tuesday, January 5, 2010 / Notices
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
All filings must (1) bear in all capital
letters the title ‘‘COMMENTS’’, ‘‘REPLY
COMMENTS’’,
‘‘RECOMMENDATIONS’’, ‘‘TERMS
AND CONDITIONS’’, or
‘‘PRESCRIPTIONS’’; (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person submitting the
filing; and (4) otherwise comply with
the requirements of 18 CFR 385.2001
through 385.2005. All comments,
recommendations, terms and conditions
or prescriptions must set forth their
evidentiary basis and otherwise comply
with the requirements of 18 CFR 4.34(b).
Agencies may obtain copies of the
application directly from the applicant.
Each filing must be accompanied by
proof of service on all persons listed on
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b) and
385.2010.
You may also register online at
https://www.ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Public notice of the filing of the
initial development application, which
has already been given, established the
due date for filing competing
applications or notices of intent. Under
the Commission’s regulations, any
competing development application
must be filed in response to and in
compliance with public notice of the
initial development application. No
competing applications or notices of
intent may be filed in response to this
notice.
o. A license applicant must file no
later than 60 days following the date of
issuance of this notice: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–31210 Filed 1–4–10; 8:45 am]
BILLING CODE 6717–01–P
VerDate Nov<24>2008
16:41 Jan 04, 2010
Jkt 220001
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 13580–000]
FFP Qualified Hydro 20 LLC; Notice of
Preliminary Permit Application
Accepted for Filing and Soliciting
Comments, Motions To Intervene, and
Competing Applications
December 29, 2009.
On September 4, 2009, FFP Qualified
Hydro 20 LLC filed an application for a
preliminary permit, pursuant to section
4(f) of the Federal Power Act, proposing
to study the feasibility of the Green
River Lock and Dam No. 1 Water Power
Project, located on the Green River, in
Henderson County, Kentucky. The sole
purpose of a preliminary permit, if
issued, is to grant the permit holder
priority to file a license application
during the permit term. A preliminary
permit does not authorize the permit
holder to perform any land disturbing
activities or otherwise enter upon lands
or waters owned by others without the
owners’ express permission.
The proposed project would consist of
the following:
(1) A 125-ft by 250-ft long power
canal; (2) a newly excavated 150-ft by
300-ft tailrace; (3) a 30-ft by 60-ft control
building; (4) a new 5 MVA substation;
(5) a 1,900-ft long transmission line; and
(6) appurtenant facilities. The proposed
Green River Lock and Dam No. 1
Hydroelectric Project would have an
average annual generation of 27
gigawatt-hours.
Applicant Contact: Ramya
Swaminathan, Free Flow Power
Corporation, 33 Commercial Street,
Gloucester, MA 01930.
FERC Contact: Allyson Conner, 202–
502–6082.
Deadline for filing comments, motions
to intervene, competing applications
(without notices of intent), or notices of
intent to file competing applications: 60
days from the issuance of this notice.
Comments, motions to intervene,
notices of intent, and competing
applications may be filed electronically
via the Internet. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site (https://
www.ferc.gov/docs-filing/ferconline.asp)
under the ‘‘eFiling’’ link. For a simpler
method of submitting text only
comments, click on ‘‘Quick Comment.’’
For assistance, please contact FERC
Online Support at
FERCOnlineSupport@ferc.gov; call tollfree at (866) 208–3676; or, for TTY,
contact (202) 502–8659. Although the
Commission strongly encourages
PO 00000
Frm 00018
Fmt 4703
Sfmt 4703
353
electronic filing, documents may also be
paper-filed. To paper-file, mail an
original and eight copies to: Kimberly D.
Bose, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
More information about this project,
including a copy of the application, can
be viewed or printed on the ‘‘eLibrary’’
link of Commission’s Web site at
https://www.ferc.gov/docs-filing/
elibrary.asp. Enter the docket number
(P–13580–000) in the docket number
field to access the document. For
assistance, contact FERC Online
Support.
Kimberly D. Bose,
Secretary.
[FR Doc. E9–31328 Filed 1–4–10; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. CP07–62–000; CP07–63–000]
AES Sparrows Point LNG, LLC and
Mid-Atlantic Express, LLC; Notice of
Availability of the Final General
Conformity Determination for Maryland
for the Proposed Sparrows Point LNG
Terminal and Pipeline Project
December 29, 2009.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) has prepared this Final
General Conformity Determination
(GCD) for Maryland to assess the
potential air quality impacts associated
with the construction and operation of
a liquefied natural gas (LNG) import
terminal and natural gas pipeline
proposed by AES Sparrows Point LNG,
LLC and Mid-Atlantic Express, LLC,
collectively referred to as AES, in the
above-referenced dockets. A separate
Final General Conformity Determination
is being prepared for Pennsylvania.
The final GCD was prepared to satisfy
the requirements of the Clean Air Act.
The FERC has determined that the
Project will achieve conformity in
Maryland.
The final GCD addresses the potential
air quality impacts from the
construction and operation of the
following LNG terminal and natural gas
pipeline facilities:
• A ship unloading facility, with two
berths, capable of receiving LNG ships
with capacities up to 217,000 m 3;
• Three 160,000 m 3 (net capacity)
full-containment LNG storage tanks;
• A closed-loop shell and tube heat
exchanger vaporization system;
E:\FR\FM\05JAN1.SGM
05JAN1
Agencies
[Federal Register Volume 75, Number 2 (Tuesday, January 5, 2010)]
[Notices]
[Pages 352-353]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E9-31210]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 12569-001]
Enloe Hydroelectric Project; Notice of Application Ready for
Environmental Analysis and Soliciting Comments, Recommendations, Terms
and Conditions, and Prescriptions
December 28, 2009.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Major License.
b. Project No.: 12569-001.
c. Date filed: August 22, 2008.
d. Applicant: Public Utility District No. 1 of Okanogan County.
e. Name of Project: Enloe Hydroelectric Project.
f. Location: On the Similkameen River, in the Town of Oroville,
Okanogan County, Washington. The project would occupy about 35.47 acres
of federal land administered by the U.S. Bureau of Land Management.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: John R. Grubich, General Manager, Public
Utility District No. 1 of Okanogan County, P.O. Box 912, Okanogan, WA
98840, (509) 422-8485.
i. FERC Contact: Kim A. Nguyen, 888 First Street, NE., Room 61-01,
Washington, DC 20426, (202) 502-6105.
j. Deadline for filing comments, recommendations, terms and
conditions, and prescriptions is 60 days from the issuance of this
notice; reply comments are due 105 days from the issuance date of this
notice.
All documents may be filed electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web
site (https://www.ferc.gov/docs-filing/ferconline.asp) under the
``eFiling'' link. For a simpler method of submitting text only comments
click on ``Quick Comment.'' For assistance, please contact FERC Online
Support at FERCOnlineSupport@ferc.gov; call toll-free at (866) 208-
3676; or, for TTY, contact (202) 502-8659. Although the Commission
strongly encourages electronic filing, documents may also be paper-
filed. To paper-file, mail an original and eight copies to: Kimberly D.
Bose, Secretary, Federal Energy Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
k. This application has been accepted and is now ready for
environmental analysis.
l. The Enloe Project would consist of: (1) An existing 315-foot-
long and 54-foot-high concrete gravity arch dam with an integrated 276-
foot-long central overflow spillway with 5-foot-high flashboards; (2)
an existing 76.6-acre reservoir (narrow channel of the Similkameen
River) with a storage capacity of 775 acre-feet at 1,049.3 feet mean
sea level; (3) a 190-foot-long intake canal on the east abutment of the
dam diverting flows into the penstock intake structure; (4) a 35-foot-
long by 30-foot-wide penstock intake structure; (5) two aboveground
8.5-foot-diameter steel penstocks carrying flows from the intake to the
powerhouse; (6) a powerhouse containing two vertical Kaplan turbine/
generator units with a total installed capacity of 9.0 megawatts; (7) a
180-foot-long tailrace channel that would convey flows from the
powerhouse to the Similkameen River, downstream of the Similkameen
Falls; (8) a new substation adjacent to the powerhouse; (9) a new 100-
foot-long, 13.2-kilovolt primary transmission line from the substation
connecting to an existing distribution line; (10) new and upgraded
access roads, and (11) appurtenant facilities. The project is estimated
to generate an average of 54 gigawatt-hours annually.
m. A copy of the application is available for review at the
Commission in the Public Reference Room or may be
[[Page 353]]
viewed on the Commission's Web site at https://www.ferc.gov using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For
assistance, contact FERC Online Support. A copy is also available for
inspection and reproduction at the address in item h above.
All filings must (1) bear in all capital letters the title
``COMMENTS'', ``REPLY COMMENTS'', ``RECOMMENDATIONS'', ``TERMS AND
CONDITIONS'', or ``PRESCRIPTIONS''; (2) set forth in the heading the
name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person submitting the filing; and (4) otherwise comply
with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, recommendations, terms and conditions or prescriptions must
set forth their evidentiary basis and otherwise comply with the
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the
application directly from the applicant. Each filing must be
accompanied by proof of service on all persons listed on the service
list prepared by the Commission in this proceeding, in accordance with
18 CFR 4.34(b) and 385.2010.
You may also register online at https://www.ferc.gov/docs-filing/esubscription.asp to be notified via e-mail of new filings and
issuances related to this or other pending projects. For assistance,
contact FERC Online Support.
n. Public notice of the filing of the initial development
application, which has already been given, established the due date for
filing competing applications or notices of intent. Under the
Commission's regulations, any competing development application must be
filed in response to and in compliance with public notice of the
initial development application. No competing applications or notices
of intent may be filed in response to this notice.
o. A license applicant must file no later than 60 days following
the date of issuance of this notice: (1) A copy of the water quality
certification; (2) a copy of the request for certification, including
proof of the date on which the certifying agency received the request;
or (3) evidence of waiver of water quality certification.
Kimberly D. Bose,
Secretary.
[FR Doc. E9-31210 Filed 1-4-10; 8:45 am]
BILLING CODE 6717-01-P